0 valutazioniIl 0% ha trovato utile questo documento (0 voti)
1K visualizzazioni0 pagine
This document is an energy audit report submitted by NEC Consultants Private Limited to Shafi Gluco-Chem (Pvt.) Ltd. It provides an introduction to the audit, describes the company's energy consumption and distribution systems, identifies potential energy savings, and provides recommendations. The audit found opportunities to improve electrical distribution, power factor, electric motor efficiency, boiler efficiency, insulation, and reduce steam and compressed air leaks. Implementing the recommendations could help lower SGC's energy costs and greenhouse gas emissions.
This document is an energy audit report submitted by NEC Consultants Private Limited to Shafi Gluco-Chem (Pvt.) Ltd. It provides an introduction to the audit, describes the company's energy consumption and distribution systems, identifies potential energy savings, and provides recommendations. The audit found opportunities to improve electrical distribution, power factor, electric motor efficiency, boiler efficiency, insulation, and reduce steam and compressed air leaks. Implementing the recommendations could help lower SGC's energy costs and greenhouse gas emissions.
Copyright:
Attribution Non-Commercial (BY-NC)
Formati disponibili
Scarica in formato PDF, TXT o leggi online su Scribd
This document is an energy audit report submitted by NEC Consultants Private Limited to Shafi Gluco-Chem (Pvt.) Ltd. It provides an introduction to the audit, describes the company's energy consumption and distribution systems, identifies potential energy savings, and provides recommendations. The audit found opportunities to improve electrical distribution, power factor, electric motor efficiency, boiler efficiency, insulation, and reduce steam and compressed air leaks. Implementing the recommendations could help lower SGC's energy costs and greenhouse gas emissions.
Copyright:
Attribution Non-Commercial (BY-NC)
Formati disponibili
Scarica in formato PDF, TXT o leggi online su Scribd
Draft Report November 01, 2011 Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report Submitted to: Mr. Yasir Shafi Executive Director Sshafi Gluco-Chem (Pvt.) Ltd. Plot B 22-26 Hub Industrial Trading Estate Distt Lasbella, Hub, Balochistan 54000 Pakistan. Tel: (92-85) 3303-719-21 Fax: (92-85) 3303-952 NEC Consultants (Pvt.) Limited Principal House, Mezzanine Floor, Plot No. 39C & 41C 22nd Commercial Street Off: Khayaban-e-Ittehad Phase II Extension, DHA, Karachi Tel: (92 21) 3589 3341 43 Fax: (92 21) 3589 3340 E-mail: epsd@nec.com.pk Website: www.nec.com.pk Submitted by: For any clarification about this Report, please contact Mr. Ibad ur Rehman, Manager (Environmental Studies Division Southern Zone) in NEC Karachi office. Draft Report November 01, 2011 Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report Subject to Change after Review by SGC Management & NEC Quality Assurance. Not to be Used for any Official Purpose.
NEC Consultants (Pvt.) Ltd. i
List of Acronyms
Chapter 1: Introduction 1 - 1
1.0 Introduction 1 - 1 1.1 Objective of the Audit 1 - 1 1.2 Scope of Work 1 - 2 1.3 Audit Methodology 1 - 3 1.4 Energy Audit Team 1 - 4 1.5 Audit Gadgets 1 - 4 1.6 Limitations 1 - 5
Chapter 2: Energy Consumption and Distribution 2 - 1
2.1 Introduction of Industry 2 - 1 2.2 Process Description 2 - 1 2.3 Utilities 2 - 3 2.3.1 Energy Sources, Consumption and Distribution 2 - 3 2.3.2 Water Cooling System 2 - 8 2.3.3 Cooling Tower(s) 2 - 9 2.3.4 Boiler(s) 2 - 9 2.3.5 Air Compressor(s) 2 - 10
2.4 Monthly Utilities Consumption & Unit Utility Rate 2 -11 2.7 Existing Energy Management Initiatives 2 - 11 2.8 Current Energy Status of the SGC 2 - 13
Chapter 3: Energy Saving Potential 3 - 1
3.1 Electrical Energy Saving Potential 3 - 1 3.1.1 Electrical Distribution System (Cable Sizing) 3 - 1
3.2 Power Factor 3 - 3 3.2.1 Power Factor Improvement Plant at Self Generation 3 - 3 3.2.2 Power Factor Improvement Utilizing KESC Connection 3 - 3
3.3 Electric Motors 3 - 4 3.3.1 Oversized and Undersized Motors 3 - 4 3.3.2 Efficiency of Motors 3 - 5 3.3.3 Maintenance Concerns 3 - 5
ToC
TABLE OF CONTENT Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. ii 3.3.4 Voltage Unbalance 3 - 6 3.3.5 Current Unbalance 3 - 8 3.3.6 Lighting System 3 - 9 3.3.7 Monitoring and Evaluation System 3 - 10 3.3.8 Variable Frequency Drives (VFDs) 3 - 10 3.3.9 Rewinding of Motors 3 - 11 3.310 Transmission Losses 3 - 11 3.3.11 Sustainable/Renewable Energy Sources 3 - 12
4.1 Electrical Energy 4 - 1 4.1.1 Electrical Energy Sources 4 - 1 4.1.2 Transformers 4 - 1 4.1.3 Power Factor Improvement (PFI) Plants 4 - 1 4.1.4 Utilization of Diesel Generator 4 - 1 4.1.5 Utilization of KESC 4 - 2 4.1.6 Recommendation for Proper Distribution (Cable Sizing) 4 - 2 4.1.7 Proper Sized Motors 4 - 2 4.1.8 High Efficiency Motors 4 - 2 4.1.9 Preventive Maintenance 4 - 3 4.1.10 Voltage Unbalance 4 - 3 4.1.11 Current Unbalance 4 - 4 4.1.12 Lighting System 4 - 4 4.1.13 Monitoring and Evaluation 4 - 4 4.1.14 Installation of VFDs 4 - 4 4.1.15 Motor Consideration with VFDs 4 - 5 4.1.16 Use of Rewound Motors 4 - 5 4.1.17 Transmission Losses 4 - 6 4.1.18 Sustainable/Renewable Energy Sources 4 - 6 4.1.19 Solar PV Electricity Generating Panels 4 - 7 Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. iii 4.2 Thermal Energy 4 - 8 4.2.1 Monitoring & Evaluation 4 - 8 4.2.2 Feed Water Treatment 4 - 8 4.2.3 Blow down 4 - 9 4.2.4 Boiler(s) Efficiency 4 - 10 4.2.5 Combustion Efficiency Boiler(s) 4 - 10 4.2.6 Economizer 4 - 12 4.2.7 Steam Traps 4 - 12 4.2.8 Insulation of Pipes, Tanks and Boilers 4 - 12 4.2.9 Leakages 4 - 13 4.2.10 Cooling tower 4 - 14 4.2.11 Compressed Air System 4 - 14
List of Tables:
Table 2.1: Installed Capacity/Sanctioned Load 2 - 3 Table 2.2: Installed Capacity and Load Served by the Transformer 2 - 4 Table 2.3: Location and Capacity of Power Factor Improvement Plants 2 - 4 Table 2.4: Consumption Record for the Year 2010-2011, (Diesel Genset) 2 - 5 Table 2.5: Consumption Record of the Year 2010-2011, (KESC to Plant) 2 - 6 Tariff: TOD-B3 Table 2.6: Chiller Data 2 - 8 Table 2.7: Cooling Tower Data 2 - 9 Table 2.8: Boiler(s) Data 2 - 9 Table 2.9: Air Compressor Data 2 - 10 Table 2.10: Monthly Consumption of Utilities 2 - 11 Table 2.11: Unit Rate of Utilities 2 - 11 Table 2.12: Status of the SGC 2 - 13 Table 3.1: Electrical Cables Voltage Drop Calculation 3 - 1 Table 3.2: Findings of Low Power Factor Penalty 3 - 4 Table 3.3: Findings of Load on Electric Motors 3 - 4 Table 3.4: Top Causes of Failures in Electrical Distribution System 3 - 6 Table 3.5: Findings of Voltage Unbalance 3 - 7 Table 3.6: Current Unbalance 3 - 9 Table 3.7: Lighting Details 3 - 10 Table 3.8: VFDs Installed at SGC 3 - 11 Table 3.9: Transmission Losses 3 - 11 Table 3.10: List of Monitoring Equipment 3 - 12 Table 3.11: Steam Generator(s) Data 3 - 13 Table 3.12: Water Quality Results 3 - 14 Table 3.13: Minimum amount of Blow down Required 3 - 15 Table 3.14: Difference in Energy Lost Between Manual and Automatic Blow down 3 - 15 Table 3.15: Annual Losses due to Manual Blow down System 3 -16 Table 3.16: Boiler Efficiency 3 - 16 Table 3.17: Combustion Analysis Test Results 3 - 17 Table 3.18: Combustion Analysis Test Results (Direct Fired Burners) 3 - 17 Table 3.19: Annual Losses Due to Lack of Insulation of Steam Distribution Network 3 - 18 Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. iv Table 3.20: Annual Losses due to Lack of Proper Insulation of the Feedwater Network 3 - 19 Table 3.21: Annual Losses due to Lack of Proper Insulation of the Blowdown Network 3 - 20 Table 3.22: Location of Steam Leakages 3 - 20 Table 3.23: Annual Losses due to Steam Leakages 3 - 21 Table 3.24: Annual Losses due to Compressed air Leakages 3 - 22 Table 4.1: Transmission Losses and Saving Opportunities 4 - 6 Table 4.2: Solar Power Systems 4 - 7 Table 4.3: TDS Reduction vs. Savings 4 - 9 Table 4.4: Combustion Analysis Test Results (Initial) 4 - 11 Table 4.4: Combustion Analysis test Results after Adjusting Boiler Air Intake 4 - 11
List of Figures:
Figure 2.1: Process Flow Diagram 2 - 2 Figure 2.2: Consumption Pattern for the Year 2010-2011 (Diesel Genset) 2 - 5 Figure 2.3: Consumption Pattern for the Year 2010-2011, (KESC to Plant) 2 - 7 Tariff: TOD-B3 Figure 2.4: Electricity Rate (Rs. /kWh) for the Year 2010-2011, (KESC to Plant) 2 - 7 Tariff: TOD-B3 Figure 3.1: Effects of Voltage Variation on Electrical Motors 3 - 3 Figure 3.2: Effects of Voltage Unbalance on Electrical Motors 3 - 8 Figure 3.3: Lack of Insulation in Evaporator Section 3 - 19 Figure 3.4: Right Lack of Insulation of Boiler Accessories 3 - 19 Figure 3.5: Lack of Insulation of Feed water Network 3 - 19 Figure 4.1: Energy Saving Comparison of Electrical Motors 4 - 3 Figure 4.2: Energy Saving with VFD by Reducing RPM 4 - 5
NEC Consultants (Pvt.) Ltd. v
CFL Compact Fluorescent Lamps CO Carbon Monoxide CO 2 Carbon Dioxide GJ Giga Joules HITE Hub Industrial Trading Estate HPL Metal Halide Lamps KESC Karachi Electric Supply Corporation kW Kilowatt kWh Kilowatt hour LIEDA Lasbela Industrial Estates Development Authority MCC Motor Control Center MW Megawatt NEC NEC Consultants (Pvt.) Ltd. PEPCO Pakistan Electric Power Company PKR Pakistani Rupees PPM Parts Per Million SGC Shafi Gluco Chem (Pvt.) Ltd. TDS Total Dissolved Solids VFD Variable Frequency Drives
LoA
LIST OF ACRONYMS
NEC Consultants (Pvt.) Ltd. 1 - 1
1.0 Introduction
Energy is the most important sources for growth of a country. Unfortunately, Pakistan has been facing serious energy crisis since 2007. Despite of some strong economic growth during the past decades and consequent rising demand of energy, no appropriate steps have been taken to increase the energy supplies consistent with the demand. Now, the demand exceeds supply and hence load-shedding is a common phenomenon through frequent power shut downs. According to Pakistan Electric Power Company (PEPCO), the current power generation of Pakistan is 12,175 MW of electricity per day, and the present demand is 18,160 MW per day. Thus, there is a shortfall of about 5,985 MW per day 1 . This shortage is badly affecting industry, commerce and daily life of the people.
The industrial sector of Pakistan is badly affected with the prevailing energy predicament, destroying about 50 percent of the total industrial sector. The only survival for the Pakistani industries is to act progressively by adopting a comprehensive strategy encompassing assessment of the current energy performance, detailed monitoring of the energy consumption patterns and ultimately the conservation of the valuable resource by adopting best available practices and employing energy efficient technologies.
Shafi Gluco Chem (Pvt.) Ltd. (hereinafter referred as SGC) being the judicious and progressive industry has hired NEC Consultants (Pvt.) Ltd. (NEC) to carryout the Energy Audit of its facility located at Hub Industrial Trading Estate (HITE) for identification of potential energy conservation areas and providing the recommendations on energy optimization and cost savings.
The field activities to collect the necessary audit data of SGC were carried out on 3 rd , 5 th . 7 th and 17 th of October, 2011. This data is then analyzed and a report of key findings and recommendations is prepared.
1.1 Objective of the Audit
The overall objective of the energy audit is to review the existing energy consumption practices in the industry, identify the key potential energy efficiency and conservation areas and provide detailed recommendations on energy optimization and cost savings.
1 http://pepco.gov.pk/pow_situation.php CHAPTER 1
INTRODUCTION Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 1 - 2 1.2 Scope of Work
The overall scope of the audit is as follows:
Conduct a general survey of the plant to review the major energy conversion installations, electric motors and machines, and thermal production processes; Collect field data to examine existing energy consumption practices and identify potential energy efficiency and conservation areas; Review alternate possible technologies and assess their suitability under local conditions; Identify and finalize the scope of work for detailed investigations; Investigate the selected technologies in detail and evaluate the saving potentials; Prepare the energy audit report of key findings and recommendations which will serve as implementation guideline to the plants management; and Present the main findings and recommendations to the industry management in a final oral presentation.
The aforementioned scope of work covers following aspects of energy conservation in particular;
Thermal Aspects:
Boiler(s) and their Accessories; Steam Distribution Network; Boiler Blowdown Network; Condensate Network; Compressors and their Accessories; Compressed Air Distribution Network; Combustion Analysis of Boiler(s) and Direct Fired Systems; House Keeping Issues pertaining to; o Insulation o Leakages Cooling Towers and their Accessories; Cooling Water Network.
Electrical Aspects:
Electricity Generation/Consumption Performance; Electricity Distribution Network; Motor Performance; and Quality of Electric Power
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 1 - 3 1.3 Audit Methodology
Audit methodology comprises of the following three phases:
1. Set up Phase
a. Kick off Meeting:
The kick off meeting was held on September 06, 2011 to discuss the scope of the audit, review the schedule of activities and clarify the roles and responsibilities of the NEC and the SGCs team deputed with the NECs energy experts. A checklist of some basic information, mandatory to proceed with the detailed energy audit was also provided to the SGCs team at the end of the meeting session.
b. Reconnaissance Visit:
The NEC audit team along with the SGCs team conducted reconnaissance visit to the industry to gain familiarity with the product manufacturing practices at the SGC, associated machinery and utilities. The visit facilitated the audit team to device the better work plan for the detailed investigation phase. The primary information about the unit was collected in accordance with the data acquisition plan which comprised of a checklists to collect all the concerned physical, technical and energy consumption data of the industry.
2. Detailed Investigation Phase
a. Data Collection:
The audit team reviewed the data collected in the first visits and identified additional data required. In this step, detailed information about the industry is collected in accordance with the assessment checklist, as discussed in the preceding step. Initially, the data available with the industry is collected and reviewed. Later, the assessment team conducts detailed field visits in the industry. Both qualitative and quantitative analysis is performed in order to acquire energy relevant data from the industry.
b. Data Analysis:
The audit data was examined to identify energy saving potential in the unit. Measures to be analyzed in more detail were decided upon in close co- operation with the SGCs team. All measures were analyzed with regard to their financial benefit and technical feasibility, starting with measures of short pay-back periods to those having a mid to long-term payback period.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 1 - 4 3. Concluding Phase
a. Preliminary Audit Report of Key Findings & Recommendations:
Initially, a draft energy audit report encompasses key audit findings and recommendations along with detailed action plan is prepared and submitted to the SGCs management for their review and comments.
b. Final Audit Report and Presentation:
After incorporating the comments from the SGC on the draft report and action plan, a final report and action plan will be prepared and presented to the SGC management.
1.4 Energy Audit Team
The assessment team comprises of the following professionals;
Mr. Faisal Aziz, Sr. Environmental Engineer/ Team Leader Syed Mustafa Saeed, Mechanical Engineer Mr. Faisal Shahzad, Electrical Engineer
1.5 Audit Gadgets
Following gadgets were used during the audit for acquisition of the primary energy related data;
Services performed by the consultant are conducted in a manner consistent with that level of care and skill ordinarily exercised by members of the engineering and consulting profession. This report does not exhaustively cover an investigation of all possible energy conservation aspects and circumstances that may exist.
In evaluating the subject site, consultants relied in good faith on information provided by the SGC, management or employees. The Consultants assume that the information provided is factual, accurate, and accepts no responsibility for any deficiency, misstatements, or inaccuracies contained in this report as a result of omission or misrepresentation of any person interviewed or contacted.
It should be recognized that the passage of time may affect the information provided in this report. Specific circumstances and conditions of a site can change. Opinions relating to the conditions are based upon information that existed at the time the conclusions were formulated.
NEC Consultants (Pvt.) Ltd. 2 - 1
This chapter presents the detail of the different forms of the energy consumed and distributed in the facility. Existing energy management practices in the industry and current status of the SGC with regards to energy management are also briefly discussed here.
2.1 Introduction of Industry
Shafi Gluco-Chem (Pvt.) Ltd. (SGC) is the most highly equipped, state-of-the art Starch based Sweeteners production facility, located in Hub Industrial & Trading State, Baluchistan. SGC makes a wide variety of rice syrups and proteins, all made enzymatically from 100% whole rice. The raw material includes white rice, brown rice and organic rice. SGC operates about 300 days a year and has a total workforce of about 200 workers, working in 2 shifts of 12 hrs each. It started its production in the year 2003 and having monthly capacity of producing 15,400 MT glucose syrup and 3,000 MT proteins.
2.2 Process Description
This section briefly describes the production process of glucose syrup at SGC. The rice flour was obtained from broken rice by using a dry milling method. The glucose produced from the slurry of various raw materials by treating with enzymes. The treated slurry is then subjected to filtration process, where rice protein is separated from the slurry by using plate type filter press. Rice proteins are collected as residue in the shape of filtered cakes, whereas the filtrate (glucose solution) is decolourised, desalted in an ion exchanger column. The dilute glucose syrup is finally evaporated under vacuum to raise the solids concentration. The concentrated syrup is centrifuged in the disc type centrifuge and the precipitate is dried by spray drying. The Figure 2.1, presents the process flow diagram of the production processes at SGC.
CHAPTER 2
ENERGY CONSUMPTION AND DISTRIBUTION Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 2
Figure 2.1: Process Flow Diagram
Source: Visual observation acquired during the field visit, 2011
Rice Screening Cleaning / Sorting
Milling
Storage
Slurry Preparation Filtration (Plate Type Filter Press)
Rice Protein Treatment/Dispatch
Enzyme Treatment
Purification (Ion-Exchanger)
Evaporation
Glucose Syrup Filling & Dispatch Centrifuge (Disc Type Centrifuge)
Major utilities at SGC include gas, electricity, steam and compressed air. The brief information on the utilities employed at SGC is as follow;
Steam Generator SGC has installed two fire-tube type boilers for the generation of steam, each have the capacity of generating 6 tons of steam per hour. The steam is utilised mainly in evaporators, conversion, heating feedwater and for drum washing.
Cooling Towers SGC has installed two induced draught cooling towers having capacities of 1,717 and 1,750 gpm, respectively. The cooling water from the cooling tower is used to lower the temperature of heat exchangers installed in the process area.
Compressors Two air compressors were installed to produce compressed air that is consumed in the manufacturing process either directly and/or to run the pneumatic equipment.
Chillers There was one reciprocating chiller installed at SGC, to provide chilled water that was utilized in the cold room for air conditioning. The chiller was not in operation during the energy audit.
Generators SGC uses LIEDA (KESC) as prime source of the electricity; In addition, it also has one 1,500 kVA diesel genset as the standby source.
2.3.1 Energy Sources, Consumption and Distribution
Electricity Sources
In order to meet the electric power requirements at SGC there is one connection taken from LIEDA (KESC) and one diesel generator-set. The connection from KESC is used as prime source of electric power while the diesel genset is reserved as a stand-by source. Table 2.1 below shows the installed capacity/sanctioned load at SGC:
Table 2.1 Installed Capacity/Sanctioned Load
Source Installed Capacity/Sanctioned Load LIEDA (KESC) 1,100 kW , 11 kV Diesel Generator No. 1 1,500 kVA , 400 V Source: The management of SGC, 2011
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 4 Distribution and Consumption
Transformers
The Diesel Generator installed at SGC generates electricity at 400 volts and supplies electric power directly to the connected load after passing through protecting equipments. Therefore no transformer is used with the diesel generator. However the connection taken from KESC is at 11,000 V; therefore a transformer is used to step this voltage down to 400 V. Maintenance of this transformer is the responsibility of SGC. Details of the installed transformer are given below:
Table 2.2 Installed Capacity and Load Served by the Transformer
Description Load Description Aprox. Load 1,250 kVA, 11 kV / 415 V From KESC to the Factory 1,100 kW Source: The management of SGC, 2011
Power Factor Improvement Plants
High power factor is the basic requirement of a well organised electrical distribution network. In order to improve power factor up to the desired value, capacitor banks have to be installed at different locations of the plant.
Capacitor banks are installed at SGC to improve the power factor. These capacitor banks operate only on the KESC connection. Automatic operation is used with these capacitors that maintain the required power factor by rearranging the number of capacitors according to the required compensation. Following table shows the location and arrangement of the capacitor banks:
Table 2.3 Location and Capacity of Power Factor Improvement Plants
Location Description Total Main LT Panel (LT Control Room) 9 steps of 50 kVAr 1 step of 25 kVAr
1 step of 25 kVAr 475 kVAr Total 475 kVAr Source: The management of SGC, 2011
Self Generation/Consumption Pattern
Diesel genset at SGC is operated only when electric power from KESC is not available. The parameters recorded are time of operation (Hrs), electrical energy units (kWh), electrical load (kW), AC frequency (Hz), voltage (V) and current (A). The data provided during and after the field visit is analysed and the monthly Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 5 generation/consumption pattern for diesel genset is presented here as Table 2.4. The graphical representation of the consumption pattern is presented as Figure 2.2.
Table 2.4 Consumption Record for the Year 2010-2011 (Diesel Genset)
Month Electrical Units (kWh/month) Oct-10 32,680 Nov-10 11,300 Dec-10 60 Jan-11 9,680 Feb-11 6,980 Mar-11 1,300 Apr-11 24,000 May-11 13,840 Jun-11 2,920 Jul-11 41,220 Aug-11 8,720 Sep-11 27,420 Total 180,120 Source: The base data is provided by the management of SGC, 2011
Figure 2.2: Consumption Pattern for the Year 2010-2011 (Diesel Genset)
Source: The base data is provided by the management of SGC, 2011 Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 6 The diesel consumption for power generation is not recorded accurately and data provided in this regard produced unseen results of unit price in terms of Rs. /kWh. However during the field survey, discussion with technical staff and data analysis yield that the average unit price is 33 Rs. /kWh; which is slightly higher than the unit price observed typically in the industries.
Consumption Pattern Utilizing KESC Connection
The prime source of electric power at SGC is KESC. SGC had sanctioned a load of 1,100 kW from KESC for the plant.
The monthly consumption pattern for the plant is presented as Table 2.5 and the graphical representation of the consumption pattern is presented as Figure 2.3.
Table 2.5 Consumption Record of the Year 2010-2011 (KESC to Plant) Tariff: TOD-B3
Month Off-Peak Units (kWh) Peak Units (kWh) Total Units (kWh) Amount Rs. Aug-10 191,487 23,987 215,474 2,060,390 Sep-10 238,196 32,297 270,493 2,618,335 Oct-10 231,124 30,677 261,801 2,932,699 Nov-10 201,012 26,890 227,902 2,376,336 Dec-10 237,244 30,779 268,023 3,003,225 Jan-11 254,092 31,360 285,452 2,626,044 Feb-11 172,673 23,161 195,834 1,844,172 Mar-11 227,482 29,286 256,768 2,424,961 Apr-11 240,970 30,910 271,880 2,515,277 May-11 88,233 10,764 98,997 1,097,670 Jun-11 405,346 80,524 485,870 4,598,120 Jul-11 247,048 47,610 294,658 2,924,220 Aug-11 150,250 33,510 183,760 1,912,829 Total 3,316,912 32,934,278 Source: The base data is provided by the management of SGC, 2011
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 7 Figure 2.3: Consumption Pattern for the Year 2010-2011 (KESC to Plant) Tariff: TOD-B3
Source: The base data is provided by the management of SGC, 2011
The above graph shows the contribution of off-peak units and peak units to the total consumption of the electrical energy. Height of each column represents the total electrical energy consumed per month (kWh/Month). Tariff for peak units is almost double as that of off-peak units; therefore peak units consumption should be maintained at minimum possible level. Following graph shows the variation of unit price (Rs. /kWh) against total unit consumption (kWh/month).
Figure 2.4: Electricity Rate (Rs. /kWh) for the Year 2010-2011 (KESC to Plant) Tariff: TOD-B3
Source: The base data is provided by the management of SGC, 2011
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 8 The variation in unit price (Rs. /kWh) is mainly affected by the maximum demand during the month, operating power factor, power consumption during peak and off- peak hours and the electricity tariff. The average unit price from the graph comes out to be 10.02 Rs. /kWh.
2.3.2 Water Cooling System
There was one reciprocating chiller installed at SGC, to provide chilled water that was utilized in the cold room for air conditioning. The chiller was not in operation during the energy audit. However, the manufacturers details of chiller are presented in the table below for reference. Table 2.6 below, shows running data of the chiller(s) installed at SGC.
Table 2.6 Chiller Data
Description Chiller#1 Unit Make YORK --- Chiller Type Reciprocating --- Serial Number L3332-F85 --- Source of Energy Electrical --- Motor Power 50 HP Chilled water Inlet temperature 25 C Chilled water outlet temperature 20 C Chilled water Inlet Pressure 2 bar Chilled water outlet pressure 1 bar Cooling water inlet Temperature 30 C Cooling water outlet Temperature 40 C Cooling water Inlet Pressure 2 bar Cooling water outlet pressure 1 bar Operating Hours Not in Running
Source: Data provided by the management of SGC, 2011
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 9 2.3.3 Cooling Tower(s)
SGC has installed two induced draught cooling towers having capacities of 1,717 and 1,750 gpm, respectively. The cooling water from the cooling tower is used to lower the temperature of heat exchangers installed in the process area. Table 2.7 shows running data of the cooling towers present at SGC.
Table 2.7 Cooling Tower Data
Description C.Tower # 1 C.Tower # 2 Unit Make KARGAR PROTEC --- Type Bottle Bottle --- Capacity(Ton) 1717 1750 gpm Water Flow --- --- gpm Air Flow 91,030 97,000 cfm Water inlet temperature 44 37.2 C Water outlet temperature 33 31.6 C Air inlet temperature --- --- C Air outlet temperature --- --- C Operating Hours 24 Standby hr/day Fan motor Power 15 15 HP Chemical(s) used Scgon 345 Scgon 345 --- Biogon 945 Biogon 945 --- Source: Data provided by the management of SGC, 2011
2.3.4 Boiler(s)
Some processes in SGC depend on thermal energy; this thermal energy was supplied by steam. To cater for the amount of steam required, SGC has installed two boilers. Table 2.8, shows running data of the boiler(s) present at SGC.
Table 2.8 Boiler(s) Data
Description Boiler # 1 Boiler # 2 Unit Make LOOS 155 LOOS 156 --- Model 1985 1985 --- Serial No. 48409 48410 --- Type Fire Tube Fire Tube --- Heating Surface Area 125 125 m 3
Steam Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 10 Description Boiler # 1 Boiler # 2 Unit o Capacity 6 6 ton/hr o Design Pressure 13 13 Psi o Working Pressure 10 10 Psi o Temperature 180 180 C Feed Water Temperature 95 95 C Daily Running Hours 24 24 Hr Days of Operation 300 300 Days Source: Data provided by the management of SGC, 2011
2.3.5 Air Compressor(s)
At SGC, three air compressors are currently being used for supplying compressed air to different equipments. The manufacturers details of these compressors are given in Table 2.9 below. Table 2.9 Air Compressor Data
Description Comp # 1 Comp # 2 Comp # 3 Units Make GA-22 GA-30 GA-30 --- Status Standby Running/Standby Running --- Cooling system Air Cooled Air Cooled Air Cooled --- Type Screw Screw Screw --- Free Air Delivery 76.1 76.7 81 L/s Maximum Pressure 11 7.5 7.5 Bar Working Pressure Load 3 4 5 Bar Working Pressure Unload 6 6 6 Bar Motor (kW) 22 30 30 kW Hours of Operation 24 24 24 Per day Source: Data provided by the management of SGC, 2011
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 11 2.4 Monthly Utilities Consumption & Unit Utility Rate
The monthly utilities consumption & Unit utility rates of SGC are presented in Table 2.10 and Table 2.11, respectively.
Table 2.10 Monthly Consumption of Utilities
S. No. Utilities Month Consumption 1 Gas 5,840,375 m 3 (Boilers) 2 Steam Not monitored 3 Water 3,261 m 3 (Boilers) 4 Electricity 270,157 kWh Source: Data provided by the management of SGC, 2011, calculations based on 300 days per year.
Table 2.11 Unit Rate of Utilities
S. No. Utilities Unit Rate 1 Gas Rs. 382.37 / MMBtu 2 Steam Not monitored 3 Water Rs._____/1, 000 gal (LIEDA) 4 Electricity Rs. 10.02/kWh (KESC) Rs. 33/kWh (Diesel Genset) Source: Data provided by the management of SGC, 2011
2.7 Existing Energy Management Initiatives
SGC, being an energy conscious organization progressively & pro-actively working in the field of resource conservation. Some of the SGC energy interventions in this regards are listed below:
Safety Gauges Pressure and temperature gauges were installed on the utility equipment and their respective distribution network.
Insulation Adequate insulation was used to restrict heat loss from hot sources and heat gain to cold sources.
Boiler Feed Water Control A dedicated softener plant was installed to maintain the boiler feed water quality.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 12 Economizer An economizer was installed on the boiler stack(s) to recover heat from flue gases and was used to increase the temperature of feed water.
Condensate network A condensate loop was installed for the recovery of condensate water.
Natural Gas Flow meter (Boiler) A gas flow meter was installed to quantify the amount of natural gas consumed by the boiler(s).
Water Flow meter (Feedwater) A water flow meter was installed to quantify the amount of water consumed by the boiler(s).
Variable Frequency Drives (VFD) SGC has already installed VFDs on different motors. A total of 8 VFDs are installed.
Power Factor Improvement Capacitor banks are installed to improve the power factor. The Power Factor observed at SGC ranges from 0.90 to 0.94 which is optimal for distribution system.
Voltage Drop Voltage was measured at Distribution Boards, motor panels and was found satisfactory. No issue regarding voltage drop was observed during the field visit.
Load Management The load is adequately managed at SGC by utilizing available resources.
Optimal Motor Sizes No oversized or undersized motor was observed at SGC during field visit.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 2 - 13 2.8 Current Energy Status of the SGC
The Table 2.12 below depicts the current Energy Status of SGC.
Table 2.12 Status of the SGC
S. No. Energy Indicators Energy Status Good Average Low 1 Boiler Feed Water Control - - 2 Safety Gauges - - 3 Condensate Network - - 4 Steam Traps - - 5 Insulation of Hot Surfaces - - 6 Economizer at Steam Generator - - 7 Steam Flow Monitoring System - - 8 Gas Flow Monitoring System - - 9 Feed water Flow Monitoring System - - 10 Compressed Air Monitoring System - - 11 Stack Monitoring System - - 12 Power Factor - - 13 Motor Loading / Sizing - - 14 Voltage - - 15 Variable Frequency Drives (VFDs) - - 16 Energy Efficient Motors - - 17 Energy Efficient Lights - - 18 Load Management - - 19 Data Management - - Legend: Energy Status Good = No gap was observed, Average = Little gaps were observed, Low = Nothing has being done in this regards. Note= The evaluation of Energy Status of the SGC presented above is based on observation taken during the field visits and perception of the assessor related to the specific field of interest, hence the opinion related to specific area might vary from person-to-person. The key objective of the evaluation is to present current picture of energy status of the industry in a snap shot and to initiate the improvement in these areas. Detailed assessment of abovementioned concerns are presented in Chapter-3 of this report.
NEC Consultants (Pvt.) Ltd. 3 - 1
The chapter elucidates the energy saving opportunities observed during the field visits. The core emphasis is given to the excessive energy consumption, resulting from diversified resource consumption at the plant. More specifically, resource conservation potential and energy improvement areas are discussed in detail in the following sections.
3.1 Electrical Energy Saving Potential
3.1.1 Electrical Distribution System (Cable Sizing)
Voltage measurement at MCCs and panels is done during the field visit and positive results are observed. The voltage drop should not exceed 2.5% of the nominal voltage at the designed current. As the voltage of the distribution system is 400V, the cables having voltage drop less than 2.5 % or 10V are considered to be properly selected. The calculated voltage drop of cables for which the data was provided is presented in the Table 3.1.
Table 3.1 Electrical Cables Voltage Drop Calculation
S. No. Load Description Full Load Current (A) Size (mm 2 ) Length (m) Calculate d V. D (V) Percent V.D 1 LT Panel to Spray Dryer 206 1 x 12 0 59 4.1 1.0 2 LT Panel to Rice Packing 32 1 x 16 107 8.0 2.0 3 LT Panel to Rice Flour 54 1 x 25 100 8.7 2.2 4 LT Panel to Boiler 65 1 x 12 0 40 0.9 0.2 5 LT Panel to Work Shop 36 1 x 50 26 0.8 0.2 6 LT Panel to Admin Offices 36 1 x 70 50 1.0 0.3 7 LT Panel to Cooling Tower 135 1 x 70 49 3.8 0.9 8 LT Panel to Silo 72 1 x 95 58 1.8 0.4 9 LT Panel to Compressor 126 1 x 70 98 7.1 1.8 10 LT to Raw Water Pump 3 54 1 x 35 107 6.4 1.6 11 LT Panel to Chiller 108 1 x 50 17 1.5 0.4 12 LT Panel to Panel N 54 1 x 25 85 7.4 1.8 13 LT Panel to Dry Feed 141 1 x 12 0 37 1.8 0.4 14 Ventilator 4.3.1 10 1 x 3 49 7.3 1.8 15 Ventilator 4.4.1 27 1 x 16 46 2.9 0.7 CHAPTER 3
ENERGY SAVING POTENTIAL Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 2 S. No. Load Description Full Load Current (A) Size (mm 2 ) Length (m) Calculate d V. D (V) Percent V.D 16 Hammer Mill 289 1 x 70 37 6.1 1.5 17 Ventilator 7.3.2 33 1 x 16 46 3.5 0.9 18 Steam Blower 20 1 x 6 9 1.1 0.3 19 Displacement Pump 19.2 10 1 x 4 14 1.3 0.3 20 Displacement Pump 19.3 10 1 x 4 14 1.3 0.3 21 Centrifugal Pump 50 20 1 x 6 39 4.8 1.2 22 Centrifugal Pump 63.1 20 1 x 6 38 4.7 1.2 23 Centrifugal Pump 63.2 20 1 x 6 40 4.9 1.2 24 Centrifugal Pump 69.1 20 1 x 6 41 5.0 1.3 25 Centrifugal Pump 82 14 1 x 10 46 2.3 0.6 26 Centrifugal Pump 111.4 14 1 x 10 46 2.3 0.6 27 Centrifugal Pump 29 10 1 x 2 27 6.4 1.6 28 Vacuum Pump 47.7 27 1 x 16 15 0.9 0.2 29 Vacuum Pump 47.8 33 1 x 16 15 1.2 0.3 30 Vacuum Pump 47.1 40 1 x 16 15 1.4 0.3 31 Centrifugal Pump 112.1 90 1 x 25 6 0.9 0.2 32 Centrifugal Pump 112.2 67 1 x 25 8 0.9 0.2 33 Centrifugal Pump 112.3 90 1 x 16 8 1.7 0.4 34 Centrifugal Pump 111.1.10 54 1 x 10 23 4.6 1.1 35 Condensate Pump 100.17 14 1 x 3 21 4.3 1.1 36 Feed water Pump CR4 10 1 x 3 5 0.7 0.2 37 Blower 1 135 1 x 25 7 1.5 0.4 38 Blower 2 27 1 x 4 5 1.2 0.3 39 Atomizer 14 1 x 3 9 1.8 0.5 40 Blower 3 20 1 x 6 5 0.6 0.2 41 Mill Motor 198 1 x 70 5 0.6 0.1 42 Blower 45 1 x 6 20 5.6 1.4 43 China Grinder 27 1 x 6 5 0.8 0.2 Source: The base data is provided by the management of SGC, 2011
In the above table, it is clearly indicated that voltage drop varies from 0.1% to 2.2%, which is fairly low as compared to the standard voltage drop of 2.5%.
It has been assessed that voltage drop at different motors could cause change in motor efficiency, power factor, running current and temperature of motor. If the motor terminal voltage is below the rated voltage it will draw more current than the rated current which will ultimately result in the overheating of the motor winding and thus reduces life of the motor.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 3 Figure 3.1, below illustrates the effects of voltage variations on motors in terms of efficiency, power factor, torque and current of motors.
Figure 3.1: Effects of Voltage Variation on Electrical Motors
Source: www.motorsanddrives.com
3.2 Power Factor
3.2.1 Power Factor Improvement Plant at Self Generation
As discussed in the Section 2.3.1 earlier, that Capacitor Banks are installed at SGC, but these capacitors operate only for KESC connection. No power factor improvement unit is used with diesel genset.
3.2.2 Power Factor Improvement Utilizing KESC Connection
Power factor improvement plant installed at SGC operates only for KESC connection. Utility bills provided during the field visit are analyzed and no power factor penalty is observed. Table 3.2, provided below, indicates the power factor and the penalty imposed for the year 2010-2011.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 4 Table 3.2 Findings of Low Power Factor Penalty
There are more than 50 motors installed at SGC. The running load of 21 potential motors is measured during the field visit. The result of running load is presented in the Table 3.3, below.
Table 3.3 Findings of Load on Electric Motors
S. No. Motor Description Volt (V) Current (A) P. F Meas. Power (kW) Rated Power (kW) Utilization % 1 Hammer Mill 395 185 0.8 5 107.6 160 67 2 Cooling Tower Pump 2 387 39 0.8 6 22.5 37 61 3 Cooling Tower Pump 3 391 44 0.8 5 25.3 37 68 4 Ventilator Mill 1 396 23 0.8 4 13.3 18.5 72 5 Ventilator Mill 2 394 18 0.8 5 10.4 15 70 6 Vacuum Pump 1 395 23 0.9 8 15.4 15 103 7 Vacuum Pump 2 395 23 0.9 6 15.1 18.5 82 8 Spray Dryer Fan 389 118 0.8 6 68.4 75 91 9 Dry Feed Blower 402 26 0.8 7 15.7 25 63 10 Raw Water Pump 394 37 0.8 9 22.5 29.8 75 Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 5 S. No. Motor Description Volt (V) Current (A) P. F Meas. Power (kW) Rated Power (kW) Utilization % 11 Steam Blower 388 14 0.8 6 8.1 15 54 12 Cooling Tower Fan 388 11 0.8 5 6.3 11 57 13 Septic Tank Pump 387 14 0.8 8 8.3 11 75 14 Feed Water Pump 385 11 0.8 8 6.5 7.5 86 15 Blower Fan Boiler 1 389 14 0.8 4 7.9 18 44 16 Blower Fan Boiler 2 385 20 0.8 6 11.5 18 64 17 Condensate Pump 1 387 7 0.8 6 4.0 7.5 54 18 Condensate Pump 2 385 8 0.8 4 4.5 11 41 19 Pump 9 398 10 0.9 0 6.2 11 56 20 Compressor 1 393 56 0.8 5 32.4 30 108 21 Compressor 2 396 49 0.8 6 28.9 30 96 Source: The motor loading parameters measured during the field visit, 2011 (Digital Clamp on Meter, Model: PS 6601)
Due to the variation of load on motors during 24 hours the over/under sized motors could not be identified on the spot. However special attention should be given to the values that are made bold under utilization column and loading on respective motors must be monitored carefully. If these motors continuously operate at or above 90% load then these motors must be replaced with higher rating motors. If overloading occurs for short period of time then it will not affect motor performance as every motor is designed to operate above 100% load for shorter interval.
3.3.2 Efficiency of Motors
Motor efficiency is the ratio of mechanical power output to the electrical power input and usually expressed as a percentage. Considerable variation exists between the performance of standard and energy-efficient motors. There are three classes of motors based on the efficiency. The highest efficiency level has been achieved by some of the leading manufacturers. Improved design, high quality materials, and optimized manufacturing techniques enabled energy-efficient motors to accomplish more work per unit of electricity consumed.
Highest efficiency of a motor is achieved at 80-85% of its rated loading. Table 3.3 represents the utilization of the assessed motors. In order to achieve the highest efficiency motor utilization should be limited to 80-85%, which could be achieved by employing properly sized motors for which regular monitoring and inspection of motors is required.
3.3.3 Maintenance Concerns
At SGC no maintenance issues are noticed during the discussion with the technical staff. SGC has a proper maintenance program for machineries/equipments. Maintenance of electrical machines is done regularly. Almost all machines are opened and checked physically and electrically, which includes check for dirt and Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 6 moisture, winding heating, loose connections, transformer oil and silica gel inspection, tightening and cleaning of the electrical connections, and bearing lubrication. If any unusual object is observed, corrective steps are taken immediately.
However electrical loads normally cycle between high and low demand; thus the thermal expansion and contraction cause connections to loosen. Electrical panels that are never cleaned, accumulate dust and dirt that deposit on these connections. The loose and dirty connections provide high resistance paths that are directly responsible for more than 30 percent of electrical failures. Another 17 percent of electrical failures are attributed to live electrical components being exposed to moisture. Table 3.4 given below, mentions the rate of failure by different causes:
Table 3.4 Top Causes of Failures in Electrical Distribution System
Cause Failure Rate Loose Connections / Parts 30.3% Moisture 17.4% Line Disturbance (other than lightning) 10.4% Defective / Inadequate Insulation 9.9% Lightning 8.1% Foreign Objects / Short Circuiting 7.3% Collision 3.9% Overloading / Inadequate Capacity 2.4% Accumulation of Dust & Dirt 2.2% All other causes 8.1% Source: http://powerhawke.com/wp-content/uploads/2011/02/PowerHawke-Brochure.pdf
3.3.4 Voltage Unbalance
Voltages unbalance occurs in a three-phase power system when voltages of all the three phases are not equal. Voltage unbalance exists in every three-phase system, but the allowable limit is 1% (NEMA MGI). Beyond this limit voltage unbalance causes larger current unbalance as a result motor/equipment operating temperature increases. There are numerous causes of voltage unbalance, some of them are:
Large and/or unequal single-phase loads (for example, arc furnaces, heater, welders, and so on). Faulty power factor correction capacitor banks. Open delta or wye transformers. Phase to phase loads this occurs with some equipment that require only single- phase but at line to line voltage (for example, 415 V welders).
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 7 During the field visit three phase voltages are measured at different places and the result of voltage unbalance is presented in the Table 3.5, below.
From the above table it is clear that percentage voltage unbalance at SGC is less than 1 %.
Resistive loads are relatively unaffected by voltage unbalance. However the most apparent effect of voltage unbalance is reduction in motor efficiency, performance and life. It causes increase in current unbalance well in excess of voltage unbalance, which causes additional heating losses. Motor may also become noisy because of torque and speed variations caused by voltage unbalance and the motors will have less effective torque and speed than normal. Figure 3.2 shows the standard de- rating of motors based on percentage voltage unbalance.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 8 Figure 3.2: Effects of Voltage Unbalance on Electrical Motors
Current unbalance exists when the currents in all phases of a three-phase power system are not equal. There are two main causes of current unbalance.
Motor Related:
It includes Unbalanced number of turns in the windings Uneven air gap
Power System Related:
Includes voltage unbalance Harmonics
Voltage unbalance produces larger current unbalance. The ratio used for this purpose is close to 1:8. Large current unbalance causes shortening of motor life, decrease in its efficiency. The limit for current unbalance is usually considered to be 10%.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 9 Table 3.6 Current Unbalance
A simple test, known as rotating the phases, is performed to determine if current unbalance is related to motor or power system. According to this method, take current readings at phase A, B and C. Now at the output of the motor starter, remove all phase wires and then connect phase A to motor conductor 1, phase B to motor conductor 2, and phase C to motor conductor 3, so that the motor rotation remains same. Now measure the current readings again. If the high current moves with the motor conductor then unbalance is due to the motor. If it stays with the appropriate phase of the starter then it is due to power system.
3.3.6 Lighting System
Tube lights, compact fluorescent lamps (CFLs), search lights and high pressure lamps (MHLs) are in use at SGC for illumination purposes. These luminaries can be replaced with energy efficient luminaries. Table 3.7 show the detail of installed lighting system: Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 10 Table 3.7 Lighting Details
Type Watts Qty. Tube Lights 40 W 199 Energy Savers 65 W 92 High Pressure Mercury Lamps 250 W 18 Search Lights 400 W 10 250 W 2 Total Lamps 321 Source: The base data is provided by the management of SGC, 2011
3.3.7 Monitoring and Evaluation System
At SGC, the electrical load at diesel generator is monitored and tabulated on hourly basis at the control room. The fuel consumption of the generator is not recorded carefully. The observed parameters of genset are voltage, current, time of operation, electrical energy (kWh), and frequency, rpm etc. The electricity bills are also checked and electricity consumption (kWh/month) is verified.
3.3.8 Variable Frequency Drives (VFDs)
VFDs belong to a group of equipment called adjustable speed drives or variable speed drives. The operating speed of a motor connected to a VFD can be made variable by simply changing the frequency of the motors supply voltage. This allows continuous process speed control.
Motor-driven systems are often designed to handle peak loads that have a safety factor. This often leads to energy inefficiency in systems that operate for extended periods at reduced load. The ability to adjust motor speed enables closer matching of motor output to load and often results in energy savings. Hence installation of variable frequency drive (VFD) to a motor-driven system can offer potential energy savings in a system in which the load vary with time.
At SGC a total of eight (8) VFDs are installed in the manufacturing plant at different motors. The data provided for the installed VFDs is tabulated in Table 3.8.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 11 Table 3.8 VFDs Installed at SGC
S. No. Motor Description VFD Rating (kW) Motor Rating (kW) Qty. Distance b/w Motor & VFD (m) 1 Atomizer 7.5 7.5 1 10 2 Atomizer 1.5 1.5 1 3 3 Conveyer 4 4 1 10 4 Pump 12.1 3 3 1 5 5 Pump 12.2 3 3 1 5 6 Rice Mill 15 15 1 10 7 Feeder 0.75 0.75 1 10 8 Grader 0.75 0.75 1 10 Source: The base data is provided by the management of SGC, 2011
3.3.9 Rewinding of Motors
Motor efficiency and losses vary considerably after rewinding. Even if the rewound motors are restored to their original condition with proper stripping and rewinding, losses are typically higher in rewound motors. At SGC, use of rewound motors is in practice.
3.3.10 Transmission Losses
Certain machines, (e.g. fans) that are driven by electrical motors, use pulley belt arrangement to transmit power from motor shaft to machine shaft. These kinds of arrangements are sophisticated and always need proper alignment and maintenance of belt and belt tightness to avoid slip losses. Energy losses in a belt drive system occur due to improper alignment and /or looseness of the belt. If either of these exists, the total power output of the motor shaft is not completely transmitted to the driven shaft. For all practical purposes, there always are transmission losses. But the maximum allowable limit for transmission losses is 4.5%; proper attention is required if it is above 4.5%. Assessment team has done some measurement on field to get the RPM on the motor pulley and on the fan shaft pulley which is shown in Table 3.9 below:
Table 3.9 Transmission Losses
S. No. Motor Description Rating (kW) Motor RPM Fan/Pump RPM Transmission Losses % 1 Steam Blower 15 1476 1946 1.12 2 Compressor (Spare) 22 1458 2009 3.55 3 Dry Feed Grinder 11 1470 1894 8.78 4 Spray Dryer 75 1462 2248 3.90 5 Blower (Hammer Mill) 18.5 1468 2048 7.82 Source: The parameters measured during field visit, 2011(Digital Stroboscope, Model: DT 2269) Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 12 From the above table it is clear that transmission losses vary from 1.12% to 8.78%. Special attention should be given to the machines having transmission losses more than 4.5%. Corrective measures e.g. tightening the belt and correcting the alignment of the pulleys should be done to keep these losses under the allowable limit.
3.3.11 Sustainable/Renewable Energy Sources
Electrical energy used at SGC is either taken from KESC or generated through diesel genset. Currently no renewable energy sources are used at SGC to generate electricity.
3.4 Thermal Energy Saving Potential
3.4.1 Monitoring and Evaluation
Monitoring devices are essential tools and are critical for running and maintaining a high level of efficiency with in a plant. The table below shows a list of equipment/devices used for monitoring and evaluation of the respective utilities.
Table 3.10 List of monitoring equipment
S. No Area / Utility Monitoring Device Installed Working 1. Boiler Steam Flow N N/A 2. Boiler Steam Temperature Y Y 3. Boiler Steam Pressure Y Y 4. Boiler Gas Flow Y Y 5. Boiler - Feed Water Water Flow Y Y 6. Boiler - Feed Water Water Temperature Y Y 7. Boiler - Feed Water Water Pressure Y Y 8. Boiler Stack Temperature Y Y 9. Boiler - Economizer Water Temperature (In) Y Y 10. Boiler - Economizer Water Temperature (Out) Y Y 11. Deaerator Water Temperature Y Y 12. Boiler Blowdown Water Flow N N/A 13. Header Boiler Room Steam Temperature Y Y 14. Header Boiler Room Steam Pressure Y Y 15. Header Converter Steam Temperature Y Y 16. Header Converter Steam Pressure Y Y 17. Header Evaporator Steam Temperature Y Y 18. Header Evaporator Steam Pressure Y Y Source: Data provided by SGC Management and Data acquired during field assessment. Key / Legend Y = Yes, N = No, N/A = Not applicable Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 13 3.4.2 Boiler(s)
At SGC, thermal energy was required in the manufacturing process for a number of applications. This thermal energy was provided by steam, which was generated by two identical boilers. The boilers details provided by SGC are listed in table below.
Table 3.11 Steam Generator(s) Data
Description Values Units Type Fire Tube Boiler ----- Generation capacity per Unit 6 t/hr No. of Units 2 ---- Total Steam Production Capacity 12 t/hr Average steam production Unknown t/hr Design pressure 13 Bar Working pressure 10 Bar Steam Temperature 180 C Saturation Steam Temperature 184.154 C Stack Temperature before economizer 215 C Stack Temperature after economizer 180 C Average Fuel Consumption Variable 8,000 12,000 m 3 /24hrs Av. Feed Water Consumption Variable 5.5-6.5 m 3 /24hrs Main distribution Line size 4 Inch (Schedule 40) Av. Feed Water Temperature 95 C Hours of Operation per day 24 hrs Days of Operation in a year 300 days Source: Data provided by SGC Management and Data acquired during field assessment.
3.4.3 Feed Water Treatment
There was a six meter cubed feed water tank installed at SGC that also served the purpose of a deaerator tank. The water used for steam generation was treated water that was provided by the softener plant dedicated for the boiler(s).
After the raw water was softened, it was passed through two heat exchangers before it found its way to the feedwater/deaerator tank. The first heat exchanger was heated by condensate and blowdown water; the feedwaters temperature was increased from 35C to 51C. The second heat exchanger was an economizer installed on the boilers stack to recover waste heat from the flue gases and it Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 14 further increased the temperature of the feedwater from 51C to 75C degrees. In the deaerator tank the water was heated to 95C+ using direct injection of steam.
The temperature of the feedwater was within the recommended feedwater temperature range. A temperature of 95C+ reduces the effect of thermal shock on the boiler and releases the absorbed gases from the feedwater primarily oxygen, this further reduces the chances of corrosion in the boiler and the steam distribution network.
Raw water, feedwater and boiler water quality was regularly tested for pH levels, Hardness, Alkalinity and TDS. Their results are shown in the table below:
Table 3.12 Water Quality Results
Parameter Make-up Water Feed Water Boiler Unit Actual Hardness 0 0 0 ppm Hardness limit 10 10 10 ppm TDS 350 400 3,000 ppm TDS limit 400 550 3,500 ppm Proton concentration 8.0 8.0 9 pH pH limit 8.5 8.5 11 pH Source: Data provided by SGC Management
The boiler TDS was maintained below 3,500 ppm by continuous surface blowdown, intermittent and continuous bottom blowdown. An intermittent blowdown was carried out regularly once in 24 hours and/or whenever the TDS came close to the limit.
The hardness was maintained below 10 ppm, which is within operating recommendations for fire tube boilers with a working pressure of 10 bar however the TDS levels for the feedwater was around 400 ppm which is above recommended levels.
High TDS levels require a greater amount of blowdown to keep the boiler water TDS limits within range. This is a waste of energy as blowdown water has a temperature close to saturation temperature and when it is replaced with feed water the boiler has to do extra work to produce the same amount of steam.
3.4.4 Blowdown
There was no flow monitoring system installed to quantify the amount of water leaving the boiler through blowdown, the minimum amount of blowdown required to maintain the TDS concentration below 3,500 ppm in the boilers was calculated as shown in the table below.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 15 Table 3.13 Minimum amount of Blowdown Required
Description Values Units Boiler Pressure 10 bar g Boiler Rating 6,000 kg/hr Maximum Allowable Boiler TDS 3,500 ppm Feedwater TDS 400 ppm No. of Boilers 2 Units Blowdown Rate 1,548.39 kg/hr Source: Field assessment observation, calculations were made based on the minimum amount of blowdown required.
At SGC blowdown was carried out manually, there were automatic blowdown valves installed but they were not functional. The energy lost due to manual operation of blowdown is shown in the table below:
Table 3.14 Difference in Energy Lost Between Manual and Automatic Blowdown
Description Values Units Maximum allowable TDS 3,500 TDS Average TDS 400 TDS Feedwater TDS 3,000 TDS Manual Blowdown System Required blowdown rate 15.38 % Total feedwater supplied 13,846.15 kg/hr Energy required to produce 12000 kg/hr steam 8,142.15 kW Automatic Blowdown System Required blowdown rate 12.90 % Total feedwater supplied 13,548.38 kg/hr Energy required to produce 12000 kg/hr steam 8,110.42 kW Difference in energy required 31.73 kW % saving in fuel cost 0.39 % Fuel supplied to boiler per year 2,803,380 m 3 /year Fuel saving per year 10,925.1 m 3 /year Source: Field assessment observation, calculations were made based on the minimum amount of blowdown required.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 16 Table 3.15 Annual Losses due to Manual Blowdown System
Description Value Unit Amount 147,508.2 PKR Fuel Saving Potential 10,925.1 m 3
Source: Field assessment observation, calculations were made based on 300 days of work in an annum
3.4.5 Boiler Efficiency
The steam consumption was variable as it depended upon the number of processes in operation. There was no steam flow monitoring system installed to quantify the amount of steam being produced. The gas flow meter and the water flow meters were common for both the boilers therefore the combined efficiency of the boilers was calculated.
The quantity of steam was deduced from the amount of water consumed by the boilers and the minimum amount required for blowdown.
Table 3.16 Boiler Efficiency
Description Values Unit Quantity of Steam 3,887 kg/hr Quantity of Feed Water 5,435 kg/hr Enthalpy of steam 2,781 kJ/kg Enthalpy of Feed Water 398 kJ/kg Steam Energy 10,809,973 kJ/kg Feed Water Energy 2,163,201 kJ/kg Energy Required 8,646,772 kJ/hr Fuel Consumption 391 m 3 /hr Calorific value of fuel 37,000.0 kJ/m 3
Fuel Energy 14,462,930 kJ/hr Boiler Efficiency 60 % Source: Calculations were made based on data provided by SGC Management and data acquired during the field assessment.
3.4.6 Boiler(s) Combustion Analysis
Excess air is required to ensure complete combustion, to allow for the normal variations in combustion and to ensure satisfactory stack conditions. The optimum excess air level for maximum efficiency occurs when the sum of the losses due to incomplete combustion and losses due to heat in flue gases is at the minimum.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 17 At SGC, no oxygen analyzer was installed on the steam generator(s) nor was a combustion analysis conducted by a third party to evaluate the combustion efficiency of the steam generator(s). A combustion analysis of the boilers was carried out by the assessment team and the results are presented in the table below:
Table 3.17 Combustion Analysis Test Results
Description Values - Boiler 1 Values - Boiler 2 Unit Excess O 2 0.1 0.1 % CO Over 4,000 Over 4,000 ppm CO 2 11.7 11.7 % Excess Air 0.1 0.3 % Stack Temperature 208 203 C Ambient Air Temperature 36.8 39.6 C Source: Data acquired from stack analysis of Steam generator(s).
Table 3.17 shows the results of the combustion analysis. The results show high concentration of carbon monoxide and the low concentration of oxygen. This is an indicator that there was insufficient oxygen required for stoichiometric combustion.
As a result, more fuel was being consumed to produce the same amount of energy required for production of steam.
3.4.7 Direct Fired Burners
Table 3.18 Combustion Analysis Test Results
Description Protein Drier Spray Drier Unit Excess O 2 16.7 19.2 % CO 795 173 ppm Stack Temperature 363 278 C Ambient Air Temperature 38.4 40.1 C Source: Data acquired from stack analysis.
The result of the combustion analysis shows the presence of excess oxygen as well as excess carbon mono oxide. Even though there is excess oxygen to facilitate complete combustion, complete combustion is not taking place.
Incomplete combustion while there is excess O 2 present in the flue gas is caused by the following factors:
Due to the misalignment of burner (Flame touches the sides of wall of combustion chamber). Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 18 Due to the lack of maintenance of the burner. Due to the use of low turndown ratio burner. Due to the use of an inefficient burner. Due to the improper mixing of Air and fuel
As a result, more fuel was being consumed to produce the same amount of energy required for heating.
3.4.8 Economizer
An economizer was installed on the boiler stack to recover energy from the flue gases leaving the boiler. The economizer was used to heat feedwater; the feedwater entering the economizer had a temperature of about 54C and left at about 71C.
The efficiency of the economizer could not be calculated as there was insufficient data available.
3.4.9 Steam Traps
Steam traps are essential components of the steam distribution to remove condensate formation with a negligible loss of live steam. Other advantages include removing air from the steam distribution network, keeping the steam dry, reducing waterhammer and making heat transfer from the steam more effective.
There were no steam traps installed at SGC to check their functionality.
3.4.10 Insulation
Steam Distribution Network
During the audit, it was observed that there were some gaps found in the insulation of the live steam distribution network. The losses due to lack of Insulation are presented in the table below.
Table 3.19 Annual Losses Due to Lack of Insulation of Steam Distribution Network
Description Value Unit Energy 560.56 GJ Amount 202,433.80 PKR Fuel Saving Potential 15,150.29 m 3
Source: Field assessment observation, calculations were made based on 300 days of work in an annum
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 19
Feedwater Network
During the audit, it was observed that there were some gaps in the insulation of the feedwater network. The losses due to lack of Insulation are presented in the table below.
Table 3.20 Annual Losses due to Lack of Proper Insulation of the Feedwater Network
Description Value Unit Energy 75.28 GJ Amount 29,705.22 PKR Fuel Saving Potential 2,034.60 m 3
Source: Field assessment observation, calculations were made based on 300 days of work in an annum
Figure 3.3: Lack of Insulation in Evaporator Section Figure 3.4: Lack of Insulation of Boiler Accessories
Figure 3.5: Lack of Insulation of Feed Water Network
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 20 Steam Leakage at Drum Washing
Blowdown
During the audit, it was observed that there were some gaps in the insulation of the blowdown network. The losses due to lack of Insulation are presented in the table below.
Table 3.21 Annual Losses due to Lack of Proper Insulation of the Blowdown Network
Description Value Unit Energy 100.09 GJ Amount 39,495.47 PKR Fuel Saving Potential 2,705.17 m 3
Source: Field assessment observation, calculations were made based on 300 days of work in an annum
Condensate Network
During the audit, it was observed that there were some gaps in the insulation of the condensate network. As the condensate is not reused in the boiler as feed water, losses due to lack of insulation of the condensate network were not added.
3.4.11 Leakages (Thermal)
Leakages at pipe fittings, valves and traps can result in substantial energy loss and resources. During the assessment, the steam, feedwater and blowdown distribution network was inspected for leakages.
Description Value Unit Total Leakage rate 685,080 M3 Amount 693,087.83 PKR Thermal Energy Wasted 1,905 GJ Source: Field assessment observation, calculations were made based on 300 days of work in an annum
Feed Water leakages
No leakages were found.
Blowdown leakages
No leakages were found.
3.5 Cooling Tower
There were two cooling towers installed at SGC, one primary and one on standby. The cooling towers were used for cooling water requirements in the process area.
The primary cooling tower was recently installed and was in good working condition. The cooling tower was clean and well maintained.
The cooling towers efficiency could not be calculated as a suitable location for flow monitoring of the cooling water could not be established.
3.6 Compressed Air System Concerns
Air compressors are required to produce compressed air that is consumed in the manufacturing process either directly and/or to run the pneumatic equipment.
There were three compressors installed, the primary compressor was run continuously and was supported by the other two when the compressed air demand was high. The primary compressor installed was run at full capacity for nearly 23 hours a day while it was supported by the secondary compressor for about 6 hours in a 24 hour period.
The compressed air demand was variable and there was no air flow monitoring system installed to calculate the amount of compressed air being produced by the compressor and/or the amount of compressed air that was consumed by the various departments and processes.
There was also a drier installed to keep the compressed air dry however, it was malfunctioning and hence bypassed. As a result there was a lot of moisture in the Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 3 - 22 compressed air lines resulting in damaging of water filter(s) installed to assist in moisture retention.
There were two receiver tanks installed to buffer the compressed air requirements. The float traps installed on the tanks to remove water from the compressed air were malfunctioning and the operators had to manually drain the accumulated water.
Draining the tanks manually should be avoided as over draining will result in compressed air being wasted and insufficient draining will result in high levels of moisture in the tank that will eventually find its way to the air driers. A compressed air drier has to work harder to sustain dry air when more moisture finds its way due to clogged filters or malfunctioning traps.
The compressed air accessories/equipment (especially in the evaporator area) was covered in dust and/or mold, leakages, broken filters and the fact that the air dryer was out-of-order for over two weeks projected the image that the compressed air system was not given sufficient importance.
3.7 Leakages (Compressed Air)
Leakages at pipe fittings, valves and distribution points/sockets can result in substantial energy loss and resources. During the assessment, the compressed air distribution network was inspected for leakages.
Table 3.24 Annual Losses due to Compressed air Leakages
Compressed Air Leakage Locations Boiler Room Air Distribution line - Damaged flexible pipe Boiler Room Chemical dosing pump Pneumatic socket Drier Bag filling machine - Pneumatic socket Evaporator Air Distribution line - Pneumatic socket Evaporator Steam reducing valve - Pneumatic socket Conversion retention valve - Pneumatic socket Mill Machine pneumatic sockets
Description Value Unit Total Leakage rate 60,480 m 3
Amount 62,532 PKR Electrical Energy Wasted 6,241 kWh Source: Field assessment observation, calculations were made based on 300 days of work in an annum
NEC Consultants (Pvt.) Ltd. 4 - 1
This chapter describes energy conservation measures for the energy saving potential areas identified in the previous chapter. By adopting these measures, industry can not only reduce its energy demand but also increase productivity and control environmental pollution, consequently.
4.1 Electrical Energy
4.1.1 Electrical Energy Sources
The electrical energy used at SGC is either taken from KESC or generated through diesel generator. The diesel generator can be replaced with gas fired generator. By doing so substantial amount can be saved. A detail assessment of this opportunity is provided in the action plan.
4.1.2 Transformers
One transformer of 1250 kVA is installed by the KESC for supplying electric power to SGC. The maintenance, repair and losses of this transformer are beard by SGC. Complete Thermography of the transformer is done during the field visit. The results show that transformer is operating efficiently and ambient temperature is within safe limits.
4.1.3 Power Factor Improvement (PFI) Plants
Capacitor banks to improve power factor are already installed at SGC. The location and arrangement of capacitors is shown in Table 2.3. Power factor at SGC is recorded during the field visit and is also calculated from the electricity bills as presented in Table 3.2. From the table it is clear that power factor is well above the allowable limit i.e. 0.90, therefore no PFI penalty is imposed by the KESC. Hence no PFI plant is proposed.
4.1.4 Utilization of Diesel Generator
Data provided during and after the field visit is analysed and concluded that diesel generator operates at 49 % of its rated capacity. Consumption pattern is shown in Figure 2.2. The highest efficiency of diesel generators is achieved at 60-80% loading. In this region the fuel consumption of the generator is optimal. Hence for low unit cost (Rs. /kWh) it is recommended to operate diesel generator at 60% 80% loading. CHAPTER 4
RECOMMENDATIONS Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 2 4.1.5 Utilization of KESC
Consumption pattern for KESC is shown in Figure 2.3 for plant load. This graph also indicates variation in the unit price (Rs. /kWh). This variation is mainly affected by the maximum demand during the month, operating power factor and the electricity tariff. As power factor is already improved therefore in order to lower down the electricity rate (Rs. /kWh) keep a regular check on the maximum demand. Load distribution should be prioritised such that no peaks in the demand occur and the demand remains constant. This could be achieved by avoiding operation of heavy loads at the same time.
4.1.6 Recommendation for Proper Distribution (Cable Sizing)
The cable/distribution data provided by SGC and recorded through inspection is analysed in Section 3.1.1. No cable is found having voltage drop more than 2.5% of the nominal voltage at the designed current. This means the present distribution system is working properly. However it is recommended to record voltage drop regularly, especially after the addition of new loads.
4.1.7 Proper Sized Motors
The load of around 21 motors is recorded during the field visit which is computed in Section 3.3.1. Load on each motor varies during 24 hours due to the variations in the process involved. Therefore over/under size motors could not be pointed out at this stage.
In order to find the proper sizing of motors, voltmeter and ammeter or energy analyser should be installed at each MCC, and loading (kW) should periodical be recorded against each motor. This practice will help to identify the over/under size motors throughout the SGC. SGC can save substantial amount of energy by employing properly size motors.
4.1.8 High Efficiency Motors
SGC can save electricity units by replacing the existing low efficiency motors with high efficiency (class 2 or class 1) motors. The comparison of energy saving by replacing efficiency class 3 motors with efficiency class 1 and efficiency class 2 motors is shown in the figure below:
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 3 Figure 4.1: Energy Saving Comparison of Electrical Motors
Source: Nico J. Kluwen, KWA Consultants, The Netherlands
From the above figure it is clear that at 75% load, the efficiency class 2 motor uses 6% less electricity than efficiency class 3 motor and efficiency class 1 motor uses 8% less electricity than efficiency class 3 motor.
4.1.9 Preventive Maintenance
Preventive maintenance is a schedule of planned maintenance actions, aimed at the prevention of breakdowns and failures. A preventive maintenance program, combined with good operational practices, will reduce the need for much corrective or emergency maintenance. All maintenance must be performed so that equipment and systems operate efficiently and effectively. Improper maintenance and repairs can lead to unsafe conditions and reduced system performance.
Preventive maintenance activities should also include equipment checks, partial or complete overhauls at specified periods, cleaning the dust and dirt, lubrication of the moving parts and so on. In addition, workers can record equipment deterioration so that they know to replace or repair worn parts before they cause system failure. It is far better to perform maintenance and repairs right the first time than to risk the consequences of a mediocre approach because an ideal preventive maintenance program would prevent all equipment failures before they occur.
4.1.10 Voltage Unbalance
The voltage unbalance is measured at different places and it is found to be less than 1% which is satisfactory. This result also indicates that the load distribution to each phase is balanced. Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 4 However it is recommended to regularly monitor voltages at different locations to verify that voltage unbalance is maintained below 1%. Also periodically check single line diagrams for the verification of uniform distribution of single-phase loads. Correct the over loaded equipments. An annual thermo graphic inspection of the equipments may help to assess the voltage unbalance in the system.
4.1.11 Current Unbalance
The current unbalance is measured at different places and it is found to be less than 10% which is satisfactory. This result also indicates that the load distribution to each phase is balanced.
However it is recommended to regularly monitor current at motor terminals to verify that current unbalance is maintained below 10%. High current unbalance is noted at no load. Therefore special attention should be given to the under-loaded motors.
4.1.12 Lighting System
As discussed in Section 3.3.6, that there is a scope of energy saving in the lighting system. Therefore existing luminaries can be replaced with energy efficient luminaries who are discussed in detail in the Action Plan.
4.1.13 Monitoring and Evaluation
It is recommended that load on diesel generator should be monitored and recorded on hourly basis. The parameters recorded should include voltage, current, power factor, kWh, frequency, excitation voltage, excitation current etc. This practice should also be done at each distribution panel and MCC, and motor load parameters should be checked on hourly basis. This practice will help to know over/under size motors and finally the proper size motors could be installed. This practice will also help to know the running load and power factor of each section of the plant. Knowing the installed load and required power factor of each section, corrective measures could be taken to improve the overall plant efficiency. Moreover diesel consumption for power generation should be recorded carefully and average unit price (Rs. /kWh) should be calculated every month.
4.1.14 Installation of VFDs
Energy can be saved by using VFDs on motors having variable load. This energy is saved by reducing motor speed according to the load. The potential of energy savings can be understand with the help of graph given below:
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 5 Figure 4.2: Energy Saving with VFD by Reducing RPM
Source: The Energy Management Handbook, 6 th Edition
After assessment of the installed motors it is recommended to install VFDs on some of them. The detailed cost-benefit analysis of the proposed VFDs is provided in the action plan.
4.1.15 Motor Consideration with VFDs
One drawback to pulse width modulated drives is their tendency to produce voltage spikes, which in some instances can damage the insulation systems used in electric motors. This tendency is increased in applications with long cable distances (more than 50 feet) between the motor and drive and with higher-voltage drives. To guard against insulation damage, inverter-duty motors, having special insulation systems that resist voltage spike damage, are used.
In addition, some increased motor heating will inevitably occur because of the inverters synthesized AC wave form. Insulation systems on industrial motors built in recent years, and especially inverter-duty motors, can tolerate this except in the most extreme instances. A greater cooling concern involves operating for an extended time at low motor RPM, which reduces the flow of cooling air and especially in constant torque applications where the motor is heavily loaded even at low speeds. Here, secondary cooling such as a special blower may be required.
4.1.16 Use of Rewound Motors
When a motor fails, one has three options:
Repair the failed motor Replace with a new standard efficiency motor Replace with a new high efficiency motor Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 6 In a typical motor rewinding, the stator is heated to a temperature high enough to burn out its winding insulation. The windings are then removed and replaced. The higher temperatures increase losses by changing the electrical characteristics of the motor's core. The average core losses are higher than what is normal for motors that had been previously rewound and also indicates increased total losses. The increasing losses result in decrease of efficiency.
Generally speaking, it is unwise to rewind a motor if the motor has already been rewound, the motor has been damaged by heat, or if the cost of rewinding the motor is more than half of the cost of a new energy efficient motor. During motor rewinding ensure quality of conductor, quantity of conductor and proper size of conductor. Avoid stator heating and hammering.
SGC should consider replacing the damaged motors with new high efficiency motors.
4.1.17 Transmission Losses
Transmission losses at belt drive systems are measured during the field visit and are analysed in Section 3.3.10 of this report. No major hardware/auxiliaries are required to overcome transmission losses. Simply take care of the alignment of the pulleys, tightness of the belts and where ever needed replace the worn belts and pulleys.
Table 4.1 shows the machines having transmission losses more than 4.5% and the saving opportunities associated with them:
Table 4.1 Transmission Losses and Saving Opportunities
Working Days = 300 days/yr Working Hours = 12 hrs/day Calculated Unit Price of Electricity = 10.02 Rs./kWh
S. No. Motor Description Rating (kW) Transmission Losses % Annual Energy Loss (kWh) 1 Dry Feed Grinder 11 8.78 2090.4 2 Blower (Hammer Mill) 18.5 7.82 2879.8 Total Energy Loss (kWh) 4,970.20 Amount (Rs.) 49,801 Source: The base data is taken from Table 4.16
4.1.18 Sustainable/Renewable Energy Sources
Among the various renewable energy options, wind and solar energy have a larger and possibly grid-scale potential. Due to the low installation cost wind energy projects are encouraged by the state and wind farms may seem more feasible for bulk power generation. However significant potential for wind farming exists only in the coastal areas that are mostly far away from the national electricity grid.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 7 Solar energy is in abundance almost all over the country and is justifiably seen as the ultimate resource to tap. Although mainly supplemental in nature, it is also a resource that addresses the problems of atmospheric pollution and climate change.
4.1.19 Solar PV Electricity Generating Panels
Photovoltaic (PV) cell is one of the many ways of using solar energy for electricity generation. PV cells can convert incident sun energy directly into electricity. Each PV cell produces very small amount of voltage. Therefore a solar panel contains number of PV cells connected in series to build voltage up to 12-24 volts. Direct Current DC produced by solar panels can be used to power the DC electric equipments or to charge a battery.
Attempts have been made in Pakistan to install small-scale photovoltaic power generators and create fabrication capability of PV. Imported solar panels are also available in the open market in Pakistan.
Solar Power System
A solar power system comprises of solar panels, charge controllers, battery banks and inverters. Following table shows certain specifications of different solar power systems: Table 4.2 Solar Power Systems
S. No. Solar Power System (kW) Available Energy (kWh/month) Initial Cost (Million Rs.) 1 1 111 0.6 2 5 557 10.0 3 10 1,113 320.0 Source: 1- Local Vendors of Solar Power 2- Panasonic-Solar Cell Book 3- www.pide.org.pk/pdf/PDR/2004/Waqasullah.pdf
The best possible and the most feasible option for adopting green energy is decreasing load on conventional sources, which can be accomplished by transferring partial load to solar power system i.e. use solar panels for lighting load, for water heaters etc. In this way initial cost and area required to build large solar power systems can be minimized.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 8 4.2 Thermal Energy
4.2.1 Monitoring & Evaluation
Steam Flow Meter(s)
In order to quantify, as to exactly how much steam is being produced and consumed and at what cost, its flow measurement is essential. Once the flow quantity is identified on a regular basis, its consumption patterns can be identified and thus its savings procedures can be developed.
It is suggested to install steam flow meters at the following locations:
Steam outlet from each boiler Steam inlet to the various consumer departments e.g. evaporators, converters, etc.
The installation of a flow meter should be followed by proper monitoring and analysis to create benchmarks for each individual steam producer and consumer.
The estimated cost of a good quality steam flow meter is Rs. 200,000 per piece.
Blowdown Flow Meter(s)
In order to quantify, as to exactly how much water is being blowdowned, its flow measurement is essential. Once the flow quantity is identified on a regular basis, savings procedures can be developed.
It is suggested to install water flow meter(s) at the following location(s):
Blowdown line from each boiler
The installation of a flow meter should be followed by proper monitoring and analysis to create benchmarks of the amount of water being removed from the boiler(s).
The estimated cost of a good quality steam flow meter is Rs. 15,000 per piece.
4.2.2 Feed Water Treatment
The TDS of the Feedwater was 400 ppm that is above the recommended level, even though high TDS does not cause scaling it cannot be ignored, high TDS levels require a greater amount of blowdown to keep the boiler water TDS limits within range. This is a waste of energy as blowdown water has a temperature close to saturation temperature and when it is replaced with feed water, the boiler has to do extra work to produce the same amount of steam.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 9 Normally the condensate water is used along with makeup water to fulfill the boilers water requirements. As condensate is distilled water, it does not contain any TDS or hardness. This dilutes the TDS concentrations of the makeup water.
At SGC, the condensate water collected is not used as feedwater as there is a chance of sugar contamination. Therefore, it is advised to further treat water to reduce to amount of TDS concentration in the feedwater. It is recommended to keep TDS concentration in the feedwater below 150 ppm. The table below shows the potential saving by reducing the amount of TDS concentration of feed water.
Blowdown water contains energy that is lost to environment when drained, recovering this energy can save feedwater heating costs significantly. Water quality plays an important role as it determines the amount of blowdown required to maintain good water quality in the boiler. Exceeding the required amount of blowdown is a direct waste of water and energy. Excessive blowdown can be controlled by installing an automatic blowdown system.
The main disadvantage of a manual blowdown system is that the operator is unaware of the current TDS level of the boiler water and/or the optimal amount of blowdown required at a given time. The result is that a greater quantity of water is discharged than that required and hence a greater amount of energy is lost.
In an automated blowdown control system, the required TDS level limits can be set and maintained with the minimum amount of blowdown required.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 10 For further recovery of energy from blowdown a flash tank could also be installed. Flash steam contains about 30-40% energy of blowdown and it can be separated from the high TDS blowdown water by the use of a flash tank.
However, before a recommendation for a flash tank can be made, regular monitoring and quantification of the amount and frequency of blowdown is required.
4.2.4 Boiler(s) Efficiency
There was insufficient data to calculate the efficiency for each boiler.
It is recommended to accurately monitor and record the following parameters for each boiler individually:
Quantity of steam produced Temperature of steam temperature exiting the boiler Quantity of feedwater consumed Temperature of feedwater Quantity of Natural Gas consumed Quantity of intermittent and continuous blowdown
4.2.5 Combustion Efficiency Boiler(s)
The purpose of the burner is to mix fuel with molecules of air in optimum proportions. It is essential for efficient boiler operation that the burner is functioning as per requirement. A poor designed boiler with an efficient burner works more efficiently than a very well designed boiler with an inefficient burner. An efficient burner is designed on the basis of maximum burner efficiency with the reduction in stack emissions.
A burner mixes air and fuel and injects into the combustion chamber. While providing a proper combustion and maintaining a proper flame stabilization at different firing rates.
Normally an efficient natural gas burner requires 2% to 3% excess oxygen and 10-15 % excess air to burn efficiently without producing excess carbon mono-oxide.
Burner maintenance Program:
Conduct stack analysis and calculate combustion at different firing rates e.g. full load and part load time. If the excess of oxygen exceeds 3%, consider modernizing the fuel / air control system by using electronic monitoring, installing of oxygen trim system or a tuning and repairing of burner. A new energy efficient burner should be considered if repair cost becomes excessive and reliability becomes an issue. Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 11 Combustion Efficiency Boiler(s):
Table 4.4 shows the results of the combustion analysis. The results show high concentration of carbon monoxide and the low concentration of oxygen and carbon- di-oxide. This is an indicator that there was insufficient oxygen required for stoichiometric combustion.
Table 4.4 Combustion Analysis Test Results (Initial)
Description Values - Boiler 1 Values - Boiler 2 Unit Excess O2 0.1 0.1 % CO Over 4000 Over 4000 ppm CO2 11.7 11.7 % Excess Air 0.1 0.3 % Stack Temperature 208 203 C Ambient Air Temperature 36.8 39.6 C Efficiency --- --- Source: Data acquired from stack analysis of Steam generator(s).
The air inlet was cleaned and the air intake was adjusted until the optimum burning was achieved.
Table 4.5 Combustion Analysis test Results after Adjusting Boiler Air Intake
Description Values - Boiler 1 Values - Boiler 2 Unit Excess O 2 1.8 2.2 % CO 1 0 ppm CO2 10.8 10.6 % Excess Air 8.5 10.3 % Stack Temperature 220 203 C Ambient Air Temperature 44.3 39.6 C Efficiency 83.2 83.4 Source: Data acquired from stack analysis of Steam generator(s).
Table 4.5, are the result of combustion analysis after the air intake was adjusted. The results now indicate optimum oxygen, carbon monoxide and carbon-di-oxide concentrations.
It is recommended to conduct a combustion analysis and burner tuning 2 4 times a year.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 12 Combustion Efficiency Direct Fired:
The result of the combustion analysis shows the presence of excess oxygen as well as excess carbon mono oxide. Even though there is excess oxygen to facilitate complete combustion, stoichiometric combustion is not taking place. As a result, more fuel was being consumed to produce the same amount of energy required for heating.
Incomplete combustion while there is excess O 2 present in the flue gas is caused by the following factors:
Due to the misalignment of burner (Flame touches the sides of wall of combustion chamber). Due to the lack of maintenance of the burner. Due to the use of low turndown ratio burner. Due to the use of an inefficient burner. Due to the improper mixing of Air and fuel
It is recommended to conduct a combustion analysis and burner tuning 2 4 times a year.
4.2.6 Economizer
An economizer was installed to recover waste heat from the flue gases leaving the boiler and this energy was used to increase the temperature of the feedwater. It is recommended to continue this practice.
4.2.7 Steam Traps
Steam traps are essential components of the steam distribution to remove condensate formation with a negligible loss of live steam. Other advantages include removing air from the steam distribution network, keeping the steam dry, reducing waterhammer and making heat transfer from the steam more effective.
Therefore it is recommended to install steam traps. An estimated cost of a good quality steam trap is Rs. 15,000-20,000 per piece.
4.2.8 Insulation of Pipes, Tanks and Boilers
Thermal insulation on process/utility equipment and piping (Steam, Condensate and, hot water, steam, etc.) has several functions:
Preventing losses and gain of heat; Maintaining consistent process temperature; Protecting employees from burn; Maintaining comfortable working environment around hot process equipment.
Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 13 The areas that lacked/had damaged insulation
Boiler and its accessories Boiler feedwater network Boiler blowdown network Live steam network
It is recommended to enclose the all specified locations by an insulating medium to conserve resources.
Insulation Maintenance Program:
Thermal insulation deteriorates over time, so systems should be regularly surveyed to replace and repair deteriorated insulation. System should be regularly surveyed to check for missing insulation. An overall survey of steam lines should be conducted to identify areas where insulation has deteriorated. Instruments (Infrared Temperature Gun) should be used to measure the effectiveness of insulation. Following any maintenance, areas where work has been performed should be inspected to see wherever insulation should be replaced or repaired. Removable insulation blankets should be installed on all equipment/areas that require frequent access. Economic insulation thickness should be applied to any hot surface equipment and its accessories.
The estimated cost of Rockwool insulation is Rs. 1,600-3,000 per meter square and the estimated cost an infrared temperature gun is Rs. 8,500 per unit.
4.2.9 Leakages
If the system leaks, the energy is lost along with the fluid medium. Leakage from the distribution system continues as long as the system is under pressure. Furthermore, the rate of leakage is almost constant, regardless of the load because the leakage is continuous, even small leaks waste a considerable amount of energy.
The following procedures may be adopted by SGC management to prevent/manage steam leakages:
Leakage Maintenance Program:
All leaks should be repaired as quickly as possible. Leaks are one of the most visible forms of energy wastage. Leakages can also pose a significant safety hazards. Leakages do not get smaller; neither does the cost of fixing them. Standard procedures should dictate that proper gaskets and packing be used in the distribution system flanges and valves. Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 14 A leak-repair specialist/team should be assigned to repair leaks when the system cannot be taken down. All systems should be designed for minimum leakage. For example, flanges and threaded piping should be minimized.
The estimated cost of fixing steam leakages is nominal.
4.2.10 Cooling tower
In order to quantify, as to exactly how much water is being circulated, its flow measurement is essential. Once the flow quantity is identified on a regular basis, savings procedures can be developed.
It is suggested to install water flow meter(s) at the following locations:
Main water line from cooling tower to the process area.
The installation of a flow meter should be followed by proper monitoring and analysis to create benchmarks.
The estimated cost of a good quality water flow meter is Rs. 15,000 - Rs. 30,000 per piece.
4.2.11 Compressed Air System
The following recommendations are listed in a priority order:
1) Compressed Air Drier
SGC has a lot of moisture in their compressed air lines and it can cause the following problems:
a. Rusting b. Scaling c. Damaging of pneumatic equipment d. Malfunctioning of control valves
After evaluating the amount of moisture in the compressed air lines, setting up a compressed air drier is recommended as a top priority.
2) Leakage Control
The compressed air network is generally visually inspected; if there are leaks (especially minor leaks) they are impossible to see with the naked eye. The best solution is to use an ultrasonic acoustic air leak detector, which can recognize the high frequency hissing sound associated with air leaks. Proactive leak detection is recommended which could save the losses caused by these air leaks.
The estimated cost of a good ultrasonic leak detector is Rs. 25, 000 per piece. Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 15 Steps in simple shop floor method of leak quantification 2 :
The method for simple shop floor measurement for Leak Quantification of a compressed air system are as follows: Shut off compressed air operated equipment (or conduct a test when no equipment is using compressed air). Run the compressor to charge the system to the set pressure of operation. Note the subsequent time taken for Load and Unload Cycles of the compressors. For accuracy, take ON & OFF times for 8 10 cycles continuously. Then calculate total ON Time (T) and Total OFF time (t). Use the above expression(s) to find out the quantity of leakage in the system. If Q is the actual free air being supplied during trial (m3/min), then the system leakage (m3/min) would be: System leakage (m3/minute) = Q T / (T + t)
3) Maintenance
Carry out preventative maintenance of not just the compressor but also the distribution network. Replace old/worn out flexible pipes with new piping and replace plastic piping with metal piping wherever possible. Clean/replace filters and drain traps. Clean dirt and debris off distribution pipes, local headers, gauges. Regularly check for moisture in compressed air line, especially at end use equipment Make sure pressure and temperature gauges are working correctly.
4) Compressed Air Monitoring
In order to quantify, as to exactly how much compressed air is being used and at what cost, its flow measurement is essential. Once the flow quantity is identified on a regular basis, its consumption patterns can be identified and thus its savings procedures can be developed.
Compressed air flow monitoring devices should be installed on the:
Output line of the compressors Input line to the various consumer departments
The units of air compressed should be noted in every shift and a bench mark should be established.
2 Steps in simple shop floor method of leak quantification Electrical Energy Equipment: Compressors and Compressed Air Systems Energy Efficiency Guide for Industry in Asia www.energyefficiencyasia.org Shafi Gluco-Chem (Pvt.) Ltd. Energy Audit Report NEC Consultants (Pvt.) Ltd. 4 - 16 5) Purchase of a new compressor
Once all the aforementioned steps have been carried out, SGC will have a better understanding of the actual compressed air requirement. Only then should SGC consider purchase of a new compressor.
After preliminary analysis of the compressed air demand, it is recommended for SGC to consider in the range of Atlas Copco GA 45 as the primary compressor while keeping the current GA 30 compressor as standby/support.
Energy-Smart Buildings Design, Construction and Monitoring of Buildings For Improved Energy Efficiency by Jacob J. Lamb, Bruno G. Professor Pollet, Inger Andresen