Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
SAIC-A-2026
WBS / BI / JO NUMBER
1-Dec-06
MECH-
CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) LAYOUT DRAWING NUMBER SCHEDULED INSPECTION DATE & TIME SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO INSPECTION LEVEL
EQPT CODE
SYSTEM ID.
PLANT NO.
ACTUAL INSPECTION DATE & TIME SAUDI ARAMCO ACTIVITY NUMBER CONTRACTOR INSPECTION LEVEL
ITEM No. A
ACCEPTANCE CRITERIA QC Documentation, Test Package & Tank Weld Map Verification: Test Diagram is submitted showing the following: A) Limits of equipment to be tested incl. test manifold & equipment included in the test. B) Test pressure of the system C) Relief valve setting D) Safety Instruction Sheet Procedure has been approved & meets the detailed requirements of SAIC-A-2001 (Review Procedure - Pressure Testing)
REFERENCE
PASS
FAIL
N/A
RE-INSP DATE
A1
A2
A3
Verify drawing conformance of tank construction. Check all nozzles, supports, attachments (orientation & dimemsion) Systematically complete, verify & accept all drawings incl. details
Contract drawings
A4
Verify complete code construction incl. support attachments. Repairs, Weld Pick-up (ID/OD), (welding) is 100% accepted.
A5
Weld Summary Record (SAEP-1160 Welding Database) was verified to indicate completion/acceptance of all weld joints, repairs, modifications & any applicable weld inspection reqmts (visual, NDE). All required inspection & testing (RT, MT, PT, PWHT, PMI) has been completed & inspection control sheet has been signed by SA. As applicable, an SAEP-1160 Welding Database is reviewed SEE SAIC-W-2087, SAIC-W-2088 are completed & accepted Post Weld Heat Treatment (PWHT) & Production Weld Hardness Testing is complete & accepted. SAIC-W-2089 & SAIC-W-2014.
A6
A7
SAEP-1160, Section 6
A8
32-SAMSS-005 is checklist for API Atmospheric Tanks. 32-SAMSS-006 is checklist for API Low Pressure Tanks. Testing has been completed in accordance with SA Inspection Requirements Form 175-324900 & following additional requirements of 32-SAMSS-005, Section 5 (Utilize SAMSS as a checklist here). Testing has been completed in accordance with SA Inspection Requirements Form 175-324901 & following additional requirements of 32-SAMSS-006, Section 7 (Utilize SAMSS as a checklist here). The tank shall be completely drained and thoroughly dried immediately after completion of the hydrostatic test. The Tank Manufacturer has a plan for disposal of hydrotest water that has been evaluated against SAEP-327 by the engineering contractor.
As Referenced
A9
A10
A11
Page 1 of 5
SAIC-A-2026
WBS / BI / JO NUMBER
1-Dec-06
MECH-
CONTRACTOR / SUBCONTRACTOR
ACCEPTANCE CRITERIA Ensure all 32-SAMSS-006 Test Preliminaries of Section 7.18.2 have been completed. USE SAMSS AS A CHECKLIST. Safety Instruction Sheet (SIS) for vessesl/equipment is complete & approved. Verify correct test pressure for system/equipment.
PASS
FAIL
N/A
RE-INSP DATE
A13 B
Field Verification/Pre-Test Inspection of API Tanks (32-SAMSS-005 & 32-SAMSS-006) Vents are provided at all high points in the position in which it is to be tested to purge all possible air during water filling.
B1
SAES-A-004
B2
Prior to final inspection & pressure testing, the inside & outside of tank shall be thoroughly cleaned of all slag, scale, dirt, grit, weld spatter, paint, oil, etc. (If internally coated special weld prep req'd)
B3
Strength of existing foundation/supports shall be confirmed to be adequate for additional weight of hydrotest fluid. STEP 1.
B4
Tank Settlement Measurements or Elev. Survey (STEP 2) Base elevation shall be established & recorded at several equidistant locations around the tank circumference in multiples of four, but not to exceed 10 m (32.8 foot) between each reference point and no less than eight (8) locations. Measurement points shall be at well marked locations on the bottom projection outside tanks or on clips welded to shell. Elevation readings are taken: 1) Before hydrostatic testing has started. 2) At filled point. PLAN RESPONSIBILITY & NOTIFICATION 3) At filled point. PLAN RESPONSIBILITY & NOTIFICATION 4) After 24* hours from filling tank at maximum fill height. *HOLD TIME. PLAN RESPONSIBILITY & NOTIFICATION 5) After tank has been emptied of test water. FINAL SURVEY PREPARE DOCUMENTATION & PLAN FOR THESE EVENTS . SURVEY RESULTS ARE FORWARDED TO SA FOR REVIEW. RESULTS ARE A PERMANENT PART OF TANK RECORDS. HOLD POINT FOR SA! USE ESTABLISHED BENCHMARKS!
32-SAMSS-005, Para. 5.6.1 & 32-SAMSS-006, Para. 7.18.11.1 Applies to Both SAMSS
B5
SURVEY STEPS & DIRECTION FOR FILLING (CRITICAL): Any differential settlement greater than 1.5 mm (60 mils) per meter of circumference, or a uniform settlement in excess of 50 mm (2"), shall be reviewed by the Saudi Aramco Engineer. Filling shall be stopped until clearance to continue has been received from the Saudi Aramco Engineer. INSPECTOR VERIFIES AND ENFORCES. SURVEY STEPS BEFORE & AFTER TESTING (CRITICAL): For tanks 15.24 m (50 foot) diameter and larger, internal bottom elevation measurements shall be made before & after hydrostatic test. These measurements shall be made at 3 meter intervals along diametric lines across the bottom. Diametric lines shall be spaced approximately 10 meters (32.8 foot) apart at the tank shell. Tanks tested by filling with Quality water per SAES-A-007 to: A) The maximum design liquid level, H specified in API STD 650. B) For a fixed roof tank, to 50 mm (2 in.) above the weld connecting the roof plate or compression bar to the top angle or shell; or C) To a level lower than that specified in items (a) or (b) when
32-SAMSS-005, Para. 5.6.2 & 32-SAMSS-006, Para. 7.18.11.2 Applies to Both SAMSS 32-SAMSS-005, Para. 5.6.3 & 32-SAMSS-006, Para. 7.18.11.3 Applies to Both SAMSS 32-SAMSS-005, Para. 5.3.5.1 API 650 Tanks ONLY
B6
B7
Page 2 of 5
SAIC-A-2026
WBS / BI / JO NUMBER
1-Dec-06
MECH-
CONTRACTOR / SUBCONTRACTOR
ITEM No.
ACCEPTANCE CRITERIA Rate of Water Filling and Water Temperature (Per API 620): (Exception) Water filling rate for non-refrigerated cylindrical tanks shall not exceed those shown in the following Table.
REFERENCE
PASS
FAIL
N/A
RE-INSP DATE
B8
REMARKS: REFERENCE DOCUMENTS: 1. SAES-A-004, General Requirements for Pressure Testing, (30 March, 2005) 2. SAES-A-005, Safety Instruction Sheet, (28 February 2005) 3. SAES-D-100, Design Criteria of Atmospheric & Low Pressure Tanks, (31 December, 2003) 5 SAES-W-017, Welding Requirements for API Tanks, (7 December 2005) 6. 32-SAMSS-005, Manufacture of Atmospheric Tanks, (31 December 2003) 7. 32-SAMSS-006, Manufacture of Low Pressure Tanks, (31 December 2003)
Contractor / Third-Party
Construction Representative*
Work is Complete and Ready for Inspection: Name, Initials and Date: Name, Initials and Date:
Saudi Aramco
PMT Representative
T&I Witnessed QC Record Reviewed Work Verified
QC Inspector
Performed Inspection Name, Initials and Date: Work / Rework May Proceed
PID Representative
T&I Witnessed Name, Initials and Date: QC Record Reviewed Work Verified
QC Supervisor
Quality Record Approved: Name, Sign and Date: *Person Responsible for Completion of Quality Work / Test
Y = YES
N = NO F = FAILED
Page 3 of 5
SAIC-A-2026
WBS / BI / JO NUMBER
1-Dec-06
MECH-
CONTRACTOR / SUBCONTRACTOR
ITEM No.
ACCEPTANCE CRITERIA Tank Settlement Measurements or Elev. Survey (STEP 2) Base elevation shall be established & recorded at several equidistant locations around the tank circumference in multiples of four, but not to exceed 10 m (32.8 foot) between each reference point and no less than eight (8) locations. Measurement points shall be at well marked locations on the bottom projection outside tanks or on clips welded to shell. Elevation readings are taken: 1) Before hydrostatic testing has started. 2) At filled point. PLAN RESPONSIBILITY & NOTIFICATION 3) At filled point. PLAN RESPONSIBILITY & NOTIFICATION 4) After 24* hours from filling tank at maximum fill height. *HOLD TIME. PLAN RESPONSIBILITY & NOTIFICATION 5) After tank has been emptied of test water. FINAL SURVEY PREPARE DOCUMENTATION & PLAN FOR THESE EVENTS . SURVEY RESULTS ARE FORWARDED TO SA FOR REVIEW. RESULTS ARE A PERMANENT PART OF TANK RECORDS. HOLD POINT FOR SA! USE ESTABLISHED BENCHMARKS! SURVEY STEPS & DIRECTION FOR FILLING (CRITICAL): Any differential settlement greater than 1.5 mm (60 mils) per meter of circumference, or a uniform settlement in excess of 50 mm (2"), shall be reviewed by the Saudi Aramco Engineer. Filling shall be stopped until clearance to continue has been received from the Saudi Aramco Engineer. INSPECTOR VERIFIES AND ENFORCES. SURVEY STEPS BEFORE & AFTER TESTING (CRITICAL): For tanks 15.24 m (50 foot) diameter and larger, internal bottom elevation measurements shall be made before & after hydrostatic test. These measurements shall be made at 3 meter intervals along diametric lines across the bottom. Diametric lines shall be spaced approximately 10 meters (32.8 foot) apart at the tank shell. Tanks tested by filling with Quality water per SAES-A-007 to: A) The maximum design liquid level, H specified in API STD 650. B) For a fixed roof tank, to 50 mm (2 in.) above the weld connecting the roof plate or compression bar to the top angle or shell; or C) To a level lower than that specified in items (a) or (b) when restricted by overflow, an internal floating roof, or other freeboard. EXACT FILL HEIGHT SHALL BE DETERMINED & MEASURED BY INSPECTOR PRIOR TO FILLING & CHECKED AGAINST DOCS. Rate of Water Filling and Water Temperature (Per API 620): (Exception) Water filling rate for non-refrigerated cylindrical tanks shall not exceed those shown in the following Table.
REFERENCE
PASS
FAIL
N/A
RE-INSP DATE
B4
32-SAMSS-005, Para. 5.6.1 & 32-SAMSS-006, Para. 7.18.11.1 Applies to Both SAMSS
B5
B6
32-SAMSS-005, Para. 5.6.2 & 32-SAMSS-006, Para. 7.18.11.2 Applies to Both SAMSS 32-SAMSS-005, Para. 5.6.3 & 32-SAMSS-006, Para. 7.18.11.3 Applies to Both SAMSS
B7
B8
REMARKS: REFERENCE DOCUMENTS: 1. SAES-A-004, General Requirements for Pressure Testing, (30 March, 2005) 2. SAES-A-005, Safety Instruction Sheet, (28 February 2005) 3. SAES-D-100, Design Criteria of Atmospheric & Low Pressure Tanks, (31 December, 2003) 5 SAES-W-017, Welding Requirements for API Tanks, (7 December 2005) 6. 32-SAMSS-005, Manufacture of Atmospheric Tanks, (31 December 2003) 7. 32-SAMSS-006, Manufacture of Low Pressure Tanks, (31 December 2003)
Page 4 of 5
SAIC-A-2026
WBS / BI / JO NUMBER
1-Dec-06
MECH-
CONTRACTOR / SUBCONTRACTOR
ITEM No.
ACCEPTANCE CRITERIA
REFERENCE
PASS
FAIL
N/A
RE-INSP DATE
Contractor / Third-Party
Construction Representative*
Work is Complete and Ready for Inspection: Name, Initials and Date: Name, Initials and Date:
Saudi Aramco
PMT Representative
T&I Witnessed QC Record Reviewed Work Verified
QC Inspector
Performed Inspection Name, Initials and Date: Work / Rework May Proceed
PID Representative
T&I Witnessed Name, Initials and Date: QC Record Reviewed Work Verified
QC Supervisor
Quality Record Approved: Name, Sign and Date: *Person Responsible for Completion of Quality Work / Test
Y = YES
N = NO F = FAILED
Page 5 of 5