Contents
Introduction 1. Overview
1.1 Scope 1.2 Purpose 2 . Definitions 3 . Loss Classification 4 Quantitative Analysis of Loss 4.1 Technical Loss 4.2 Non-Technical Loss 5. 6. Loss Targeting & Regulatory Regime Loss Reduction Measures 6.1 Technical Loss Reduction Measures 6.2 Non-Technical Loss Reduction Measures Annex A (informative) Case Study Annex B (informative) Technical Modeling and Assumptions Annex B-1: Guidelines for the Application and Approval of Caps on the Recoverable Rate of Distribution System Loss (MERALCO, The Philippines) Annex B-2: Loss Factor Calculation - B-2.1: PEA (Thailand) Loss Factor Coefficient Calculation - B-2.2: EVN (Viet Nam) Technical Losses and Non-Technical Loss Calculation Annex C (informative) Loss Management Practices of HAPUA Members Annex C-1: Distribution Losses in HAPUA members - C-1.1 Technical Losses - C-1.2 Non-Technical Losses Annex C-2: Loss Management Practices - C-2.1 Technical Losses Management Practice of PEA - C-2.2 Non-Technical Losses Management Practice of PEA - C-2.3 HAPUA Member Accuracy Meter Check
Page 2 of 81
Introduction
(This introduction is not part of Guidelines for Minimizing Losses in Energy Delivery of HAPUA Member)
Energy losses in power system delivery contributes a major cost to electricity utilities. As measures in reducing energy losses brings significant benefit to utilities, energy loss reduction has been set as a key performance indicator (KPI) of most utilities and are closely monitored by the regulators.
The goal of this guide is to provide useful information on best practices for managing losses in energy delivery system for HAPUAs members. We hope this guide will be used as a reference for regulator to evaluate the energy loss performance of utilities.
The Working Group on Project Formulating Guidelines for Minimizing Losses in Energy Delivery had the following membership: Mr. Harry Hartoyo, Project Coordinator Mr. Pongsak Harnboonyanon, Chair
Cambodia:
Thailand:
Mr.Wallop Kittiwiwat Mr.Suthat Viriyasuthee Mr.Wirote Buaklee Mr.Sermchai Jaruwatanadilok Mr.Werawat Buatong Mr.Decha Viriyacharoenkit Mr.Kangwan Jarernkornburi
Mr.Doddy Pangaribuan Ms. Phommany Lattanalangsy Mr.Amir Mahmod Abdullah Mr Mohd Hadi bin Sohod
Myanmar:
Page 3 of 81
1. Overview
This guide contains information on methods to estimate and to reduce losses in energy deliver system and is written for engineer, economist, executive, and policy maker who have to design and determine on losses management. However, it may not achieved optimum loss level by using this guide , it may help related parties to create a systematic loss management and share experiences in loss reduction among HAPUA countries. This guide will help the engineers and economists optimize the loss reduction programs. The concept of energy loss management in this guide can be expressed as the following chart.
Step #1 Loss Evaluation 1. Quantify technical loss (TL) and non-technical loss (NTL). 2. Separate TL and NTL by voltage level and service area.
Step #2Loss Reduction Project Arrangement 1. Set up financial return criteria of the project. 2. Create loss reduction project following financial and planning criteria. 3. Assign project timing and responsible agencies. 4. Formulate rewards and penalties scheme for loss target control.
Step #3 Loss Targeting 1. Formulate loss target based on voltage level in each separated service area. 2. Submit/Report loss target to regulator/ shareholder. If regulator requires lower loss target, utilities may negotiate regulator for more investment/subsidies approval and necessary criteria change.
Page 4 of 81
1.1 Scope This guide will identify factors that contribute to energy losses evaluation and suggest appropriate energy losses reduction measures in energy delivery in distribution system.
1.2 Purpose The purpose of this guide is to establish the useful information for Non-Technical and Technical Losses reduction management. The guide includes a common policy, strategy and best practice activities for minimizing losses in distribution systems.
Page 5 of 81
2 .
Definitions
Customer: Any person or entity supplied with electricity service under a contract with a Distributor.
Distribution System Losses or Total Losses: The energy input including those delivered to the Distribution System by the Transmission System, Embedded Generating Plants, other Distribution Systems, and User Systems with generating facilities minus the energy output (i.e., electricity delivered to the Users of the Distribution System) for a specified billing period. Distribution Utility: Any Electricity Cooperative, Private Corporation, government-owned utility, or existing local government unit, which has an exclusive franchise to operate a Distribution System.
Energy: The integral of power with respect to time, measured in Watt-hour (Wh) or multiples thereof.
Energy Input. Energy delivered to the Distribution System by the Transmission System, Embedded Generating Plants, other Distribution Systems, and User Systems with generating facilities. Energy Output: Energy delivered to the Users of the Distribution System.
Load: An entity or electrical equipment that consumes electricity. Load Loss: The electrical loss due to the resistance of conductors that varies with the square of the electric current. Load Model: The representation of electrical load in Load Flow simulations for the purpose of calculating Technical Losses. Metering Equipment: The electrical measurement devices including instrument transformers, wiring, communications, and other auxiliary devices associated with metering. Network Model: The equivalent electrical circuits that mathematically represent electrical systems (e.g., Distribution System) which for calculating electrical parameters or simulating its behavior or performance. It consists of resistance and reactance of the electrical equipment, devices and conductors. No-Load Loss: The fixed loss incurred in electrical equipment regardless of the loading level. This includes the fixed loss dissipated in transformers, voltage regulators, capacitors, inductors and other electrical equipment. Non-Technical Loss: The component of Distribution System Losses that is not related to the physical characteristics and functions of the electrical system. It is caused primarily by human.. Non-Technical Loss includes the electricity loss due to pilferage, tampering of meters, erroneous meter reading and/or billing, and unmetered customers, etc.
Page 6 of 81
Technical Loss: The component of Distribution System Losses that is inherent in the physical delivery of electric energy including load loss and no-load loss. Three-Phase Load Flow: The analytical tool that simulates the power flows in an unbalanced threephase Distribution System.
Page 7 of 81
3. Loss Classification
Distribution System Losses or Total Losses in this guide shall be classified into 2 categories as follows: (1). Technical Losses (2). Non-Technical Losses The Technical Losses is the component of Distribution System Losses that is inherent in the physical delivery of electricity. It includes the Load and No-Load (or Fixed) Losses in the following: Group 1: Lines Loss which consists of (1) Primary Distribution Lines (2) Secondary Distribution Lines Group 2: Distribution Transformer Loss Group 3: Loss of Other Equipment such as (1) Power capacitor (2) Voltage transformer and current transformer for energy measurement The Non-Technical Losses is the component of Distribution System Losses that is not related to the physical characteristics and functions of the electrical System, and is caused primarily by human error, whether intentional or not. Non-Technical Loss includes the electricity lost due to pilferage, tampering of meters, and erroneous meter reading and/or billing. Distribution System Losses will be presented as this following figure.
Technical Losses
Non-Technical Losses
Etc.
Page 8 of 81
Load Factor will be identified by load measurement. A typical value of A and B are 0.3 and 0.7 [1 Buller F.H., C.A. Woodrow, Load Factor-Equivalent Hour Values Compared, Electr.World, vol. 92, No. 2july 14, 1928, pp.59-60] respectively. The value of A and B depend on load characteristic and network configuration. It may not be equally used for every system. A and B factors should be performed for each type of system which may be classified by area type (such as urban, rural, or industrial) or load density and line length.
(4.3)
The following table shows the other values of A and B (calculation for the values of A, B and LLF (Loss Factor) appeared in Annex B-2)
Page 9 of 81
Table 1: The typical values of A and B coefficient Case A Line* 0.33 Transformer** 0.2
B 0.67 0.8
*PEA research project [1] ** Tennessee Valley Public Power Association [2], Distribution System Loss Reduction Manual Project LR-1(Booth & Associates, Inc. Consulting Engineers, 1994)
If loss factor is already calculated, energy loss, due to load losses, will be quantified as follows: Energy Loss (Load Losses) = Loss Factor x Peak Loss x Time Period (4.4)
Peak Loss and Load Factor Calculation: Case 1: Load Losses of Lines Line peak loss will be performed by three phase load flow calculation. Peak load data of each point in a distribution system for line losses calculation can be estimated by allocating a peak load (identified by measurement) of lines that is measured at substation. The load allocation depends on the size of transformer. Case 2 Load Losses of Transformer, Peak loss will be calculated by, Peak Loss of Transformer = Full load loss (klf) x [Peak load (kVA) / Rated power of transformer (kVA)] 2 (4.5) Most power transformers will be installed with power meter and load data will be recorded. In this case peak load and load factor information is easily to obtain. In case of distribution transformer, power meter are usually not installed. Therefore peak load data can be supposed by using load data which are recorded in the assumed peak load period. Energy delivered on distribution transformer will be identified by energy records of every customer connected which can be found in billing system. Load factor will be calculated by Load factor (Distribution transformer) = energy records of every customer connection / [Peak Load (kVA) x Time period of billing] (4.6) 4.1.2 Transformer No-Load Losses Transformer No-Load Losses or Transformer Fixed Loss will be calculated in terms of energy as follows: Energy Loss (Transformer No-Load Losses) = No-Load Loss Specification x Time Period (4.7) No-Load Loss Specification is No-Load Loss level indentified in transformer specification To evaluate technical losses of interested areas, every network and equipment may be calculated. However, this approach cannot be possibly performed according to very large numbers of network and equipment. A sample of network and equipment will be selected for calculation to represent technical Page 10 of 81
losses of the area. The sample selection criteria should be set carefully. Geographical data, load density and network line length may be appropriate factors to be considered when setting selection criteria. 4.2 Non-technical Losses Non-technical losses shall be the residual loss after subtracting the technical Loss from the Total Losses. Non-Technical Losses = Total Losses Technical Losses The errors of non-technical losses calculation from equation 4.7 consist of: (1) Errors in accounting and record keeping that distort total losses calculation. The causes of total loss errors are (1) the difference of energy input collection period and energy output collection period and (2) incorrect meter reading due to human errors. These errors can be mitigated by applying Automatic Meter Reading which automatically collect energy input and output information. (2) Errors in technical losses computation. Some parts of technical losses may not be included in technical losses calculation because they are (1) too complex to represent in mathematic model, for example, leakage current of insulators, (2) too little and able to be negligible such as losses of energy measurement instrument and (3) errors in technical information of the network. (4.8)
Page 11 of 81
The quantity of total losses and technical losses at each voltage level shall be evaluated. The non-technical losses can be calculated by using equation 4.7. The abnormal points and their causes can be identified by performing root cause analysis. The accuracy of loss calculation depends on the availability of data and information. 2. Criteria of Loss Reduction Planning, which comprise budget, financial return of loss reduction project (internal rate of return, net present value or payback period). There are many methodologies to manage the causes of losses. Loss reduction that is less costly can be selected first. This measures will then be implemented until the funds allocated exceeds the criteria. Financial returns for each loss reduction measure will be evaluated. Loss reduction measures with financial returns that cannot meet the criteria will be rejected or suspended before developing the action plan. 3. Action Plan, including lists of loss reduction projects, time schedule and responsible agencies. Action plan is based on selected loss reduction measures. Utilities shall assign tasks of loss reduction measures to each responsible agency and establish key performance indicator (KPI), agency performance evaluation system, penalty and reward scheme for motivating assigned agencies. These agencies shall also implement the exact concept to their teams for effectively implementation.
Page 12 of 81
4. Expected results of each loss reduction project and Loss targeting of each period (A period may be one year). Loss target can be established by two approaches. The first approach is the bottom up approach when the ground staff develop their action plans. The second one is the top down approach where the regulator or executives of utilities set target for the utility. However, both approaches need action plan to meet the target. In case Top-down approach, fund is usually provided sufficiently to achieve the target. Roadmap will be revised periodically. The benefit of Loss Roadmap will help regulators to set up electricity tariff criteria linked to loss performance to the benefit of utilities. 5.2 Regulatory Regime The key success factors of loss control are 1. 2. 3. 4. Setting appropriate target. Agencies that are responsible and act with integrity. Have a loss performance evaluation system in place. Setting up a rewards and penalties scheme.
To accomplish regulator target and maximize utility efficiency, rewards and penalties scheme will be set up to drive utility to improve loss level. Some regulators currently allow some part of energy loss to be passed through electricity tariff. Therefore utilities are persuaded to keep energy loss level lower than the specified energy loss in electricity tariff structure in order to be more profitable. In the future, regulators will increasingly be more stringent to check on utilities by regularly reviewing loss compensation in electricity tariff structure. In line with regulators intention, utility will encourage regional offices to implement loss reduction program. In general, loss reduction programs are related to many regional offices. Loss committees, which comprise representatives of all related units, are a good way to built up a strong cooperation for effective implementation. Funds provision is the key factor if the regulators/shareholders require loss level that is lower than its technical loss. The expected improvement will not occur if utilities are not allowed to invest on better or higher quality equipment and smart devices for detecting abnormal energy usage. The criteria of loss reduction investment have to be considered directly by regulator or policy maker.
Page 13 of 81
The main purpose of new substation construction and replacement of conductor of a bigger size is to increase power capacity of distribution system. These measures require substantial investment. The benefit of loss reduction usually is not high enough to meet the financial criteria. For voltage level increment, there are two points of view. The first is to increase voltage level of distribution system. As with the new substation construction and replacement of conductor of a bigger size, the main purpose is to increase power capacity of distribution system. The second is to increase voltage level at purchasing points between utility and large customers. In this case, overall loss level will be dramatically decreased but the problems of loss control still exist. Regional offices will abandon such program if they did not achieve the desired loss level. Technical loss reduction measures will be discussed as follows. 6.1.1 Network Reconfiguration The main concept of this technique is to define the optimal path of distribution line. There are many alternatives to re-configure the network, subject to power system reliability consideration and existing set up of the network. The solution for this technique is the status of switches in the target areas. Due to the difference of load model and assumptions made, the optimization technique will be different in many commercial programs. The advantage of this technique is low cost but its solution is affected by network changes. The solution has to be revised periodically or when there is a significant change in the network. This technique has been shown to reduce up to 28% of the existing energy loss [2]. The result of loss reduction is dependent on the existing power system. In cases where power capacitors are installed in the system, network reconfiguration can reduce more losses because power capacitors are changed to reduce electrical current in the new path. This situation is equivalent to changing the position of power capacitors although the power capacitor is not physically moved. Page 14 of 81
6.1.2 Load Balancing Load balancing is one of the low cost techniques for technical loss reduction because it does not require additional network equipment. It only requires load level and phasor information at each load point. In case 3 phase 4 wires system, load balancing can reduce about 5%-23% of energy loss [2]. The significant reduction occurs because neutral wire current is decreased. The loss reduction result of this technique can be shown as follows [ 1 ]
1.8 1.7 1.6
Loss, unbalance/PLoss, balance
10
20
30 40 % Unbalance
50
60
70
Figure 3: Unbalance load effect: 3 phase 4 wires system In case 3 phase 3 wires system, load balance may not be reduce energy loss as much as 3 phase 4 wire system. Load balance will only distribute load current in this case. Result of loss reduction can be shown [ 1 ]
Figure 4: Unbalance load effect: 3 phase 3 wires system As mentioned above, load balancing technique is the interesting loss reduction technique for 3 phase 4 wire system. In general, the effect of load balancing is more obvious during the peak load period. Although this concept is simple and easy to perform, utility will not benefit much from this technique.
Page 15 of 81
To get more benefit from this technique, load information and processes of load balancing have to be considered. If customer can be categorized by using load characteristic, energy usage of each customer is a good choice to use for load balancing. In radial distribution system, load balancing shall be done at the end of every lateral and energy loss of neutral wire in every lateral will decrease and utility will get more benefit than only applied load balancing in the main line. The main problem of load balancing is the lack of data, especially phasor information of customers. Some utility have to survey distribution network before execute this measure. This process will increase resources and cost. However, as it is inevitable , the data collected has to be managed well. If database system of this information is not shared and is inaccurate, new meters can be installed to capture the data for load balancing but the cost will be extremely high. Geographicalll Information System (GIS) and sound database management may be required to overcome this. 6.1.3 Power Factor Improvement In general, most of loads require reactive power which causes low power factor and high current in the lines. Most of power factor improvement is capacitor installation that intends to compensate reactive power in power systems. The sizing and location of capacitor for loss minimization is the load point, eventhough there are many constraints to this. Power factor improvement can be done by utility and customer. In many countries, large customers control their power factor at purchasing point as required by regulation. If power factor of the customer violate the regulation, utility will penalize (VAR-charge) that customer. The regulation of power factor will be approved by regulator or the authority concerns. For utility, there are two alternatives to improve power factor. The first one is to install capacitor at the secondary side of distribution transformer. The purpose of this alternative is to reduce copper loss of transformer. In general, the capacitor size for this is a fixed-type. The sizing of capacitor is dependent on transformer load characteristic which comprises load power factor and minimum load level. The chosen size will compensate reactive power of minimum load level. The second one is to install capacitor in distribution network. This is the Optimal Capacitor Placement (OPC) method. It is an optimization method and can be expressed as follows: Objective function; Minimize {Total Cost = Energy loss Cost + Investment Cost} or Maximize {Total Benefit = Energy loss reduction Gain Investment Cost} Constraint; Subject to: Voltage level of all point shall not be exceeded the regulation
Power system modeling for optimal capacitor placement will be the same as load flow calculation except load profile is included in the calculation. It can be represented by daily load curve or load duration curve. Load duration curve method is recommended because it is more simply and less time consuming. As the load level is fluctuated unpredictably, the benefit that can be derived from using the daily load curve method will be minimal.
Page 16 of 81
aQk for capacitor installation. Capacitor will be installed in the location which is given the minimum index. The index will be determined by the following methods:
1. Use Jacobian matrix, which is a component of Newton-Rapshon method of load flow calculation. [2] 2. Compute loss reduction by simulating a capacitor installation in every available location. The size of capacitor for simulation may be chosen by using the smallest size of utility fixed capacitor. The fixed type capacitor will be firstly selected until it is no longer effective or when there is voltage level violation. The switched type will then be used. The flow chart of optimal capacitor placement is as follows: (this flow chart is used for DigSlient Program)
Page 17 of 81
6.1.4 Loss Specification Improvement Significant loss reduction can be achieved by tightening the specification on losses reduction for major equipments, especially power transformer and distribution transformer. No-load loss and Copper loss of transformer can be specified more stringently but the equipment will inadvertently cost more. In the case of cable, there are two main types of losses; Voltage dependent losses are dielectric losses and losses due to charging current. The use of cable with low capacitance and cable made of higher quality materials will mitigate such losses. This can be achieved with tight specifications but it would inadvertently increase the cost. Current dependent losses are conductors and sheaths losses. Conductor losses are mainly caused by skin effect and proximity effect. Sheath losses are mainly due to circulating and eddy currents, especially when single core cable is being used and sheath is bonded at both ends. The use of Miliken conductor will reduce the skin effect for large conductor size. Losses due to proximity effect can be reduced by increasing the distance between cables and management of current flowing in parallel conductors. To reduce sheath losses, single core cable are either single point bonded or cross-bonded. The effect of eddy current can be reduced by increasing the phase separation. However, before changing the specifications, cost benefit analysis should be carried out to weigh the benefits derived from loss reduction against the higher equipment cost.
Page 18 of 81
6.2.1.2 Meter Tampering In addition to the factors discussed above, theft of electrical energy causes an increment in nontechnical losses. Since it is often not possible to catch the offenders, the amount of energy loss cannot be determined and resulting in revenue loss. Stolen energy is, therefore, considered as a part of losses. Theft by the existing customers through tampering of meters is a predominant cause of utility revenue loss. Almost all categories of customers are involved in power theft. However, priority should be given to high value service customers for more effective and immediate revenue recovery. There are many ingenious way for tampering meter. New methods are constantly being discovered as shown:
Spiders: Small holes are drilled into the meters and live spiders or spiders' eggs crammed into them. The spiders' webs slow down the metering mechanism, giving a false reading. Needles: Pins are inserted into a hole, slowing down the meter's recording wheel to give a flash reading or even a zero usage. Magnets: Small magnets attached to the outside of the meter casing will stop the meter from registering, or slow it down. Chewing gum: Gum is often used to stop the meter completely but it is taken out just before the meter reading is taken. Bypassing: this will be power sourced illegally from underground cables and overhead wires or by passing the neutral wires in meters. Others :
Intentional burning of meters; Changing the sequence of terminal wiring; Tampering the seals of meters; - Disconnecting Neutral wires;
6.2.1.3 Defective Metering and Meter Reading Error Non-technical losses are also caused by some deficiencies in the functioning of the utility such as defective metering and meter reading error. These losses are not due to any deliberate action of the customers. They are due to internal shortcomings of the utility and, hence, are that much easier to tackle. Some of these factors are given below Inaccurate metering system installed on outgoing radial feeders and distribution transformers (inaccurate meters can result in errors in loss assessment). Slow or defective meters at customer premises. Errors in the CT/PT ratios (in case incorrect ratios are considered in billing). Errors in assessment of consumption by un-metered customers (like street lights, public amenities, traffic lights etc.). Errors in computing provisional consumption for customers with defective meters or for customers whose meters have not been read. Over burdened CT. Wrong readings and data frauds: In many utilities the meters readers were in connivance with the customers to record lower reading than the actual reading registered at the meter. Stuck up meters. No readings was furnished by the meter reader, and at times, repeatedly. Constant nil consumption cases reported without any comment. Page 19 of 81
Progressive readings recorded in disconnected services. No relation between the meter capacity and the load. Adoption of wrong multiplication factors (MF) for billing as the change in MF is not intimated to the billing agency. Unintentional errors in meter reading. Intentional errors in meter reading (collusion by meter readers). Data punching errors. Data punching errors by data entry operators. Lack of validation checks. Lack of management summaries and exception reports on meter reading.
6.2.1.4 Tardy Billing and Poor Revenue Collection In addition to the external factors mentioned above, non-technical losses are also caused by billing and collection. These losses are due to internal shortcomings of the utility and, hence, are that much easier to tackle. Some of these factors are given below Non payment by customers, where utility does not have a method for timely disconnection. Lack of a system for carrying out regular (monthly) energy accounting to monitor losses Energy accounting errors (by not following a scientific method for energy audits). Errors in raising the correct bill. Manipulation/changes made in meter reading at billing centers lack of a system to assure integrity in data. Lack of system to ensure bills are delivered. Lack of system to trace defaulters including regular defaulters. Lack of system for timely disconnection. Care to be taken for reliable disconnection of supply (where to disconnect). 6.2.2 Measures for Non-Technical Loss Reduction The measures for reducing Non-Technical losses depend on the factors that cause them and these will be discussed separately. 6.2.2.1 Measures for Controlling Illegal Connection 6.2.2.1.1 Stopping Theft by Direct Tapping Various measures can be taken by the electricity supply authorities to stop theft of energy by direct tapping as follows: Setting up of Vigilance Squads (where these have not been set up). Carrying out surprise inspections by Vigilance Squads. Periodic inspection of low tension (LT) feeders by the special Vigilance Squads for tracing unauthorized customers and direct tapping from line. Prosecution proceedings against persons indulging in theft of energy to secure convictions in the Court. Therefore, the materials, wire and equipment may be kept as evidence to be produced at the court hearing to prove the criminal offences. Imposition of heavy fines on customers found guilty of committing theft of energy. Starting a drive for regularizing unauthorized connections and simplifying procedure for new connections.
Page 20 of 81
6.2.2.1.2 Use of Insulated Conductors Use of modern and effective equipment, like Aerial Bunched (AB) Cables/partial insulated LT lines in theft prone areas along with high voltage distribution system can prove to be an effective deterrent to theft. The insulated cables make it more difficult to tap energy. The AB cables can be installed on the same poles used for street lighting and telecommunication circuits. This would save considerable cost and also avoid associated problems of communication. 6.2.2.1.3 Public Relation and Awareness Campaigns by the Utility Some change in the value system of the society is also needed. The opinion makers and social leaders should be involved to effectively tackle this massive social issue. Some amount of public relations work by the utility is needed to tackle this menace. It can help in publisizing widely that the effect of theft will result in tariff increase for the genuine customers, and also resulting in poor reliability and quality of supply such as having unreliable voltages, burnt appliances and failed transformers. 6.2.2.2 Measures for Controlling Meter Tampering The following steps can be taken to reduce such non-technical losses: The energy meter could be housed in a sealed box and made inaccessible to the customers. Multi-core PVC cables could be used as service mains instead of single core wires. Severe penalties may be imposed for tampering. Theft of electricity should be publicized as a social and economic crime to make the public awared and informed of the provisions in electricity laws in this regard. Extensive checking of metering accuracy and detection of tampering should be undertaken. Customers meters should be re-located outside of the customer premises. Potential link should be provided inside the body of the energy meter rather than inside the thermal cover. This prevents the potential link to be disconnected by the customer. Energy variation in consumption must be regularly checked for all categories of customers and suspected cases should be kept under close scrutiny through special checking. Strict control and monitoring of meter readers to prevent malpractice. There should be provision of swapping of duties between meter readers and ledger clerks. 6.2.2.3 Measures for Reducing Defective Metering and Meter Reading Error Some methods to prevent non-technical losses due to defective metering and meter reading error are given below Stringent installation procedures has to be spelt out clearly and in details indicating all the required checks and tests to ensure all checks are strictly complied with and all tests are carried out accordingly during meter installation. Use of electronic meters with tamper and load survey logging features for all categories of customer. Use of optical port for taking the reading for all categories of customers. Sealing of meters with seals and having proper seal management system. Installation of CTs/PTs in sealed boxes so that terminals are not exposed for tampering / bypassing. Testing of the metering system as a whole to ensure accuracy. Ensuring accuracy in meter reading and billing activities by generating exception lists and following up on exceptions.
Page 21 of 81
Carrying out regular energy audits covering the feeder and all end customers to ensure that there is no revenue leakage beyond the permissible technical loss. Having clearly visible and accessible seals that can be subjected to easy inspection Setting up standards/practices/ procedures that will reduce wrong meter reading Expert training for new meter readers Promoting the use of new reading technologies (Handhelds/AMR) Introduction of prepaid meters
In addition to these measures, non-working and defective meters should be identified and replaced. There are many existing services that are not installed with meters, these services should be installed with meters immediately. Similarly, a large-scale drive is necessary for bringing all unauthorized customers on to the rolls. Besides, utilities should purchase adequate quantity of meters both for fresh services and for replacement of the defective meters in the existing services. Metering facilities should be installed not only for measuring the electricity sold to the customers but also for monitoring the energy consumption at different voltage levels. The electromechanical meters tend to get sluggish over a period of time. Old meters should be replaced in a phases and in a timely manner with high accuracy static meters, especially for high value services customers and at places where the load varies substantially. Electromechanical meters should be replaced with electronic meters having ultrasonic welding. CT meters should be adopted instead of whole current meters for LT high value services. Advanced metering technologies, viz. prepaid metering and remote meter readers should also be used. 6.2.2.4 Meter Installation Meter installations have often been considered as a low skill, labour oriented activity. The quality of installations must be given due importance to guard against non-technical losses. The installation practices should take into account various classifications of meters Type of meter: These cover meters of different accuracy classes used for residential, commercial and industrial purpose. The different types of meters are as follows: single phase meters, 3 phase 4 wire Whole Current meters, 3 phase 4 wire CT connected meters, 3 phase meters for HT supplies (CT/PT connected meters), For the HT customers meter with tamper logging features should be used. Nature of application: The metering applications can be categorized under the following broad headings: Tariff metering (for customers), Inter utility tariff metering, and System metering (for feeders and DTs). Location of meters It is important to recognize that different applications require different installation practices and functional specifications for the meters. Mere focusing on the installation practices alone without proper functional specifications will not serve the purpose. The location of meters, i.e., type or nature of site where meters are to be installed is equally important, as installation practices differ as per the following types of site: Indoor Installations, Outdoor installations at/near transformers, and Outdoor installations on poles.
The major cause of loss of revenue has been due to improper installations practices that allowed tampering of the metering systems. Certain installation practices to prevent this are given below
Page 22 of 81
A Visually Traceable and joint free incoming cable, or shrink wrapped sealed joint
helps to prevent tampering. Have a clear and visible seals that can be easily accessible for inspection Mount the meter and CTs inside a box with a clear window, where the internal terminations and connections cannot be accessed without breaking through the seal Ensuring height and location of the installation for easy readability of meters
Locating meters in public domain an alternate location for the meter can be on the poles from where service cables are laid. With this installation, the meters are positioned at a height in full public view. This makes tampering work such as bypassing the meter and direct connections difficult. 6.2.2.5 Measures for Reducing Tardy Billing and Poor Revenue Collection Correct billing and timely delivery of bills will go a long way in improving the collections. The normal complaints in the billing process are: non-receipt/ late receipt of bills, receipt of wrong bills, wrong reading/ status, table readings and wrong calculations. All these can be avoided by going for computerized spot billing as is already done in some countries. A thorough understanding by the readers on the status of the meter is a main factor for the success of the system. Common billing software must be adopted to exercise meaningful control, for review, storage and retrieval of the customer database. Efforts have to be made to minimize the bill processing time. Bill processing time is the average number of days that transpire from the meter read date until bill issuance. Monthly billing should be achieved for the convenience of the customer and also for psychological reasons. Stringent checks must be adopted in the billing process in order to plug the leaks. The billing department should detect the majority of billing errors internally before a bill is issued (e.g., based on a consumption reading that does not follow a customers billing history). This will greatly reduce the errors. In some Distribution Companies, bill delivery is problematic, particularly, in the zones where power theft is prevalent. The utility must have an effective bill delivery system with penal clauses for nondelivery of bills. The power distribution companies have a unique advantage of contacting millions of citizens at least once in a month. This should be utilized to the full advantage to explain the latest initiatives and seek the customers support in their own interest and in the interest of the company. In most power distribution utilities, delays in payments or non-payment are the major cause of nontechnical loss. Collection effectiveness refers to the Distribution Companys ability to collect payment in a timely manner against the bills it issues. Performance on this front is affected by the limited utilitys recourse for non-payment and delayed payment and the inability to write-off bad debts or negotiates payments with customers. The utilities should have a system where defaulters are short-listed immediately after nonpayment within due date with amount and time, etc. Special collection drives, coupled with intensive inspections, in the areas where the payment history is bad, brings positive results. For recovery of arrears, the utility should list defaulting customers; send reminders / notices; initiate legal proceedings; and Resort to disconnection, if need be. Enhanced customer convenience should be the guiding factor for smooth collections. This can be done by introducing multiple payment locations and not restricting them to a particular division/subdivision. Other steps that can be taken are: Provision of additional counters, depending upon the crowd, having Flexible Timings. Providing comfort to customers, e.g., drinking water, toilet, sitting arrangement at collection centers. Page 23 of 81
Installation of electronic cash register machines for collection and counting cash. Drop box facilities and roping in more collection agencies to eliminate lengthy queues.
The following are summary of the measure to reduce the tardy billing and poor revenue collection Setting up standardised practices and procedures that will reduce inaccurate billing. Introduce meter readings verification report from the billing system. Define meter estimation procedures. Setting up standards/practices/ procedures that will reduce meter estimations. (e.g. billing system locks the account for more than three estimations). Introduce prepayment, AMR (Automatic Meter Reading). Disconnect where the premises cannot be accessed after two reminders. Setting up standards/practices/ procedures that will reduce delayed billing for new customers. Introduce intelligent billing that will pick up all un-billed customers. Introduce door to door delivery service for bills. Setting up standards/practices/ procedures that will reduce cases of un-billed customers. Verify if all dormant customers/ accounts in the billing system are not supplied. 6.2.2.6 Additional Measures Utilities can adopt Management Information System (MIS) and carry out energy accounting and audit for preventing non-technical losses. Development ofMIS Effective use of Information Technology(IT) can play a major role in loss reduction and ensure better management efficiency of distribution utilities. Distribution utilities should institute MIS for effective monitoring and control. The reports that can be generated from MIS are given below: Feeder-wise/Distribution Transformer-wise loss, this could be done through by installing meter at the secondary side of transformer in order to detect NTL; Equipment failure and interruption analyses for the feeder; Customer analyses (kWh/kW); Realization Index ($/kWh) for each category and feeder as a whole; Consumption rise or drop by more than 20%; Payment update; Day-wise and amount-wise payments received from the customers; Communication with banks regarding payments realized; Identifying the defaulters; Recovery of arrears; Listing of defaulting customers; Sending reminders/notices; and Disconnections due. The asset and customer database of the Utilities often gets outdated over a period of time. It is therefore necessary to keep the database updated on a regular basis. The outdated information of the customer such as contract demand, multiplication factor (CT/PT) can be a source of error contributing to nontechnical losses. The utility should also have past track records on customers tampering their meters. This information is available from the analysis of the meter. (MIS can be effectively used for this purpose.) Energy Accounting and Auditing To tackle losses effectively it is necessary to compute the losses accurately, identify high loss areas and segregate these losses into losses due to commercial as well as technical factors. For this, utilities establish an Energy Accounting System area-wise to establish the losses on a continuous basis. Experience in many parts of the world demonstrates that it is possible to reduce the non-technical losses in a reasonably short period of time by carrying out energy audits, prioritizing the results and focusing on high loss areas. Energy accounting helps in devising a systematic plan for handling the non-technical loss in the system and in finding out whether the purpose has been adequately served.
Page 24 of 81
Accounting and auditing in the electricity sector involves evolving procedures and checks to account for energy from the generating stations down to the customer level. In the present scenario, the focus should be from grid substations at sub-transmission levels to supply power to customers at various voltage levels. The objective is to prepare an energy account so as to establish the energy input and quantum consumed by/billed to various categories of customers. This leads to identification of high loss areas, which, in turn, would help in finetuning strategies and action plans to reduce losses. The accounting system should ensure that the energy made available at substation, distribution feeder, distribution transformer and units utilized by customers, respectively, are checked to ensure the differences is reasonable and within the permissible limits. For proper energy accounting, metering equipment must be installed both at the sending and receiving ends. This activity should cover review of the existing energy accounting system, replacement of defective meters and installation of meters at appropriate locations for proper energy accounting. Important services, feeders, distribution transformers and towns should be taken up for this exercise. Installation audits are a short-term measure for preventing non-technical loss. These audits cover the inspection of the site and a detailed testing. Installation audits are needed to detect and correct any problems that may have resulted from poor installation practice or by unscrupulous acts by the customers. During the installation audits, aspects such as accuracy of the meters, accuracy of CTs and PTs, present load on the meter, fuses, ferruling of wires, evidence of tampers, etc. are checked. In addition, the terminals are opened for inspection and the connections re-tightened. Thus, the installation audits also cover the preventive maintenance aspects of meter installation. The frequency of installation audits have to be determined objectively and appropriately based on observations and conditions from the field and other data generated through energy audits. Typically installation audits need to be carried out at least annually for 3-phase or HV customers and at least once in 3 years for single phase customers. Most Regulatory Commissions have already specified the frequency for meter testing.
Page 25 of 81
Annex A (informative) Case Study Case Study of PLN Bali 1. Introduction The milestone of PLN Bali to become a World Class Service Company started in 2003 when the management of PLN Bali realized that PLN Bali must have a long term vision i.e. to become a world class services PLNs regional office by 2007. This vision was considered too optimistic and even impossible to realize at that time considering that it was the first time that PLN regional office declared that they want to achieve a world class services. Nobody would have thought that such vision was achievable. PLN Bali started its mission by mapping out its performance and compared it to Hong Kong Electric Company, which was considered as one of a World Class Company. One of criteria was the distribution losses must not exceed 7%. At 2003, distribution loss of PLN Bali was 12.14% and by 2007, the distribution loss has gone down to 6.86% and it did not stop there. By July 2009, the distribution loss has lowered further to 4.9%. The success of Bali has become a trigger for other PLNs regional office to realize that such a low loss is achievable. 2. Major operational statistics
Rated capacity peak load no. of customers energy sales electricity tariff distribution loss Unit MW MW customers GWh Rp/kWh % 2003 550 372 659,971 1,981 672 12.14 2004 550 385 673,233 2,079 678 9.72 2005 550 401 683,419 2,165 683 8.61 2006 550 422 698,725 2,211 691 7.53 2007 580 456 717,428 2,387 696 6.86 2008 580 482 738,654 2,563 712 5.92
3. Strategy of Loss Minimization Loss minimization strategy began with identifying source of losses in both technical and non technical losses. Technical losses depend on construction and configuration of distribution network while non technical losses depend mainly on the accuracy of energy transaction point. In terms of investment cost and time, minimizing technical losses require high investment and long period, while non technical losses incur lower cost and shorter period of time.
Page 26 of 81
Technical loss minimization started with strengthening distribution network through planning, construction, and operation and maintenance activities. At the same time, non technical loss minimization program was carried out by ensuring accuracy of meter and meter reading, and minimizing illegal tapping of supply. Theoretically, distribution losses could easily be identified and managed. However, experience showed that one important factor as to why the loss came down very slowly was because people is not awared of the significance of losses. Thats why one of the main strategies was to educate and to campaign against high losses. It was also realized that since the loss had become an important Key Performance Indicator for Regional Office, loss reporting must be guided to reflect real condition. Otherwise, the real loss could never be specified and people tended to report what they thought good enough to deliver. Once the reporting mechanism has been agreed, the loss management could be monitored and evaluated periodically to reveal the real condition. In line with the campaign to raise awareness on the importance of loss minimization, PLN Bali declared loss minimization action plan each quarter with branch office recognising the loss improvement of each branch office and reward them through a simple ceremony. Branch offices are ranked according to their loss level improvement for the award.
4. Loss minimization Activities
customers 17.079 3.375 pts pts pts pts kms s/s 59.076 0 0 0 10,7 0 0 194
No
Activities
2004 114 60 21 49 0 0 0
2006 57 0 48 33 33 0 189
2008 130 34 84 48 48 0 0
1 Inserted s/s < 160 kVA 2 Trans load management 3 Transf. load balancing 4 Maintenance of main fuse Contact 5 Maintenance of Fuse Holder 6 Replacement of transf. Jointing 7 Replacement of Inlet / Outlet cables
Page 27 of 81
1,530 2,550 11,667 9,431 11,992 10,224 6,682 11,667 10,961 14,542 10,224 6,682 1,300 446 3,240 3,021 1,501 2,340 68 95 608 1,458 1,990 357 133 97 182 28 15 9 51 128 201 149 166 439 1,066 143 212 18,950 15,961 18,877 12,586 7,415
5. Conclusion
The success of PLN Bali Loss Minimization program shows that it takes full commitment from management and all members to fight against loss. Once the awareness has been raised, the management set up strategic plan with monthly action plan which can be verified and monitored regularly. It is important that the strategic plan is translated into action in a systematic manner and divided into stages for ease of monitoring and evaluation. Management must design reporting mechanism to ensure that the loss minimization progress was reported periodically and accurately. The rewarding system was also carried out to encourage competition amongst Branch Offices as well as a updating of loss targeting declaration which is done during regional office 3-monthly meeting. After 5 years of implementation, the significance of loss minimization movement has been internalised into PLN Bali personnel. Now is the time to search for a new method of loss minimization program instead of continuing with the same method. By constantly looking for new method, it is expected that the continuous improvement spirit will be maintained and refreshed, so as to meet future challenges with confidence.
Page 28 of 81
Graph-2: Loss level of branch offices v.s. Flag Loss Semester I 2009
No 1 2 3 4 5 6 7 8 9
Branch AP Kuta AP Singaraja AP Gianyar AP Klungkung AP TM APD AP Negara AP Denpasar AP Tabanan 3,7 3,9 4,2 4,8 4,8 4,8 5,49 5,84 6,0 6
Loss (%)
Loss Flag Platinum Platinum Platinum Platinum Platinum Platinum Gold Gold Gold
Page 29 of 81
Consistent and Sustainable Focused and measurable target Reporting Application HR and IT preparedness Organizational Structure VISION
2012
T : 4,00%
Of DISTRIBUTION
2011
T : 4,50%
2010
T : 5,00%
2009
T : 5,50%
Page 30 of 81
Distribution Network Models For purpose of calculating the Technical Loss, the Distribution System shall be represented by Distribution Network Models that are appropriate for Three Phase Load Flow simulations. All equipment, devices and conductors of the Distribution System shall be characterized to capture the unbalances due to equipment construction, installation configurations, and connection and due to the unbalanced loading. In addition, the models must capture the Load-Losses and No-Load (or Fixed) Losses of all Distribution System equipment, devices and conductors except for metering burdens which are estimated separately. The Distribution System shall be modeled by an interconnected network represented by series and shunt impedances and/or admittance-parameter network in which a common node is used as a reference as illustrated in Figure A-1. Self and mutual impedance and/or admittances of each Distribution System element (e.g., line, transformer, etc.) shall be included.
Line Mode Overhead Sub-transmission and Primary Distribution Lines shall be represented by a three-phase pi () equivalent network with the corresponding self and mutual impedances of the phase and ground conductors as shown in Figure A-2.
Page 31 of 81
The series self- and mutual-impedances of conductors are given by the Carson equations for the series parameters:
The shunt parameters consist of self- and mutual-capacitive reactance due to the voltages (potential) and electrical charges of the conductors and their images below the ground as illustrated in Figure A-3 and can be obtained from the following equations:
If conductor w represents the overhead ground wire or grounded neutral wire, then vw is zero, and the matrix in equation (8) can be reduced using kron reduction technique and then inverted to obtain the following self- and mutual-capacitance of the lines:
Page 32 of 81
The admittance parameters (Y) can be obtained from the inverse of the capacitive reacta where w and f are frequencies in radians per second and cycles per second, respectively. Underground and Submarine Cables shall be modeled similar to the overhead lines with considerations to the self and mutual impedances of the core, sheath and armor conductors. Secondary Distribution Lines and Service Drops are similarly modeled except for the shunt capacitances and mutual reactance which may be neglected. Transformer and Voltage Regulator Models Transformer and Voltage Regulator Models shall be developed based on the structure of magnetic circuit and connections of the windings. The leakage (series) impedance and the magnetizing (shunt) admittance shall capture the self and mutual impedance or admittance parameters of the transformer or voltage regulator coils.
Shunt Capacitors and Inductors Shunt Capacitors shall be modeled as lumped loads that are connected to a Bus with either constant resistance and reactance or constant real and reactive power demand as illustrated in Figure A-4. The real component of the power represents the Fixed Losses in the capacitors while the reactive power is injected into the Bus that is required for power quality improvement.
Page 33 of 81
Shunt Inductors shall be modeled as lumped impedance (i.e., series resistance and reactance) parameters that are connected to a Bus as shown in Figure A-5. The inherent resistance of the inductor shall account for the losses which vary with the square on the current drawn by the inductor.
Series Inductors shall be modeled as series impedance like a Distribution Line without the shunt components and mutual reactances as illustrated in Figure A-6. The inherent resistance of the inductor shall account for the losses which vary with the square on the current through the inductor.
Typical Load Curves for different types of customers and customer monthly energy billing are the basic input to the Load Models. The total energy consumed by each customer is convolved to the normalized load curve for the type of customer to determine the hourly power demands as illustrated in Figure A-7. Power factor of the load are specified based on measurements or reasonable assumptions. Figure A-8 shows the step-by step procedure of converting energy consumption (kWhr in one billing cycle) to 24-hourly kW demands. The real power demand Pt for time t is obtained from the per unit (p.u.) demand Pt divided by the total area under the normalized load curve. Another set of data specifying the hourly demand is the hourly power factor (pft) to compute for the hourly reactive power demand (Qt). These real power and reactive power may be divided into three components to represent constant power, constant current and constant impedance loads if their coefficients are known. For purposes of segregating Distribution System Losses, Constant P and Q load models shall be acceptable. Figure A-9 shows the complete hourly real and reactive demand for a typical residential customer.
Page 34 of 81
Distribution Utility may develop more accurate load models by preparing as many load curves as possible through a load survey for each type or even sub-type of customers that can capture seasonal variations. Also, different load curves may be used for weekdays and weekends.
Page 35 of 81
Annex B-2: Loss Factor Calculation Annex B-2.1: PEA (Thailand) Loss Factor Coefficient Calculation
Table A: Load Measurement Data Time 0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Total I (A) 100 90 85 80 70 75 90 130 160 200 190 190 185 180 190 195 185 180 190 190 195 190 160 120 3620 I2 10000 8100 7225 6400 4900 5625 8100 16900 25600 40000 36100 36100 34225 32400 36100 38025 34225 32400 36100 36100 38025 36100 25600 14400 598750 B A = 598750/(200 x 24) = 0.62 Step 3# Calculate A and B coefficient by analyzing the loss factor equation. Loss Factor = A x Load Factor + B x (Load Factor)2 , A+B =1 0.62 = A x 0.75 + B x 075 2 = (1-B) x 0.75 + B x 0.5625 = 0.69 = 0.31
Y_
= 3620/(200 x 24) = 0.75 Step 2# Calculate Loss Factor (LLF). Loss Factor = ( Load Current)2x24)
Y_
Load Current2)/((Maximum
Page 36 of 81
Annex B-2.2: EVN (Viet Nam) Technical Loss and Non-Technical Loss Calculation
1. Background Electrical Energy Losses - AA (kWh) are the losses incurred in the transfer of electricity over a Transmission and distribution network includes Technical loss - AAT (kWh) and non technical loss AAC (kWh).
AAT Losses vary with line length and depends on the amount of power being transferred. Overall losses can vary from year to year as they depend on factors such as network configuration, conductors, transformers, utilization level, load profile and power factor of the system (level of reactive power support), etc.
To implement losses mapping and bring out suitable measures to reduce power losses, annually calculate technical losses and non technical losses are very importance. 2. Technical losses calculation There are two components of technical losses on a distribution network. a. Load Losses: These losses depend on the electricity being supplied through the distribution network. These losses are proportional to the square of the current being supplied through the network equipment such as sub-transmission, distribution and, LV lines and distribution transformers.
Load Losses are calculated on the relevant part of the network under peak demand condition using PSS/ADEPT software. Peak Losses are modeled in PSS/ADEPT using peak demand measure or calculate from daily load curve and energy consumption for each bus (i) in the network. A feeder has n buses, operation in duration T (hrs), energy consumption is A (kWh) and max demand is P (kW). Load at each bus can be calculated as follows: Pmax i = 3. U. I max . cos or