DOTs Context Sensitive and Sustainable Solutions approach provides a unique perspective to the traditional transportation engineering. It incorporates activities that foster workforce growth and development; reflects the communitys cultural, aesthetic, and historic interests; maintains mobility and safety; ensures sound stewardship of the natural environment; and promotes cost-effective decisionmaking. The desired result of the bridge program is an improved state transportation infrastructure that reduces transit-based limitations on trade and economic progress while instilling a socially and environmentally responsible culture of sustainability.
FRONT COVER: Though not all of the bicycle-pedestrian improvements to Bundle 210, Interstate 84: Sandy River to Jordan Road, are finished, the path is already open for use.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
he Oregon Department of Transportation is primarily known for its highways and bridges, but the agency also oversees other modes of transportation, such as rail, and we are always on the lookout for opportunities to update routes for pedestrians and cyclists as we work on the motor vehicle infrastructure. Bundle 210, I-84: Sandy River to Jordan Road, gave us a chance to improve the safety and accessibility of a juncture for several popular paths on the edge of the Columbia River Gorge National Scenic Area. The project lies just south of the delta of the Sandy River with the Columbia River, adjacent to the often-visited U.S. Forest Service Thousand Acres park. Scenic bike routes intersect there that run along both rivers. To travel between these routes, cyclists and pedestrians were negotiating a single narrow tunnel and local roadways with blind corners and no bike lanes, or riding alongside vehicles travelling at highway speeds. We were able to vastly improve these hazardous situations as part of the design and construction of the new I-84 bridges. Both east- and westbound cyclists can now ride on a 16-foot-wide multi-use path separated from the eastbound interstate bridge by a barrier railing that meets design guidelines for projects in the scenic area. Below the new bridges, two tunnels will allow access between Thousand Acres, north of the I-84 bridges, and Lewis and Clark State Park and its parking and picnic facilities south of the bridges; they are parallel to but separate from Jordan Road, for safety. Final paving of all paths will take place in summer 2014, as construction on the westbound bridge winds down. West of Bundle 210, ODOT Region 1 will continue improving cyclist and pedestrian access in this area with a Jobs and Transportation Act project for I-84 exit 17 in Troutdale. A marked bike lane and a sidewalk will be added to the west side of Marine Drive under the interstate. We are happy to be able to help keep all kinds of traffic moving in Oregon. Regards,
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
TABLE OF CONTENTS
he following section provides details about the status of each bundle, spending and cash flow, and contracts. Program Goals page 4 Program Summary page 13 Project Status page 14 Appendix A: Cash Flow page 53
Appendix B: Cost Report page 54 Appendix C: Oregon Transportation Commission Summary page 55
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
As illustrated in Figure 1, there were no design jobs in August, and program management jobs dropped back to a lower level. Construction sustained 292 jobs, 99 more than in July but 297 fewer than one year ago. Indirect and induced jobs totaled 460, an increase of 112 over July but 420 less than August 2012. Figure 2 shows the forecasted bridge program jobs based on the budget approved by the Bridge Oversight Committee and the cost-loaded schedule for delivery of the bridge projects. Program management as a portion of the total jobs is based on the July quarterly cash flow analysis.
Figure 2: OTIA III State Bridge Delivery Program projected jobs Note: Projected jobs are based on the most recently approved BOC schedule and expenditures as well as the June 2013 Oregon Bridge Delivery Partners quarterly cash flow analysis. Job numbers through 2012 are actual, while job projections in 2013-2014 are based on the April 2012 IMPLAN model update. Program jobs are forecasted into 2014.
Based on the IMPLAN model, between 2009 and 2011 the average number of jobs associated with the bridge program was just under 2,150 annually. Job numbers in 2012 were nearly identical to those in 2011 and will continue to decline as the bridge program nears completion in 2014.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
The bridge program created or sustained nearly 1,100 jobs in 2011 and approximately the same number in 2012. For the duration of the bridge program, the average number of jobs created or sustained annually is forecast to be about 2,200.
Estimating the Impact of the OTIA III State Bridge Delivery Program
The bridge program generated more than $3.3 million in total income and just under $267,000 in tax revenue for state and local governments in August (jobs and income data are derived from IMPLAN, using expenditures from the ODOT TEAMS Report). August 2013 figures are significantly lower than those of August 2012 due to reduced construction expenditures, which is expected. Expenditures will continue to fall as bundles are completed. Figure 3 shows income and taxes paid in August for the bridge program; Figure 4 shows income and taxes paid to date.
Figure 3: August 2013 income vs. tax revenue for the OTIA III State Bridge Delivery Program
Figure 4: Total income and taxes paid through August 2013 for the OTIA III State Bridge Delivery Program Note: In Figure 3 and Figure 4, the IMPLAN model predicts tax revenues from total income and includes business income taxes, personal income taxes and property taxes.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Investing in Oregon
Oregonians and Oregon-based companies continue to benefit from activities related to the bridge program. Work is progressing on Bundle 220, I-5: Willamette River Bridge, with both spans now open to traffic and only minor tasks remaining before the project reaches second note. The most recent payment data for the project shows that prime contractor Hamilton Construction has spent 93 percent of its funds on Oregon companies. Thus far, Hamilton has paid out more than $86 million, and $80.4 million of that has gone to Oregon-based companies. Two of the Oregon firms benefiting from the expenditures were Deerwood Building Supplies of Eugene and EZ Grade Inc. of Stayton.
Figure 5: OTIA III State Bridge Delivery Program payments to DMWESB firms vs. non-DMWESB firms
Figure 6: OTIA III State Bridge Delivery Program contract values for DMWESB firms vs. non-DMWESB firms
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Figure 7: Monthly OTIA III State Bridge Delivery Program schedule and budget performance
Figure 8: Annual OTIA III State Bridge Delivery Program schedule and budget performance
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Figure 9: The percentage of OTIA III State Bridge Delivery Program bridges under construction that are free of height, width or weight restrictions
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Figure 10 shows the annual forecast of when bridge program bridges will be free of construction work zones. Figure 11 shows the remaining number of loadrestricted bridges in the bridge program and when they are scheduled to be removed from the Restricted State Bridges List maintained by ODOTs Bridge Engineering Section Load Rating Unit.
Figure 10: When OTIA III State Bridge Delivery Program bridges will be free of construction work zones
Figure 11: Number of load-restricted bridges in the OTIA III State Bridge Delivery Program
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
A flier advertised Karl Wiesekes presentation on the Whilamut Passage Bridge at a recent Oregon APWA luncheon.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Environmental Programmatic Permitting
The bridge program took advantage of a streamlined process for environmental permitting to design projects that are sensitive to their environment, save money and accelerate the completion of work. Figure 12 summarizes the programmatic permitting for bridge program projects.
Figure 12: Summary of programmatic permitting for the OTIA III State Bridge Delivery Program as of Aug. 31, 2013
1, 2
Notes: 1) Two bridges in Bundle 215 were permitted before transitioning to no work; therefore, the number of completed permits is 208. 2) Bundle 210 followed the programmatic process. Due to design constraints, that project ended up obtaining individual permits, but they met and followed the intent of bridge program standards and therefore will be recorded as complete. Regulatory agencies have approved the necessary documentation.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Figure 13: OTIA III State Bridge Delivery Program funds obtained as of Aug. 31, 2013
Date Submitted
Funding Body FHWA Transportation Enhancement Program (administered by ODOT) FHWA Transportation Enhancement Program (administered by ODOT) FHWA Highways for Life
Target
Status
April 2009
January 2009
Bundle 209
$718,019
November 2006
Bundle 401
July 2005
FHWA Supportive Services Funds Environmental Protection Agency (in conjunction with the Lane Regional Air Pollution Authority) Environmental Protection Agency (in conjunction with the Lane Regional Air Pollution Authority) FHWA Innovative Bridge Research and Construction
Workforce Development Plan Engine upgrades and retrofitted exhaust controls on construction equipment Clean-burning fuels in construction equipment
July 2005
$120,000
Received
March 2005
$80,000
Received
July 2004
Bundle 206
$1,000,000
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
PROGRAM SUMMARY
Figure 14: OTIA III State Bridge Delivery Program design summary as of Aug. 31, 2013 Note: Figure 14 is based upon current forecast schedule dates.
Figure 15: OTIA III State Bridge Delivery Program construction summary as of Aug. 31, 2013 Note: Figure 15 is based upon current forecast schedule dates.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
PROJECT STATUS
Overall Status Definitions
In the Project Status Summary table, the overall status of each bundle is identified under the following colors: Bundle status is green if both Schedule and Budget are green. Bundle status is yellow if either Schedule or Budget are yellow and neither are red. Bundle status is red if either Schedule or Budget are red. Bundle status is complete if no further project bundle activities are reported. Note: See page 19 for a schedule and budget status definitions.
Design-Bid-Build
coordinators. complete based on the contractors progress estimate prepared from Contract Payment System (CPS).
Construction Complete. Percent
Design-Build
complete based on the contractors progress estimate prepared from CPS (design cost center).
complete based on the contractors progress estimate prepared from CPS, less the design percent complete.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Project Status Summary Table
All project bundles, except those scoped as No Work, are summarized on the following table. They are listed in sequential order with the first digit representing the bridge program stage (i.e., Bundle 305 is in Stage 3, Bundle A04 is in Stage 1A, etc.). For each bundle, a corresponding bundle information sheet is available at the page number provided. Completed bundles have an abbreviated bundle information sheet in this report, and a full report is available online at www.obdp.org/dashboards.
Design Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Bundle Number
Overall Status
Other Bridges
Bundle Name
20 21 23 24 25 25 25 26 26 26 27 27 27 28 28 28 29 29 29 30 30
210 220 257 259 101 102 103 105 152 154 A01 A02 A04 A05 A06 A07 A08 A11 A12 A51 202
I-84: Sandy River - Jordan Road - Bundle 210 I-5: Willamette River Bridge - Bundle 220 OR 58: Salt Creek Tunnel & Half Viaducts - Bundle 257 I-84: Kamela Interchange - 2nd St. Undercrossing (La Grande) - Bundle 259 Mt. Hood to Chemult (D/B) - Bundle 101 Central Oregon Bridges (D/B) - Bundle 102 US 97: Nevada Avenue to Green Springs Drive - Bundle 103 Zig Zag River - Bundle 105 Spring Creek to Shady Pine Road - Bundle 152 Willow Creek - Bundle 154 I-5: South Douglas County/Louse Creek - Bundle A01 I-5: Clarks Branch to Tunnel Mill Race (D/B) - Bundle A02 I-5: Whiteaker Avenue - London Road - Bundle A04 US 26: Ochoco Creek - Bridge Creek - Bundle A05 I-5: Seven Oaks Interchange - Bundle A06 I-5: North Albany Interchange - Bundle A07 I-5: Row River Construction - Bundle A08 Oregon Avenue - I-5 Overcrossing (Creswell) - Bundle A11 I-5: McKenzie and Willamette River Temporary Bridges Bundle A12 US 26: Rush Creek - Antone - Bundle A51 I-84: Stanton Boulevard - Snake River - Bundle 202
G G R R C C C C C C C C C C C C C C C C C
0 0 3 0 2 13 0 3 0 0 0 2 0 0 1 0 1 1 0 0 0
Step 12 - Progress 50%-100% Step 12 - Const. Progress 50% 100% Step 12 - Progress 50%-100% Step 11 - Progress 0%-50% Step 12 - Complete Step 12 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 12 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Construction Complete
79% 93% 68% 10%
Page
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Design Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Bundle Number
Overall Status
Other Bridges
Bundle Name
30 31 31 31 32 32 32 33 33 33 34 34 34 35 35 35 36 36 36 37 37 37 38 38 38 39 39 39
203 204 205 206 207 208 209 211 212 213 215 216 217 218 221 222 224 225 226 251 255 256 301 302 303 304 306 307
I-84: Burnt River (Dixie Creek) - Lime Interchange Bundle 203 I-84: Encina - Durkee Bridge Repairs - Bundle 204 I-84: Pendleton - North Powder - Bundle 205 I-84: Irrigon Junction - Hilgard Interchange - Bundle 206 I-84: Fifteen Mile Creek - US 97: Spanish Hollow Creek Bundle 207 I-84: Cascade Locks - 2nd Street (Hood River) - Bundle 208 I-84: Dodson - Tanner Creek - Bundle 209 I-5: Wilsonville - Hayesville Interchange (D/B) - Bundle 211 I-5: North Santiam - Kuebler Boulevard (Salem) - Bundle 212 I-5, OR 228 and OR 34: Albany Bridge Repairs - Bundle 213 I-5: McKenzie River (Spores) - Goshen Grade (D/B) Bundle 215 I-5: Sodom Ditch - Calapooia Oflow - Bundle 216 OR 58: Odell Creek - Crescent Creek - Bundle 217 OR 58: Willamette Relief - Logging Road - Bundle 218 OR 58: US 97 Overcrossing - Bundle 221 I-84: Rock Creek - Hostetler Way - Bundle 222 I-84: Exit 64 (Hood River) - Bundle 224 I-84: Hood River - Mosier Creek - Bundle 225 I-84: The Dalles - Fifteen Mile Creek IM - Bundle 226 I-5: Beltline Interchange - Bundle 251 I-5: North Jefferson Interchange - North Albany Interchange (SB) - Bundle 255 I-84/US 395: Stanfield Interchange Improvements Bundle 256 I-5: Eagle Mill Road - Neil Creek Road - Bundle 301 I-5: Creek & County - Central Point - Bundle 302 I-5: South Wolf Creek - Foothills Boulevard - Bundle 303 I-5: Louse Creek - US 199 - Bundle 304 I-5: Weaver (D/B) - Bundle 306 I-5/OR 42: Winston - McLain Avenue - Bundle 307
C C C C C C C C C C C C C C C C C C C C C C C C C C C C
2 6 1 7** 4** 11** 5** 4** 7 8** 10** 6** 2 8** 1 2 1 1 0 2 3 1 5 4** 13** 3 7 5**
3 0 18 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 2 8 2 0 1 0 0 1 0
Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 12 - Complete Step 14 - Complete Step 14 - Complete Step 12 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 13 - Project Closeout Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 12 - Complete Step 14 - Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Construction Complete
Page
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Design Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Bundle Number
Overall Status
Other Bridges
Bundle Name
40 40 40 41 41 41 42 42 42 43 43 43 44 44 44 45 45 45 46 46 46 47 47 47 48 48 48 49
308 309 310 312 313 314 315 316 317 351 352 353 355 357 401 404 405 409 414 415 426 427 428 453 457 460 461 462
I-5: North Umpqua River Bridges (Winchester) - Bundle 308 I-5: Rice Hill Frontage Road - Comstock Cemetery Road Bundle 309 I-5: Coast Fork Willamette - Martin Creek - Bundle 310 I-5: Camas Swale - Saginaw Road - Bundle 312 I-5: Homestead to South Gold Hill - Bundle 313 I-5: Valley View Road (North Ashland Interchange) Bundle 314 I-5: Canyonville - Glendale Interchange - Bundle 315 I-5: Green Springs Highway (Exit 14) - Bundle 316 I-5: North Umpqua River Bridge NB (Winchester) Bundle 317 I-5: Graves Creek Bridge Replacement - Bundle 351 I-5: South Umpqua River and CORP (Shady) - Bundle 352 I-5: Sutherlin to Roseburg (D/B) - Bundle 353 I-5: Exit 99 Interchange Improvement and Bridge Replacements - Bundle 355 I-5: Del Rio Road/Winchester Interchange - Bundle 357 OR 38: Elk Creek - Hardscrabble Creek (D/B) - Bundle 401 OR 31/US 395: Cattlepass - Crooked Creek - Bundle 404 OR 42: Beaver Creek - Mid-Fork Coquille River - Bundle 405 US 20: Harris Road & WPRR - Marys River - Bundle 409 US 395: McKay Creek - Silvies Slough (D/B) - Bundle 414 US 30: Big Creek - Tide Creek - Bundle 415 OR 19: Harper Creek - Mule Shoe Creek - Bundle 426 US 395: Canyon Creek - US 26: Dixie Creek - Bundle 427 US 20: Beaver Creek - Little Beaver Creek - Bundle 428 US 97: Willowdale - Madras Bridges - Bundle 453 OR 7: Powder River - Bundle 457 OR 82: Minam Viaduct & Wallowa River (Minam) Bundle 460 US 395: Smith Creek - Fox Creek - Bundle 461 OR 82: Grande Ronde River and INP Railroad (Indian Creek) - Bundle 462
C C C C C C C C C C C C C C C C C C C C C C C C C C C C
0 0 0 0 0 0 0 0 0 0 4 5 0 0 0 0 3 0 0 0 0 0 0 2 0 0 0 0
Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 13 - Project Closeout Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 12 - Complete Step 14 - Complete Step 13 - Project Closeout Step 12 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 12 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Construction Complete
Page
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Design Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Bundle Number
Overall Status
Other Bridges
Bundle Name
49 49 50 50 50 51 51 51 52 52
508 509 510 511 512 513 556 557 558 560
I-5: Elkhead Road - OR 126: Knowles Creek (D/B) Bundle 508 OR 200: South Fork Siuslaw River - Bundle 509 OR 6: Devils Lake Fork Wilson River - Bundle 510 US 26: East Fork Dairy Creek - McKay Creek - Bundle 511 OR 6: Wilson River - US 26: Highway 47 WB over PNWR (Vadis) - Bundle 512 OR 200: Bear Creek - Bundle 513 US 26: OR 217 - Sylvan Interchange - Bundle 556 US 199: E/W Fork Illinois River Bridge Replacements Bundle 557 US 26: Kern Creek - Lancaster Creek - Bundle 558 OR 230/OR 138: North Umpqua - Upper Rogue - Bundle 560 Totals
C C C C C C C C C C
0 0 0 0 0 0 1 2 0 0 79
Step 12 - Complete Step 13 - Project Closeout Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete Step 14 - Complete
100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
36 OTIA III bridges in No Work bundles are not shown; 1 OTIA III Bridge in Bundle 454 is not included Includes bridges that were rescoped to No Work or Tentative No Work
**
Construction Complete
Page
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108
Bundle Information Sheets
Bundle Information Sheet Abbreviations
ACOE ATA BOC BOT CEI CM/GC CPM D/M/W/ESB DP DAP DAW EA MPB
Army Corp of Engineers Agreement to Agree Bridge Oversight Committee Bridge Operations Team Construction Engineering Inspection Construction Manager/General Contractor Consultant Project Manager Disadvantaged/Minority/Women/Emerging Small Business Design Package Design Acceptance Package Design Acceptance Workshop Expenditure Account ($) Major Projects Branch
NTP OBDP ODOT OPL OTIA PS&E PE RFC RFI RFS ROW TCP WOC
Notice to Proceed Oregon Bridge Delivery Partners Oregon Department of Transportation Office of Project-Letting Oregon Transportation Investment Act Plans Specifications & Estimate Preliminary Engineering Released for Construction Request for Information Request for Services Right of Way Traffic Control Plan Work Order Contract
OTIA III Stage 2 I-84: Sandy River - Jordan Road - Bundle 210
Contract Number: Key Number: OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT Area Manager: ODOT BDU Area Manager: ODOT BDU CPM: OBDP Coordinators: A&E Firm--Project Manager: Contractor--Contact: Percent Complete:
Project Bundle Scope Summary: This bundle consists of two replacement bridges (06875 and 06875A) and two repair bridges (06945 and 06945A). Work also includes a pedestrian tunnel at Jordan Road. Project Bundle Status: Programmatic Permits: The Sandy River bridges (06875 and 06875A) are outside the parameters for programmatic permits due to the large volumes of fill material required. Individual permits for Department of State Lands and US Army Corps of Engineers have been acquired. Project Bundle Activities/Accomplishments: Eastbound Sandy River Bridge: Finish work on the eastbound Sandy River Bridge is ongoing which includes painting the splice plates and staining. Surface texturing (shot-blast) of pedestrian pathway is complete. Painting of crossbeam at Bent 4 is complete; prep work at Bents 2 and 3 crossbeams is underway.
Financial Summary ($ 000's) BOR Budget (OTIA III Bridge Only) BOC Budget (OTIA III Bridge Only) Non-OTIA III Bridge Budget Total Bundle Budget Cost Item
Totals
Westbound Sandy River Bridge: Installation of drilled shafts is complete. Reinforcement tied, columns formed and concrete placed at Bents 2, 3 and 4. Pile driving and installation of launcher beams for WB gantry system is in progress. Riprap placement is underway at Bent 1. Wall 5 sheet pile and riprap installation are underway, and structure excavation for placement of Class 700 riprap within the width of the WB Sandy River Bridge is in progress. Removal of work bridge slips is underway. Forming of Bents 2 and 3 crossbeams has begun. Demolition of old WB structure is complete.
Budget $83,729
Forecast $82,236
Eastbound Jordan Road: Overcrossing bridge widening is complete. The eastbound portion of the pedestrian tunnel is complete. Westbound Jordan Road: Completed driving pile for wingwall D at southeast corner. Installed lagging between pile and placed controlled low strength material (CLSM) behind wingwall. Installation of reinforcement is underway.
Project Bundle Notes of Interest: The contractor was directed to use an overhead construction method in lieu of conventional work bridge and crane delivery. This revised approach adds an additional year of contract time to the project (added by CCO).
The project received federal transportation enhancement funds to complete a section of bicycle path under the Sandy River bridges. The contract has received approval for a revised in-water work timeframe of May 1 to Nov. 30. Issues Being Worked: The state is reimbursing local residents the cost of flood insurance.
Step 12 - Const. Progress 50% - 100% I-5: Willamette River Bridge - Bundle 220
Contract Number: Key Number: OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT Area Manager: ODOT BDU Area Manager: ODOT BDU CPM: OBDP Coordinators: Design/Build Contacts:
G Overall G Schedule G C13480 K14259 08329 (21038/39) None 2 -- Lane Frannie Brindle Jim Cox Karl Wieseke Design: -Construction: Byron Perry OBEC Consulting Engineers Hamilton Construction Co.
Design: 100% Const.:
Budget
Percent Complete:
93%
Project Bundle Scope Summary: Bundle is for replacement of two bridges located on I-5 in Eugene/Springfield. The Willamette River Bridge (08329) will be replaced with separate northbound and southbound bridges (21038 and 21039). The Patterson Slough Bridge (08187) will also be replaced with separate northbound and southbound structures (21041 and 21077). Other work includes roadway improvements, architectural enhancements, park improvements, new overhead sign structure, 13 walls and a pedestrian/bike viaduct. Project Bundle Status: Programmatic Permits: Complete. Project Bundle Activities/Accomplishments: Willamette River Bridge: NB 21038 - The bridge is open to public traffic. Travel lanes are in permanent alignment, SB 21039 - The bridge is open to public traffic. All gawk screens have been removed. Travel lanes are in temporary alignment. Work bridge removal is underway.
Financial Summary ($ 000's) BOR Budget (OTIA III Bridge Only) BOC Budget (OTIA III Bridge Only) Non-OTIA III Bridge Budget Total Bundle Budget Cost Item
Totals
Patterson Slough Bridge: SB 21041 - Bridge is open to public traffic. Travel lanes are in temporary alignment. NB 21077 - Bridge is open to public traffic. Travel lanes are in permanent alignment. Roadway: FN1 (Franklin I-5 NB off-ramp) is open to public traffic. Travel lane is in permanent alignment. LS1/LN1 - southern median work: barriers are slip formed, inlets are raised, and base paving is complete. Right-of-Way: Remaining tasks for the Roadway Weather Information System include fencing and camera installation.
Budget $204,621
Forecast $204,581
Project Bundle Notes of Interest: P20 (Viaduct) (Structure 21327): Construction on all crossbeams has been completed. All salvaged beams have been placed. Remaining work on the bundle includes: Completing all stream restoration south of the UPRR tracks, finishing all design enhancements, completing I-5 southern median work, and finalizing all viaduct construction and park path work.
..Number:
I-5: Willamette River Bridge - Bundle 220 (Supplemental) See Bundle 220 for additional information
Contract Number: Key Number: ODOT RegionCounty: Design Firm: CM/GC Firm:
OTIA III Bridges: Non-OTIA III Bridges: ODOT BDU Area Manager: OBDP Design Coordinator: OBDP Constr. Coordinator: Schedule Forecast 01/31/15
G G G
NTP: Complete:
Actual 07/02/09
Budget $ 52,601
% Compl.: 92%
Scope: DPs 1 and 2 include removing decommissioned Willamette River Bridge, constructing access to the south bank, relocating pathways, establishing staging area in the park, constructing cofferdams and pile driving, constructing parallel work bridges east and west of the decommissioned bridge, installation of the automatic traffic recorder, and constructing the demolition containment system.
Overall G Schedule G Budget G % Compl.: 99%
Scope: DP 3 includes removing the existing Patterson Slough Bridge, constructing the new Willamette River and Patterson Slough southbound bridges, removing and replacing retaining walls, and procuring northbound Patterson Slough concrete girders. Other activities include work on riprap, drainage, sound wall footings, asphalt, striping, temporary illumination, and signage. G Overall G Schedule G Budget % Compl.: 92% DP 4 NTP: Complete: 03/01/10 10/31/14 10/01/10 10/31/14 09/27/10 $ 13,346 $ 12,542 $ 11,254
Scope: DP 4 includes construction of the northbound and southbound roadway, the northbound Patterson Slough Bridge, retaining walls, and drainage.
Overall G Schedule G Budget G % Compl.: 92%
DP 3
NTP: Complete:
08/12/09 10/31/14
10/16/09 10/31/14
10/20/09
37,136
36,800
36,608
Scope: DP 5 includes construction of the northbound Willamette River Bridge and demolition of the temporary structure. Other tasks include sound wall placement, all landscaping, permanent illumination and final pathway work. Note: Actual expenditures are for the soundwall and tree wall at Patterson Slough (part of CCO 9 with an NTP date of Aug. 10, 2010). Cost Scope: Cost for SFO's, EWO's, contingencies, anticipated, and pre-construction items. SUBTOTAL CONSTRUCTION ONLY: SUBTOTAL PE, CEI, ROW, Utility Relocation: TOTAL: Notes:
1. Scope descriptions are for general reference and are not intended to be all-inclusive.
DP 5
NTP: Complete:
07/29/10 01/31/15
01/01/11 01/31/15
08/10/10
47,501
### 48,140 $
43,586
11,547
12,930
3,581
G Budget 14416 K16035 07188 (21567) 07187, 07186, 07185 2 -- Lane Frannie Brindle Jim Cox Ann Sanders -Design: Garry Moyer Construction: Byron Perry Region Design Capital Concrete Construction, Inc.
Design: 100% Const.: 68%
Project Bundle Scope Summary: This bundle consists of one OTIA III replacement bridge (07188), three non-OTIA III replacement bridges (07185, 07186, and 07187), and lowering the floor of an adjacent tunnel (02539). All structures are located on Oregon 58 near Oakridge (mile post 56). Project Bundle Status: Programmatic Permits: The BOC approved alternative permitting. Project Bundle Activities/Accomplishments: The pile footings for all the viaducts are available to traffic. The project is nearly ready for winter shutdown. The contractor has successfully completed lowering the tunnel floor. The contractor has completed work on the tunnel liner and is set to begin painting and lighting repair. The project work requires full closures of Highway 58, Monday through Thursday nights 8 p.m. to 6 a.m. and flagging operations when the highway is open. Check for project information at http://www.58tunnel.com. Project Bundle Notes of Interest: ODOT Region 2 staff is managing this project and performing CEI services. Chuck Lemos is the ODOT project manager. Numerous short-term road closures and restrictions involving single-lane traffic configuration are anticipated. The project will receive Forest Highway Program funds to install variable message signs (VMS) on each side of the tunnel. A revised staging plan calls for paved surfaces throughout most of construction.
Financial Summary ($ 000's) BOR Budget (OTIA III Bridge Only) BOC Budget (OTIA III Bridge Only) Non-OTIA III Bridge Budget Total Bundle Budget Cost Item
Totals
Budget $12,331
Forecast $12,212
Mobile home traffic will be allowed on Highway 126 when Highway 58 is closed for construction.
Issues Being Worked: Due to project delays, work will extend into the 2014 construction season. ODOT and the contractor are in discussions for completing this work. Discussions on traffic requirements for next year are ongoing.
I-84: Kamela Interchange - 2nd Street Undercrossing (La Grande) - Bundle 259
Contract Number: Key Number: OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT Area Manager: ODOT BDU Area Manager: ODOT CPM: ODOT BDU CPM: OBDP Coordinators: A&E Firm--Project Manager: Contractor--Contact: Percent Complete:
G Budget C14555 K17989 00449A None 5 -- Union Craig Sipp Jim Cox Ken Patterson Ronald Reisdorf Design: Byron Perry Construction: William Barnhart Region Design Oregon Mainline Paving, LLC
Design: 100% Const.: 10%
Project Bundle Scope Summary: This bundle consists of one repair bridge (00449A) that was originally repaired in Bundle 206, and also includes a non-OTIA funded project. Project Bundle Status: Project awarded to Oregon Mainline Paving on April 29, 2013. Project Bundle Activities/Accomplishments: All design work is complete. Only the westbound portion of the structure will be completed in 2013 due to delays in obtaining a Right of Entry from Union Pacific Railroad. (See Issues Being Worked for details.)
Project Bundle Notes of Interest: Bid letting delayed at the request of bidding community due to two large projects (over $50 million) being let on the same date. Issues Being Worked: The Class 2 preparation process specified for the bridge deck is being modified and will result in a cost reduction. Class 3 preparation will be required for areas of the existing bridge deck. Because a portion of this work will occur over railroad right of way, the contractor will require a Right of Entry. ODOT will have to compensate the contractor for obtaining the ROE and for the additional insurance not required in the original contract. The ROE from Union Pacific is still pending.
Financial Summary ($ 000's) BOR Budget (OTIA III Bridge Only) BOC Budget (OTIA III Bridge Only) Non-OTIA III Bridge Budget Total Bundle Budget Cost Item
Totals
Budget $706
Forecast $706
Completed Projects
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
I-84: Fifteen Mile Creek - US 97: Spanish Hollow Creek Bundle 207
Project Bundle Scope Summary: This bundle consisted of one replacement bridge (20875) and one repair bridge (08894). Two bridges (07771 and 08893) were scoped to No Work. Bundle 207 included design services and funding for two bridges (07392 and 08276) constructed in Bundle 222, one bridge (07393) and barrier replacement project constructed in Bundle 225, and one Interstate Maintenance (IM) project constructed in Bundle 226. 00308A (20875), 07771, 08893, 08894 None 4 -- Wasco and Sherman -Ronald Reisdorf September 14, 2012 $17,701
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
I-5: North Jefferson Interchange - North Albany Interchange (SB) - Bundle 255
Project Bundle Scope Summary: This bundle included the repair or replacement of 11 bridges on I-5 north of Albany. The three OTIA III bridges were repaired and the remaining eight non-OTIA III bridges were replaced. 08124, 08122, 08121 08115 (19217), 08119 (19218), 08120 (19219), 08125 (19220), 08127 (19222), 19224, 19226, 19227 2 -- Marion, Linn --June 1, 2006 $26,879
ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
Completed Projects
I-5: Rice Hill Frontage Road - Comstock Cemetery Road - Bundle 309
Project Bundle Scope Summary: This bundle consisted of six repair bridges (07644A, 07642, 07640, 07640A, 07567B, and 07569A) and the Interstate Maintenance (IM) pavement preservation project (I-5: Martin Creek - Anlauf Roadway Repair). Bridge 07584A was scoped to No Work. 07644A, 07642, 07640, 07640A, 07567B, 07569A, 07584A None 3 -- Douglas -Chris Hunter April 30, 2010 $5,833
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
OR 82: Grande Ronde River & INP Railroad (Indian Creek) - Bundle 462
Project Bundle Scope Summary: OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's): This bundle consisted of one replacement bridge (08780) in Region 5. This bridge was designed in Bundle 460. 08780 (21292) None 5 -- Union Ken Patterson Ronald Reisdorf October 12, 2012 $5,239
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
OTIA III Bridges: Non-OTIA III Bridges: ODOT Region--County: ODOT CPM: ODOT BDU CPM: Completion Date: Expended ($000's):
Completed Projects
Completed Projects
Completed Projects
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108 APPENDIX A: CASH FLOW
OTIA III State Bridge Delivery Program Cash Flow Projection
$250 $225 $200 Current Budget (Incr.) Actuals (Incr.)
$1,200 $1,400
$1,000
$600
$400
$200
$25 $Current Budget (Incr.) Actuals (Incr.) Current Budget (Cum.) Actuals (Cum.) Planned (Oct. '05 MPR)*
$0
2002 $0.0 $0 $0 $0 $1
Program Calendar Years Notes: Budget data source is OBDP BRS; forecast timeframe is based on August 2013 month end OTIA III Program Master Schedule calendar years. Actuals are current as of August 2013 month end. Value will be increased as the current calendar year progresses. * The October 2005 MPR cash flow was based on anticipated accruals. Budget curves are based on anticipated expenditures (lagged to account for payment processing). Actuals for 2009 include a ~$9.6 M reduction for January 2009; expenditures were reallocated to OBDP Program Management Oversight. Actuals for 2010 include a ~$12.3M reduction for November 2010; expenditures were reallocated to non-OTIA III (SAFETEA-LU) on Bundle 220.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108 APPENDIX B: COST REPORT
Stages Stage 1 10-000 11-000 12-000 13-000 14-000 10-000 11-000 12-000 13-000 14-000 10-000 11-000 12-000 13-000 14-000 10-000 11-000 12-000 13-000 14-000 10-000 11-000 12-000 13-000 14-000 Design ROW Utility Relocation CEI Construction Stage 1 Subtotal Design ROW Utility Relocation CEI Construction Stage 2 Subtotal Design ROW Utility Relocation CEI Construction Stage 3 Subtotal Design ROW Utility Relocation CEI Construction Stage 4 Subtotal Design ROW Utility Relocation CEI Construction Stage 5 Subtotal Design ROW Utility Relocation CEI Construction Original (EBOR) Budget 6,604,344 6,604,344 44,028,960 57,237,648 54,397,577 54,397,577 362,650,510 471,445,663 52,404,972 52,404,972 349,366,480 454,176,424 21,091,889 21,091,889 140,612,590 182,796,367 11,614,565 11,614,565 77,430,435 100,659,566 146,113,346 146,113,346 974,088,975 1,266,315,668 77,255,333 1,343,571,000 Sep. 2005 Approved Budget 7,491,000 4,471,000 58,483,000 70,445,000 37,727,000 420,000 40,237,000 350,545,000 428,929,000 40,800,000 979,000 43,100,000 369,032,000 453,911,000 16,740,000 884,000 19,699,000 137,662,000 174,985,000 12,074,000 352,000 14,297,000 125,657,000 152,380,000 114,832,000 2,635,000 121,804,000 1,041,379,000 1,280,650,000 62,921,000 1,343,571,000 Approved Changes (3,058,899) 337,925 (945,377) (2,424,961) (6,091,312) 31,207,018 375,782 224,060 18,302,773 71,939,809 122,049,442 7,312,148 2,422,328 1,275,683 (6,470,207) (62,516,612) (57,976,660) 6,214,255 (614,952) 19,747 (11,838,227) (28,842,004) (35,061,181) 9,162,849 170,641 87,234 (7,305,696) (59,803,039) (57,688,011) 50,837,371 2,691,724 1,606,724 (8,256,734) (81,646,807) (34,767,722) 45,000,000 (53,803,278) (43,571,000) Aug 2013 Approved Budget 4,432,101 337,925 3,525,623 56,058,039 64,353,688 68,934,018 795,782 224,060 58,539,773 422,484,809 550,978,442 48,112,148 3,401,328 1,275,683 36,629,793 306,515,388 395,934,340 22,954,255 269,048 19,747 7,860,773 108,819,996 139,923,819 21,236,849 522,641 87,234 6,991,304 65,853,961 94,691,989 165,669,371 5,326,724 1,606,724 113,547,266 959,732,193 1,245,882,278 45,000,000 9,117,722 1,300,000,000
3
Aug 2013 Expended 47,841 307,602 4,275,028 4,630,471 345 14,086 29,933 44,364
9,940
Expended to Date 4,213,175 337,946 3,672,754 55,976,742 64,200,617 68,567,577 556,034 224,060 45,121,515 383,755,234 498,224,420 50,021,582 3,138,006 825,776 32,815,151 311,385,212 398,185,727
21,624,368 269,048 19,747 7,646,677 109,795,686
Stage 2
Stage 3
Stage 4
337 10,277 952 2,816 3,768 48,186 332,580 4,308,113 4,688,880 4,688,880
139,355,525 20,943,060 443,860 82,278 5,866,908 60,420,274 87,756,381 165,369,762 4,744,895 1,151,861 95,123,005 921,333,148 1,187,722,671 1,187,722,671
Stage 5
OTC Allocation to Pioneer Mt.-Eddyville Project Phase 2 19-000 Program Reserve Stage Total w/Program Reserve Oversight Oregon Bridge Delivery Partners Major Projects Branch Environ./Engr. Baseline Rpts. & Streamlining Compliance Auditing & Performance Mgmt. Gorge Aesthetic Design Manual Miscellaneous (IGAs) Oversight Total Grand Total 87,332,115 26,717,855 21,250,000 12,000,000 350,000 2,000,000 149,649,970 1,493,220,970 87,332,115 26,717,855 21,250,000 12,000,000 350,000 2,000,000 149,649,970 1,493,220,970
2 2 2 2 2 2 2
Bonding Budget and Fees have been deleted from the cost summary report per direction of OTIA III Program Funding Committee.
2 3
Oversight Budgets updated February 17, 2011 to align with forecasted expenditures. OTC allocation to Pioneer Mt. - Eddyville Project Phase 2 approved on January 16, 2013.
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108 APPENDIX C: OREGON TRANSPORTATION COMMISSION SUMMARY
Final Report
Summary of Design:
Previous Month Bridges Remaining to Begin Design: 0 Bridges in Design: 0 Total Design: 0 Previous Month 7 0 202 209 Previous Month 84 84
Summary of Construction:
Bridges in Construction: D/B/B Bridges Open to Traffic: Bridges with Construction Complete: Total Construction:
$ $ $ $
$ $
293
293
893,511,519
$ (1,200,275)
892,311,244
Summary of Design/Build
Bridges Remaining for Design & Construction: Bridges in Design & Construction: D/B Bridges Open to Traffic: D/B Bridges with Construction Complete: Total Design/Build:
Change 0 0 0 0 0 Change 0 0
Grand Total Design/Build: Grand Total OTIA III Program Budget (w/o PM): Program Target: OTC Allocation - Pioneer Mt. Eddyville Project Phase 2: Program Reserve:
72 365
0 0
72 365
353,571,034
353,571,034
$ 1,247,082,553
$ (1,200,275)
OTIA III STATE BRIDGE DELIVERY PROGRAM Monthly Progress Report No. 108 APPENDIX D: REFERENCE LIST
The following items, previously published in the OTIA III State Bridge Delivery Program Monthly Progress Report, can now be found online at www.obdp.org/mpr. Safety Status Summary of Stages 1-5 Progress Summary of Stages 1-5 Progress by Project A&E and Construction Contracts Master Schedule Performance Measurement 13-Month Look Ahead