Sei sulla pagina 1di 8

Project Cumulative Cost Data

Project Name:
Reporting Periods: 7/05 8/05 9/05

Put your Organization Name Here

<See instructions below>


10/05 11/05 <=== Enter reporting periods here. ===>

<==== Planned Cost per Reporting Period ====>


Planned Phase Cost Initiation $10,000 Monthly % of cost
$4,000 40% $6,000 60% $0 $0 $0 $0

Planning $40,000 Monthly % of cost

$0

$8,000 20%

$16,000 40%

$16,000 40%

$0

$0

$0

$0

$0

$0

Execution $10,000,000 Monthly % of cost

$0

$0

$0

$800,000 8%

$800,000 8%

$800,000 8%

$800,000 8%

$1,000,000 10%

$1,000,000 10%

Control $0 Monthly % of cost

Enter

percent

cost

per

unit time

below

Close $0 Monthly % of cost

Enter

% cost

per

unit time

below

Total Planned Project Cost:


Budgeted Cost per Reporting Period:

$10,050,000

Time unit of project:

Months

$4,000

$6,000

$8,000

$16,000

$16,000

$800,000

$800,000

$800,000

$800,000

$1,000,000

$1,000,000

Cumulative Plan Cost:

$4,000

$10,000

$18,000

$34,000

$50,000

$850,000

$1,650,000

$2,450,000

$3,250,000

$4,250,000

$5,250,000

Actual Cost: Cumulative Actual Cost:

$3,840 $3,840

$5,580 $9,420

$7,100 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005]

Page 1 of 8

Printed on: 11/27/2013

Project Cumulative Cost Data


Instructions: Before you enter any data, do the following: - Determine the total cost of each project phase - Determine the number of reporting periods that each project phase will last (e.g. 3 months) - Determine (or guestimate) the percent of cost that will occur during each reporting period for each phase To enter planned project values (note: all data entry cells are white): 1. Enter project name in the space provided 2. Enter reporting periods in cells D4 through AA4 (e.g. weeks, months or quarters as dates (shown) or month1, month2, etc.) 3. Enter cost of each project phase under Planned Phase Costs 4. Enter the % of phase cost planned for each Reporting Period in the white cells provided. (see Initiation and Planning for an example of how this is done). Leave unused cells blank. Planned cost per period displays above the % you entered. Cells in column AB will be red until the total percent for the project phase equals 100%. 5. Enter time unit of the project. This is "Months" in the example. This is used as a label on the chart in the next tab. 6. Planned cost per reporting period display in the 'Budgeted Cost per Reporting Period" line 7. Planned Cumulative Cost displays in the "Cumulative Planned Cost" line 8. Enter Actual Costs per reporting period as the data become available. The cumulative actual cost will display in the Cumulative Actual Cost line. It is normal for the last correct cumulative cost figure to repeat through all succeeding months. Do NOT delete these numbers! 9. Modify the graph in the Cumulative Cost Curve tab as explained on that sheet When should you use this template: - Use this template when you need a Cumulative Cost Curve and you have a good idea of how your costs will be broken out over the course of your project. - This template is useful for projects that last between 4 and 24 reporting periods and where rough estimates of cost per reporting period are adequate. - See companion document "CumulativeCostCurve_Percent_SampleData.xls" to see what a completed project looks like.

Put your Organization Name Here

Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005]

Page 2 of 8

Printed on: 11/27/2013

Project Cumulative Cost Data

Put your Organization Name Here

12/05

1/06

2/06

$0

$0

$0

$0

$0

$0

$0

$2,000,000 20%

$3,200,000 32%

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$2,000,000

$3,200,000

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$7,250,000

$10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000 $10,450,000

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

$0 $16,520

Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005]

Page 3 of 8

Printed on: 11/27/2013

Project Cumulative Cost Data

Put your Organization Name Here

Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005]

Page 4 of 8

Printed on: 11/27/2013

<See instructions below>


$60,000
$50,000

Cumulative Cost

$40,000 $30,000 $20,000 $10,000 $0 7/05 8/05 9/05 Months 10/05

Initial Setup Once you have entered all of your Planned data in the Raw Data tab, do the following: - Click once on the chart to select it and then click Chart on the toolbar - Click Source Data and then Series - Click Budgeted Cost and then in the Values box change "Raw data" to inlcude only the columns in which you have entered For example, if your project will last 12 months you will have planned data in columns D through O, so the value for Raw D be ='Raw Data'!$D$26:$O$26

Adding Actual Cost Data As you add Actual Cost values, click once on the chart to select it and then click Chart on the toolbar - Click Source Data and then Series - Click Actual Cost and then in the Values box change "Raw data" to inlcude the latest column in which you have Actual C the example we have Actual data for 3 months, so the last Actual data is in Column F. The value for Raw Data should be ='Raw Data'!$D$30:$F$30

Note: this chart is easily added to a Word document. Just click on the chart, right click and Copy, then Paste into the Word doc

below>

Budget Cost Actual Cost

11/05

e columns in which you have entered planning data. s D through O, so the value for Raw Data should

the toolbar

t column in which you have Actual Cost data. In this F. The value for Raw Data should

d Copy, then Paste into the Word document.

Raw Data Tab


Instructions: Before you enter any data, do the following: - Determine the total cost of each project phase - Determine the number of reporting periods that each project phase will last (e.g. 3 months) - Determine (or guestimate) the percent of cost that will occur during each reporting period for each phase

To enter planned project values (note: all data entry cells are white): 1. Enter project name in the space provided 2. Enter reporting periods in cells D4 through AA4 (e.g. weeks, months or quarters as dates (shown) or month1, month2, etc.) 3. Enter cost of each project phase under Planned Phase Costs 4. Enter the % of phase cost planned for each Reporting Period in the white cells provided. (see Initiation and Planning for an of how this is done). Leave unused cells blank. Planned cost per period displays above the % you entered. Cells in column AB will be red until the total percent for the project phase equals 100%. 5. Enter time unit of the project. This is "Months" in the example. This is used as a label on the chart in the next tab. 6. Planned cost per reporting period display in the 'Budgeted Cost per Reporting Period" line 7. Planned Cumulative Cost displays in the "Cumulative Planned Cost" line 8. Enter Actual Costs per reporting period as the data become available. The cumulative actual cost will display in the Cumulative Actual Cost line. It is normal for the last correct cumulative cost figure to repeat through all succeeding months NOT delete these numbers! 9. Modify the graph in the Cumulative Cost Curve tab as explained on that sheet

When should you use this template: - Use this template when you need a Cumulative Cost Curve and you have a good idea of how your costs will be broken out over the course of your project. - This template is useful for projects that last between 4 and 24 reporting periods and where rough estimates of cost reporting period are adequate.

- See companion document "CumulativeCostCurve_Percent_SampleData.xls" to see what a completed project looks

Cumulative Cost Curve tab

Initial Setup Once you have entered all of your Planned data in the Raw Data tab, do the following: - Click once on the chart to select it and then click Chart on the toolbar - Click Source Data and then Series - Click Budgeted Cost and then in the Values box change "Raw data" to inlcude only the columns in which you have entered For example, if your project will last 12 months you will have planned data in columns D through O, so the value for Raw D be ='Raw Data'!$D$26:$O$26

Adding Actual Cost Data As you add Actual Cost values, click once on the chart to select it and then click Chart on the toolbar - Click Source Data and then Series - Click Actual Cost and then in the Values box change "Raw data" to inlcude the latest column in which you have Actual C the example we have Actual data for 3 months, so the last Actual data is in Column F. The value for Raw Data should be ='Raw Data'!$D$30:$F$30

Note: this chart is easily added to a Word document. Just click on the chart, right click and Copy, then Paste into the Word doc Template source: http://www.cvr-it.com

ths) od for each phase

es (shown) or month1, month2, etc.)

. (see Initiation and Planning for an example e % you entered.

n the chart in the next tab. ne

actual cost will display in the epeat through all succeeding months. Do

f how your costs will be broken

nd where rough estimates of cost per

ee what a completed project looks like.

e columns in which you have entered planning data. s D through O, so the value for Raw Data should

the toolbar

t column in which you have Actual Cost data. In this F. The value for Raw Data should

d Copy, then Paste into the Word document.

Potrebbero piacerti anche