Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Product Presentation
Intellix BMT 300
TM
Bushing failure
Bushings have been identified as the cause of about 15% of all transformer failures
According to Doble, the leading cause of >100MVA transformer failure is bushing failure (35%) A Western Power survey of 2096 transformer failures in ANZ found that bushing were only second to OLTC as the initially source of failure. Over 50% of failures are catastrophic, leading to: Total loss of the transformer Environmental issues due to oil release Likely property damage Possible human casualties
BMT 300 - Product presentation v9 - April 2013 - slide 2
It will alert personnel of developing fault conditions at an early stage and provide vital additional health information on the bushings and the transformer.
How it works
The BMT 300 connects to the 3x HV bushing tapping points using custom made adaptors. Option for both HV and LV bushings (6 bushings). Using the same adaptor, it measures leakage current , low/power frequency signals (used for BM) and high frequency signals (used for PD).
Additional sensors are used: - Ultra precise GPS timing signal - Ambient temperature & humidity - Top oil temperature - CT on neutral
Uses the same PERCEPTION software (as used by TRANSFIX products) to visualize and analyze the results for: Bushing status (% change in C1, % change in PF) Presence of Partial Discharge activity
We, like all other on-line systems, work on the assumption that: The 3 bushings are part of a 3 phase system The load on all 3 bushings is fairly similar Phase difference between phases assumed to be ~120o and consistent The 3 bushings are very similar Not two bushings will fail simultaneously
We are therefore looking for the bushing which characteristics are changing significantly compared to the initial install value and more than the other two.
Bushing - Capacitance C1
First we calculate what the reference leakage current should be for the baseline C1 value measured when the bushing was installed. We then continuously measure the leakage current of each bushing from the test tap and calculate the % change in current which is the same as the change in capacitance C1. We then plot the percentage change in C1 value. This is indicative of a loss in dielectric efficiency: Nameplate C1 +/-5% - bushing acceptable Nameplate C1 +/-5% to +/-10% - monitor bushing Nameplate C1 +/-10% or greater - replace bushing To make it easier to see the largest change of the 3 and to eliminate load and temperature that affect all 3 bushing, we use a polar plot where we plot the sum of the three vectors, each vector with magnitude equal to the percentage change.
The affected bushing appears clearly, bushing B in this case, with the change in current/capacitance
Up to 150% of nameplate PF - bushing acceptable From 150% to 200% of nameplate PF - monitor bushing Above 200% increase in nameplate PF - replace bushing
BMT 300 - Product presentation v9 - April 2013 - slide 9
Partial Discharge - PD
The high frequency signals associated with Partial Discharge activity in the transformer are detected from the HV bushing adapter. They are then discriminated against to try and ensure that the PD detected is internal to the transformer and not external (corona discharge). A final discrimination check can be done manually by comparing PD activity changes with the humidity correlation factor. The system records: the number of PD events (PD count) - in units the average amplitude of the PD pulses (PD value) in pC
Utility value It then calculates the Partial Discharge Index (PDI) in mW to represent the average apparent PD power over a pre-defined period.
BMT 300 - Product presentation v9 - April 2013 - slide 10
Outside influence - PD
PD being very rapid to develop means that a shutdown is required quickly after it is detected. Unfortunately, PD can also be generated externally to the transformer through Corona discharge in the environment. This occurs during electrical storms in high humidity environments, especially with rain and wind. To make sure that we dont raise false alarm, we will use 3 discrimination methods: 1. Polar plots. Corona will affect all bushing to the same extent and any PD appearing on all 3 bushings equally will be negated. 2. Correlation with humidity. Comparing increases in PD linked to increases in the Humidity correlation factor to detect corona. 3. Pulse Polarity Detection. Comparing the direction of the signals received from the bushing adapters with that of the neutral CT. Same polarity: external, Opposite polarity: internal.
BMT 300 - Product presentation v9 - April 2013 - slide 12
Polar plots
In a polar plot, the measured value for each of the three bushings/phases are shown as vectors at angles 0o (phase A), 120o (phase B), 240o (phase C) . The magnitudes at a particular time are the percentage difference of the measured value compared to the reference value. By plotting the vector sum of the three differences on the polar plot, any common cause affecting all 3 bushings will be eliminated and the difference in the affected bushing will appear much more clearly. Evolution over time is also shown by the darkening of the blue vector colour.
Here clearly there is difference of up to 0.4% compared to nominal for bushing B compared to the others.
Alarms
Alarms Alarms can be set for two different warning levels: caution (Hi) and danger (Hi-Hi). Alarms can be set on: Capacitance % change Power Factor % change PD Counts PD value Partial Discharge Index value PDI rate of change Separate service alarm
RG58C/U coaxial cable is used (Belden part no: 8262) to connect from each adapter (x3) and from neutral CT to the BMT cabinet. Cable is run in sealed conduit. Cable can be purchased in rolls of 150m (500ft).
BMT 300 - Product presentation v9 - April 2013 - slide 15
Resistor
Resistor
GDT
GDT
User Interface
HMI Sunlight visible colour LED indicators for power and the status of the 3 alarm relays
Software Results can be downloaded and visualized using GEs Perception software
Outputs
Digital Modbus RTU/ASCII protocol over isolated RS-485 Comms Option 1: Fiber Optic Modbus RTU over serial multimode Fiber Optic (ST connector) instead of standard output Comms Option 2: Multi-master option Modbus TCP over Ethernet (RJ-45 connector) or Modbus TCP over multimode 10Mbps Fiber Optic (ST) Relays 3 dry contact relays Used for warning (Hi), alarm (hi-Hi) and service
Perception
RS485
DGA data and trending Bushing data, trending and polar plots
.
Note: If need to connect to more than one Master: Perception and something else (like a SCADA system), you must use the Multi-Master option (see next slide).
Modbus TCP
Modbus TCP
LAN
Modbus TCP
MULTINET FE
Ethernet 10 Mbps
RS-485
Modbus RTU
RJ45 Modbus TCP FIBRE OPTIC RJ45 Modbus TCP Modbus TCP
LAN
ETHERNET FIBRE OPTIC
Note: only one 10Mbps Ethernet connection at a time to the LAN: Fibre Optic or RJ45
Applications
Customers:
T&D utilities Industrials Transformer manufacturers And not just for transformers
but for any asset with oil filled bushing that are part of a 3 phase system e.g. CTs, switches,
BMT 300 - Product presentation v9 - April 2013 - slide 22
Questions ?