COMMISSIONING GROUND MOUNTED DISTRIBUTION SUBSTATION AND SWITCHGEAR TEST REPORT

SUBSTATION No: LOCATION: FEEDER: FILE REFERENCE:

Manufacturers Test Report for Transformer*


Manufacturer: Voltage Ratio: Rating (kVA): Vector Group: Serial No: Has manufacturers and final assemblers test report been sighted and approved, including test results for: Insulation Resistance, AC High Voltage Withstand, Oil Dielectric Strength, Ratio, Winding Resistance, Induced Voltage, Impedance. Yes No

Manufacturers Test Report for HV Switchgear*


Manufacturer: Voltage Rating: Switchgear Type: Serial No: Has manufacturers and final assemblers test report been sighted and approved, including test results for: Insulation Resistance, AC High Voltage Withstand, Main Contact Ductor, Earth Switch Ductor, Oil Dielectric Strength, Functional Tests, Type Tests Yes No

Manufacturers Test Report for LV Switchgear*


Manufacturer: Voltage Rating: Switchgear Type: Serial No: Has manufacturers and final assemblers test report been sighted and approved, including test results for: Insulation Resistance, Ductor, Functional Tests, Type Tests Yes No

Earth Resistance

Attach a layout sketch of the Transformer earth mat if not standard and location of additional earthing

Instrument Number: Location HV Earth Ohms Location LV Earth Instrument Number A to B+C+E B to A+C+E C to A+B+E Ohms

Insulation Resistance

Results in Megohms

HV Switchgear All switches / circuit breakers closed (at 5 kV)


Switch 1 open (or fuse removed) Switch 2 open (or fuse removed) Switch 3 open (or fuse removed)

A+B+C (side 1) to A+B+C (other side) A+B+C (side 1) to A+B+C (other side) A+B+C (side 1) to A+B+C (other side) @ 1 min @ 5 min @ 10 min

Transformer

Winding HV to LV+E HV to E LV to E

Voltage 5 kV 5 kV 2.5 kV

LV Switchgear (at 2.5 kV)

All switches / circuit breakers closed Switch 1 open (or fuse removed) Switch 2 open (or fuse removed) Switch 3 open (or fuse removed) Switch 4 open (or fuse removed) Switch 5 open (or fuse removed) Switch 6 open (or fuse removed)

A to B+C+E

B to A+C+E

C to A+B+E

A+B+C (side 1) to A+B+C (other side) A+B+C (side 1) to A+B+C (other side) A+B+C (side 1) to A+B+C (other side) A+B+C (side 1) to A+B+C (other side) A+B+C (side 1) to A+B+C (other side) A+B+C (side 1) to A+B+C (other side)
Page 1 of 2 Form SP0406C01 Ver 3

Check this is the latest version before use.

Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

COMMISSIONING GROUND MOUNTED DISTRIBUTION SUBSTATION AND SWITCHGEAR TEST REPORT


Voltage Measurements
Instrument Number: Location LV Bus (unloaded) LV Bus (loaded) Voltage on Tap Position __________ A-N B-N C-N Tap Ratio Voltage ___________-_______ A-B B-C C-A

Phase Rotation
Phase Rotation: A-B-C C-B-A Instrument Number:

Polarity
Location Tested: Test Method Used: Polarity Correct: ________________________ ________________________ Yes No Instrument Number:

Load Measurements
Instrument Number: Location Transformer Load LV feeder 1 LV feeder 2 LV feeder 3 LV feeder 4 LV feeder 5 LV feeder 6 A phase amps B phase Amps C phase Amps N amps

Check Items
Operational Nameplates in place Safety signs in place Yes Yes No No No No No No No No No No No NA NA Interlocks to stop paralleling feeders No Yes functional Physical inspection of equipment complete Yes No transport bracing removed, connections tight, buswork and cabling installed correctly Functional test of operation including Yes No interlocks okay HV and LV fuses correct size and installed Yes No correctly Fuse size marked on switchgear No Yes Spare fuses on site No Yes Locks in place and operational No Yes Phasing Out facility on Switchgear No Yes Fault Indicator Installed on Switchgear No Yes If Yes to the above Fault Indicator is connected to circuit

Access to switchgear clear of Yes obstructions Emergency exit marked and unobstructed Yes Surge diverters correct voltage rating HV earth connections checked LV earth connections checked CMEN bonding in place Neutral to Main Earth link in place HV cable test SP0407C01 completed LV cable test SP0405C01 completed Yes Yes Yes Yes Yes Yes Yes

NA

Remarks and Non-Conformances


* Manufacturers test certificates not required to be sighted for individual units where equipment has been purchased and accepted as part of an approved Ergon Energy period contract.
COMMISSIONING OFFICER: DATE: SUPERVISOR: