Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Who we are!
Unincorporated JV Rio Tinto (80% & manager) and Sumitomo Group (20%) 230 staff and 500 contractors Copper and gold producer Total production to the end of 2009 715,000 tonnes Cu 985,000 ounces Au
1,630 ha of mine lease within 5,670 ha of agricultural land (+ 2,102 ha nearby) Current Life of Mine is 2024
Site Overview
TSF1
E27 E22
TSF2
E48
E26
2 km
S
Hoisting Shaft
N
E48
L1 L1
Access Decline
E26
L1
9800 Level Main Decline
L2
9450 Level
L2N
Conveyor Declines
800m
4-Way Tipple
BK Crusher
Hoist to surface
1050tph conveyor
Multiple equipment interactions Dust Uncontrolled draw point flows Rock falls Whole body vibration
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2 Second production trial at Lift 2 mine E48 Project commences construction E48 Project scope varied to include autonomous LHDs Full implementation of autonomous loaders on E48 Production level
Concept to Production
Concept
Develop Scope: Network Barriers LHD interface
Conduct Risk Assessment (each aspect) Handover to production: Risk register Operating procedures Maintenance procedures Documentation Training systems
Lessons Learned: Navigation system able to accurately control the location of the LHD Automated haulage and dump cycle successfully tested Operator comfortable with teleremote load function
Issues raised: Reliability (sensitivity) of barrier system Barrier system required to comply with AS61508 On-board processing capacity limits LHD speed to 12-13kph
Barrier system must contain the LHD under all circumstances Prevent access of unauthorised personal and trips the LHD in the event the area is accessed Comply with the requirements of AS 61508 to achieve an appropriate level of safety Typical Barrier Setup
Trial design: Automated loader operating in central two extraction drives on Lift 2 extraction level LHD running in 3rd gear Automated loader responsible for 25% of mine production Barrier system compliant with AS 61508 9450 L Extraction Level
Crusher
ED3 ED4
Production metrics:
mins Availability Utilisation MTBF
Max 24hr production of 414 buckets vs 382 buckets/24 hr period in Week 11 Max 12hr production of 212 buckets vs 207 buckets/12 hr period in Week 13
Upgraded automation equipment and software Additional offsite OEM technical support 24/7 Upgraded communications between site and OEM offices Additional training for both maintenance and operations personnel
100.0% 90.0% 80.0% 60.0% 50.0% 40.0% 30.0% 20.0% 10.0% 0.0% Avail. & Util. 70.0%
LH D 2
LH D 2
LH D 2
LH D 2
Availability
Utilisation
We have demonstrated operability of the automation system achieving comparable results to manually operated machines!
Do we continue to test and develop the MineGem automation system? Improve reliability of the system 4th gear function (speed) Traffic management (multiple units interacting) How does automation fit with our future plans? At Northparkes (E48 Project)? Within Rio Tinto? What are the alternatives?
Available systems
Sandviks AutoMine Caterpillars MineGem (DAS) Atlas Copco
REVIEW
Automated LHDs are key enabler for Rio Tintos UG mining ambitions
Final Pit Grasberg Pit
Dom
ESZ
re
Fully integrated
Freeport: Hybrid - LHD + party automation system 3rd MineGem on Caterpillar LHD
OEM LHD
automation system
Additional: 7. 8. Support both electric and diesel LHDs Support very large complex mass mining operations
E48 Automation
Complete turn key package with Sandvik 5 x AutoMine-ready LHDs delivered by Q3 2010 Control room upgrade Automation install to commence in Sep 2010 with Zone 1 commissioning in Feb 2011 Completion in Jun 2011
AutoMine
Daily draw order Extraction tunnel priorities Production scheduling input Manual production list modifications
Daily drawpoint tons Progressive drawpoint tons Current drawpoint statuses Cycle time data Drawpoint status history
Operating Manager
Production schedule Production reports Manual production list Auto mission list Updated drawpoint statuses Fleet status Drawpoint status
Operator Station
SCADA (Citect)
System Operator
Crusher bin level Crusher operational status Crusher bin withdrawal rate U/Cut pass levels Rockbreaker status
Tele-operation commands
Auto LHD/Truck
S
E26 GRP314
Hoisting Shaft
Lift 1 Not mined Lift 1
N
E48
Concentrator
E22
Lift 1
9800L
Lift 2/2N
9450L
Lift 3 Lift 1
n or Decli Convey
es
Monzonite Stock
Lift 2
Cross Section
Automation @ Northparkes
VISION
+
EXPERIMENTATION
+
PERSEVERANCE
INNOVATION