ABSTRACT AND DETAILED ESTIMATE FOR THE EXISTING TILED ROOF RESIDENTIAL BUILDING TO BE REMOVED

AND PROPOSED CONSTRUCTION OF R.C.C. ROOF RESIDENTIAL BUILDING TO BE REMOVED AND PROPOSED
CONSTRUCTION OF R.C.C. ROOFTS.NO.98 PT, WARD V, BLOCK NO.9, KAMARAJAN STREET,
SENTHANEERPURAM, VARAGANERI VILLAGE, ARIYAMANGALAM ZONE, TRICHY CITY CORPORATION.
OWNER NAME: R. SURESH
SL.NO.

DESCRIPTION OF WORKS

EST. AMOUNT : Rs.10,00,000.00/NO.

01. Dismantling the existing brick work & remove the roof
TotalAll round the wall
1
36.07 ----

QTY.

0.91

32.82

SAY 33.00 M x Rs. 750/02. Proposed B.W. in C.M. 1:5


All around the wall
Parapet Wall

24,750.00

1
1

36.07 0.23
13.65 0.23

0.91
0.91

7.55
2.86
------10.41

SAY 11.00 M x Rs.8100/03.

56,100.00

R.C.C. in 1:2:4 for lintel, sunshade, beam & Roof


Lintel
1
36.07
Sunshade
1
18.00
Beam
1
36.07
Roof
1
5.41

0.23
0.61
0.23
8.24

0.15
0.10
0.23
0.11

1.24
1.10
1.91
4.90
-----9.15

Say 10.00 M x Rs.12800/-

04.

Remove the existing doors and windows


MD
Main Door
1
D1
Door 1
1
D2
Door 2
1
W1
Window 1
1
KW
Kit window
1
V
Ventilator
1

SAY 12.00 M x Rs.1200/-

AMOUNT IN Rs.

1,28,000.00

1.06
0.91
0.76
1.52
1.52
0.91

-------------------

2.13
2.13
2.13
1.92
1.52
0.61

2.26
1.94
1.62
2.92
2.31
0.56
------11.61
14,400.00

05.

06.

Supplying of doors and windows for first class


Rose wood are used
As per item No. 4
SAY 12.00 M x Rs.6000/-

Plastering in C.M. 1:5


All-round the wall
Kitchen
Toilet
Hall
Hall

1
1x2
1x2
1x2
1x2

11.61
72,000.00

27.30
7.48
3.58
5.26
7.93

----------------

5.20
3.05
3.05
3.05
3.05

DEDUCTION OF DOORS AND WINDOWS


As per item No. 5 x 2

141.96
45.63
21.84
32.09
48.37
--------289.89
23.22(-)
-------266.67

SAY 267.00 M x Rs.800/-

07.

Existing floor are removed


Hall
Hall
Toilet
Kitchen

2,14,400.00

1
1
1
1

4.96
3.20
1.75
4.96

2.97
2.06
1.83
2.58

-------------

14.73
6.59
3.20
12.50
------37.02

SAY 38.00 M x Rs.800/-

08.

Flooring C.M. 1:5 and fixing with first class


Marionette tiles
As per item No. 7
SAY 38.00 M x Rs.3500/-

09. Ceiling plastering in c.m.1:3


AS per item No. 8
SAY 38.00 M x Rs.800/-

30,400.00

37.02
1,33,000.00

37.02
30,400.00

10. White washing and colour wash using in


First class snowcem are used
As per item No. 6 + 9 = 266.67 + 37.02 =
SAY 304.00 M x Rs./500.00

11. Weathering course using first class brick jelly


And lime mortar are used with fixing tiles
Open Terrace
1
SAY 39.00 M x Rs.800.00
12.

303.69
1,52,000.00

4.96

----

7.78

38.59
31,200.00

Painting for doors and windows for first class


Synthetic enamel pant are used
As per item No.5
SAY 12.00 M x Rs.1000.00

11.61
12,000.00

13.

Provision for underground drainage deposits

L.S.

6,000.00

14.

Provision for Electrification arrangements

L.S.

40,000.00

15.

Provision for Inner and outer sanitary arrangements

L.S.

10,000.00

16.

Provision for Bore well & Electric Motor arrangements L.S.

10,000.00

17.

Provision for cub boards arrangements

L.S.

15,000.00

18.

Provision for kitchen slab arrangements

L.S.

10,000.00

19.

Provision for other unforeseen items

L.S.

20.350.00
-----------------------Total
Rs.10,00,000.00
-------------------------------------------------------------------------------------------------------------------------------------------------

ENGINEER