Sei sulla pagina 1di 3

The lesson learnt for Piping and Mechanical: There are some conflicts in specification which furnished by client.

. But these differences could not be found by during checking before award and during preparation of drawings. This mistake affected to engineering as well as construction so much. .. . . So we have to study carefully all specification and incorporate between disciplines in project. During checking P !D" we should pay more attention to #$ote% below. These can affect to &T'" specification" drawings (or e)ample" the length of fle)ible hose was determined in datasheet. *owever the connection from where to where usually noted in P !D. Based on these notes" the length of fle)ible hose can be changed in comparison with the length shown in data sheets. Sometimes the length too short or too long is also suitable for installation and operation. During checking !sometric from client" we should update the modifications and changes in to + common P !D in order to control easily. The performance &T' was no so good. There was still some Top,up &T' due to low contingency" wrong &T'" the changes lesson learnt for the ne)t project by many ways- ascending the contingency" the bulk material shall be ./0 and add more ./0 for *12 line" and more 3 D* lines as contingency" and add more gaskets for swing spool !n the design stage" we have to take care to ensure the hydro test can be done later. The spool shall have the vent- drain 4flageolet and blind flange5 at the pocket where water can be trapped. (or bolts at the joints where have insulation gasket or T67 should be longer than the length as normally case. !n the !sometric drawings" the bolts" nut and gaskets should be put on *12 lines at tie in point between onshore and offshore in order to avoid missing material during fabrication onshore lines. During review and incorporate vendor data" the orientation of jack up rig shall be considered in order to avoid clashing to the e8uipment" instrument such as fire water monitor" eye wash and shower" lighting 7lso pay more attention for SP items. The space around corrosion coupon has to be enough to connect 9etrieving Tool. (or 2ontinuous Drainers Trap" :e need do check carefully the direction of flow for model in PD&S and installation correctly. (lame 7rrestor location should be near the end of vent boom to arrest the flame as soon as possible. (or manual valves" e8uipment" the space around them shall ade8uate for operation and maintenance. :hen we establish the hydro test package register" to make sure all of lines included in this list. ;esson learn is the lines which connect to riser 4behind shutdown valve5 to be

performed hydro test onshore despite of *12 lines name to ensure one golden weld joint only. The connection joint inside e8uipment" especially is where storing pressure" the flange type must be used" no threaded type which is difficult for repairing and replacement. The self contain eye wash and shower is an e)ample. The leaking found at many threaded connection joints. !t takes time to repair it. The e8uipment lifting procedures were submitted late lead to comments from client. These procedures should be approved by client minimum one day before lifting e8uipment. <alve re8uirement of lock open and lock close. Some of manual valves don=t have the mechanism for lock open and lock close. 9e8uire to access this unit during TB>.

+. (or /? packages which scope supply of *;@'2 handover to P<2,&S for management" are delayed or effect to installation or operation due to these reason listed belowA , 'pen and 2losed Drain SkidA The *armonic (ilter delayed due to it had supplied by many sub of sub,contractor that caused more difficult to e)pedite. The lesson learnt of this is any package should define clearly main groupA Priority items group and normal items groups and e)pedite accordingly. Diesel 2onditioning SkidA The beam siBe had change according to the TC. But it did not inform to construction for the welding of skid=s foundation. !t took a long time for repair foundation to meet with the siBe of skid. (uel Das SkidA 7lco=s <alves had the wrong dimension hole. C2s Package witnessed to check material together <endor" they did not make sure all material shall be received with correct not only 8uantity but also good 8uality such as Dimension according to the re8uirements or not. :ell 2lean,up (ilterA The <endor Data not follow as the project communication line. That made missing many documents as well as information for all parties and their action. (7T informed and Package >ngineers witness at &anufacturer but C2 not re8uested to involve that reason why the good delivered with some descriptions not meet with the re8uirements. 7n e)ample" the insulation" grating" location and direction of Pressure gauges etc ;esson learnt is at (7T stage" (inal inspection to issue !nspection 9elease $ote C2 shall be re8uired to involve and limit the punch list. Pig ;auncherA *ydro Test at &anufacturer did not safety as some picture of the report. !t shown that the Blind flange was cut from a plate" although as the re8uirements it should

be a Standard item" and only 8ualified material used for the Test. ;esson ;earnt for this is before any hold point" all material and e8uipment are used for the Test shall be reviewed carefully and with all precondition. .. (or Pedestal 2rane PackageA This package is free issued by *;@'2. This package delayed one month that effected to construction at P<2,&S Site. The hydraulic horses were too long that caused the torsion and effected to the life of hose. 'therwise" the spare parts supplied not satisfy the actual re8uirement. !t takes a long time for buying when <endor run S7T at P<2,&S Site. Swagelok fitting had not supplied as the re8uirements. >specially" the hydraulic oil used for S7T mi)ed between two types with the same Standard but different &anufacturer. This thing caused identical oil and created problems with the *ydraulic System of 2rane. 7lthough it was accordingly the instruction of <endor" but it cannot acceptable. ;esson learnt of this is check carefully the spare parts based on actually re8uirements of parts at pre,commissioningE commissioning stagereview carefully B'& to confirm that all material shall be provided according to the specification re8uirements- all <endor=s instruction should be re,check and make sure follow the guide as 2odes and Standards. F. PS< and 9upture Disk Package G The calculation shown that the siBe of PS< changed. !t should be update to Detailed >ngineering and the isometric shall be changed accordingly. But it did not inform and effected to engineering and construction. ;esson learnt of this is taking notes for all packages that their calculation could be effected to other as P!D" isometric and it shall be made &T' and purchased timely. 3. 7ccess (itting Package G justification P' due to the re8uest from 2ustomer ?.

Potrebbero piacerti anche