STATE UNIVERSITY CONSTRUCTION FUND

MANAGEMENT
OF

CONSTRUCTION PROJECTS

353 Broadway, Albany, New York 12246 518 320320-3210 Fax: 518 689 689-2638 www.sucf.suny.edu 11/21/11 21/11 dw

TABLE OF CONTENTS

Construction Document Phase Prologue Construction Prologue Construction Contracts Table 1 Contract Check List Table 2 Contract Distribution Construction Phase Payments and Reimbursements Closeout of Construction Contract Publicity and Disclosures Appendix

PAGE NO. 3 4 7 8 9 10 17 35 40 41

Office of Construction Management Management of Construction Projects

Page 2 Construction Prologue

Construction Document Phase Prologue

Construction Prologue Activities Prior To Bidding The Bidding Period Addenda and Amendments to Fund Documents Bid Tabulation After Bid Opening Bid Analysis Meeting Pre-Award Meeting Contract Award Building Permits

Office of Construction Management Management of Construction Projects

Page 3 Construction Prologue

Construction Prologue
The Consultant has been guided through the design phases of its project by the State University Construction Funds three objectives achieving quality architecture, on schedule and within budget limitations. The product of these efforts will be lost unless it continues to pursue these objectives during the construction of the project. Final achievement of these objectives depends not only on the Consultants proper involvement during design but on its continued and proper involvement during construction. This document does not supersede any provisions of the Contract In achieving these objectives during design, the Fund has emphasized the Consultants responsibility for project development and management. Therefore, it is imperative that the responsibility for the management of projects under construction rests with the Consultant. This manual is devoted to the design and construction phase procedures and requirements necessary to achieve the Funds objectives during construction and to assist the Consultant in assuming its full responsibilities1. It is understood the purpose of this manual is to provide guidance in these procedures and does not supersede any provisions of the contracts. The Consultant is required to provide proper staffing capacity and resources for taking projects through design phases. It is equally important to properly organize and staff a project during construction. The Fund expects the Consultant to provide complete services during the construction phase with frequent inspections of the work at the job site by its office personnel and those of its Consultants. In addition, the Fund requires that the Consultant maintain, at the site, a field staff sufficient to provide for the daily administration of construction. Planning and organizing for the staffing of this field office should begin well before the project is put on the construction market. The number and composition of the field staff should be planned in consideration of the type and complexity of the construction project and with the aim of organizing the staff to meet the Funds major objectives. ACTIVITIES PRIOR TO BIDDING: During the construction document phase, the Consultant is to develop a plan of organization for its field staff and submit the proposed plan to the Fund Assistant General Manager, Office of Construction Management, for approval. After approval of the plan, the Consultant and its Consultants shall conduct interviews to fill the authorized positions after bid. The nominations (with the proposed salaries and a resume of the candidates' experience) are to be sent to the Assistant General Manager, Office of Construction Management. Final interviews will be arranged and, upon consent of the Fund, a salary and starting date for employment will be established. THE BIDDING PERIOD: The most important role the Consultant plays during the bidding period is in attracting and interesting qualified Contractors to participate in the bidding for construction of SUCF projects. To best attract and interest qualified Contractors in Fund projects, the Consultant may have to begin these activities prior to putting a project on the market. This may require the Consultant to make an inventory of Contractors who have bid or
Where Federal funds are involved, the separate Fund bulletin dealing with projects involving Federal Funds should be followed
1

Office of Construction Management Management of Construction Projects

Page 4 Construction Prologue

might be expected to bid on projects in its area and to seek out those Contractors to determine their willingness to bid on the project or to attempt to stimulate such interest. An assessment of Contractor interest is important for developing a final cost estimate for the project. During the bidding period, the Consultant shall report weekly, in writing, to the Funds Design Project Coordinator2 the names, addresses and roles of all those requesting plans and specifications. In addition, the report should indicate its appraisal of the sincerity of potential bidders. It should describe the activity that it is engaging in to attempt to interest additional Contractors or subcontractors in bidding the project. The Consultant must also submit a final report, three days prior to the bid opening, which then currently identifies likely bidders. ADDENDA AND AMENDMENTS TO FUND DOCUMENTS: No addenda, revisions, deletions or additions will be made by the Consultant to the Funds standard documents without prior approval by the Fund. All addenda issued by the Consultant during the bid period are to be approved by the Fund prior to being issued, and only in extreme cases will an addendum be issued during the last week of the bidding period. AFTER BID OPENING: With the opening of bids, responsibility for monitoring the bid project continues within the Design Section of the Office of Design. The Consultants primary point of contact in the Fund remains the designated Design Project Coordinator. The Funds Project Coordinator assignment, from design to construction, will be changed effective with award of the construction contract. BID ANALYSIS MEETING: After the bid opening there may be a Bid Analysis Meeting at the Fund offices with representatives of the Design Section of the Office of Design and Construction Management for the purpose of analyzing bids. This meeting must be attended by the Consultant and its principal Consultants. The Consultant chairs the meeting and must prepare minutes for distribution to the participants. The Consultant, Design Project Coordinator and Regional Director of Design are provided with one copy of all bid proposals for use in analyzing bids. There is a Post-Bid Checklist specimen included in the Appendix, which is to be followed. At the end of this meeting, the original copies of all bids must be deposited with the Fund for inclusion in the permanent record. Immediately after the three lowest bids have been identified, the Fund will notify these bidders via email, requesting each bidder name its principal subcontractors and provide all other qualifying data within the 48-hour time limit specified in Information for Bidders, Section 8, Submission of Post-Bid Information. This may be an update of previously filed data in the case of Contractors who previously submitted this material. The request also emphasizes that submission must be prepared in duplicate, one copy to be submitted directly to the Consultants main office and one copy directly to the Fund Assistant General Manager, Office of Construction Management. The necessary documents must be received no later than 2:00 P.M. of the second business day following opening of bids. PRE-AWARD MEETING: As soon as possible after the qualifying data has been reviewed, a Pre-Award Meeting may be scheduled and convened by the Consultant with the concurrence
2

Fund Project Coordinator will be designated for each project.

Office of Construction Management Management of Construction Projects

Page 5 Construction Prologue

of the Fund. The purpose of the Pre- Award Meeting is to assess the capacity of the low-bid Contractor to perform the necessary work. The assessment considers the character and scope of the Contractors past performance, financial capacity, availability of personnel, equipment, and the capability of the nominated subcontractors. In some instances it may be desirable to review the qualifications of Contractors other than the lowest bidder at this meeting to provide the Consultant with information necessary to permit a viable recommendation for the award of the Contract. Prior to this meeting the Consultant must review the experience and qualifications of the low bidder and its designated subcontractors with other Consultants, Contractors, and the Owner for whom they have previously performed work. Usually, the Pre-Award Meeting is held at the Fund office. The Consultant chairs the meeting and prepares the minutes. Attendees at this meeting should include the Consultant and its Principal Consultants, the low-bidding Contractor with, if special project conditions warrant, its proposed Principal Subcontractors and Fund representatives. On the basis of the qualifying data and any other information received and discussed at the Pre-Award Meeting, the Consultant will submit to the Design Regional Director, in writing, its recommendation on the award of a Contract. CONTRACT AWARD: The Bidding Period ends with an affirmative decision by the Fund regarding the award of the Contract. The successful low bidder will be sent a Notice of Award letter which serves as the Funds formal letter of intent. Concurrently, the Funds legal office will assemble the complete formal Contract for execution by the Contractor, and the Fund. The Contract will be forwarded to the Contractor for execution under cover of a separate Fund letter, as described in the next section of this manual titled Construction Contracts. It is important that Contractors, Consultants and other involved parties recognize no payments may be made under the authority of the Notice of Award letter. Full execution of the Contract is required prior to physical work commencing on the site. Issue of the Notice of Award letter also marks, internal to the Fund, the transition of project coordination responsibility from the Design Section to the Construction Management Section. A construction phase Project Coordinator will be assigned who will monitor formal Contract execution status and, when nearly complete, contact the Consultant and Contractor to schedule a Pre-construction Orientation Meeting. BUILDING PERMITS: Building Permits will be issued by the Design Section of the Office of Pre-Construction Services. Prior to construction, the Fund will mail to the Contractor the building permit for the project or, if applicable, a waiver of the building permit. This document must be posted conspicuously on the construction site for the duration of the project.

Office of Construction Management Management of Construction Projects

Page 6 Construction Prologue

Construction Contracts
CONTRACT DOCUMENTS: The Construction Contract is the agreement between the Fund and the Contractor for the construction of the Project. By the Bid Opening, the Project Consultant must have delivered to the Fund Assistant General Manager, Office of Construction Management six (5), unbound copies of the following documents: A. B. C. D. E. F. G. H. I. J. K. Covers and Cover Sheet Table of Contents Notice to Bidders Information for Bidders Agreement List of allowances included in bidding documents List of unit prices included in bidding documents (prices are to be left blank) Performance Bond Labor and Material Bond Division I of the Technical Specifications All Addenda

After the project is awarded, the Funds legal office prepares the Contract (Agreement) and forwards the documents to the Contractor for execution. A copy of a letter of transmittal containing instruction for Contract execution is included as Item 2 of the Appendix. After the Contractor signs the Contract (Agreement) and returns to the Fund, the Fund will then sign and return one original Contract back to the contractor. When the Contractor receives the completed Contract, the Fund will issue the Notice to Proceed letter. The Contract start date is at receipt of the Notice to Proceed letter. REFERENCE TABLES: Table 1 is a Contract checklist indicating the items that must be completed in all Fund construction Contracts. Table 2 indicates the distribution of Fund construction Contracts after execution by both parties and approvals by the necessary governmental agencies.

Office of Construction Management Management of Construction Projects

Page 7 Construction Contracts

TABLE 1 CONTRACT CHECKLIST PROPOSAL


PAGE P-1 Bidders Name and Address Full Project Title Project Location SUCF Project Number Completion Date Liquidated Damages (If none, so state) PAGE P-2 Item 5.A: Total Bid (Words and Figures) Item 5.B: Alternates (Words and Figures) for Proposed Work Item 5.C: Unit Prices Item 6: Allowance PAGE P-3 Bid Security Amount Contractor Name Signature/Title of Contractors Authorized Officer Seal (If Corporation) Item 9: Addenda, with date(s) PAGE P-4 Bidders Official Address. If Bidder is a corporation list of corporate officers, or partners or joint venture, or individual owner, with names and addresses. AGREEMENT PAGE A-1 Contractors Name and Address Date (Effective Date in Notice of Award) Full Project Title, including SUCF Number Completion Date Liquidated Damages PAGE A-15 4.01: Total Contract Amount (words/figures) PAGE A-28: Contractors Name Signature of Contractors Authorized Officer Seal (If Corporation) PAGE A-29 Acknowledgements SCHEDULE Unit Prices (must confirm with those in Notice of award; if none, so state) SCHEDULE II Allowances (Type/amounts; if none, so state) LABOR AND MATERIAL BOND PAGE B-1 Contractors Name and Address Surety Company Name and Address Contract Amount (words/figures) Contract Date Project Title, including SUCF No. Date (On or after Contract Date) Contractors Name Signature of Contractors Authorized Officer Seal (If Corporation) Surely Name Signature of Suretys Attorney-in-Fact or other representative Seal of Surety (If corporation) ACKNOWLEDGEMENT BY PRINCIPAL PAGE B-3 Complete all blanks in Acknowledgement of Principal (Contractor), including notary signature, notary seal, showing expiration date of notarys commission. Complete all blanks in Acknowledgement of Surety, including notary signature, notary seal, date (should on or after Contract date). PERFORMANCE BOND PAGE B-2 Contractors Name and Address Surety Company Name and Address Contract Amount (words/figures) Contract Date Project Title, including SUCF No. Date (on or after Contract date) Contractors Name Signature of Contractors Authorized Officer Seal (If Corporation) Surety name Signature of Suretys Attorney-in-Fact or other representative Seal of Surety (If Corporation) be

Office of Construction Management Management of Construction Projects

Page 8 Construction Contracts

TABLE 2 CONTRACT DISTRIBUTION3

Document

General Construction Contract:


Distribution (Executed) 2 To the Fund 1 To the Consultant 1 To the Contractor

Total Copies Required: 4

Federal Contract:
Distribution (Executed) 2 To the Fund 1 To the Consultant 1 To the Contractor 1 To Federal Government

Total Copies Required: 5

The Contractors corporate seal must appear on all papers which it signs.

Office of Construction Management Management of Construction Projects

Page 9 Construction Contracts

Construction Phase

Pre-Construction Orientation Meeting Correspondences, Reports, Construction Phase Submittals Communication between Fund Consultants and Contractor Communication with Bonding Company Reports to the Fund Construction Phase Review of Submittals Full-Time Superintendent Job Meetings Backcharging Asbestos and Lead Abatement Projects PCB and Regulated Materials Projects Sales and Use Taxes and Exemption Changes to the Contract Claims and Disputes

Office of Construction Management Management of Construction Projects

Page 10 Construction Phase

Construction Phase
The Consultant shall furnish general administration for each construction Contract awarded for the project until final completion and acceptance by the Fund for construction of the project, including services throughout the guarantee period. Pre-Construction Orientation Meeting: The Orientation Meeting is held to review the purpose, goals, organization and Contract requirements as related to the project. The meeting affords an opportunity for those individuals who will be working together to become familiar with each other, clarifying the responsibilities of each party. The meeting will be chaired by the Consultant and is usually held at the project site. Attendees will include Fund personnel, Consultants representative, General Contractor (designed mechanical, electrical, and other proposed principal subcontractors as required), and a representative of the University/College if applicable. A representative of the Federal Government (or any other relevant potential sponsor) may be present if a Federal project is included. The purpose of the meeting will be to review: The administrative aspects of the construction phase. An overview of the project, drawing attention to any particular aspect or special condition associated with the project, along with a generic discussion of the Contractors proposed overall construction schedule. Special attention is to be given to contractual phasing requirements.

This meeting is also for the implementation of solutions to the coordination of issues related to maintenance and control of pedestrian and vehicular traffic, construction fencing (long and short duration), safety, Contractors control to the site, parking, temporary utilities, etc. Correspondence, Reports Construction Phase Submittals COMMUNICATION BETWEEEN FUND, CONSULTANTS, AND CONTRACTOR: The Consultant and the Contractor will communicate directly with each other unless directed otherwise. Copies of all correspondence are to be issued to the Fund Project Coordinator on all matters. The Consultant, as the Funds Representative, will provide determinations of the content/intent of the technical plans and specifications. The Consultant has the sole responsibility for receiving and acting upon all technical submittals of all types, including samples, shop drawings, catalog cuts, brochures, test data, etc. For interpretation affecting Contract cost and/or material substitution, prior concurrence of the interpretation must be obtained from the Fund. It is the Consultants responsibility to monitor the Contractors scheduling of submissions.

Office of Construction Management Management of Construction Projects

Page 11 Payments and Reimbursements

There are particular items for which the Consultant should instruct the Contractor to submit, simultaneously to the Fund Project Coordinator at the time the originals are sent to the Consultant: These items are as follows: 1. PROJECT SCHEDULE: An initial project schedule in the form of a suitable chart, diagram or bar graph is required to be submitted for approval within 15 days after receipt of Notice to Proceed, showing sufficient detailed information to reflect the first 90 days of Contract activity. Since the Fund strives to hold the initial project orientation meeting as soon as possible after award, the 90-day schedule should be available for review at this meeting. Within 60 days after receipt of Notice to Proceed, the Contractor shall submit a Working Plan Schedule, which shall be a critical path method schedule. The Contractors provided schedule is reviewed for constructability and conformity to the Contract requirements. Therefore, if the Contractor chooses to accelerate the projects completion date from the contractual completion date, the Fund realizes that it is everyones benefit to progress a project schedule as efficient and timely as the Contractor deems appropriate. It should be noted that the Contractors schedule does not change the contractual completion date. The project schedule is to be reviewed by the Consultant and forwarded to the Fund with comments. The Fund will respond to the Consultant with the Funds review prior to responding to the Contractor. The Project schedule is not to be approved, only returned to the Contractor with comments. The project schedule must indicate the Contract completion date. Both of these items must be submitted and reviewed before the Contractor may receive its initial payment and that said date should be shown on the project schedule, along with any early targeted completion date. 2. CONTRACT BREAKDOWN (Fund Form CF-C2): Prior to submitting an initial payment, the Contractor must obtain an approved Contract breakdown (Schedule of Values) for the purpose of tracking Contract completion and payment. The breakdown shall provide sufficient detail on one page, as required by both the Consultant and the Fund, to have a full understanding of Contract progress. If the scope and size of the project does not allow enough detail to be provided on the CF-C2 (Appendix Item 6), supplemental details shall be shown on Fund Form DC-5 (Appendix Item 9). In general, the Fund only pays for work in place, and the Contract breakdown should only reflect these types of activities, with the exception of bonds. Bonds should be listed as Item 1 on the Contract Breakdown Sheet (CF-C2); proper proof of payment of the bonds as required by the Fund shall be provided before payment of said item. The guarantee item, if required by the Contract, shall be listed as the last item. Any deviations to this format as requested by the Contractor, shall have the approval of both the Consultant and the Fund. The Contract breakdown should be forwarded to the Fund with recommendations. The Consultant must have the Funds concurrence of the Contract breakdown prior to approval.

Office of Construction Management Management of Construction Projects

Page 12 Construction Phase

After review of the Contractors Contract Breakdown and the Consultants recommendation, the Fund will advise, in writing, the Consultant of its decision. This decision will be communicated, in writing, by the Consultant to the Contractor. 3. LIST OF PROPOSED SUBCONTRACTORS AND VENDORS: All subcontractors are approved by the Consultant but only with Funds concurrence with the exception of the subcontractors designated by the Fund in the Notice of Award. The General Contractor is responsible to submit a complete subcontractors listing with qualification within 30 days of Notice of Award. 4. COST PROPOSALS: (See Change Order / Field Order Section for more detailed information). 5. CLAIMS: (See Claims and Disputes). When a Contractor reserves his rights and submits a claim, the Consultant must then review the claim and provide comments and recommendations to the Fund. No copy of this correspondence is sent to the Contractor or the Campus. The Fund will review the Consultants recommendations and respond. COMMUNICATION WITH BONDING COMPANY: No communication should be sent by the Consultant employed by the Fund to a Contractors Bonding Company unless such a letter has been approved, in writing, by either the Funds Counsel or Assistant General Manager, Office of Construction Management. REPORTS TO THE FUND: The Consultant must submit the following reports to the Fund: Log of shop drawings and sample submittals (Substitutions and equivalents must be identified) - Monthly Daily Field Reports - As Requested Open Item Log at Project Meetings RFI Log at Project Meetings Log of required tests At onset of project, updated as requested O&M Training and Commissioning Requirements As requested

The format for each respective report shall be submitted by the Consultant within the first 30 days to the Fund for approval. CONSTRUCTION PHASE REVIEW OF SUBMITTALS: For all Fund projects which include a liquidated damages clause, every effort is to be made to avoid situations that would stimulate claims for delay or impact to be made against the Fund. Such claims nullify the effectiveness of the liquidated damages clause and cause untenable delays in construction. During the construction phase, shop drawings and other submittals of the Contractor are to be reviewed and, when acceptable, approved promptly. Shop drawings are to be reviewed as quickly as possible after their receipt and approval letters sent to the Contractor immediately when such drawings and other submittals are acceptable.

Office of Construction Management Management of Construction Projects

Page 13 Construction Phase

When shop drawings and other submittals are found unacceptable or incorrect, their rejection should be prompt, complete and documented. Whenever shop drawings and other submittals do not meet Contract requirements, the Consultant is to notify the Contractor immediately, in writing, with a copy of the notification to the Fund. FULL-TIME SUPERINTENDENT: Section 2.06 of the Contract requires a full-time superintendent. In his absence, an individual must be named, acceptable to the Consultant and Fund, having authority to receive and execute instructions given by the Consultant or its representative. The full-time superintendent with qualifications must be submitted to the Consultant and the Fund for acceptance. JOB MEETINGS: Job meetings are to be scheduled and conducted by the Consultant at least bi-weekly and more frequently, if deemed necessary. The Consultant representative, subconsultants (as stipulated in the Consultants Agreement), the Fund Project Coordinator, the Contractor and subcontractor or subcontractors (as requested) are to attend. A representative of the University/College may also participate, as an observer. Meeting minutes are to be issued by the Consultant. BACKCHARGE: When a Contractor fails to perform what the Consultant considers Contract work, the Consultant must direct the Contractor, in writing, to perform the work prior to taking any other action to complete the work. The Consultant must obtain prior approval from the Fund before such a letter is transmitted to the Contractor (see Item 20 of Appendix for sample letter). ASBESTOS ABATEMENT: The Contractor will be required to provide substantial documentation, in duplicate, for Asbestos Abatement work. Appendix Item 21 is an Asbestos Material Removal Fact Sheet that must be completed and submitted to the Fund prior to any work commencing on asbestos abatement. In addition to this Fact Sheet, the Contractor will be required to provide documentation relative to the required notification, tests, licenses, approvals, certifications, etc., that are required by specifications for the project. Prior to the commencement of work involving asbestos demolition, removal and/or renovation, the Contractor must submit to the Fund the name of its on-site asbestos supervisor responsible for such operations, together with documentation that such supervisor has completed an Environmental Protection Agency approved training course for asbestos supervisors. A Pre-Abatement Meeting will be held prior to commencement of work. This information must be recorded on the Asbestos Material Removal Fact Sheet (Appendix Item 21). PCB TRANSFORMERS AND CONTAMINATED MATERIAL: Projects that require the removal and disposal of regulated material such as PCB Transformers, contaminated duct work, hazardous and non-hazardous contaminated material, etc. will require detailed record keeping. Appendix Item 22 is a fact sheet for record keeping on these types of projects. The actual records that should be kept in the project files will vary, depending on the project and type of material removed. The fact sheet should be completed by the Fund Project Coordinator from information supplied by the Contractor and the Consultant.

Office of Construction Management Management of Construction Projects

Page 14 Construction Phase

SALES AND USE TAXES AND EXEMPTIONS: Under the Funds lump-sum contract, all supplies and materials incorporated into the project are exempt from all local and State sales and compensating use taxes, unless stated otherwise by the Fund. No sales tax exemption certificate or other certificate is required to be issued by the Fund for such exemption. However, under the requirements of the New York State Department of Taxation and Finance (518-457-5431 or www.tax.ny.gov), each Contractor must file a request for Tax Exemption Certificate (Form ST-120.1) which it will be required to supply to its vendors and subcontractors. CHANGE AND FIELD ORDERS: Fund procedures are intended to minimize the number of change and field orders. All change and field orders must be authorized by the Fund in writing. No action should be taken by the Consultant to solicit proposals for changed work from the Contractor without prior approval of the Fund. Whenever feasible, changes must be priced before work is authorized. In the case of emergency or under conditions where the scope of work cannot be determined in advance without causing unacceptable impact to the progress of the work, the Fund will direct the Consultant to issue an Authorization to Proceed letter. Proceed Orders are issued only when time is of the essence and proper staffing of an anticipated change will materially impact the completion of a project or result in additional costs to the Fund. The accepted form for such a letter appears in the Appendix of this document (Item 19). Prompt payment for all work satisfactorily completed is Fund policy. Therefore, timely processing of change and field orders is required so as to not impede job progress. This necessitates the Contractor to submit a complete package with breakdowns for processing. Information copies of all correspondence between the Consultant and the Contractor regarding change orders and field orders are to be furnished concurrently to the designated Fund Project Coordinator and the field office. After a change has been authorized in principle by the Fund, the Consultant must request the Contractor to present a proposal showing a detailed breakdown of items of work including an overall value for labor and material and the portions of work to be done by the Contractor and/or Subcontractors. Unsupported lump-sum quotations are not acceptable. Where appropriate, Contract unit prices should be utilized and identified as such. The Consultant must review the Contractors proposal for reasonableness of the itemization, quantities and prices and for Contract compliance. If the proposal is acceptable, the Consultant should submit the proposal together with their review and recommendations, to the Funds Project Coordinator to obtain authorization to either prepare a formal change order/ Field Order approval. The Letter of Recommendation should include the following items: a. b. c. Statement describing the change. The reason for the change. A copy of the detailed quotation (proposal) submitted by the Contractor, suppliers, and subcontractors.

Office of Construction Management Management of Construction Projects

Page 15 Construction Phase

d. e. f. g. h. i.

The Consultants stated evaluation of the reasonableness of quantities and price in accordance with Sections 2.04, 2.05 and 4.02 through 4.05A of the Contract. Attachment of, or reference to, supplementary data such as descriptive literature, sketches, revised drawings, etc The Consultants recommendation for an extension of time (which the Contractor must have explicitly requested in writing for a specific period). An indication as to whether the change will require work of other trades and if so, whether work will involve additional costs, changes or credits. Recitation of form, agent and date of advance authorization by the Fund. Any other pertinent data.

The Contractor is not to be copied with the Consultants letter of recommendation to the Fund. The Fund will electronically transmit change orders, Form CF-C9, to the Consultant. The Consultant will sign three (3) copies and transmit same to the Contractor directing same to sign all three (3) copies and to return all originals to the Change Order Section of the Fund. Upon approval of the change order, approved copies will electronically be transmitted. For Field Orders, the Fund will electronically transmit the authorization letter to the Contractor. The Contractor can then request payment for any completed work via the Contract allowance. The change/field order form contains the cost and a description of the work with reference to applicable drawings. Necessary deletions from and/or additions to the specifications should appear in the body of the change/field order under the Description of Change portion or on a separate attached sheet. The total amount shown on the body of each change/field order, including those computed on the basis of unit prices, is to be a lump sum. After a change order has been processed by the Fund, the Fund will forward two copies to the Consultant, who, in turn must retain one copy and deliver one to the Contractor. The Contractors Monthly Application for Payment should list all executed change orders on SUCF Form CF-C3 with the summation of additive and deductive change orders posted on Form CF-C2 (see Appendix Items 6 and 7). All approved field orders will be listed on SUCF Form CF-C11 (see Appendix Item 8). CLAIMS AND DISPUTES: If a Contractor maintains that any work being performed is extra work to the Contract and the Consultant does not agree with the Contractors position, the Contractor must follow the procedures outlined in Article 11, Section 2.03 of the Contract. The Contractor must also follow these procedures if he believes any action by the Consultant or the Fund is contrary to terms and conditions of the Contract. When a Contractor fails to perform what the Consultant considers Contract work, the Consultant must direct the Contractor, in writing, to perform the work prior to taking any other action to complete the work. The Consultant must obtain prior approval from the Fund before such a letter is transmitted to the Contractor (see Item 20 of Appendix for sample letter).

Office of Construction Management Management of Construction Projects

Page 16 Construction Phase

Payments and Reimbursements


CONTRACTORS MONTHLY REQUESTS Initial Request Electronic Payment Application Procedures Regular Monthly Payment Meetings Payment Forms Table 3 Payment Forms Review and Payments Payment for Materials SUBSTANTIAL COMPLETION FINAL PAYMENT WAGE RATE CERTIFICATIONS GUARANTEE PERIOD INSPECTIONS GUARANTEE PAYMENT LABOR AFFIDAVITS FROM GENERAL CONTRACTOR

Office of Construction Management Management of Construction Projects

Page 17 Construction Phase

Payments and Reimbursements It is policy of the Fund to ensure prompt action is taken on requests for payment. The following procedure has been established to expedite Contractors Monthly Applications for Payment: Introduction This document provides a step-by-step reference for submitting Contractor payment applications electronically via the Funds web-based Contract Management Reporting System, also known as CMR. Any questions regarding these procedures or the payment request process should be directed to your SUCF Construction Project Coordinator. Primary Steps of the Payment Submission Process Step 1 Step 2 Step 3 Step 4 Obtain access to CMR through your construction coordinator. Log in to CMR System. In CMR, enter schedule of values and submit for approval. Verify that contractual requirements and supporting documentation required for payment approval is up-to-date and/or completed (see Construction Management Procedures Manual). In CMR, enter application for payment, submit for approval and print Certification. Obtain required signatures on Certification and forward with required supporting documentation to Project Coordinator.

Step 5

Step 1 - Obtaining Access to CMR In order to submit payment requests electronically, you will need access to the SUCF CMR system. In order to obtain access, please complete the Contractor Access Request Form provided to you during your orientation meeting and return it to your SUCF Construction Project Coordinator. Once your request has been processed, you will receive an e-mail with your log-in ID and initial password. Please note that passwords will need to be changed every 90 days. Step 2 Logging into CMR Go to appls.sucf.suny.edu using your internet browser Select Business Partners Enter the user ID and password provided to you Select Contract Management Reporting from the menu on the left, which will bring you the CMR Main Menu.

Office of Construction Management Management of Construction Projects

Page 18 Payments and Reimbursements

General Information

The Main Menu can always be accessed at any point by clicking on Contract Management Reporting on the left side of the screen. To go back to a previous submenu, you can click either the Back button at the bottom of the screen or your browser back button. It is recommended that you return to the Main Menu prior to exiting the application. Data entry in CMR may result in system messages that will appear near the top of the screen. Messages in Green appear when an action, such as submitting a payment application for approval, has been successful, messages highlighted in Yellow are informational only, and messages highlighted in Red indicate that a correction is needed before you can proceed any further.

Office of Construction Management Management of Construction Projects

Page 19 Payments and Reimbursements

At any time prior to electronically submitting the payment request to the Fund, you may edit and save the information by clicking on the Save button at the bottom of the screens. The system is designed to time out after a period of 30 minutes of no activity, at which time all unsaved work will be lost. It is therefore a good idea to save your work regularly. Saved work can always be edited later until it is actually submitted.

Step 3 Entering and Submitting the Schedule of Values for Approval From the Main Menu, select the Schedule of Values (Contractor) option. Enter the Contract Number and click Go.

When the Schedule of Values screen appears, click on the first blank line and enter a short description for the first work item. Tab to the amount column and enter the value of the work item. After the work item amount been entered, tab to the CSI Type field and use the drop down menu to select the CSI type most closely affiliated with that work item. Repeat this procedure for all work items. Note: The number of work items is limited to 24. The Guarantee Amount will automatically be calculated and will appear as the last work item at the bottom of the Schedule of Values.
Page 20 Payments and Reimbursements

Office of Construction Management Management of Construction Projects

You may save your work at any time by clicking on the Save button. However, if the total of the values entered does not equal the Contract Value, an out of balance message will appear. Your work will stay out of balance until you save your work. After all information has been entered and verified, you can submit the Schedule of Values to the Fund for approval. Please note that the system will not allow you to submit the schedule until it is in balance. Once the Schedule of Values has been submitted to the Fund for approval, you will no longer be able to make any changes. However, you will be able to view or print the Schedule of Values at any time.

Step 4 Contractual Requirements and Supporting Documentation Attach all needed documents, see Table 3. Step 5 Entering Payment Application and Submitting for Approval From the CMR Main Menu, select Application Setup/View (Contractor) You can add or view payment requests from this screen. A list of your payment requests, along with their current status will appear on the lower portion of the screen.

To view a payment application that you have previously submitted, click on view at the right of the appropriate payment application on the list. To enter a new payment application, enter the contract number and click on Add Request for Payment. The contract number will begin with T00. Be sure to enter the complete contract number. The Entry screen is separated into tabs to organize the information for input.
Page 21 Payments and Reimbursements

Office of Construction Management Management of Construction Projects

Basic Data Tab

Work Period Ending date This is the last date through which work has been completed for this payment application. The work period ending date must be before the contract end date. Last Payment Check this box if all work has completed and this is the last and final application request.

Schedule of Values Tab

Office of Construction Management Management of Construction Projects

Page 22 Payments and Reimbursements

All items of work listed in the approved Schedule of Values will appear here, along with the cumulative percent complete amounts for all approved payment applications. For the first payment application on a project, all values will be at 0%. For each item, Tab to the Percent Complete Column and edit the percentages to reflect the percent complete for the payment application you are submitting. The system will calculate the corresponding Present Estimate and Uncompleted Balance for each work item.

Field Orders Tab

Approved field orders along with their related proposals will appear on this screen. Field orders that have been billed in full will appear at the bottom of the screen and cannot be edited. Similar to the Schedule of Values tab, the field orders and related proposals will be listed and the corresponding cumulative percent complete amounts will appear in the Percent Complete column. If no payment has been made for a particular field order proposal, the corresponding value will be at 0%. Tab to the Percent Complete Column and edit the percentages to reflect the percent complete for the payment application you are submitting. The corresponding Present Estimate and Uncompleted Balance will be calculated automatically. (To see additional information on a particular proposal, click on the proposal number.)

Office of Construction Management Management of Construction Projects

Page 23 Payments and Reimbursements

Change Order Tab

Approved change orders along with their related proposals will appear on this screen. Change orders that have been billed in full will appear at the bottom of the screen and cannot be edited. Similar to the Schedule of Values and Field Orders tabs, the change orders and related proposals will be listed and the corresponding cumulative percent complete amounts will appear in the Percent Complete column. If no payment has been made for a particular field order proposal, the corresponding value will be at 0%. Tab to the Percent Complete Column and edit the percentages to reflect the percent complete for the payment application you are submitting. The corresponding Present Estimate and Uncompleted Balance will be calculated automatically. (To see additional information on a particular proposal, click on the proposal number.

Office of Construction Management Management of Construction Projects

Page 24 Payments and Reimbursements

Retention Tab

Amounts withheld from the current payment request, based on the contract, will be calculated and displayed on this tab.

MWBE Tab

All MWBE Contractors in the approved MWBE Utilization Plan will appear here, along with the approved plan values.

Office of Construction Management Management of Construction Projects

Page 25 Payments and Reimbursements

For each contractor listed, enter the scheduled start date and end date for that contract in the appropriate columns. In the Amount Paid Since Last Pay App column and enter the value of the amount actually paid to the MWBE firm since the last application for payment was submitted to the Fund. If any changes have been made to the contractors shown or plan values, including the addition of new MWBE contractors or increase to plan amounts, you must contact the Opportunities Program Office by calling (518) 320-1650 or via e-mail at sucf.opportunitiesadmin@suny.edu before submitting the payment application. Once the Opportunities Program Office has been contacted, you can add new contractors to the MWBE Tab by entering the following information: o The name of the Contractor o The Contractors federal ID number o Select the appropriate trade designation from the drop down menu o Select MBE or WBE o Provide start date and end date for the contract o Enter the Plan amount (full value of the signed subcontract) o Enter the amount paid since the last payment application was submitted.

Summary Tab

A payment application can only be submitted to the Fund for approval from this tab. Click on the Submit button at the bottom of the screen to submit the application for approval. Once the application has been submitted, it cannot be changed.

Office of Construction Management Management of Construction Projects

Page 26 Payments and Reimbursements

Payment Certification

After a payment request has been submitted to the Fund, a button to print the Payment Certification Page will appear. (The certification page can also be printed at a later date from the reports tab.) Once printed, the Certification Page must be signed by the Contractors authorized representative (and notarized) and then signed by the Consultant. (It is not acceptable for someone to sign on behalf of or for the authorized representative of the Contractor or the Consultant.) After the necessary signatures have been obtained, the signed Certification Page, along with any supporting documentation (see SUCF Project Coordinator for details) should be forwarded to the SUCF Project Coordinator. Last and Final Payment if the application is the last payment, an additional section is printed on the certification. (Consult your SUCF Project Coordinator for additional information).

CONTRACTORS MONTHLY REQUESTS: At the joint review sessions, both the Contractors and Consultants representative must have authority to commit their firms in reference to approval of monthly payment applications. For the review session, the Contractor should prepare the draft requisition in such a way that all items have necessary backup data and all computations are accurate. A thorough understanding of Fund procedures and adherence to them will avoid delay in the processing of requisitions by the Fund Controller, and in subsequent payment by the State Comptroller. INITIAL REQUEST: Three approvals are required before a Contractors first monthly request for payment may be processed. They are: (1) approval of the Contract by the Fund, and assignment by it of a Contract number, (2) acceptance by the Fund of the Contractors Contract breakdown and job progress schedule, and (3) MBE/WBE Program. These should be approved before the first payment meeting. In addition, before a first monthly request for
Office of Construction Management Management of Construction Projects Page 27 Payments and Reimbursements

payment may be processed, proof of required Contractors insurance must have been received and approved by the Fund. The Contract breakdown must include an item for the one-year guarantee obligation and the amount thereof is to be $5,000 or one-half of one percent of the original Contract award, whichever is the lesser amount. REGULAR MONTHLY PAYMENT MEETINGS: In general, monthly payment meetings are held at approximately the same time each month at the jobsite. It is encouraged that a payment meeting be held in conjunction with a bi-weekly project meeting. Approximately five working days prior to the monthly payment meeting the Contractor shall prepare and review on site a draft copy of the payment application with the Consultant/Site Representative. Draft copy is to include Contract Breakdown CF-2, listing of Change Orders and Field Orders, and any appropriate Requisition Work Sheet DC-5s. Initial comments and questions by the Consultant should be addressed at this time. At the ensuing monthly payment meeting a final review of the application will be performed by the Fund and the Consultant(s). The Contractor will have prepared three copies of its payment application which is to include all pertinent payment forms. The Contractor prepares the Monthly Application as follows: The CF-C1, CF-C2; CF-C3, CFC8, CF-C11 and DC5s where applicable will be filled in and signed, as verification, by the Consultant and Contractor before the meeting is adjourned. The Fund Project Coordinator should leave the payment meeting with two executed Payment Forms that will be returned to the Funds main office for processing. It is not the intent for payment applications to be mailed back and forth from Contractor to Consultant to the Fund. The hard copy of the CF-C1 Form is to be signed, notarized, dated and submitted the Fund.

Office of Construction Management Management of Construction Projects

Page 28 Payments and Reimbursements

PAYMENT FORMS: The Contractors Monthly Application for Payment is to be made used by the Funds Contract Management Reporting (CMR) System, samples of which are included in the Appendix.
CF-C1 Statement of Account Contractors Monthly Application for Payment (Date of Contractors signature cannot be prior to the work period ending date). Form requires a notarized contractor signature. Payment Summary Report A detailed summary of the payment application. Contract Breakdown - The form should be limited to one page. The Requisition Worksheet, DC-5 Form, is a backup form which may be used to provide a detailed breakdown of items listed on CF-C2. List of Change Orders. This is a supplemental form to the requisition, for listing of all change orders that have been executed. Only fully executed Change Orders are to be listed. List of Field Orders. This is a supplemental form to the requisition, for listing of all field orders that have been executed. Only fully executed Field Orders are to be listed. Wage Rate Certifications. These are payment affidavits required by the New York State Department of Labor pursuant to Section 220-a of the Labor Law, and must be completed in duplicate with original signatures. These forms are required from the General Contractor, all subcontractors and sub-subcontractors performing work under the Contract. One copy is for the Fund Accounting Unit, and a third copy must be placed in the Fund project file. These forms are only required on the final payment and the guarantee payment when work is performed during the warranty period. Verification of subcontractor(s) payment from previous payment application. This form is required only for the third set when requested by the Fund Project Coordinator. Each subcontractor who has received payment from the previous requisition must file one. The Requisition Number on the form references the General Contractors payment application number. Summary of Subcontractors and Sub-subcontractors. (Submit in duplicate with final payment only.) Minority/Womens Business Enterprise Program Payment Report. Each payment application shall include Detail of Payments to MBE/WBE Subcontractors and Suppliers, Form CF-C8. The Contractor shall transfer all information to this form relative to MBE/WBE Subcontractors and suppliers. If no payment is due to one or more listed subcontractors or suppliers enter None in the appropriate space. Release. Submit in duplicate with final payment or at a time as determined by the Fund Project Coordinator.

CF-C1A CF-C2

CF-C3

CF-C11

CF-C4As

CF-C5

CF-C7A

CF-C8

C-5

Office of Construction Management Management of Construction Projects

Page 29 Payments and Reimbursements

In summary, one (2) original set of the completed payment forms, with backup, as required, must be submitted, with original signatures, by the contractor to the SUCF Coordinator, as shown in the table below. Foreign Contractors as defined by Section 4.15 Paragraph (d) of the contract are additionally required to submit, as part of each initial and final contract payment request, a certificate from the New York State Tax Commission stating that all New York State taxes have been satisfied.
TABLE 3 PAYMENT FORMS IN ADDITION TO ELECTRONIC PAYMENT APPLICATION Set No. TO Set No. 1 Original Signature FUND Accounting Unit Electronic CMR CF-C1 CF-C4As CF-C7A C-5 Set No. 2 Original Signature FUND Project File Electronic CMR CF-C1 CF-C4As CF-C7A C-5 Backup Data Backup Data Backup Data Set No. 3 Copy Consultant File Hard Copy CMR CF-C1 Set No. 4 Copy Contractor File Electronic CMR

Backup data may include DC-5, or approved equivalent, as requested by the consultant or the Fund. Additional documents may be requested to substantiate a request for payment and any certifications required for payment of materials stored off the job site. INSURANCE RENEWALS: If any component of insurance coverage lapses during the contract, the contractors monthly payment will not be processed. Asbestos Abatement Insurance The contractor shall notify the consultant when asbestos abatement work has been completed by the contractor. The consultant reviews work and if finalized issues letter to Construction Project Coordinator stating asbestos abatement work has been completed. Copy will be forwarded to SUCF Controllers Services and SUCF Counsels Office to eliminate need to renew asbestos abate insurance. PAYMENT FOR MATERIALS: Payment for materials delivered to site will be in accordance with Section 4.12 of the Construction Agreement. Payment for materials stored off-site will be in accordance with Section 4.14. The Contractor shall notify in advance, prior to the payment meeting, that materials stored off site will be requisitioned for. It is the Contractors responsibility to coordinate and provide assistance to the consultant for verification of materials stored off site. For materials stored off-site a Certificate of Insurance for Material Stored Offsite must be completed, appendix item 23. SUBSTANTIAL COMPLETION: When the project is substantially complete, in accordance with the provision of Section 4.10 of the Agreement, a final inspection is to be conducted in accordance with the provisions of the Section entitled Closeout of Construction Contracts. At that time the Consultant shall prepare a list of all uncompleted, unaccepted and corrective work to be performed together with the estimated value thereof. After approval of this list by the Fund, the Contractors retainage may be reduced to the cost of performing the work on the list plus an amount necessary, in the Funds judgment, to satisfy any claims, liens or
Office of Construction Management Management of Construction Projects Page 30 Payments and Reimbursements

judgments against the Contractor which have not been suitably discharged. Before such payment is to be made, the following items must be addressed, except that a dollar value may be assigned to the items having an asterisk (*), with such items placed on the punch list. The Checklist for Substantial Completion, form CF-C6, appendix item 29, may be utilized to expedite this process. *KEYS: The Fund Project Coordinator has verification that the door keys, keyboards and master keys have been received by the campus. *MONEY DUE TO THE CAMPUS: All water, power, fuel, telephone and other outstanding bills due to the Campus have been satisfied. *OPERATING INSTRUCTIONS AND SPARE PARTS LISTS: Basic mechanical and electrical systems of the project and all special equipment, complete operating instructions and spare parts lists have been formally transmitted to the campus. *BONDS, WARRANTIES and GUARANTEES: The Construction Project Coordinator has obtained verification that, as required by the SUCF Agreement, all bonds, guarantees and warranties exceeding the normal one-year guarantee period have been received by the Campus. All guarantees and warranties shall identify the respective SUNY Campus as the Owner. *CHARTS AND DIAGRAMS: Wiring diagrams, valve charts and other charts or diagrams required by the specifications must be framed under glass and mounted on the walls in the mechanical and electrical equipment rooms as required by the Contract. *OPERATING TESTS: All required tests must be been made and the results furnished to the Fund, the Campus and the Consultant prior to the turnover of projects. Especially important are the results of life safety tests and their certification. The Consultant is responsible for turning over to the Fund a testing log and respective test reports at the completion of the project. RELEASE: The Contractor must provide an executed C-5 Final Release, appendix item 5, which accompanies the final application for payment. *RECORD INFORMATION FROM THE CONTRACTOR: The Consultant has received from the Contractor all record information required by SUCF Agreement Section 2.24 Record Drawings and General Requirements. *CAMPUS PERSONNEL TRAINING / DEMONSTRATIONS: Mechanical, electrical systems and equipment have been demonstrated to the Campus operating personnel, in the presence of the Contractor and under the supervision of the consultant. Operation and Maintenance Manuals must be submitted by the Contractor, reviewed and approved by the Consultant and turned over to the Campus prior to scheduling training/demonstrations. PUNCH LIST: The Consultant, Sub-Consultants, Contractor, Fund Project Coordinator, and a representative of the Campus have verified by inspection that the final punch list

Office of Construction Management Management of Construction Projects

Page 31 Payments and Reimbursements

has been established. acceptance.

The punch list must be incorporated into SUCF final

*RECORD OF TRANSMITTALS: The consultant must document, in detail by formal letter(s) of transmittal, every item that it is required to be transferred to the Campus. An information copy of each transmittal must be furnished to the Fund Project Coordinator as evidence that the material has been transmitted. FINAL PAYMENTS: For projects that do not include a guarantee payment, the term Final Payment is used for processing an application for payment when all work has been accepted, excluding guarantee obligations, judgments, claims or liens against the contractor. When processing Final Payments please follow the instructions below for the Electronic Payment Application. ___________________________________________________________________________ Basic Data Tab

Work Period Ending date This is the last date through which work has been completed for this payment application. The work period ending date must be before the Contract end date. Last Payment Check this box if all work has completed and this is the last and final application request.

WAGE RATE CERTIFICATIONS: Contractors are required to submit the following prior to or at final application for payment: CF-C4A1 - Prime Contractors Certification, appendix Item 11 CF-C4A2 - Subcontractors Certification, appendix Item 12
Page 32 Payments and Reimbursements

Office of Construction Management Management of Construction Projects

CF-C4A3 - Sub-subcontractors Certification, appendix Item 13 CF-C7A - Summary of Wage Rate Certification, appendix Item 14 Failure to furnish the required forms will result in SUCF withholding a portion of the contract sum.

The following outlines the final certification and reporting procedures required to implement Chapter 698, Laws 1988 (Labor Affidavits) for all public improvement contracts. 1. The Prime Contractor must provide each subcontractor with a copy of the schedule of wages and supplements specified in the Contract before the subcontractors work is started. 2. The Prime Contractor must immediately obtain the subcontractors certification. Such certification must be submitted by the prime contractor prior to or with the final payment, see form CF-C4A2 - Subcontractors Certification - appendix item 12. 3. If a sub-subcontractor is involved, it is the subcontractors responsibility to obtain the certification from the sub-subcontractor that he/she has in fact received the wage rates contained in the subject project. The Prime Contractor must immediately obtain the sub-subcontractors certification from the subcontractor which must be submitted by the Prime Contractor with the final payment. See CF-C4A3 - Subcontractors Certification appendix item 13. 4. If revised schedules of wages and supplements are published, the Prime Contractor must provide each subcontractor with such revised schedules and obtain a revised subcontractors certification, and the subcontractor must follow the same procedure with each sub-subcontractor. Revised schedules must be obtained for each updated wage rate period when the respective contractor is working on site. 5. Sub-subcontractors certification, subcontractors certification, and Prime Contractors certification must be submitted to the Office of State Comptrollers prior to or with the Prime Contractors final payment request. Failure to obtain and provide the required certifications will impact the Contractors final payment. 6. Updated wage rates are to be obtained by the Prime Contractor at the time they become effective from the Department of Labor. Wage rates will be posted at the Department of Labors website: www.sucf.suny.edu/design/wage.shtml It is the Prime Contractors responsibility to provide the wage rate updates to every subcontractor and obtain all certifications as described in paragraph 4 above. The Fund is not responsible for issuing wage rate updates after the project is bid. Additionally, the Prime Contractor is responsible for obtaining and collecting the certifications. Prior to or for the final payment, a CF-C7A - Summary of Wage Rate Certification will be required and the certifications from the subcontractors and sub-subcontractors listed must be attached.
Office of Construction Management Management of Construction Projects Page 33 Payments and Reimbursements

Final payment will not be made without these certifications and it is recommended that three originals be obtained promptly by the prime contractor at the time a subcontract is executed. Please note that sending the Fund a copy at the time of certification does not relieve the Prime Contractor from the responsibility of attaching all original certifications to the final payment. GUARANTEE (LAST) PAYMENT: For projects that include a guarantee payment, the term Guarantee Payment is the last payment application processed once the punch list and warranty items are completed and the guarantee period expires. When project completion has been verified, the Contractor must submit to the Consultant the guarantee application for payment including CF-C1, CF-C4A1 accompanied by C-5 - Release Form throughout the Funds Electronic Payment Application. The C-5 Release Form is only required if changes in the final value of the Contract occurred between final acceptance and the end of guarantee period. PRIME CONTRACTORS CERTIFICATION FROM GENERAL CONTRACTOR: The General Contractor must submit a Prime Contractors Certification (Ref. CF-C4A1 Item 11) for its work on both the final and guarantee payments. The payroll period ending date must cover the time period of the payment.

Office of Construction Management Management of Construction Projects

Page 34 Payments and Reimbursements

Closeout of Construction Contract


GENERAL

COMPLETION AND ACCEPTANCE Substantially Complete Facility Ready Punch List Development Contact Requirements Project Delays Partial Turnover Certificates of Occupancy Turnover to the Campus

END OF ONE-YEAR GUARANTEE PERIOD

Office of Construction Management Management of Construction Projects

Page 35 Closeout of Construction Contract

GENERAL
Except where the Campus requires partial acceptance or possession prior to completion of the contract, the steps detailed in this section of this manual entitled Final Payment and End of Guarantee Period will apply. The following guidelines are intended to standardize Fund procedures for closeout of construction Contracts and are published for the information and guidance of Campuses Consultants, Contractors and the Fund. Final Inspections are made before turning over a project to Campus control. Guarantee inspections are made near the end of the guarantee period, normally just prior to one full year after formal acceptance of the project by the Fund and project turnover to Campus control.

COMPLETION AND ACCEPTANCE


SUBSTANTIALLY COMPLETE: When all Contract work is substantially complete and the project can be utilized for its intended purpose the Contractor must submit a letter to the Director of Construction, copied to the Consultant, stating that the project is ready for inspection. If a building permit has been issued on the project, see section Certificates of Occupancy below for required documentation. FACILITY READY: The Consultant and the Fund Project Coordinator have jointly determined that the facility is prepared for final inspection. INSPECTION AND PUNCH LIST DEVELOPMENT: The process of developing and issuing the punch list will vary depending on the scope, value and type of project. Projects with limited scope and value may condense process into fewer phases. Projects with vast scope and value may expand process into several phases. The following provides an outline for developing the punch list: 1. The Consultant must prepare a complete list with explicit descriptions of all uncompleted work for the project. Concurrently, the Consultant shall have all subconsultants prepare a complete list with explicit descriptions of all uncompleted work for the project. The list must be issued as a single uniform document from the Consultant incorporating items provided by all sub-consultants. The list of deficiencies will be utilized for a final inspection walk through by the Fund, Campus, Consultant, Subconsultants and Contractor. 2. The Campus, Consultant, Contractor and Fund must review the list independently or as a group prior to or while physically inspecting the project. 3. The inspection shall be performed as follows: Roof Interior space Mechanical and electrical systems

Office of Construction Management Management of Construction Projects

Page 36 Closeout of Construction Contract

Exterior Site work

4. After the inspection has been completed, any new items discovered during the inspection will be added to the list. The uncompleted work list, as amended during the inspection, should be reproduced by the Consultant and furnished to the Contractor, the Campus and the Fund. If necessary, the Campus, Consultant, Sub-consultants, Contractor, and Mechanical and Electrical Subcontractors will assemble for a meeting conducted by the Fund representatives. Questions will be addressed concerning incomplete or missing items and punch list completion schedule. The Fund will utilize the list of items as the basis for the final acceptance punch list. It shall be the prerogative of the Fund as the result of the inspection to make the decision to accept the facility from the Contractor. Additional punch list items shall not be added after the Fund has issued the punch list with the Final Inspection and Acceptance letters. The Contractor must complete the punch list prior to the end of guarantee and before receiving final payment. Items will not be added to the punch list after final inspection. In the event a defect develops or is discovered subsequent to final acceptance, the issue will be identified as a guarantee item. Guarantee items are to be resolved as soon as possible, during the guarantee period. The heating, ventilating and air conditioning systems of a building may not be effectively balanced until the building is fully occupied. Preliminary balancing may be required ahead of the final inspection, may be required. Final balancing of these systems may be considered to be a Contract requirement to be met after final acceptance. All equipment in the building must be running during the walk-through. The Campus will be given the opportunity to acknowledge the Final Inspection and Acceptance, but concurrence by the Campus is not required to close out a project. This procedure will be modified, as required, depending on scope and size of project. CONTRACT REQUIREMENTS: Conditional to the scope and value of the project, the Contract documents will require various forms of documentation and inspections required for final acceptance of a project. Therefore, each project will entail development of a unique process leading to final acceptance. The process may include, and not be limited to: Demonstration of equipment Development and review of operation manuals Testing Development and review of record drawings As built drawings Warranties Commissioning electrical, mechanical and plumbing systems Coordination of commissioning agent requirements

PARTIAL ACCEPTANCE: Contracts which include multiple buildings, phased construction, rehabilitation of limited areas of buildings, or site utility work may be partially accepted using
Office of Construction Management Management of Construction Projects Page 37 Closeout of Construction Contract

the procedure described above for each building, phase, building segment or specific utility individually. When a project is ready for final inspection in the winter and the exterior and site work cannot be properly inspected. The Fund will follow the above procedure, excluding exterior and site work for later inspection and turnover. CERTIFICATES OF COMPLETION OR OCCUPANCY: A project for which a building permit has been issued requires a Certificate of Completion or Certificate of Occupancy to be issued by the Office of Design and Construction Management - appendix item 30. A Temporary Certificate of Completion or Occupancy may be issued for a partial acceptance appendix item 31. Prior to issuance of a Certificate of Occupancy, the following forms and letters must be completed: Completion letter from the Contractor appendix Item A-27 Acceptance letter from the Consultant with uncompleted work list appendix Item A-28 The Construction Inspection Report appendix item A-32 The Final Inspection Report appendix item A-33 The Fact Sheet appendix item A-34

A project for which a Building Permit Waiver has been issued will not require a Certificate of Completion or Occupancy. The Construction Inspection Report, Final Inspection Report, and Fact Sheet are not required for projects with Building Permit Waivers. PROJECT DELAYS: Timely acceptance and turnover to the Campus and timely execution of project documentation is important. A memo must be included in the project close out documentation for any project which has been accepted more than 6 months after the Contract completion date as indicated in the bid documents. Likewise, a memo must be included in the project close out documentation for any project which is being accepted effective more than 6 months prior to the date of the Final Inspection and Acceptance letters. The Project Delay Memo should detail the extent of and reasons for the delay. TURNOVER TO THE CAMPUS: The turnover is documented by formal letters of Final Inspection and Acceptance, to the Campus President and the Contractor from the Assistant General Manager, Office of Design and Construction Management or the Director of Construction. Turnover of a portion of the project shall be documented similarly. Prior to issuing formal letters of Final Inspection and Acceptance, all projects require the following documents to be completed and submitted for inclusion in the Contract file. Completion letter from the Contractor appendix Item A-27 Acceptance letter from the Consultant with uncompleted work list appendix Item A-28 Campus Sign-off appendix Item A-35 Building Permit Waiver as previously issued or Certificate of Completion or Occupancy and related documents Project Delay Memo, if required

Office of Construction Management Management of Construction Projects

Page 38 Closeout of Construction Contract

END OF ONE-YEAR GUARANTEE PERIOD


The one-year guarantee normally starts with the jointly agreed upon date of turnover for each portion of a facility. Approximately, thirty days prior to end of the one-year guarantee period, the Fund shall request the Campus to submit a list of items, in writing, to be considered for inclusion in the Consultants formal guarantee list to be transmitted to the Contractor. The Fund will provide this listing to the Consultant who in turn will notify the Campus and the Fund of items that are not considered covered by the guarantee and issue the final list to the Contractor. Additional items will not be added once the final consultant/campus guarantee list has been generated. The Campus will be given the opportunity to acknowledge the End of One Year Guarantee Period, but concurrence by the Campus is not required to execute an End of One Year Guarantee Period. The Consultant or the Fund will, after the Contractor corrects all guarantee deficiencies, schedule the End of Guarantee inspection after coordinating with the Campus and the Fund. If any guarantee items are still not completed at the time of inspection, the Contractor will have to complete all guarantee items before a guarantee payment is made. Timely completion of work and timely execution of project documentation is important. A memo must be included in the project close out documentation for any project for which End of One Year Guarantee Period letters are dated more than 18 months after the effective date of project acceptance. The Project Delay Memo should detail the extent of and reasons for the delay. The end of the one year guarantee period will be documented by formal letters to the Campus and the Contractor. Prior to issuing formal End of One Year Guarantee letters, all projects require the following documents to be completed and submitted for inclusion in the Contract file. Campus Sign-off appendix item A-38 End of One Year Guarantee Period letter to Campus appendix item A-39 End of One Year Guarantee Period letter to Contractor appendix item A-40 Delay Memo, if required

Office of Construction Management Management of Construction Projects

Page 39 Closeout of Construction Contract

Publicity and Disclosures


Fund projects frequently are newsworthy. The Fund is interested, not only in cooperating with various news media, but also in utilizing any available material to communicate with the public. Each Fund project is related to other similar projects, to the entire Campus and to the general construction program of the University. Coordination of information to be disseminated to the public is required, regardless of the media to be employed. This dictates careful review of any releases, statements, statistics, estimates, utterances, etc. to verify their accuracy and to insure their compatibility with other information. There may be no disclosure of information regarding Fund plans, Contracts, related matters, etc. without written permission from the Fund. All releases, regardless of their form (news release, photograph, article, speech, press interview, schemes, maps, etc.) must be transmitted to the Funds main office, via the Funds Project Coordinator, to assure appropriate and rapid approval by the Fund. You should be aware that the internet is not a completely reliable transmission medium. The State University Construction Fund does not accept any liability for any data transmission errors such as data loss or damage or alteration of any kind, including, but not limited to any direct, indirect or consequential damage, arising out of the use of the Funds online system.

Office of Construction Management Management of Construction Projects

Page 40 Publicity and Disclosures

APPENDIXES
APPENDIX A -- Forms APPENDIX B Process Flow Charts

Office of Construction Management Management of Construction Projects

Page 41 Appendix A -- Forms

APPENDIX A -- FORMS TABLE OF CONTENTS


Post Bid Checklist (DC-1) ..................................................................................... A-1 Construction Contract Transmittal Letter (to Contractor)....................................... A-2 Project Administrative Activity Schedule ............................................................... A-3 Listing of Project Reports Required During Construction Period ........................... A-4 Contractors Monthly Application for Payment (CF-C1)......................................... A-5 Contractors Monthly Application for Final Payment (CF-C1) .............................. A-5A Payment Summary Report (CF-C1A) ................................................................. A-5B Contractors Monthly Application for Payment (Contract Breakdown) (CF-C2) ..... A-6 Listing of Change Orders (CF-C3) ........................................................................ A-7 Listing of Field Orders (CF-C11) ........................................................................... A-8 Requisition Work Sheet (DC-5) ............................................................................. A-9 Certification of Monthly Payment (CF-C5)........................................................... A-10 Prime Contractors Certification (CF-C4AI) (2 pages) ......................................... A-11 Subcontractors Certification (CF-C4A2) ............................................................. A-12 Sub-subcontractors Certification (CF-C4A3) ...................................................... A-13 Summary of Subcontractors Wage Rate Certifications (CF-C7A) ....................... A-14 M/WBE Payment Report (CF-C8) .................................................................... A-15 Release (C-5) ..................................................................................................... A-16 Certificate of Insurance (C-10) ............................................................................ A-17 Contract Change Order (CF-C9). ........................................................................ A-18 Contract Field Order (CF-C9A) ......................................................................... A-18A Sample Authorization-To-Proceed Letter ............................................................ A-19 Form of Backcharge Letter ................................................................................. A-20 Asbestos Material Removal Fact Sheet (2 Pages) .............................................. A-21 Regulated Materials Disposal Fact Sheet ........................................................... A-22 Materials Stored Off-Site Certificate of Insurance ............................................... A-23 Request for Federal Tax Identification Number................................................... A-24 Building Permit.................................................................................................... A-25 Waiver of Building Permit.................................................................................... A-26 Letter from Contractor Advising Contract Complete ............................................ A-27 Letter from Consultant Recommending Acceptance and Occupancy ................. A-28 Checklist for Substantial Completion Payments (CF-C6) .................................... A-29 Certificate of Occupancy ..................................................................................... A-30 Temporary Certificate of Occupancy................................................................... A-31 Construction Inspection Report ........................................................................... A-32 Final Inspection Report ....................................................................................... A-33 Fact Sheet for Projects with Building Permit/Certificate of Occupancy ............... A-34 Final Inspection Acceptance Sign-off .................................................................. A-35 Final Inspection Acceptance Letter (to Campus) ................................................ A-36 Final Inspection Acceptance Letter (to Contractor) ............................................. A-37 End of One Year Guarantee Sign-off .................................................................. A-38 End of One Year Guarantee Letter (to Campus)................................................. A-39 End of One Year Guarantee Letter (to Contractor) ............................................. A-40 Labor Rate Breakdown (CF-C10) ....................................................................... A-41 CMR Quick Reference Guide ............................................................................. A-42 SUCF Electric Payment Request System Set-Up Form ...................................... A-43
Office of Construction Management Management of Construction Projects Page 42 Appendix A -- Forms

ITEM A-1

STATE OF NEW YORK STATE UNIVERSITY CONSTRUCTION FUND


POST BID CHECKLIST

Present at Post Bid Meeting: SUCF No. ______________________________ Campus ________________________________ NAME FIRM Project Title ___________________________

_______________________ _______________________________________________________________________ _______________________ _______________________________________________________________________ _______________________ _______________________________________________________________________ _______________________ _______________________________________________________________________

ACTIONS
All participants informed as to confidential nature of discussions. Proposals checked for possible information (addenda acknowledged, corporate seal, all blanks filled) Fax sent for 48-hour data Appendix A requested in Fax Bid deposit checks returned to other than low 3 Time and place set for Pre-Award Meetings: Place Date Hour __________ _________ _________

YES

NO

REMARKS

Consultant requested to tabulate and analyze unit prices from all bidders prior to Pre-Award Meeting Consultant requested to review alternates and recommend selection to SUCF Consultant furnished Contract checklist (copy attached), and requested to start assembly of 6 copies of contract, (7 copies if assigned-sub, or a Federal Grant is involved) Consultant furnished copy of Management of SUCF Projects Consultant furnished copy of Federal Grant Check List (when applicable)

ADDITIONAL REMARKS:

Signed:________________________________ Date: __________________

DC-1

ITEM A-2

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

(Date)

(Contractor Name) (Address) (Address)

Re:

(Project Title) (Campus) SUCF Project No.

Dear Sirs/Mesdames: You are the apparent low bidder for the referenced Project and your proposal is being evaluated for acceptance and contract award. In order to expedite the contract award process, please execute all of the four enclosed copies of the Contract Documents in the following manner: 1. On the signature page of the Agreement (A-33), have an authorized officer or principal of your firm sign on the line below the name of the firm. If a corporation, also affix the corporate seal. On the Acknowledgments page (A-34), see the enclosed "Instructions For Execution of Acknowledgments". On the Labor and Material Bond (page B-1) and the Performance Bond (page B-2), see the enclosed "Instructions For Execution of Labor and Material Bond and Performance Bond". On the Acknowledgments page (B-3), see the enclosed "Instructions For Execution of Acknowledgments".

2.

After the Contract Documents have been executed in accordance with the above directions, kindly return all of the enclosed documents to the Fund as soon as possible. If the Fund accepts your Proposal and awards the Contract to you, it will issue a Notice of Award to you and execute the copies of the Contract Documents you have returned. It will then return to you a fully executed copy of the Contract Documents. We also enclose copies of the following forms, to be filled out and returned to the Fund with the Contract Documents: a. Certificate of Insurance;* and b. Builder's Risk Insurance Breakdown.

Foreign contractors (i.e., entities not organized under the laws of the State of New York) must also furnish, with their initial and final payment applications, a certificate from the New York State Department of Taxation and Finance, Tax Compliance Division, to the effect that all of the contractors' taxes have been paid.

Unless these forms are promptly furnished by you, properly filled out, it will not be possible for the Fund to fully process your Contract and no payments may be made thereunder. This letter does not constitute an award of the Contract. If you are awarded the contract, you will be notified by a separate Notice of Award. Please also forward the necessary certificates of insurance to the Fund. Without proof of all required insurance coverage, no payment can be made. Very truly yours,

William K. Barczak Counsel Enclosures * In the event that this contract requires asbestos abatement work, it is your responsibility, under Section 5.06, sub-division e of the Agreement, to obtain asbestos abatement insurance.

ITEM A-3 PROJECT ADMINISTRATIVE ACTIVITY SCHEDULE


BIDDING DOCUMENTS (NB, IB) CONTRACT DOCUMENTS (A, PB, LMB) REFERENCE A, Section 2.19 A, Section 2.19 A, Section 2.19 A, Section 2.18 (Consultant must have Fund concurrence of their approval of subcontractors) A, Section 2.18 A, Section 2.18 A, Section 2.24 A, Section 2.25 A, Section 5.06 A, Section 5.07 A, Section 5.06 A, Section 2.20 IB, Section 9 IB, Section 10 P, Section 10 A, Section 3.01 A, Section 3.02 A, Section 3.04 A, Section 2.02 A, Section 2.02 A, Section 2.03 A, Section 2.26 A, Sections 4.10, 4.11 A, Section 4.08 A, Section 4.18 A, Section 4.20

DATA / REPORT Shop drawings and sample Submission Schedule (for approval) Approval of Shop Drawings Submission of one copy of all approved Shop Drawings Names of subcontractors (other than those named in 48-hour information) Approval of Subcontractors Payment of Subcontractors by Contractor Submission of Record Drawings Guarantee Period Proof of Contractors Compensation and liability insurance coverage Builders Risk Insurance coverage provided by Contractor Owners Liability Insurance Approval of products other than specified Notice of Award Performance, Labor, and Material Bonds Formal Contract signing Work Commencement Time Progress Schedule Notice of Conditions Causing Delay (in writing) Appeal from Consultants decision (verified) Dispute based on Fund or Consultant determination (in writing) Claim for disputed work (documented statement) Right to Default Contractor (written notice) Requests for Progress Payments Billing Breakdown of Contract amount Final requisition and final payment (written notices) Guarantee Payment Contr.

FULFILLMENT DATE In accordance with shop drawing and sample schedule Within 15 days after receipt At project completion Within 30 days after Notice of Award Within 10 days of submission Within 10 days of date Contractor receives payment Prior to acceptance of work by Fund One Year (minimum) or longer if so agreed Prior to commencing work Prior to approval of progress payment covering insurable work Prior to commencement of work at site Prior to incorporation into the project 45 days after bid opening 10 days after Notice of Award 10 days after Notice of Award Receipt of Notice to Proceed Letter 30 days after Notice of Award Within 10 days after commencement of condition(s) causing delay Within 10 days of decision date Within 10 days after Fund or Consultant determination Within 30 days after being required to perform disputed work 3 days notice (anytime) Monthly Prior to submission of first partial payment request Acceptance of Contract work One year following acceptance of work by Fund and request by Contractor

ROUTING FROM / TO Contractor / Consultant Consultant / Contractor Contractor / Consultant Contractor / Consultant Consultant / Contractor Contractor / Subcontractors Contractor / Consultant Fund / Contractor Contractor / Fund Contractor / Fund Contractor / Fund Contractor / Consultant Fund / Contractor, Consultant Contractor / Fund, Consultant Contractor / Fund, Consultant Fund/Contractor Contractor / Consultant Contractor / Fund, Consultant Contractor / Fund (cc Consultant) Contractor / Fund, Consultant Contractor / Consultant Fund / Contractor, Consultant Contractor / Fund, Consultant Contractor / Fund Contractor / Fund, Consultant Contractor / Consultant, Fund

A = Agreement

IB = Information for Bidders

PB = Performance Bond

LMB = Labor of Material Bond

NB = Notice to Bidders

ITEM A-4

LISTING OF PROJECT REPORTS REQUIRED DURING CONSTRUCTION PERIOD

TITLE

PERIOD COVERED

PREPARED BY

DISTRIBUTION

FORMAT

Field Report

Monthly

Consultant

Fund (1 copy)

Developed by Consultant

Shop Drawing Log

Bi-Weekly

Consultant

Fund (1 copy)

Developed by Consultant

RFI Log

Bi-Weekly

Consultant

Fund, Contractor

Fund Standard

Open Item Log

Bi-Weekly

Consultant

Fund, Contractor

Fund Standard

Pre-award Meeting Report

Ad hoc

Consultant

Minutes to Attendees

Developed by Consultant

Pre-Construction Orientation Meeting Report

Ad hoc

Consultant

Minutes to Attendees Consultant (2 copies) (1 field office,1 Consultant) Contractor (1 copy) Fund (when requested) Fund Coordinator (1 copy)

Developed by Consultant

Testing Lab Reports

Periodically (as required)

Testing Lab

Consultant/Lab.

Progress Photos Digital

Monthly

Contractor

Fund Standard

Substantial Completion Payment (Item 27 Appendix)

Ad hoc

Contractor

Attendees (3 copies) At inspection

Fund Standard

Accident Reports

Ad hoc

Contractor

Consultant, Fund

As required by circumstances

Asbestos/Reports, Regulated Materials

Ad hoc

Contractor

Fund (1 copy) SUNY (1 copy) Consultant (1 copy)

As required

ITEM A-5

ITEM A-5A

CF-C1

ITEM A-5B

ITEM A-6

CF-C2

ITEM A-7

CF-C3

ITEM A-8

CF-C11

ITEM A-9

REQUISITION WORK SHEET


STATE UNIVERSITY CONSTRUCTION FUND 353 Broadway ALBANY, NY 12246

Sheet

Of

Sheets

CONTRACTOR: ___________________________________________________________ REQUISITION NO. _________________ DATE ENDING _____________ PROJECT NO. TITLE: LOCATION: ________________________

No. 1

Description 2

Quantity 3

Unit 4

Unit Price 5

Total Price 6

% Compl. Last Request 7

Amt Compl. Last Request 8

% Compl. to Date 9

Total Amt Complete to Date 10

Amt Added to This Request 11

Amt Left to Complete 12

DC-5

ITEM A-10

STATE UNIVERSITY CONSTRUCTION FUND


353 Broadway Albany, New York 12246

CERTIFICATION OF MONTHLY PAYMENT

SUCF Project No. ___________________Date: ___________________ Project Title: _________________________________________________________________

This is to certify that the General Contractor ______________________________________ has made payment of $ Requisition No. for work performed by this subcontractor as covered by , for the period from ______________ to ________________ inclusive.

____________________________________________________
Name of Subcontractor

__________
Date

___________________________________________________________________________________________________

Signature

General Contractor to complete all blanks at top of sheet and forward to subcontractor with payment. Subcontractor to execute and immediately return to General Contractor for inclusion with next requisition.

CF-C5

ITEM A-11

OFFICE OF THE STATE COMPTROLLER

DIVISION OF PRE-AUDIT AND ACCOUNTING RECORDS


BUREAU OF STATE EXPENDITURES

New York State Labor Law, Section 220-a Prime Contractors Certification 1. That I am an officer of and am duly authorized to make this affidavit on behalf of the prime Contractor on Public Contract 2. That I fully comprehend the terms and provisions of Section 220-a of the Labor Law. 3. That, except as herein stated, there are no amounts due and owing to or on behalf of laborers employed on the project by the Contractor. (Set forth any unpaid wages and supplements, if none, so state). Name Amount No.

4. That the Contractor hereby files every verified statement required to be obtained by the Contractor from the subcontractors. 5. That, upon information and belief, except as stated herein, all laborers (exclusive of executive or supervisory employees) employed on the project have been paid the prevailing wages and supplements for their services through , the last day worked on the project by their subcontractor. [Set forth any unpaid wages and supplements, if none, so state and utilize clause 5 (A)]. Name Amount

(5A)

That the Contractor has no knowledge of amounts owing to or on behalf of any laborers of its subcontractors.

( continued )

CF-C4A1

New York State Labor Law, Section 220-a Prime Contractors Certification (Page 2)

6. In the event it is determined by the Commissioner of Labor that the wages or supplements or both of any such subcontractors have not been paid or provided pursuant to the appropriate schedule of wages and supplements, then the Contractor shall be responsible for payment of such wages and supplements pursuant to the provision of Section 223 of the Labor Law.

Signature

Print Name

Title

ACKNOWLEDGEMENT: STATE OF NEW YORK COUNTY OF } }

SS

On this

day of

20_____________

before me personally came __________________________________________ to me known and known to me to be the person described in and who executed the foregoing instrument and he/she acknowledged that he/she executed the same.

____________________________________ Notary Public

If this affidavit is verified by an oath administered by a notary public in a foreign country other than Canada, it must be accompanied by a certificate authenticating the authority of the notary who administers the oath. (See CPLR 2309(c); Real Property Law, 311,312).

CF-C4A1

ITEM A-12 OFFICE OF THE STATE COMPTROLLER

DIVISION OF PRE-AUDIT AND ACCOUNTING RECORDS


BUREAU OF STATE EXPENDITURES

New York State Labor Law, Section 220-a Subcontractors Certification 1. That I am an officer of _________________________________________________ a subcontractor on Public Contract No. and I am duly authorized to make this affidavit on behalf of the firm. 2. That I make this affidavit in order to comply with the provisions of Section 220-a of the Labor Law. 3. That on , we received from (the prime Contractor) a copy of the initial/revised schedule of wages and supplements Prevailing Rate Schedule Case Number (PRC) specified in the public improvement contract. 4. That I have reviewed such schedule(s), and agree to pay the applicable prevailing wages and to pay or provide the supplements specified therein.

Signature Print Name Title

ACKNOWLEDGEMENT: STATE OF NEW YORK COUNTY OF On this day of } }

SS 20

before me personally came _____________________________________________ to me known and known to me to be the person described in and who executed the foregoing instrument and he/she acknowledged that he/she executed the same.

Notary Public
If this affidavit is verified by an oath administered by a notary public in a foreign country other than Canada, it must be accompanied by a certificate authenticating the authority of the notary who administers the oath. (See CPLR 2309(c); Real Property Law, 311,312).

CF-C4A2

ITEM A-13 OFFICE OF THE STATE COMPTROLLER

DIVISION OF PRE-AUDIT AND ACCOUNTING RECORDS


BUREAU OF STATE EXPENDITURES

New York State Labor Law, Section 220-a Sub-subcontractors Certification 1. That I am an officer of subcontractor of Contract No. of the firm. a subcontractor to _____________, a the prime Contractor on Public Improvement and I am duly authorized to make this affidavit on behalf

2. That I make this affidavit in order to comply with the provisions of Section 220-a of the Labor Law. 3. That on , we received from (the subcontractor of the ) (Contractor) a copy of the initial/revised schedule of wages and supplements Prevailing Rate Schedule Case Number (PRC) specified in the public improvement contract. That I have reviewed such schedule(s), and agree to pay the applicable prevailing wages and to pay or provide the supplements specified therein.

4.

Signature Print Name Title ACKNOWLEDGEMENT: STATE OF NEW YORK COUNTY OF

} }

SS

On this day of 20 before me personally came to me known and known to me to be the person described in and who executed the foregoing instrument and he/she acknowledged that he/she executed the same.

Notary Public County

If this affidavit is verified by an oath administered by a notary public in a foreign country other than Canada, it must be accompanied by a certificate authenticating the authority of the notary who administers the oath. (See CPLR 2309(c); Real Property Law, 311,312).

CF-C4A3

ITEM A-14 STATE UNIVERSITY OF NEW YORK STATE UNIVERSITY CONSTRUCTION FUND SUMMARY OF WAGE RATE CERTIFICATION(S)

INSTRUCTIONS: List each subcontractor and/or sub-subcontractor used on this Contract and their last day of work. When submitting your Final and End-of-Guarantee payment applications, attach this form (in triplicate) along with the latest Wage Rate Certifications, in triplicate, for your own firm and each subcontractor and/or sub-subcontractor. *NOTE: CONTRACTOR Last day or work must be within the time frame of the latest Wage Rate Certification. CAMPUS

SUCF NO.

CONTRACT NO.

PROJECT TITLE

SUBCONTRACTOR OR SUBSUBCONTRACTOR

LAST DAY OF WORK

DATE OF LATEST WAGE RATE CERTIFICATION

The foregoing is a true and accurate listing of all subcontractors and sub-subcontractors employed on this Contract to date of completion. ______________________________________________
Legal name of person, partnership or corporation

By ______________________________________________
Signature

_______________________________________________
Address (State, Zip Code) (Street, City)

_________________________________________________
Name, Title

CF-C7A

ITEM A-15

CF-C8 revised 02/11

ITEM A-16

STATE OF NEW YORK

STATE UNIVERSITY CONSTRUCTION FUND

RELEASE

KNOW ALL PERSONS BY THESE PRESENTS, that the undersigned hereby acknowledges that pursuant to a contract dated the __________day of _______________________________, wherein the undersigned agreed to furnish for the State University Construction Fund all the work necessary to complete the construction of

the Fund has paid or will pay the undersigned, or a person, firm or corporation claiming by or through the undersigned, the sum of _________________________________________________________________ dollars ($_______________________), said amount being the full and entire sum due from the Fund to the undersigned under said contract, except for monies being retained by the Fund pursuant to the provisions of the aforesaid contract, including, but not limited to, money, if any, due to the undersigned by reason of extra work, labor or materials furnished or performed in connection with, relating to, or arising out of the subject matter of said contract. In consideration of such payment, the undersigned hereby releases and discharges the Fund, its officers, agents and employees, of and from all claims of liability to the undersigned for anything furnished or performed in connection with, relating to or arising out of the contract or out of the work covered by said contract, including but not limited to, all claims for extra work, labor or materials and for any prior act, neglect or default on the part of the Fund or any of its officers, agents, or employees in connection therewith, except for the aforesaid retained monies. The undersigned further acknowledges that neither the aforesaid payment nor acceptance by the Fund of the work covered by the aforementioned contract shall in any way or manner operate as, or constitute a release or waiver of the undersigned's obligations, undertakings or liabilities under said contract or in any way affect or limit the same. IN WITNESS WHEREOF, the undersigned has caused its name to be hereunto subscribed and its seal to be hereunto affixed this __________ day of ________________________________.

_______________________________________________________ Name of Contractor

By _____________________________________________________
Affix Seal here

C5

ITEM A-17

CONTRACTORS CERTIFICATE OF INSURANCE

TO:

State University Construction Fund State University Plaza 353 Broadway Albany NY 12246

This is to certify that the insurance policy listed below has been issued by the undersigned and is in full force and effect on the date borne by this Certificate. Name/Address of Insured Contractor __________________________________________________________ __________________________________________________________ __________________________________________________________ Title/Proj Number to which this Certificate applies Insurance Type Workers Compensation __________________________________________________________ Limits of Liability As required by law $ ___________ Each Occurrence Contractors Comprehensive General $ ___________ Aggregate Bodily Injury Liability and Property Damage Liability Contractors Automobile Liability Bodily Injury Liability and Property Damage Liability Owners Protective Liability Bodily Injury Liability and Property Damage Liability $ ___________ Combined Single Limit $ ___________ Each Accident or Occurrence $ ___________ Combined Single Limit $ ___________ Each Occurrence $ ___________ Aggregate $ ___________ Combined Single Limit Policy No. Effective Expiration

Builders Risk Excess or Umbrella As an inducement to the Fund to approve the undersigned as an insurance company issuing the policies listed above, and this Certificate as being in compliance with the construction Contract between the Fund and _______________________________________________________the undersigned insurance company, duly licensed to do business in the State of New York, hereby agrees as follows: 1. 2. That the insurance policies listed above conform, in all respects, with the requirements set forth in Sections 5.06 and 5.07 of Article V of the Agreement been the Fund and Contractor. That the insurance policies listed above shall not be changed or cancelled and that they will automatically be renewed upon expiration and continued in force until final acceptance by the Fund of all the work covered by the aforesaid construction Contract unless the Fund is given thirty (30) days written notice to the contrary. That the Fund shall not be liable for the payment of the premium on any of the insurance policies listed above and that such premium shall be payable by the Contractor named above who shall also receive any dividends or other refunds due under the above-listed insurance policies. The Insurer certifies that there is no inconsistency or conflict with or between any of the terms, provisions and conditions hereof and any of the terms, provisions and conditions of the policies listed above except for the following: ________________________________________________________________________________________________________________

3.

4.

5. That without the undersigneds foregoing agreements neither it nor this Certificate of Insurance would be approved by the Fund. Name of Insurance Company

Phone

Authorized Representative (Original Signature Required)

Date

Item A-18

CF-C9

Item A-18A

CF-C9

ITEM A-19

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

Consultant Consultant Address Attention: SUBJECT: Gentlemen: You are hereby authorized to have the following work performed: Proposal No. PROCEED ORDER AUTHORIZATION

It is understood that the amount of the Contract Consideration is to be increased on a time and material basis for this change by the execution of a subsequent documented change to the Contract. In order that the Contractor be paid promptly for this work, a detailed proposal must be obtained from the Contractor and submitted promptly with your review and recommendation permitting the issuance of a formal change authorization to the Contract. Very truly yours,

John K. Hagen, Jr., P.E. Director of Construction Management


C: Contractor

Change Proposal File


John K. Hagen, Jr., P.E., Director of Construction, Office of Construction Management (518) 320-3210 Fax: (518) 689-2638 E-Mail: john.hagen@suny.edu

ITEM A-20

FORM OF BACKCHARGE LETTER

DATE Re: SUCF Project No. Title Campus

Contractor Name Address Gentlemen: You are hereby directed to perform the following work: (Describe work and location thereof) In the event that you fail to comply with this directive within three (3) working days of the receipt hereof, the Fund, under Section 4.06 of the Agreement, will omit said work from your Contract, may have the same performed by another Contractor and will backcharge your Company by the issuance of a credit change order for all costs and expenses it incurs in connection with your failure to comply with this directive. Such work is preliminarily estimated to be valued at (amount in words) dollars ($numeric value) but this amount is not firm and in no way limits the amount of the credit change order(s). This direction or the issuance of the aforesaid credit change order(s) are without prejudice to any other rights, remedies or claims of the Fund under the Contract. Very truly yours,

Signed by Consultant or SUCF

ITEM A-21

STATE OF NEW YORK STATE UNIVERSITY CONSTRUCTION FUND ASBESTOS MATERIAL REMOVAL FACT SHEET

_____________ _________________________________________ SUCF PROJ NO. PROJECT TITLE SCOPE OF WORK:

__________ DATE

______________________________________________________________________

ASBESTOS CONTRACTOR: Name/Address (if applicable) _________________________________________ _________________________________________ _________________________________________ Phone # ____________________________ Contract Awd Amt: ____________________ Contract Completion Date: ______________

GENERAL CONTRACTOR:

________________________________ ________________________________ ________________________________

Phone # _______________________________ Asbestos Lic #: ________________________________ Expiration Date: _______________________________

ASBESTOS ABATEMENT PERSONNEL: (Attach Additional Sheets as Required) Social Certificate Name Title/Function Sec. # Number Expiration Date 1. ___________________________________________________________________________________ 2. ___________________________________________________________________________________ 3. ___________________________________________________________________________________ 4. ___________________________________________________________________________________ 5. ___________________________________________________________________________________ ASBESTOS ABATEMENT WORK : (Attach Additional Sheets as Required) Bldg. (1) Usage Removal Location (Bldg./Room) Material (2) Removed Methods of Removal

Quantity (3)

1. __________________________________________________________________________________ 2. __________________________________________________________________________________ 3. __________________________________________________________________________________ 4. __________________________________________________________________________________ 5. __________________________________________________________________________________ Date Removal Begins: ________________________ Asbestos Carrier: ___________________________ __________________________________________ __________________________________________ Phone No.: ______________________________ Ends: ___________________________ Disposal Site: ____________________ ________________________________ Phone No.: _______________________

Hauler Permit No(s).:__________________________________________________________________ __________________________________________________________________________________________


NOTE: In addition to the above information, the Contractor shall submit all required documentation as stipulated by the New York State Labor Law Article 30; Part 56, 12NYCRR, which includes a copy of the asbestos contractor license and all asbestos handling certificates, waste transporter permits, disposal receipt acknowledgement, and air test reports (prior, during, and after abatement).

STATE OF NEW YORK STATE UNIVERSITY CONSTRUCTION FUND ASBESTOS MATERIAL REMOVAL FACT SHEET KEY

1.

BUILDING USAGE A. B. C. D. E. F. G. H. I. Administration Academic Library Health/Physical Education Dining Halls Dormitory Mechanical Room Steam Tunnel Other

2.

MATERIAL REMOVED A. B. C. D. E. F. G. H. I. J. K. L. M. N. Acoustical/Decorative Plasters ADP Fireproofing Materials FM Troweled Wall/Ceiling Plasters TCP Mud Joints/Tees MJT Pipe Covering (List Size Pipe) PC Boiler/Hot Water Tank Insulations BHTI Panels/Ceiling Tiles . PCT Transite Panels TP Vent/Drain Pipes (List Size) VDP In-Place Gaskets IPG Vinyl Asbestos Siding VAS Vinyl Asbestos Tile . VAT Vinyl Asbestos Roofing VAR Other (Describe) O

3.

QUANTITY OF MATERIAL S.F. Square Feet (i.e. walls, ceiling, structural members, etc.) L.F. Linear Feet (i.e. pipe, etc.)

4.

REMOVAL METHODS A. B. C. D. E. Wet Dry Glovebag Tent Other

ITEM A-22

State University Construction Fund Regulated Materials Disposal Fact Sheet

________________________ SUCF Project No./Campus

______________________________________________________________________ Project Title Date

Scope of Work: ______________________________________________________________________ Campus Generator No.: _________________________________________________________ General Contractor: Name / Address: Telephone No. _____________________________ _____________________________
___________________________________

Subcontractor: (if applicable) _____________________ _________________________________


________________________________________

_____________________________

Telephone No. ____________________

Contract Award Amount: Contract Completion Date: Contract No.:

_____________________________________ _____________________________________ _____________________________________

Listing of Regulated Materials Removed: (attach additional sheets as required) Description: 1. ________________________ 2. ________________________ 3. ________________________ 4. ________________________ 5. ________________________ Qty/Units ________ ________ ________ ________ ________ Method of Disposal __________________________ __________________________ __________________________ __________________________ __________________________ Classification ____________ ____________ ____________ ____________ ____________

Date Removal Began: _____________ Location of Disposal Site(s): Name/Address ____________________ _________________________________ _________________________________
________________________________________

Date Disposal Complete: ________________ Transportation: Name/Address __________________________ _______________________________________ _______________________________________


_______________________________________________

Telephone No. _________________ Facility Permit No. _________________ Expiration Date: ___________________ Material Testing

Telephone No. __________________________ Hauler Permit No. ________________________ Expiration Date: _________________________

Required: _________________________ Not Required: ___________________________

CF-C9

ITEM A-23
CERTIFICATE OF INSURANCE FOR MATERIALS STORED OFF-SITE

To:

State University Construction Fund State University Plaza 353 Broadway Albany, New York 12246

This is to certify that the insurance policies listed below have been issued by the undersigned and are in full force and effect on the date borne by this Certificate.

Name and Address of Insured Contractor

______________________________________________________________ ______________________________________________________________ ______________________________________________________________

Title and Number of ______________________________________________________________ Project to which this ______________________________________________________________ Certificate applies: ______________________________________________________________

KIND OF INSURANCE Builder's Risk w/ broad form extended coverage endorsement

LIMITS OF LIABILITY $ _______________________________

POLICY NO.

EFFECTIVE

EXPIRATION

As an inducement to the Fund to approve the undersigned as an insurance company issuing the policies listed above and this Certificate as being in compliance with the construction contract between the Fund and _____________________________________ _________________________________________, the undersigned insurance company, duly licensed to do business in the State of New York, hereby agrees as follows: 1. That the insurance policies listed above conform, in all respects, with the requirements set forth in Section 4.14(1)(c) of Article IV of the Agreement between the Fund and the Contractors. That the insurance policies listed above shall not be changed or cancelled and that they will automatically be renewed upon expiration and continued in force until final acceptance by the Fund of all the work covered by the aforesaid construction contract unless the Fund is given fifteen (15) days' written notice to the contrary. That the Fund shall not be liable for the payment of the premium on any of the insurance policies listed above and that such premium shall be payable by the Contractor named above who shall also receive any dividends or other refunds due under the above-listed insurance policies. The Insurer certifies that there is no inconsistency or conflict with or between any of the terms, provisions and conditions hereof and any of the terms, provisions and conditions of the policies listed above except for the following: _________________________________________________________________________________________________

2.

3.

4.

Name of Insurance Company

Phone

Authorized Representative (Original Signature Required)

Date

CISM

5/04

ITEM A-24

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

Contractor Contractor Address SUBJECT: Request for Federal Tax Identification Number for SUCF Project No. Contract No. D

Gentlemen: Effective immediately, the Office of State Comptroller requires the Federal Employer Identification number or Social Security number of payees before processing payments. To comply with this requirement we will need the social security numbers for individuals or the employer identification number for partnerships or corporations. To set up our file of tax identification numbers, we are forwarding this form letter. Will you please enter in the box after your name above the tax identification number that will apply to the State University Construction Fund project listed under subject. Please return a completed copy of this letter to the State University Construction Fund, to my attention as promptly as possible. Very truly yours,

SUCF Controller

ITEM A-25
Rev. 6/02

STATE UNIVERSITY CONSTRUCTION FUND


CONSTRUCTION BUILDING PERMIT
Consultant of Record: Project Title: SUNY Campus: SUCF Project No.: Effective Date of Permit: Expiration Date of Permit: Attached are copies of the code analysis and code conformance drawings (required for all new buildings and major rehabs), if available, prepared by the Architect and the Fund Code Review Comments for each phase. BASIC INFORMATION New Code (Codes of New York State, Title 19 Dept of State) Nature of Work: _______________________________________________ _______________________________________________ Gross Area by Floor: Basement: First: Second: Third: Building Occupancy Classification: Construction Type: Project fully sprinklered ______ sq.ft. ______ sq.ft. ______ sq.ft. ______ sq.ft.

______________________ ______________________ Yes No

Based upon the code conformance reviews documented in the attached material, the Fund to the best of its knowledge and belief, has determined the project is substantially in compliance with the requirements of the New York State Uniform Fire Protection and Building Code. Permission is granted to proceed with construction subject to the periodic inspections required by the Certificate of Occupancy.

_______________________________________ Christopher P. Marcella, Director of Design Offices of Preconstruction Services & Design ______________________________________ Code Compliance Manager
cc: To P. McSorley - attached to Notice of Award

ITEM A-26

STATE UNIVERSITY CONSTRUCTION FUND WAIVER OF BUILDING PERMIT REQUIREMENT

Project Title: SUNY Campus: SUCF Project No.

Based on a review of the program this project consists of necessary repairs and/or replacement in kind which will not materially change the structural elements and/or the plumbing, electrical or heating/ventilation systems of the building in which it will be constructed. OR Based on a review of the program this project consists of sitework such as roads, parking lots, landscape or site utilities and does not involve work inside a building except for utility connections.

Christopher P. Marcella, Director of Design Offices of Preconstruction Services & Design

TO: FROM: DATE:

Christopher P. Marcella (Coordinator)

No changes have been made to the above project during design that would effect the determination that a Building Permit is not required.

cc: P. McSorley - attached to Notice of Award

ITEM A-27

(CONTRACTOR LETTERHEAD)

Date Re: SUCF Project No. Project Title Campus

State University Construction Fund 353 Broadway Albany, New York 12246 Attention: Mr. John K. Hagen, Jr. Director of Construction COMPLETION OF PROJECT

Subject: Gentlemen:

Please be advised that the captioned project has been completed in accordance with the Contract Documents and is ready for acceptance and occupancy. Very truly yours,

(Officer of the Company)

cc:

Consultant Project Coordinator

ITEM A-28

(CONSULTANT LETTERHEAD)

Date Re: SUCF Project No. (Project Title) State University

State University Construction Fund 353 Broadway Albany, New York 12246 Attention: Mr. John K. Hagen, Jr. Director of Construction ACCEPTANCE OF PROJECT

Subject: Gentlemen:

Please be advised that to the best of our knowledge and belief, the captioned project has been completed in accord with our Contract Documents, and the project conforms to all requirements of the New York State Uniform Fire Prevention and Building Code. It is our recommendation that the project be occupied, and that a Certificate of Occupancy be issued for the project. Very truly yours,

(Consultant of Record)

ITEM A-29
STATE OF NEW YORK

STATE UNIVERSITY CONSTRUCTION FUND CHECKLIST FOR SUBSTANTIAL COMPLETION

SUCF Project No. Project Title:

Campus:

INITIALS Keys Money due Campus Operating Instructions Spare Parts Lists Shop Drawings Cuts and Brochures Bonds, Guarantees, etc. Record Information to Architect Punch List Established Campus Personnel Instructed Release

REMARKS

Notes:

Approved by: Date:

CF-C6

ITEM A-30

STATE UNIVERSITY CONSTRUCTION FUND CERTIFICATE OF OCCUPANCY

Consultant of Record: Project Title: SUNY Campus: SUCF Project No.: Effective Date of Occupancy:

To the best of our knowledge and belief, the captioned project has been substantially completed in accordance with the Contract Documents, the Building Permit issued for the Project, and with Change Order Nos. 1 through *. Based on periodic inspections that have been made during the construction of the project and the Final Inspection on XXX, permission is granted to occupy the project.

___________________________________ John K. Hagen, Jr., Director of Construction

__________________________________ Code Compliance Officer

*See final Change Order for final cost and Change Order file for changes relating to this project

ITEM A-31

STATE UNIVERSITY CONSTRUCTION FUND TEMPORARY CERTIFICATE OF OCCUPANCY

Consultant of Record: Project Title: SUNY Campus: SUCF Project No.: Effective Date of Occupancy:

To the best of our knowledge and belief, the captioned project has been substantially completed in accordance with the Contract Documents, the Building Permit issued for the Project, and with Change Order Nos. 1 through *. Based on periodic inspections that have been made during the construction of the project and the Final Inspection on XXX, permission is granted to occupy the following portion of the project. LIST OF SPACES TO BE OCCUPIED Until the Contract has been substantially completed, the remainder of the project should not be used until a permanent Certificate of Occupancy is issued.

______________________________ John K. Hagen, Jr., P.E. Director of Construction _______________________________ Code Compliance Officer
*See final Change Order for final cost and Change Order file for changes relating to this project

ITEM A-32

CONSTRUCTION INSPECTION REPORT


Consultant: Project Title: SUNY Campus: SUCF Project No.

ITEM Foundations Super Structure Electrical Plumbing HVAC Fire Protection Fire Detection Exits

DATE STARTED

DATE COMPLETE

INSPECTED BY

CHANGE ORDER RE: ITEM

ITEM A-33
FINAL INSPECTION REPORT

Consultant of Record: Project Title: SUNY Campus: SUCF Project No.: On (Date), a Final Inspection of the captioned project was made by the following: Represented by: Fund SUNY Consultant Engineer(s) General Contractor Subcontractor(s)

The project was found to be substantially completed in accordance with the Contract Documents, the Building Permit issued for the project, and with Change Order Nos. 1 through X, except for the attached Punch List.* The Contractor, by letter dated X, stated that the project has been completed in accordance with the Contract. The Consultant, by letter dated X, has recommended to SUCF acceptance of the project.

Fund Project Coordinator

_____________________________ Regional Director of Construction

*See final Change Order for final cost and Change Order file for changes relating to this project

ITEM A-34 FACT SHEET FOR PROJECTS REQUIRING BUILDING PERMIT AND CERTIFICATE OF OCCUPANCY
1. 2. SUCF Project No. ................................................................................................................. Project Title: .......................................................................................................................... Campus: ................................................................................................................................ Award Value: ....................................................................................................................... $ Final Value: ......................................................................................................................... $ Consultant of Record: ............................................................................................................ Date of Building Permit .......................................................................................................... Expiration Date of Building Permit ......................................................................................... Date of Extension of Building Permit: .............................................................................. N/A Expiration Date of Extended Building Permit ................................................................... N/A

3. 4. 5. 6. 7. 8. 9.

10. Date of Partial Acceptance Inspection: ............................................................................ N/A 11. Date of Temporary Certificate of Occupancy: .................................................................. N/A 12. Date of Letter to President regarding Partial Acceptance of Project and Transmitting Temporary Certificate of Occupancy .................................................... N/A 13. Date of Contractor's Letter of Project Completion .................................................................. 14. Date of Consultants Letter Recommending Acceptance: ...................................................... 15. Date of Final Inspection Report: ............................................................................................ 16. Date of Certificate of Occupancy: .......................................................................................... 17. Date of Letter to President regarding Final Acceptance of Project and Transmitting Certificate of Occupancy: ........................................................................... 18. Code Compliance Manager issuing Permit ............................................................................ 19. Code Compliance Manager issuing Temporary Certificate of Occupancy: ...................... N/A 20. Code Compliance Manager issuing Certificate of Occupancy: ..............................................

ITEM A-35

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

State University Construction Fund 353 Broadway Albany, New York 12246 Attention: Subject: Gentlemen: On X, an inspection of the above-referenced project was made by representatives of the Campus, State University Construction Fund, the Consultant, and the Contractor. The project is accepted, subject to the attached Punch List, as of 8:00 a.m. on X, at which time the College will be solely responsible for the operation, maintenance and security of the facility. This marks the start of the one-year guarantee period. Director of Construction FINAL INSPECTION AND ACCEPTANCE (FINAL)

ACKNOWLEDGED: For the Campus: State University Construction Fund:

Designated Campus Officer Title

___________________________________ Fund Project Coordinator

ITEM A-36

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

President Campus Address SUBJECT: FINAL INSPECTION AND ACCEPTANCE (FINAL) :

Dear President

On XXX, an inspection of the above-referenced project was made by representatives of the College (), State University Construction Fund (coordinator); the Consultant, and the Contractor ( ). The project is accepted, subject to the attached Punch List, as of 8:00 a.m. on XXX, at which time the College will be solely responsible for the operation, maintenance, and security of the facility. This marks the start of the one-year general guarantee period. During the one-year general guarantee period, all contractual construction defects are required to be corrected by the Contractor without any additional cost. In order to ensure that this requirement is fully complied with by the Contractor, it is imperative that your authorized Campus representative or representatives promptly notify the undersigned in writing of any contractual construction defects of which they may become aware. It is essential that this notification be given promptly, and that it not be deferred until the end of the one-year general guarantee period, in order for the Fund to timely notify the Contractor and have the defect corrected. Very truly yours,

John K. Hagen, Jr., P.E. Director of Construction Management


cc: Facilities Information Services

John K. Hagen, Jr., P.E., Director of Construction, Office of Construction Management (518) 320-3210 Fax: (518) 689-2638 E-Mail: john.hagen@suny.edu

ITEM A-37

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

Contractor Address SUBJECT: Gentlemen: On XXX, an inspection of the above-referenced project was made by representatives of the College (), State University Construction Fund (coordinator); the Consultant (); and the Contractor ( ). The project is accepted, subject to the attached Punch List, as of 8:00 a.m. on XXX, at which time the College will be solely responsible for the operation, maintenance and security of the facility. This marks the start of the one-year general guarantee period. Very truly yours, FINAL INSPECTION AND ACCEPTANCE (FINAL)

John K. Hagen, Jr., P.E. Director of Construction Management


cc: Consultant Information Services

John K. Hagen, Jr., P.E., Director of Construction, Office of Construction Management (518) 320-3210 Fax: (518) 689-2638 E-Mail: john.hagen@suny.edu

ITEM A-38

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

State University Construction Fund 353 Broadway Albany, New York 12246 Attention: SUBJECT:
Gentlemen:

Director of Construction END OF ONE-YEAR GUARANTEE PERIOD

As the result of the inspection made on XXX of the above-referenced project at the Campus by representatives of the Campus and State University Construction Fund, the Contractor was found to have complied with all requirements of its one-year guarantee. ACKNOWLEDGED: For the College: For State University Construction Fund:

Designated Campus Officer

__________________________________ Fund Project Coordinator

John K. Hagen, Jr., P.E., Director of Construction, Office of Construction Management (518) 320-3210 Fax: (518) 689-2638 E-Mail: john.hagen@suny.edu

ITEM A-39

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

President Campus Address SUBJECT: END OF ONE-YEAR-GUARANTEE PERIOD

Dear President XXXX: On X, an inspection of the referenced project was made by representatives of the Fund ( ), and the Campus ( ). The Contractor was found to have complied with all requirements of its one-year guarantee. Very truly yours,

John K. Hagen, Jr., P.E. Director of Construction Management

cc:

Facilities

John K. Hagen, Jr., P.E., Director of Construction, Office of Construction Management (518) 320-3210 Fax: (518) 689-2638 E-Mail: john.hagen@suny.edu

ITEM A-40

STATE UNIVERSITY CONSTRUCTION FUND


State University Plaza 353 Broadway
Albany, NY 12246
www.sucf.suny.edu

Date Re: SUCF Project No. Project Title Campus

Contractor Address SUBJECT: Gentlemen: On X, an inspection of the referenced project was made by representatives of the Fund ( ), and the Campus ( ). The Contractor was found to have complied with all requirements of its one-year guarantee. Very truly yours, END OF ONE-YEAR-GUARANTEE PERIOD

John K. Hagen, Jr., P.E. Director of Construction Management

cc:

Consultant

John K. Hagen, Jr., P.E., Director of Construction, Office of Construction Management (518) 320-3210 Fax: (518) 689-2638 E-Mail: john.hagen@suny.edu

Item A-41

LABOR RATE BREAKDOWN

SUCF Project No.: Contractor:

Project Location: Date: _____________

Trade: ________________________________________________ Effective Date: *Base Hourly Rate: Payroll Taxes and Insurance F.I.C.A. Federal Unemployment State Unemployment **Workmans Compensation ***B.I. & P.D. Disability TOTAL Payroll Taxes and Insurance Rates: Base Rate (X) Total % = Supplemental Benefits Vacation Health & Welfare Pension Annuity Education/App. Training Industry $ Hour ______ ______ ______ ______ ______ ______ ______ ______ ______ Total Hourly Fringe Benefits Hourly Labor Rate: Base Rate, Taxes/Insurance and Fringe Benefits $______ $______ % Hour ______ ______ ______ ______ ______ ______ % $_________ Expiration Date: __________________ $________

*If any supplemental benefits are paid in the hourly rate, submit two (2) separate weekly copies of a certified payroll. **Workmans Compensation, B.I. and P.D. rates are net Contractor cost after premium discounts, experience modification and assessments have been applied against the manual rate. ***In accordance with Sections 4.02 and 5.06 of the Contract Documents, only payroll related liability insurances are reimbursable.

Office of Construction Management Management of Construction Projects

Page 79 Appendix B Processing Flow Charts

ITEM A-42

Office of Construction Management Management of Construction Projects

Page 80 Appendix B Process Flow Charts

ITEM A-43

Office of Construction Management Management of Construction Projects

Page 81 Appendix B Process Flow Charts

Item A-43

Office of Construction Management Management of Construction Projects

Page 82 Appendix B Process Flow Charts

APPENDIX B FLOW CHARTS TABLE OF CONTENTS

Final Inspection and Acceptance flow Chart ......................................................... B-1 End of One Year Guarantee Flow Chart ............................................................... B-2

Office of Construction Management Management of Construction Projects

Page 83 Appendix B Process Flow Charts

ITEM B-1

FINAL INSPECTION and ACCEPTANCE


Contractor Consultant SUCF Construction Receipt of Letter Advising Contract Complete (27) Campus

Letter Advising Contract Complete (27)

Receipt of Letter Advising Contract Complete (copy 27)

Confirmation of Project Substantial Completion

Uncompleted Work Items List

Project Final Inspection Walk Through

Acceptance Letter and Punch List (28)

Checklist for Substantial Completion, CF-C6 (29)

Final Inspection Acceptance Sign-Off (35)

Sign & Return Final Inspection Acceptance (35)

Construction Inspection Report (32) (if required) Final Inspection Report (33) (if required) Fact Sheet for Certificate of Occupancy (34) (if required)

Certificate of Occupancy (30) (if required)

Receipt of Final Inspection Acceptance Letter (37)

Receipt of Final Inspection Acceptance Letter (copy 37)

Final Inspection Acceptance Letters (36 and 37)

Receipt of Final Inspection Acceptance Letter (36)

ITEM B-2

END OF ONE YEAR GUARANTEE


SUCF Construction

Contractor

Consultant

Campus

Receipt of Guarantee List

Guarantee List

Guarantee Issues

Guarantee Issues

Deficiencies Corrections Final Balancing of HVAC Systems

End of Guarantee Inspection

Completion of Corrections End of Guarantee SignOff Letter (38) Sign & Return End of Guarantee Sign-Off Letter 38)

Receipt of End of Guarantee Letter (40) Receipt of End of Guarantee Letter (copy 40)

End of Guarantee Period Letters (39 and 40)

Receipt of End of Guarantee Letter (39)