Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Guidance: Yellow cells are the input information to be suitably filled. Green cells are to be reviewed and modified/updated if need be. Red letters to be suitably corrected.
Ground level at STP Site at Inlet chamber Drain level at outlet at chainage 11325 IL of Out fall Sewer(1000 mm) with slope 1 in 1100 at STP Average Flow Average Flow Peak Flow : Peak Flow : Minimum Flow Minimum Flow Peak Factor Factor 2.25 2 209.5 Mtr 206.2 Mtr 215.68 Mtr 25 MLD 0.29 M3/sec 56.25 MLD 0.65 M3/sec 12.5 MLD 0.14 M3/sec 56.25 MLD 0.65 M3/sec 15 Sec 9.77 cum 0.8 Mtr 12.21 M2 3.5 Mtr 3.5 Mtr
45 degree 0.71 0.60 m 2.12 1.03 mtr 21 nos 20 nos 10 mmx75 mm 1230 mm 50 mm
Total width of channel: Provide Openings No of bars Size of Coarse Screen-Width Size of Coarse Screen-Length Velocity in Channal u/s of Screen Velocity through Screen Head Loss No Clogging Velocity when 50% clogging Head Loss when 50% clogging
mm
m m
m m/sec m
Two grit removal tank (1 w +1 S) each capable of handling peak flow, will be provided. They are designed to remove grit particle of size of 0.15 mm size and above with a specific gravity of 2.3 Q/A=VS x n/(1-)-n-1
Where--Desired efficiency of removal of grit particle VS -settling velocity of minimum size of grit particle to be removed Q/A--Design surface overflow rate applicable for grit chamber to be designed n-an index which a measure of the basin performance Here value taken Say Here VS value taken Here n value taken-1/8(for very good performance) Hence surface over flow rate(Q/A)=(Vs*n)/(((1-)^-n)-1) Say This Q/A value has to be reduced to allow for deposition of sand during sand strom by Then design overflow rate Peak flow(m day) Hence area required for peak flow
3/
75 % 0.75 1225 m3/m2/day 0.13 806.42 m3/m2/day 810 m3/m2/day 10.00% % 729 m3/m2/day 56250 (m3/day) 77.16 m2
Each side of square grit chamber 8.78 mtr. Hence provide tank length 9.00 mtr. Hence provide tank Width 9 mtr. Detention time taken is 1 minute Depth of tank will be 0.48 mtr. However in order to provide adequate depth for the grit 0.9 mtr. scraping mechanism, increase to This gives detention time is 1.87 minute the detention time of 1.87(slightly higher) minute is immaterial for mechanically cleaned grit removal tank Hence size of grit removal chamber is 9 x9x0.9 Flow height above, H 0.12 m weir,Q=(2/3)*Cd*L*H^1.5*((2g)^.5),Cd=.6,L=9 DESIGN OF CHANNEL FROM GRIT CHAMBER TO DISTRIBUTION CHAMBER
Peak flow velocity taken Area required Depth taken Then width of channel will be 0.65 0.8 0.81 0.7 1.16 M3/sec M/sec m mtr. mtr.
2
Q- average flow - volumetric BOD loading(Range between 100-400 gm/m3/day) =20T-100(as per MEAFNRCD) T=mean temperature in coldest month in 0C (The manual by DANIDA ENRECA suggests T as mean in coldest month or quarter. In quarter it is 15.55) hence is Hence Volume of tank(V) Detention time Detention time of 2 days or more is desirable to achieve sufficient BOD removal Hence Volume of each tank (V) Hence Volumetric BOD loading() is BOD removal efficiency(in %)=2T+20 For liquid depth Area at mid depth Length shall be L=2B Hence mid depth width B=(area/2)1/2 Hence mid length LSide slope of pond is 1V :2.5 H Depth for Sludge bottom below Mid depth Free Board Top of embankment above mid depth Hence total top length(L) Hence total top width(W) Area at top Hence total bottom length (L) Hence total bottom width(W) Area at Bottom Provide three anaerobic pond each of 108.8mx63.1m at top surface and 78.8mx33.1 m surface at bottom
8333 (m3/day)
13.89
177.8 kg/ha/day 14061 m3 1.69 day 2.00 day 16667 m3 150 gm/m3/day 47.78 % 4 mtr. 4167 m2 45.6 mtr. 91.3 2.5 1 2.5 1 3.5 108.8 6869 78.8 33.1 2611 mtr. mtr. mtr. mtr. mtr. mtr. m2 mtr. mtr. m2
63.1 mtr.
where E is elevation in meters= then s is Influent BOD to facultative pond value of s is considered recommended as MEAFNRCD
210
From equation (as per world bank paper) facultative mid depth area can be calculated as(A) A=10 x Li x Q/s A-facultative area at mid depth in m2 Li-influent BOD concentration in mg/l, Li is BOD to be removed Effluent to be used for restricted irrigation as such 100 effluent BOD is ok however on safe side design for effluent BOD of Li= then A is Divide the area in two ponds(area of each facultative pond) at middle of tank Take L=2B Then width B=(A/2)1/2 Then L is at mid depth Hence area at mid depth is Adopt liquid depth Adopt depth for sludge Adopt Free Board Total Depth of tank Area at bottom embankment slope H/V Length at bottom width at bottom Hence area at bottom is Length at top including 1.0 mt free board width at top including 1.0 mt free board Area at top including 1.0 mtr free boardVolume of pond V=h/6(S0+4S1+S2) h-height(liquid depth) S0-area at top S1-area at mid water depth S2-area at bottom Hence V of each tank is Then detention time of each tank is Total detention time of anaerobic + facultative pond is Total area of ll afacultative ponds at top Total area of all anaerobic ponds at top Total area Assuming footprint area of units as % of total area Hence total area is1.5 m 45456 m2 42678 m2 39978 m2 64037 m3 5.12 days 7.12 days 90912 m2 20608 m2 111520 m2 60.00% % 185867 sqm 75
146 M 292 M 42678 M2 1m 0.5 m 1m 2.5 2.5 285.9 m 139.8 m 39978 m2 298.4 m 152.3 m 45456 m2
Hence total area in hectare taken as Total BOD removal in facultative pond Hence Effluent BOD is
18.59 hactare 19 81.66 mg/l 75 mg/l 231481 0.04 9259.26 8692.08 1.07 1
cum per capita/year cum/year
cum
years
years
0.325520833 1.5 0.24 0.1 0.34 0.30 0.33 0.75 0.74 60.00 0.027 0.042 0.068
Allow free fall Total Head loss Half flow from one anaerobic pond, Length of weir
0.1 m 0.19 m 1.50 m 0.145 0.600 0.51 40.00 0.011 0.020 0.031 0.145 3 0.09 0.1 0.19 0.145 0.600 0.51 40.00 0.011 0.020 0.031 0.145 0.600 0.51 40.00 0.011 0.020 0.031 0.289 0.80 0.58 160.00 0.041 0.025 0.066 1.0 0.289 0.4 0.8 0.000090 0.1 cum/sec m m/sec m m m m cum/sec m m m m cum/sec m m/sec m m m m cum/sec m m/sec m m m m cum/sec m m m m m m/sec sqm m m in 1000
Flow Flow in LPS say Head Pump working Pump stand bye Flow in each pump pump efficiency Pump KW Motor KW Say Total No of pumps working + stand by Delivery Pipe velocity Pipe Area for combined flow of two pumps Pipe dia Say Pipe dia of delivery for each pump, velocity Pipe Dia Say Suction Pipe dia
0.289 289.35 290.00 15.00 2.00 2.00 145.00 60.00 35.54 39.09 40.00 4.00 0.75 0.387 0.702 750 2.25 0.29 300 250 25 30 521 4 12.88 13.00 531 1.16 0.06 2798412.9 0.898
Free Board
F=(log10 A)^.5-1, F= Wave height,H, (g*H)/V^2=.0026((gFe/V^2)^0.47, Fe is fetch,V is wind velocity, H=
Helminth Removal
R % removal=100(1-0.14 Exp(-0.38)) R % removal as per the table in book by DANIDA 99.33 % 98.6 %