Sei sulla pagina 1di 20

Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Chapter 1 – Introduction – Key Points

• “Good practice” does not mean that the knowledge described should always be applied uniformly on all projects; the project management team is responsible for
determining what is appropriate for any given project (PMI Bold)
• A project is a temporary endeavor undertaken to create a unique product, service or result
• Progressive elaboration is a characteristic of projects, meaning that it is developed in steps, and continues by increments. For example, items might be described in broad
terms at the start of the project but be defined in detailed terms by the conclusion of the project – from the preliminary project scope statement to the verified project scope
statement supported by a detailed WBS
• Projects are different than operations; projects are supposed to complete their objective and then cease to exist; operations continue indefinitely and sustain the business
• Projects are often conducted to support the organizations’ strategic plan, and to support one or more strategic element:
o Market demand
o Organizational need
o A customer request
o A technological advance
o A legal requirement
• Project management is the application of knowledge, skills, tools and techniques to project activities to meet project requirements
• Project management is accomplished through the application and integration of the project management processes of initiating, planning, executing, monitoring &
controlling, and closing
• Managing a project includes 1) identifying requirements 2) establishing objectives 3) balancing scope, timing and cost 4) adapting the plan to different concerns of
stakeholders
• The five areas of expertise in the project management team include
o The project management body of knowledge (PMBOK)
o Application area knowledge, standards and regulations
o Understanding the project environment
o General management knowledge and skills
o Interpersonal skills
• Application area knowledge, standards and regulations are usually defined in terms of 1) functional departments (i.e. legal, marketing) 2) technical elements (i.e. software
development) 3) management specializations (i.e. government contracting) 4) industry groups (i.e. energy, financial services)
• Standards are guidelines or a preferred approach (i.e. ISO) and regulations are government-imposed requirements such as laws (i.e. EPA, contract law)
• The project environment includes cultural and social environment (people demographic, education, organizational accountability), the international and political
environment (time zones, different countries) and physical environment (is the team co-located?)
• General Management Knowledge and Skills including planning, executing and controlling to support the company. Supporting areas include 1) accounting 2) purchasing
3) sales 4) contracting 5) manufacturing & distribution 6) planning 7) HR 8) health and safety 9) IT
• The management of interpersonal relationships includes 1) communication 2) influence 3) leadership 4) motivation 5) negotiation 6) problem solving
• Programs vs. Project management – a program is a group of related projects that need to be managed in a coordinated fashion, such as the development of a new product
that contains multiple assemblies and includes related activities such as marketing plans
• A portfolio is a group of projects or programs that are managed together to meet company objectives, such as those to support a line of business or internal process
improvement
• Projects may be broken into subprojects, such as skilled labor (construction) on a larger project
• A Project Management Office is an organization to manage and coordinate projects that are under its domain. A PMO can oversee programs or projects. PMO’s are of
varying forms depending on the organization, where they can coordinate, manage or even execute projects

1
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
• Key PMO features may include 1) coordination of resources 2) run PM Methodology 3) document repository 4) monitoring of project managers 5) coordination of overall
project standards
• PMO’s are different from project managers in that the project manager works on their specific project, while the PMO manages resources across multiple projects. The
project manager manages scope, schedule, cost and quality while the PMO manages overall risk, opportunity and interdependencies across projects. The project manager
reports on one project, while the PMO provides consolidated project reporting

Chapter 2 – Project Life Cycle and Organization – Key Points

• The project life cycle includes the phases necessary to work a project from beginning to end. The transition from one phase to another is generally recognized by some
kind of a deliverable or handoff. These phases generally define 1) work to be done that phase 2) when deliverables are generated 3) resources used in each phase 4)
control of each phase
• Costs generally are low at the start, are highest during middle phases, and drop off as the project is being completed
• Uncertainty and risk is highest at the start of the project and likelihood of project completion increases as it moves toward the concluding phases
• Stakeholders can more easily make changes at the start of the project early on; later the cost of changes grows very high as the project moves towards completion
• The completion and approval of one or more deliverables characterizes a project phase. A deliverable is a work product that can be viewed and assessed
• A project phase generally concludes with a review of the deliverable and to determine whether the deliverables are accepted or if more work needs to be done
• After each phase is completed authorization is generally needed to begin the next phase of the project (i.e. “kill point”)
• A typical project has the following phases:
o Initial – inputs include 1) ideas 2) project management team; outputs include 1) charter 2) scope statement
o Intermediate – outputs include 1) plan 2) baseline 3) progress 4) acceptance
o Final – outputs include approval, handover and the ultimate project deliverable, the product
• The reason that projects are initiated are to resolve business problems or to take advantage of opportunities
• The PRODUCT life cycle is “above” the project life cycle – it includes operations & development (which occur after the project has been completed) and include the
business plan, which starts before the project begins
• Project stakeholders are people involved in the project or impacted by the project. Stakeholders can be defined widely (i.e. the community who is impacted by pollution
and congested after the project to build a plant is completed) or narrowly (those working on the project). Negative stakeholders don’t want the project to be completed
(i.e. environmentalists). Positive stakeholders want the project to succeed
• Every project includes the following stakeholders
o Project manager – manages the project
o Customer / user – the people who use the end product generated by the project
o Performing organization – the company that the project team works for
o Project team members – doing the work
o Project management team – the managers running the project
o Sponsor – the group that provides the money and authorizes the project
o Influencers – not directly related to the project, but can impact the outcome
o Project Management Organization (PMO) 0 if it exists, may have some responsibility for completion
• Note that stakeholders may have differing objectives – finance may want it done for the lowest price, marketing may want the most features, IT may want the newest
technology, and environmentalists may want it to fail outright
• There are 2 major types of project-based organizations
o Organizations that make money by completing projects for other companies, such as consultants, architects, companies that make products for the US Military,
etc…
o Organizations that chose to adopt “management by projects” and have systems and processes in place to facilitate projects

2
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
• Non project based organizations often lack tools and systems for project management, making a successful completion less likely
• Organizational cultures impact projects – entrepreneurial companies may accept high risk projects, and rigid hierarchy companies may challenge project managers who
seek authority
• There are 3 major types of organizations – 1) functional 2) matrix (with weak, balanced or strong types) and 3) projectized
• Functional organizations are traditional organizations with work “silos” like HR, accounting, production, marketing, etc… In these organizations the project manager has
little (formal) authority, finds it hard to obtain resources, reports to a functional manager, and is part time w/part time admin staff
• The projectized organization has most employees engaged in project work, and project managers have high authority and visilibity
• The “matrix” organization has elements of project and functional organization, where the project manager may report to 2 bosses (functional and project), and the weak
vs. strong shows the degree of autonomy and resources that the manager has available
• A PMO can exist in any organization type. The role may vary from advisor to having project managers report to the PMO
• The Project Management System consists of the tools, techniques, methodologies, resources, and procedures used to manage a project

Chapter 3 – Project Management Processes for a Project – Key Points

• In order for a project to be successful, the team must


o Select correct processes
o Use a defined approach to meet requirements
o Comply with requirements to meet stakeholder needs
o Balance 1) scope 2) time 3) cost 4) quality 5) resources 6) risk to complete the project
• The project manager is always responsible for determining what processes are appropriate for that project. This is known as “tailoring” the project
• Project team processes generally fall into one of the following categories:
o Project processes generally initiate, plan, execute, monitor, control and close a project
o Product-oriented processes create the product and vary by area
• The five process groups are 1) initiating 2) planning 3) executing 4) monitoring & controlling 5) closing
• Plan – Do – Check – Act is another way to accomplish this
• The Process Groups are not Project Phases!
• Initiating group for formal authorization of a project or a project phase. The basic scope, duration, deliverables and resources for the project are determined at this time.
The relationship of the project to the organization’s strategic initiatives is also identified. The project manager is also assigned during this phase. The project charter is
written, and when the charter is approved, the project becomes officially authorized. It is critical to involve stakeholders during the initiation phase
• The planning process group is used to plan and manage the project. These processes identify, define and mature the project scope, cost and schedule. Significant changes
during the life of the project will trigger the need to revisit planning process items. Key deliverables of the planning process include the project management plan, scope
planning, the WBS, activities, sequencing and scheduling, cost estimating & budgeting, and planning for risk, HR, communications and quality
• The executing process group contains the steps necessary to perform the work laid out in the project plan to meet the project’s objectives. The vast majority of the
project’s budget will be spent in this phase
• The monitoring and controlling process group contains steps and processes needed to watch project execution to identify potential problems and corrective action can be
taken to keep the project on track. This group also influences the factors that could thwart change control to ensure only approved changes get made (i.e. stop scope
creep)
• The closing process group includes the processes needed to formally conclude the project and hand off the completed product to the end customer
• All of the steps below (44) are mapped into the five groups listed above

3
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Integration Management – Processes & activities required to ensure that the various elements of the project are properly coordinated to meet stakeholder expectations.
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
4.1 Develop Project Charter ♦ Contract ♦ Project selection ♦ Project Charter Initiating Sponsor initiates the charter; charter
which formally authorizes a ♦ SOW (includes business methods includes 1) requirements to satisfy needs
project need, scope description, ♦ Project mgmt (“what”) 2) business needs that the project
strategic plan) methodology addresses (“why”) 3) justification 4)
♦ EEF ♦ PMIS named project manager 5) milestones 6)
♦ OPA (templates, ♦ Expert judgment assumptions 7) constraints (“fixed dates”)
procedures) 8) business case 9) summary budget
4.2 Develop Preliminary ♦ Project charter ♦ Project mgmt ♦ Preliminary project Initiating Scope includes 1) objectives 2) product
Project Scope Statement ♦ SOW methodology scope statement requirements 3) acceptance criteria 4)
which provides a high level ♦ EEF ♦ PMIS project deliverables 5) constraints &
scope description ♦ OPA ♦ Expert judgment assumptions 6) project organization 7)
initial risks 8) milestones 9) initial WBS
10) high level cost estimate 11) project
configuration mgmt requirements 12)
approval requirements
4.3 Develop Project ♦ Preliminary project ♦ Project mgmt ♦ Project management Planning Plan includes 1) processes selected 2) level
Management Plan that scope statement methodology plan of implementation 3) tools to be used 4)
documents what is needed to ♦ Project management ♦ PMIS includes config interactions 5) how to execute work 6)
define, prepare, integrate & processes mgmt system to identify how to control changes 7) how to do
coordinate all subsidiary ♦ EEF changes to product and configuration mgmt 8) baselines use 9)
plans ♦ OPA control changes communication needs 10) project phases
♦ Expert judgment 11) key mgmt issues
4.4 Direct & Manage Project ♦ Project management ♦ Project mgmt ♦ Deliverables Executing Actions include 1) perform activities 2)
Execution by executing the plan methodology ♦ Requested changes spend money 3) train staff 4) manage
work defined in the project ♦ Approved corrective ♦ PMIS ♦ Implemented change vendors 5) implement standards 6) create,
management plan to meet actions requests control & validate deliverables 7) manage
requirements defined in the ♦ Approved preventive ♦ Implemented risk & risk response activities 8) adapt
scope statement actions corrective actions scope changes as needed 9) manage
♦ Approved change ♦ Implemented communications 10) collect project data
requests preventative actions including cost & milestones 11) collect &
♦ Approved defect repair ♦ Implemented defect document lessons learned and process
♦ Validated defect report repair improvement actions
♦ Administrative closure ♦ Work performance
procedure information (status,
budget, % complete)

4
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Integration Management – Processes & activities required to ensure that the various elements of the project are properly coordinated to meet stakeholder expectations.
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
4.5 Monitor & Control ♦ Project management ♦ Project mgmt ♦ Recommended Monitor & Actions include 1) compare actual vs. plan
Project Work through the plan methodology corrective actions Control 2) determine corrective actions needed 3)
processes required to initiate, ♦ Work performance ♦ PMIS ♦ Recommended analyze risks & ensure corrective actions
plan, execute & close a information ♦ Earned Value technique preventative actions taken 4) maintain information base 5)
project to meet performance ♦ Rejected change ♦ Expert judgment ♦ Forecasts status reporting 6) forecasting
objectives defined in the requests ♦ Recommended defect
project management plan repair
♦ Requested changes
4.6 Integrated Change ♦ Project management ♦ Project mgmt ♦ Approved change Monitor & Change control is needed because projects
Control by reviewing all plan methodology requests Control seldom run according to plan. Changes
change requests, approving ♦ Requested changes ♦ PMIS ♦ Rejected change must be managed; also includes
changes & controlling ♦ Work performance ♦ Expert judgment requests documenting changes and only releasing
changes to the deliverables information ♦ Project management approved changes. Defect repair must be
& organizational process ♦ Recommended plan (updates) validated and quality controlled.
documents preventative actions ♦ Project scope
♦ Recommended management (updates) Configuration management also occurs –
corrective actions ♦ Approved corrective identify changes, determine if changes
♦ Recommended defect actions have been implemented, and verify
repair ♦ Approved preventative changes after complete.
♦ Deliverables actions
Every documented change must either be
♦ Approved defect repair
accepted or rejected by some authority.
♦ Validated defect repair
♦ Deliverables
4.7 Close Project by ♦ Project management ♦ Project mgmt ♦ Administrative closure Closing Updates after project completion include
finalizing all activities across plan methodology procedure 1) formal acceptance documentation
all of the project process ♦ Contract documentation ♦ PMIS ♦ Contract closure (written) 2) project files updated 3) project
groups to formally close the ♦ EEF ♦ Expert judgment procedure closure documents prepared (even for
project ♦ OPA ♦ Final product, service projects halted before completion) 4)
♦ Work performance or result historical information is used to update the
information ♦ OPA (updates) “lessons learned” database
♦ Deliverables

5
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Scope Management – Processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully;
focus on what is and what is not included in the project
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
5.1 Scope Planning by ♦ EEF ♦ Expert judgment ♦ Project scope Planning Project scope management plan includes
creating a project scope ♦ OPA ♦ Templates, forms, management plan 1) process to prepare detailed scope based
management plan which ♦ Project charter standards on preliminary scope 2) process to create
includes how the WBS will ♦ Preliminary project WBS from scope 3) process to specify
be created & defined scope statement verification of deliverables 4) process to
♦ Project management control scope changes
plan
5.2 Scope Definition by ♦ OPA ♦ Product analysis ♦ Project scope statement Planning Preparation of a detailed scope statement
developing a detailed ♦ Project charter ♦ Alternatives ♦ Requested changes is critical to the project success. Includes
project scope statement ♦ Preliminary project identification ♦ Project scope 1) objectives 2) scope description 3)
scope statement ♦ Expert judgment management plan requirements 4) boundaries (excluded
♦ Project scope ♦ Stakeholder analysis (updates) items) 5) deliverables 6) acceptance
management plan criteria 7) constraints 8) assumptions 9)
♦ Approved change organization 10) risks 11) milestones 12)
requests funding 13) cost estimate 14)
configuration management requirements
15) project specifications 16) approval
requirements
5.3 Create Work Breakdown ♦ OPA ♦ WBS templates ♦ Project scope statement Planning Decomposition divides work into smaller
Structure (WBS) by ♦ Project scope statement ♦ Decomposition (updates) elements by 1) identify deliverables 2)
subdividing the deliverables ♦ Project scope ♦ WBS structure and organize WBS 3)
& work into smaller, more management plan ♦ WBS dictionary decomposing upper WBS into lower level
manageable components ♦ Approved change ♦ Scope baseline detailed components 4) assign ID codes to
requests ♦ Project scope WBS components 5) verifying that degree
management plan of decomposition is sufficient.
(updates)
♦ Requested changes Each component must be assigned, and
defined in terms of how the project will
actually be executed and controlled.
5.4 Scope Verification ♦ Project scope statement ♦ Inspection ♦ Accepted deliverables Monitor & Scope verification is primarily concerned
through formal acceptance ♦ WBS dictionary ♦ Requested changes Control with acceptance of the scope by
of the completed project ♦ Project scope ♦ Recommended stakeholders
deliverables management plan corrective actions
♦ Deliverables

6
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
5.5 Scope Control by ♦ Project scope statement ♦ Change control system ♦ Project scope statement Monitor & Uncontrolled changes called “scope
controlling changes to the ♦ WBS ♦ Variance analysis (updates) Control creep”. Change is inevitable, thus this
project scope ♦ WBS dictionary ♦ Replanning ♦ WBS (updates) process is needed
♦ Project scope ♦ Configuration ♦ WBS dictionary
management plan management system (updates)
♦ Performance reports ♦ Scope baseline
♦ Approved change (updates)
requests ♦ Requested changes
♦ Work performance ♦ Recommended
information corrective action
♦ OPA (updates)
♦ Project Management
Plan (updates)

7
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Time Management - Processes required to ensure timely completion of the project
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
6.1 Activity Definition by ♦ EEF ♦ Decomposition ♦ Activity list Planning The activity list does not include any
identifying the specific ♦ OPA ♦ Templates ♦ Activity attributes schedule activities that are not required as
activities that must be ♦ Project scope statement ♦ Rolling Wave planning ♦ Milestone list part of the project scope.
performed to produce the ♦ WBS ♦ Expert judgment ♦ Requested changes
various project deliverables ♦ WBS dictionary ♦ Planning component
♦ Project management (control account,
plan planning package)
6.2 Activity Sequencing by ♦ Project scope statement ♦ Precedence ♦ Project schedule Planning PDM (a.k.a Activity on Node) uses 4
identifying and documenting ♦ Activity list diagramming method network diagrams types of dependencies (F-S, F-F, S-S, S-F).
dependencies among ♦ Activity attributes (PDM) ♦ Activity list (updates)
schedule activities ♦ Milestone list ♦ Arrow diagramming ♦ Activity attributes ADM (a.k.a. Activity on Arrow) uses only
♦ Approved change method (ADM) (updates) F-S dependencies. Allows dummy
requests ♦ Schedule network ♦ Requested changes activities to show logical relationships.
templates (Usually shown as a dashed line.)
♦ Dependency
determination 3 types of dependencies - mandatory,
♦ Applying leads and lags discretionary (best practices) and external.
6.3 Activity Resource ♦ EEF ♦ Expert judgment ♦ Activity resource Planning
Estimating through ♦ OPA ♦ Alternatives analysis requirements
estimating the type & ♦ Activity list ♦ Published estimating ♦ Activity attributes
quantity of resources needed ♦ Activity attributes data (updates)
to complete each activity ♦ Resource availability ♦ Project management ♦ Resource breakdown
♦ Project management software structure
plan ♦ Bottom-up estimating ♦ Resource calendars
(updates)
♦ Requested changes
6.4 Activity Duration ♦ EEF ♦ Expert judgment ♦ Activity duration Planning
Estimating by estimating the ♦ OPA ♦ Analogous estimating estimates
number of work periods ♦ Project scope statement (use actual duration of ♦ Activity attributes
which will be needed to ♦ Activity list similar activity from (updates)
complete individual ♦ Activity attributes past)
activities ♦ Activity resource ♦ Parametric estimating
requirements (hours per meter)
♦ Resource calendars ♦ Three-point estimates
♦ Project management (average of most likely,
plan (risk register, optimistic &
activity cost estimates) pessimistic)
♦ Reserve analysis
8
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Time Management - Processes required to ensure timely completion of the project
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
6.5 Schedule Development ♦ OPA ♦ Schedule network ♦ Project schedule Planning Critical Path is the longest path through a
by analyzing activity ♦ Project scope statement analysis ♦ Schedule model data network diagram and shows earliest
sequences, activity ♦ Activity list ♦ Critical path method ♦ Schedule baseline completion of a project.
durations, and resource ♦ Activity attributes ♦ Schedule compression ♦ Resource requirements
requirements to create the ♦ Project schedule ♦ What-if scenario (updates) CPM uses the most likely estimate to
project schedule network diagrams analysis ♦ Activity attributes calculate the float to determine project
♦ Activity resource ♦ Resource leveling (updates) duration and scheduling flexibility.
requirements ♦ Critical chain method ♦ Project calendar
Critical chain modifies schedule to account
♦ Resource calendars ♦ Project management (updates)
for limited resources. Define critical path,
♦ Activity duration software ♦ Requested changes
then apply resources – often path changes.
estimates ♦ Applying calendars ♦ Project management
♦ Project management ♦ Adjusting leads and lags plan (updates,
Schedule can be showed as a network
plan (risk register) ♦ Schedule model including schedule
diagram, bar chart (gantt), or milestone
management plan)
chart.
6.6 Schedule Control – ♦ Schedule management ♦ Progress reporting ♦ Schedule model data Monitor & Key measures include Schedule Variance
controlling changes to the plan ♦ Schedule change control (updates) Control (SV) and Schedule Performance Index
project schedule including ♦ Schedule baseline system ♦ Schedule baseline (SPI).
1) determining current status ♦ Performance reports ♦ Performance (updates)
of project schedule 2) ♦ Approved change measurement ♦ Performance Progress reporting includes actual start and
influencing factors that requests ♦ Project management measurements finished dates, and remaining durations for
cause changes 3) software ♦ Requested changes unfinished activities..
determining that the ♦ Variance analysis ♦ Recommended
schedule has changed 4) ♦ Schedule comparison corrective actions Schedule revisions are a special category
managing changes as they bar charts ♦ OPA of schedule updates – generally
occur incorporated in response to approved
♦ Activity list (updates)
change requests. The original schedule
♦ Activity attributes
baseline and model are saved to prevent
(updates)
loss of data.
♦ Project management
plan (updates)

9
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Cost Management – processes in planning and controlling costs so that the project can be completed within budget
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
7.1 Cost Estimating through ♦ EEF ♦ Analogous estimating ♦ Activity cost estimates Planning Top down / analogous estimating is
approximating the costs of ♦ OPA ♦ Determine resource cost ♦ Activity cost estimate generally less costly and less accurate than
the resources needed to ♦ Project scope statement rates supporting detail other techniques.
complete project activities ♦ WBS ♦ Bottom-up estimating (description, basis of Bottom-up estimating accuracy is driven
♦ WBS dictionary ♦ Parametric estimating estimate, assumptions, by size of work items being estimated.
♦ Project management ♦ Project management constraints, ROM) Reserve analysis includes “known
plan (schedule & software ♦ Requested changes unknowns”.
staffing mgmt plan, risk ♦ Vendor bid analysis ♦ Cost management plan Project in initiation phase as rough order
of Magnitude (ROM) of –50/+100%, later
register) ♦ Reserve analysis (updates)
could go to –10%/+15%
♦ Cost of quality
7.2 Cost Budgeting by ♦ Project scope statement ♦ Cost aggregation ♦ Cost baseline Planning Cost baseline is a time-phased budget to
aggregating estimated costs ♦ WBS ♦ Reserve analysis ♦ Project funding measure and monitor cost performance.
of individual activities or ♦ WBS dictionary ♦ Parametric estimating requirements
work packages to establish a ♦ Activity cost estimates ♦ Funding limit ♦ Cost management plan Reserve are budgeted for unplanned, but
cost baseline ♦ Activity cost estimate reconciliation (updates) potentially required, changes to project
supporting detail ♦ Requested changes scope and cost – not part of the project
♦ Project schedule cost baseline or earned value.
♦ Resource calendars
Project funding requirements are derived
♦ Contract
from the cost baseline.
♦ Cost management plan
7.3 Cost Control by ♦ Cost baseline ♦ Cost change control ♦ Cost estimate (updates) Monitor & ♦ PV - Planned Value (also Budget at
influencing factors that ♦ Project funding system ♦ Cost baseline (updates) Control Completion BAC)
create cost variances & requirements ♦ Performance ♦ Performance ♦ EV - Earned Value
controlling changes to the ♦ Performance reports measurement analysis measurements ♦ AC - Actual Cost
project budget ♦ Approved change ♦ Forecasting ♦ Forecasted completion ♦ ETC – Estimate to Complete
requests ♦ Project management ♦ Requested changes ♦ EAC – Estimate at Completion
♦ Project management reviews ♦ Recommended Formulas to remember:
plan ♦ Project management corrective actions ♦ Schedule Variance = EV-PV
software ♦ Organizational process ♦ Cost Variance = EV-AC
♦ Variance management assets (updates) ♦ Schedule Performance Index = EV/PV
♦ Project management ♦ Cost Performance Index = EV/AC
plan (updates) (<1.0 overrun, 1.0 on budget, > 1.0
underrun)
♦ SPI, CPI used to forecast completion
date and project cost projection

10
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Quality Management – processes to ensure that the project will satisfy the needs for which it was undertaken & implements the quality management system
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
8.1 Quality Planning by ♦ EEF ♦ Cost-benefit analysis ♦ Quality management Planning Quality is “the degree to which a set of
identifying which quality ♦ OPA ♦ Benchmarking plan inherent characteristics fulfill
standards are relevant to the ♦ Project scope statement ♦ Design of experiments ♦ Quality metrics requirements”
project and determining how ♦ Project management ♦ Cost of quality (COQ) ♦ Quality checklists Customer Satisfaction: Conformance to
to satisfy them plan ♦ Additional quality ♦ Process improvement requirements, specifications, and fitness
planning tools plan (steps to analyze for use.
processes to identify
waste & non-value Quality is planned in, not inspected in.
added items Cost of quality is total cost of all efforts
♦ Quality baseline related to quality. Project may not reap
♦ Project management benefits since they are later in product
plan (updates) lifecycle (i.e. lower returns)
8.2 Perform Quality ♦ Quality management ♦ Quality planning tools ♦ Requested changes Executing Deming: Plan, Do, Check, Act
Assurance by employing plan and techniques ♦ Recommended Kaizen (Continuous Improvement): Small
activities to ensure the ♦ Quality metrics ♦ Quality audits corrective actions improvements in products or processes to
project employs all ♦ Process improvement ♦ Process analysis ♦ Process analysis reduce costs and ensure consistency of
processes needed to meet plan ♦ Quality control tools ♦ Quality control tools products or services.
requirements ♦ Work performance and techniques and techniques
information ISO 9000: An international standard that
♦ Approved change describes a recommended quality system.
requests Does not include quality procedures or
♦ Quality control forms.
measurements Heuristic is a rule of thumb (e.g. Rule of
♦ Implemented change Seven)
requests
♦ Implemented corrective
actions
♦ Implemented defect
repair
♦ Implemented
preventative actions

11
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Quality Management – processes to ensure that the project will satisfy the needs for which it was undertaken & implements the quality management system
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
8.3 Perform Quality Control ♦ Quality management ♦ Cause and effect ♦ Quality control Monitor & ♦ +/- 1 sigma = 68.26%
by monitoring specific plan diagram measurements Control ♦ +/- 2 sigma = 95.46%
project results to determine ♦ Quality metrics ♦ Control charts ♦ Validated defect repair ♦ +/- 3 sigma = 99.73%
if they comply with relevant ♦ Quality checklists ♦ Flowcharting ♦ Quality baseline ♦ +/- 6 sigma = 99.99 %
quality standards and ♦ OPA ♦ Histogram (updates)
Variable: Characteristic to be measured
identifying ways to ♦ Work performance ♦ Pareto chart ♦ Recommended
eliminate causes of (e.g. size, shape)
information ♦ Run chart corrective actions
Attribute: The measurement (e.g. inches,
unsatisfactory performance ♦ Approved change ♦ Recommended
♦ Scatter diagram pounds)
requests ♦ Statistical sampling preventative actions
Statistical Independence: The probability
♦ Deliverables ♦ Inspection ♦ Requested changes of 1 event occurring does not affect the
♦ Defect repair review ♦ Recommended defect probability of another event occurring.
repair
♦ OPA
♦ Validated deliverables
♦ Project management
plan (updates)

12
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Human Resource Management – process the organize & manage the project team
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
9.1 Human Resources ♦ EEF (organizational, ♦ Organization charts and ♦ Roles and Planning
Staff management plan includes 1) staff
Planning by identifying, technical, interpersonal, position descriptions responsibilities (role,
acquisition 2) timetable 3) release criteria
documenting project roles, logistical & political) (hierarchical charts, authority,
4) training needs 5) recognition & rewards
responsibilities & reporting ♦ OPA (templates, matrix charts, text responsibility,
6) compliance 7) safety
relationships as well as checklists) formats) – responsibility competencies required)
creating the staffing ♦ Project management assignment matrix ♦ Project organization
management plan plan (activity resource (RAM) charts
requirements) ♦ Networking ♦ Staffing management
♦ Organizational theory plan
9.2 Acquire Project Team ♦ EEF ♦ Pre-assignment ♦ Project staff Executing Conflict Resolution Techniques:
by getting the human ♦ OPA ♦ Negotiation assignments ♦ Problem Solving (Address interests)
resources needed to ♦ Roles and ♦ Acquisition ♦ Resource availability ♦ Compromising (Middle ground)
complete the project responsibilities ♦ Virtual teams ♦ Staffing management ♦ Forcing (Impose judgement)
♦ Project organization plan (updates) ♦ Withdrawal (Avoidance)
charts ♦ Smoothing (Peace keeping)
♦ Staffing management
PMI recommends Problem Solving as best
plan
choice followed by compromising.
Forcing is last.
9.3 Develop Project Team ♦ Project staff ♦ General management ♦ Team performance Executing Maslow’s Hierarchy of Needs (in order):
by improving competencies assignments skills assessment includes 1) ♦ Physiological (Lowest)
& interactions to enhance ♦ Staffing management ♦ Training improvements in skills ♦ Safety
project performance plan ♦ Team-building activities for individuals 2) ♦ Social
♦ Resource availability ♦ Ground rules improvements in ♦ Esteem
♦ Co-location competencies for the ♦ Self-Actualization (Highest)
♦ Recognition and group as a whole 3)
reduce staff turnover MacGregor’s Theory X – People must be
rewards
rate constantly watched. They are incapable,
avoid responsibility, and avoid work.
MacGregor’s Theory Y – People are
willing to work without supervision and
want to achieve.
Ouchi's Theory Z - People work
effectively when secure, consulted and
held collectively responsible.

13
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Human Resource Management – process the organize & manage the project team
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
9.4 Manage Project Team ♦ OPA ♦ Observation and ♦ Requested changes Monitor & Lessons learned documentation can
by tracking member ♦ Project staff conversation ♦ Recommended Control include 1) org charts as templates 2) rules
performance, providing assignments ♦ Project performance corrective actions or techniques that were particularly
feedback, resolving issues ♦ Roles and appraisals ♦ Recommended successful 3) virtual teams, location items
and coordinating changes to responsibilities ♦ Conflict management preventative actions that were successful 4) special skills
enhance project ♦ Project organizational ♦ Issue log ♦ OPA (updates) discovered during the project
performance charts ♦ Project management
♦ Staffing management plan (updates)
plan
♦ Team performance
assessment
♦ Work performance
information
♦ Performance reports

14
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Communications Management – Processes required to ensure timely and appropriate generation, collection, dissemination, storage and ultimate disposition of project
information; provide the critical links among people & information that are needed for successful communications
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
10.1 Communication ♦ EEF ♦ Communications ♦ Communications Planning Communication Methods:
Planning by determining the ♦ OPA requirements analysis management plan ♦ Formal Written – Project Plans/Charters
information and ♦ Project scope statement ♦ Communications (provides 1) ♦ Formal Verbal – Presentations,
communications needs of ♦ Project management technology stakeholder Speeches
the stakeholders plan (constraints, requirements 2) info to ♦ Informal Written – Memos, e-mail
assumptions) be communicated 3) ♦ Informal Verbal – Meetings,
responsibility 4) Conversations
methods & frequency
5) escalation 6) Comm. Channels: N(N-1)/2 where N is
updating ) equal to the number of people.

10.2 Information ♦ Communications ♦ Communications skills ♦ OPA Executing
PM should spend 70 - 90% of their time
Distribution through making management plan ♦ Information gathering ♦ Requested changes communicating.
needed information and retrieval systems
available to project ♦ Information distribution Basic elements of communication:
stakeholders in a timely methods ♦ Sender (or encoder)
manner ♦ Lessons learned process ♦ Message.
♦ Receiver (or decoder)
10.3 Performance Reporting ♦ Work performance ♦ Information presentation ♦ Performance reports Monitor & Performance Reporting Tools:
by collecting and information tools ♦ Forecasts Control ♦ Status Report
disseminating performance ♦ Performance ♦ Performance ♦ Requested changes ♦ Progress Report
information including status measurements information gathering ♦ Recommended ♦ Trend Report
reporting, progress ♦ Forecasted completion and compilation corrective actions ♦ Forecasting Report
measurement & forecasting ♦ Quality control ♦ Status review meetings ♦ OPA ♦ Variance Report
measurements ♦ Time reporting systems ♦ Earned Value**
♦ Project management ♦ Cost reporting systems
plan (performance
measurement baseline)
♦ Approved change
requests
♦ Deliverables

15
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Communications Management – Processes required to ensure timely and appropriate generation, collection, dissemination, storage and ultimate disposition of project
information; provide the critical links among people & information that are needed for successful communications
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
10.4 Manage Stakeholders ♦ Communications ♦ Communications ♦ Resolved issues Monitor &
by managing management plan methods ♦ Approved change Control
communications to satisfy ♦ OPA ♦ Issue logs requests
he requirements of, and ♦ Approved corrective
resolve issues with, project actions
stakeholders ♦ OPA
♦ Project management
plans (updates)

16
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Risk Management – processes concerned with planning, identifying, analyzing and responding to project risk; objective is to increase the probability & impact of
positive events and to decrease the probability and impact of adverse events
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
11.1 Risk Management ♦ EEF ♦ Planning Meetings and ♦ Risk Management Plan Planning Risk management plan includes
Planning by deciding how to ♦ OPA analysis methodology, roles, responsibilities,
approach, plan & execute ♦ Project scope statement budget, timing, scoring / interpretation,
the risk management ♦ Project management thresholds, reporting, tracking, etc.
activities for a project plan Risk Categories:
♦ Technical
♦ Project management
♦ Organizational
♦ External
11.2 Risk Identification by ♦ EEF ♦ Documentation reviews ♦ Risk register (includes Planning Risk Components:
determining which risks ♦ OPA ♦ Information gathering list of risks, potential ♦ Risk event
might affect the project and ♦ Project scope statement techniques responses, root causes, ♦ Risk event probability
documenting their ♦ Risk management plan ♦ Checklist analysis and updated risk ♦ Risk event consequence
characteristics ♦ Project management ♦ Assumptions analysis categories) ♦ Risk event status
plan ♦ Diagramming
techniques
11.3 Qualitative Risk ♦ OPA ♦ Risk probability and ♦ Risk register (updates) Planning Use of low precision data may lead to
Analysis by prioritizing ♦ Project scope statement impact assessment faulty analysis.
risks for further analysis or ♦ Risk management plan ♦ Probability and impact Risks calculated as high or moderate
action by assessing & ♦ Risk register matrix would be prime candidates for further
combining their probability ♦ Risk data quality analysis.
of occurrence & impact assessment
♦ Risk categorization
♦ Risk urgency
assessment
11.4 Quantitative Risk ♦ OPA ♦ Data gathering and ♦ Risk register (updates) Planning Quantitative analysis follows qualitative
Analysis through ♦ Project scope statement representation including 1) analysis.
numerically analyzing the ♦ Risk management plan techniques probabilistic analysis
Objectives include:
effect on overall project ♦ Risk register ♦ Quantitative risk of the project for
objectives of identified risks ♦ Project management ♦ Determine probability of reaching
analysis and modeling schedule & cost
project objectives
plan (schedule techniques (sensitivity outcomes 2) prioritized
list of quantified risks ♦ Determine size of contingency needed
management plan, cost analysis, expected
monetary value analysis, 3) trends in ♦ Identify risks requiring most attention
management plan) based on their priority
and decision tree quantitative risk
analysis, modeling & results) ♦ Identify realistic cost and scope targets
simulation)

17
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Risk Management – processes concerned with planning, identifying, analyzing and responding to project risk; objective is to increase the probability & impact of
positive events and to decrease the probability and impact of adverse events
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
11.5 Risk Response ♦ Risk management plan ♦ Strategies for negative ♦ Risk register (updates) Planning Contingency Plan is a management plan
Planning by developing ♦ Risk register risk or threats (avoid, ♦ Project management that identifies alternative strategies to be
options & actions to transfer or mitigate) plan (updates) used to ensure project success if specified
enhance opportunities & ♦ Strategies for positive ♦ Risk-related risk events occur.
reduce threats to project risks or opportunities contractual agreements Fallback plan is a management plan that
objectives (exploit, share or identifies alternative project approaches if
enhance) the risk has high impact, or if the strategy
♦ Strategy for both risks might not be fully effective.
and opportunities
(acceptance) Contingency Reserve accounts for known
♦ Contingency response risks that have been accepted.
strategy Secondary risks arise from implementing
the contingency plan.
11.6 Risk Monitoring and ♦ Risk management plan ♦ Risk reassessment ♦ Risk register (updates) Monitor & Purpose of Risk Monitoring is to
Control by keeping track of ♦ Risk register ♦ Risk audits ♦ Requested changes Control determine if:
identified risks, monitoring ♦ Approved change ♦ Variance and trend ♦ Recommended ♦ Risk responses implemented as planned
residual risks and requests analysis corrective actions ♦ Risk response actions were as effective
identifying new risks, ♦ Work performance ♦ Technical performance ♦ Recommended as planned
executing risk response information measurement preventative actions ♦ Project assumptions are still valid
plans and evaluating their ♦ Performance reports ♦ Reserve analysis ♦ OPA ♦ Risk trigger has occurred
effectiveness throughout the ♦ Status meetings ♦ Project management ♦ Risk exposure has changed
project life cycle plan (updates)

18
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet

Project Procurement Management – processes required to acquire goods and services from outside the performing team; administering contractual obligations placed on the
project team by the contract
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
12.1 Plan Purchases and ♦ EEF ♦ Make or buy analysis ♦ Procurement Planning Contract Type:
Acquisitions by determining ♦ OPA ♦ Expert judgment management plan ♦ FP – Fixed Price or Lump sum.
what to purchase or acquire ♦ Project scope statement ♦ Contract types ♦ Contract statement of (Simplest form is PO) – risk on seller
and when to do it ♦ WBS work – needs to be ♦ CR – Cost Reimbursable (cost plus fee,
♦ WBS dictionary clear, complete and cost plus fixed fee or cost plus incentive
♦ Project management concise fee) – place risk on buyer
plan (risk register, risk- ♦ Make or buy decisions ♦ T&M – Time and Materials (aspects of
related contractual ♦ Requested changes FP and CR contracts) - Moderate cost
agreements, resource risk to buyer.)
requirements, project
schedule, activity cost
estimates, cost baseline)
12.2 Plan Contracting by ♦ Procurement ♦ Standard forms ♦ Procurement Planning
Procurement management plan can include
documenting products, management plan ♦ Expert judgment documents
1) type of contract 2) independent
services & results ♦ Contract statement of ♦ Evaluation criteria (can estimates 3) standardized procurement
requirements and identifying work include cost, technical documents 4) constraints & assumptions
potential sellers ♦ Make or buy decisions capability, financial 5) lead times for contracting coordination
♦ Project management capacity, business type, 6) make-or-buy documentation 7)
plan (risk register, risk- references, etc…) scheduled dates in contracts 8)
related contractual ♦ Contract statement of performance metrics for managing
agreements, resource work (updates) contracts
requirements, project
schedule, activity cost
estimates, cost baseline)
12.3 Request Seller ♦ OPA ♦ Bidder conferences ♦ Qualified sellers list Executing All bidders conference Q&A should be put
Responses by obtaining ♦ Procurement ♦ Advertising ♦ Procurement document in writing and issued to all potential sellers
information, quotations, bids management plan ♦ Develop qualified package as an addendum to the procurement docs.
offers or proposals ♦ Procurement documents sellers list ♦ Proposals

19
Project Management Institute (PMBOK 2004 3rd Edition) – PMP Preparation Worksheet
Project Procurement Management – processes required to acquire goods and services from outside the performing team; administering contractual obligations placed on the
project team by the contract
Area Process Inputs Tools and Techniques Outputs / Deliverables Process Other Notes
Group
12.4 Select Sellers by ♦ OPA ♦ Weighting system ♦ Selected sellers Executing Objectives of Negotiation:
reviewing offers, choosing ♦ Procurement ♦ Independent estimates ♦ Contract ♦ Obtain a fair and reasonable price
among potential sellers, and management plan ♦ Screening system ♦ Contract management ♦ Develop a good relationship with the
negotiating a written ♦ Evaluation criteria ♦ Contract negotiation plan seller (should be a win-win situation)
contract ♦ Procurement document ♦ Seller rating systems ♦ Resource availability Items to negotiate include:
package ♦ Expert judgment ♦ Procurement Responsibilities, authority, applicable law,
♦ Proposals ♦ Proposal evaluation management plan technical and business mgmt approaches,
♦ Qualified sellers list techniques (updates) contract financing, and price.
♦ Project management ♦ Requested changes
plan (risk register, risk-
related contractual
agreements, resource
requirements, project
schedule, activity cost
estimates, cost baseline)
12.5 Contract ♦ Contract ♦ Contract change control ♦ Contract Monitor & Contracts are often managed by a contract
Administration by managing ♦ Contract management system documentation Control department who have authority and
contract & relationship plan ♦ Buyer-conducted ♦ Requested changes responsibility for contracts. The PM must
between the buyer & seller; ♦ Selected sellers performance review ♦ Recommended work closely with this group to ensure that
documenting performance to ♦ Performance reports ♦ Inspections and audits corrective actions project objectives are met.
establish corrective actions, ♦ Approved change ♦ Performance reporting ♦ OPA
and manage contract change requests ♦ Payment system ♦ Project management
♦ Work performance ♦ Claims administration plan (updates)
information ♦ Records management
system
♦ Information technology
12.6 Contract Closure ♦ Procurement ♦ Procurement audits ♦ Closed contracts Closing Centralized Contracting – A separate
through completing and management plan ♦ Records management ♦ OPA (update contract contracting office handles contracts for all
settling each contract, ♦ Contract management system file, deliverable projects.
including resolution of any plan acceptance, and lessons Decentralized Contracting – A contract
open items ♦ Contract documentation learned documentation) administrator is assigned to each project.
♦ Contract closure
procedure

20

Potrebbero piacerti anche