Sei sulla pagina 1di 18

Network Construction - Design Pack

Cover and Contents Sheet

6164128B0002

Issue: 1 Page 1 of 1

DESCRIPTION AND CONTACTS


Title: Location: Remarks: Timing: Designer: TM: PDM: PS: Verifier: Authoriser: Origin:

10018832_78_VIC CSF EPGZ D&C Full Epping Post var


Iqbal, Saadat Baulch, Ian W Rawson, Terry I Walton, Dale Aylmer, Brett T Iqbal, Saadat
TM - Team Manager Ph: Ph: Ph: Ph:

0419 139 081 03 8649 4037


03 6212 8093 03 8633 1578

Fax: Fax: Fax: Fax: Date: Date: 03 6231 3157 03 8633 2353

Signature: Original is signed Signature: Original is signed

NECD31 - VIC Transmission & Switching


PDM - Project Delivery Manager PS - Project Specialist

DISTRIBUTION
[ E ] Email Copy [ P ] Paper copy [ Q ] QM [ T ] TCSS

ASSOCIATED PACKS
PACK NO. ACTIVITY DESCRIPTION

6164128B0001 6164128B0002

10018832_78_VIC CSF EPGZ D&C Full 10018832_78_VIC CSF EPGZ D&C Full

ATTACHMENTS
A B C D E Overview Project Notes Cable Runway Integral Material List Equipment Layout

Issue
1 1 1 1 1

Network Construction - Design Pack


Overview

6164128B0002
Attachment A

Issue: 1 Page 1 of 2

1 1.1

Overview Purpose & Scope


The purpose of this project is to provide CFC SMR Superstructure on the Ground Floor Epping Exchange in accordance with TM00100A02-Exchange Common Infrastructure, CN1234 Superstructure: Cable Only Variant. As per all Cable Only Variant Superstructure, Optical Fibre Ducting is not required for this deployment

Site Name
EPPING

Site Address
BLD 1- 44 COULSTOCK ST EPPING VIC, 3076

FLOOR
Ground

Equip Code
EPGZ

All work to be performed as outlined under the NC H&S Action Plan.

1.2

Integral Details
Network Activity Nos 6164128.0101 6164128.0222 Work Breakdown Structure (WBS) N.10087.03.0004.078.01 N.10087.03.0004.078.22 Description PM Install & Commission

1.3

Timing
The Customer Required By Date is: Refer to PS Schedule.

1.4

Interdependencies
Not Applicable

1.5

Related Documents
Document Not Applicable Interdependencies / Relationships NIL

1.6

Project Quality Plan


For a copy of the quality plan for this project please contact the Project Specialist.

1.7

MOP and Acceptance Procedure


Where necessary, the installer is to supply MOPs and WINs to detail the work covered by this project.

1.8

Hazard Management, Worksite Safety Inspections


The project site was visited. Detected hazards at the site visit are listed in the table below. Project supervisors are required to also assess the site and implement Network Constructions Safety Plan as per CSD22001 (Health and Safety Management in Network Construction). For projects with less than five staff on site, the Take Five Process as described in the Work Pack may be used. In this case risks may be assessed using the quick risk level guide at :http://www.in.telstra.com.au/ism/hse/manageyourrisks.asp .

Network Construction - Design Pack


Overview

6164128B0002
Attachment A

Issue: 1 Page 2 of 2

For projects with five or more staff on site, the construction staff are expected to complete a JSA. The JSA form is supplied by the Project Officer from within the PSHSP (Project Specific Heath & Safety Plan).

Hazard Element None Identified

Possible Hazard Possible Hazards are to be identified during the Pre-Construction Take 5 or JSA process. This should include identifying work areas that may contain asbestos.

1.9

Environmental Clearance
The risks associated with the activity have been deemed negligible by the National EMS Co-ordinator. A national exemption from completing an environmental risk assessment has been applied. A copy of the current Transport & Wireless exemption form is included in the Work Pack.

1.10 Network Hazard Classification


The activities as described in this design are such that the project is classified as Type C Network Hazard. Installer to submit necessary hazard advices.

1.11 Powers and Immunities


Item Powers and Immunities Options Project contains BELOW THE LINE facilities and activities only.

1.12 Health, Safety and Environment Issues


Before commencing work at this site please refer to the on-site Hazards Log to determine whether asbestos is present or not. If any asbestos is found to be present it is to be dealt with in accordance with CSD22110. Beware of any non-registered / concealed hazards. If any property maintenance work is found to be required at the site please notify Sentinar on 1800 622 203 so that they can arrange for the rectification of the site problems found. If site cleaning or grounds maintenance work is found to be required please contact Service Delivery using the Webform found at NonUrgent Service Request - Network Sites or Email ! CD&G Cleaning & Grounds .

1.13 Environmental Management Plan


The basic elements of Environmental Management are set out in the Environmental Handbook document at this link. Environmental Handbook . These should be adhered to when carrying out the work specified in the work package.

1.14 Buildings Requests

Epping Floor Epping Structural Epping Floor Epping Wall Gnd Floor Epping Covering Request.docx Engineer Request.docx Penetration Request.docx Penetration Request.docx Exchange Electrical Bldg Req.docx

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 1 of 11

1 1.1

Project Details Site Details:


Epping BLD 1-44 Coulstock St Epping VIC, 3076 EPGZ VX1055/11

Site Name: Site Address Site ID Drawings

1.2

Scope of Work
The wall between the Maintenance Control and Power & Battery Room will be removed as part of the BES Scope of Work. This is to be completed before Construction begins. The timing of this is to be assessed by the Project Specialist. A Buildings Request has been submitted for new Exchange Flooring to facilitate the NBN area. This work may be actioned by BES Pre-Construction; in this case the Buildings request will not be needed. This is to be assessed by the Project Specialist. A Buildings Request has been submitted for the Pre-Construction removal of existing False Ceiling Mounted Fluoro Lights. A Licensed Electrician is required for this work. This work may be actioned by BES Pre-Construction; in this case the Buildings request will not be needed. This is to be assessed by the Project Specialist. A Buildings Request has been submitted for the removal of a wall mounted GPO on the Northern Wall of the Power & Battery Room. A Licensed Electrician is required for this work. A Buildings Request has been submitted for the relocation of a wall mounted GPO on the Western Wall of the MDF Room where a new Wall mounted Cable Riser will be required. A Licensed Electrician is required for this work. Remove the existing 150mm Wall Mounted Tray on the Northern Wall of the Power & Battery Room that was utilized for the 240V GPO Conduit. Remove the existing Alarm Indicator Panel from the North West corner of the Power & Battery Room. This may be actioned as part of the BES work. Remove the existing section of 2800mm high Wall Bar on the Northern Wall of the Maintenance Control Room. Reduce in length (cut back) the existing Wall Mounted Cantilever Brackets on the Southern Wall of the Power & Battery Room. Establish MID CLEARANCE superstructure & trays for H2 and OMF area for any compliant New Network Equipment. Ensure that the area is compliant with the H2 - suites with 1520mm centre spacing for Mid Clearance, refer to deployment standard 005747-B135 for details. Also ensure that this superstructure is isolated from any existing superstructure. 600mm H - frames shall be used for H2 area. Location of the area: H2 and OMF area shall be located at GD/92 to GD/95. Start building area from rack position 16 Backwards. Augment the existing 150mm Wall Mounted Earth Cable Tray in the South West corner of the MDF Room to provide adequate clearance for the proposed 450mm Cable Riser access to runway. A Buildings Request has been submitted for a Floor Penetration in the South West corner of the MDF Room.

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 2 of 11

A Buildings Request has been submitted for a Wall Penetration in the South East corner of the MDF Room above the existing penetration for the 150mm Earth Cable Tray. Establish a 450mm Wall Mounted Cable Riser in the South West corner of the MDF Room above the new Floor Penetration. Establish a new Wall Mounted 450mm Cable runway on the Southern Wall of the MDF Room that also incorporates the existing 150mm Earth Cable Tray. A Buildings Request has been submitted for an Engineers Report for this activity. Establish a new Ceiling Suspended section of 450mm Cable runway between the wall penetration and the new NBN deployment. A Buildings request has been submitted for an Engineers Report for th is activity. Refer to CADLINK drawing VX1055/11 for floor plan. Ensure all labelling and DBoR entry is completed as part of this project. In CADLINK ensure the superstructure build is identifiable over the rack positions, i.e. I need to be able to see what installed & reserved rack position's have superstructure installed above.

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 3 of 11

2 2.1

Project Notes Installation of CN1234 Superstructure.


Notes:

Drawings in this design pack are not to scale and are to be used as a guide only. The installer is to double check all appropriate measurements within the CFC area prior to starting the installation. If any discrepancies exist, please advise the designer. Refer to Documents & Cadlink Drawings below and Drawings in the Equipment Layout of this Design Pack. Some information in the documents & drawings below have been superseded by document:- Technical Specification TM00100A02 - Exchange Common Infrastructure CN1234 Superstructure: Cable Only Variant. Installation to be in accordance with the following Documents: : Except where approved exemptions apply. o Technical Specification TM00100 & amendments Exchange Common Infrastructure CN1234 Superstructure. o Technical Specification TM00100A01 Exchange Common Infrastructure CN1234 Low Clearance Superstructure. Where Applicable o Technical Specification TM00100A02 Exchange Common Infrastructure CN1234 Superstructure: Cable Only Variant o Technical Specification TM00100A03 Exchange Common Infrastructure CN1234 Mid Clearance Superstructure: Where Applicable o Deployment Standard 005747-335551 Network equipment area Common Infrastructure o New Document 005747-B135 - NBN Co in Telstra Buildings Floor Layout and Common Infrastructure o Technical Specification TM00330A03 Next Generation Common Facilities Alarm Alarm Peripherals & Sensors (For Temperature Sensor Installation). o Document TM00181 Exchange Common Infrastructure Cable Runways. o Design Guidelines For FSAM 576F Cable Runway- ALT-6415 o Deployment Standard 005747- 405602 Telepower & Building Alarms NGCF-AMS Sites o Document 007338 C13-11 - Next generation Common Facilities Alarm Management System (NGCF-AMS) o CN1234-xxx Drawings. Refer to attached list

Drawing List CN1234-COM_1-1 v8.xlsx

2.2

Project Details: Work Required:


Refer to the attached drawings & Cadlink Drawing VX1055/11

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 4 of 11

(i)

Existing 150mm Wall Mounted Tray

Existing 240V GPO and conduit to be removed as per Buildings Request.

Remove the existing 150mm Wall Mounted Tray and mounting Brackets on the Northern Wall of the Power & Battery Room that is utilized for the 240V Conduit.

(ii)

Alarm Indicator Panel

Remove the Alarm Indicator Panel. This may be done by BES during the Building Works.

(iii)

Remove Existing Wall Bar

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 5 of 11

Remove the existing Wall Bar on the Northern Wall of the Maintenance Control Room. (iv) Wall Mounted Cantilever Brackets

Cut back existing Wall Mounted Cantilever Brackets.

(v)

Superstructure - CN1234-MC-11 Install Suite infrastructure in rack positions 11-16 for H2 and 5-16 for ODF. Refer to H2 and ODF superstructure and attached floor plans drawings for additional detail.

Network Construction - Design Pack


Project Notes (vi) (vii) (viii) (ix)

6164128B0002
Attachment B

Issue: 1 Page 6 of 11

Install wall bar at end of suite GD/92-93 and GD/94-95 to support top bars and on both side walls. Install 6 x 600mm (H2 and OMF) and 5 x OMF I-Frames in suite positions 5-16. Install Top Bars between H frames, in each suite GD/92-93 and GD/94-95. Install top bars from the end of rack 16 to the wall bar. Install tie bars from each suite to the wall bars. Ladder - Not Required for CN1234-MC-11 Planar Shelf - Not Required for CN1234-MC-11 Safety Rail- Not Required for CN1234-MC-11 Intra Suite trays & supports H2 Suite GD/92-93 Refer to Drawings:CN1234-MC-11_2-1-2 CN1234-MC-11_2-2-2 CN1234-MC-11_16-1 CN1234-COM_38-1 CN1234-COM_38-2 Plan & elevation View 1520 Suites Overhead Cable Support Isometric View Kit Intra suite Tray & Supports Tray Fibre Cable Drop RHS Tray Fibre Cable Drop LHS

(x)

Install Intra suite tray supports. Install 150mm ST3 tray, for Optical Fibre Sheathed Cable, onto frame support from the inter suite tray. Install a new RHS S/I 353/01587 or LHS S/I 353/01588 (as required) dropper from the new section of O/F tray. Install 2 x 150mm ST3 tray, for DC Power Cable, onto Tie Bar from the inter suite tray. Install 2 x 150mm ST3 tray, for Signal Cable, onto Tie Bar from the inter suite tray. Intra Suite trays & supports OFF/OMF Suite GD/94-95 Refer to TM00100/A02/A03 & drawings for additional details. Refer to Drawings:CN1234-MC-11_2-1-1 CN1234-MC-11_16-1 CN1234-COM_38-1 CN1234-COM_38-2 Plan & Elevation view Kit Intra Suite Tray & Supports Tray Fibre Cable Drop RHS Tray Fibre Cable Drop LHS

Install OMF Intra suite Tray Kits S/I 353/01821 above suites GD/94-95 Positions 5-16. Refer to floor layout and TM00100A03 for additional details. Secure Trays with hold down brackets S/I 353/02407, M8 Hex Head Set Screws S/I 353/02211, M8 Channel Nuts S/I 353/02146 and M8 Flat Washers S/I 353/02271. Install both Uni-Directional Trays. Install a new LHS O/F dropper S/I 353/01588 from the intra suites section of O/F tray. Install a new LHS S/I 353/01588 (as required) from the inter suite section of O/F tray adjacent to suite GD/94-95 refer to CN1234-MC-11 2-1-1.

(xi)

Inter suite trays & supports

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 7 of 11

Refer to TM0100A03 & drawings:CN1234-MC-11_16-2-1 CN1234-MC-11_2-2-2 CN1234-COM_39-2 T Junction (353/01549) CN1234-COM_39-5 Bracket 150mm Infill PC for 353/1549 Inter Suite Cable Frame Overhead Isometric View Bracket 300mm ST3 TRY

Install the inter suite support frames at the end of Suite GD/92-93 and GD/93-94 as per documentation & drawings. Install 450mm ST3 tray, for Optical Fibre Sheathed Cable, onto frame supports. Install a 300mm and 150mm Infill (as required H2 or ODF suite) ST3 T Junction Bracket (353/01549) to join the intra suite O/F tray to the inter suite O/F tray

Network Construction - Design Pack


Project Notes 2.3 Suite Lighting

6164128B0002
Attachment B

Issue: 1 Page 8 of 11

Install suite lighting on Aisle Lighting Kit S/I 353/01625. Kit to be installed in the aisle between suites. Install lights spaced at 1500mm pitch along each lighting conduit. Connect lights to existing circuit if possible, if not an additional lighting pendant will be required in each suite as per Buildings Request. 2.4 240V AC Switched Outlet for Test Equipment Install Test Socket Pendant 151/00799 at end of suite Note the Switched Socket Pendant is to be installed by a licensed electrician. One test socket outlet should be installed, in each of the following locations:- Between Suite GD/92, GD/93-94 and GD/95, 3 metres from the end of the suite measured from rack 1 end of the suite and then every 6 meters. - Socket consists of the following 1 x Test Socket Outlet mounting Bracket 353/01591 and 1 x 240V AC Switched Outlet 151/00796. - Connect socket to pendant with 6 metre preterminated cable 151/00798. Refer to:- Document TM00100A03. Sections 3.1.12 & 3.3.9 Drawings CN1234-COM-44_1-1 and CN1234-COM-44_1-2 2.5 Labelling All labelling is to comply with the relevant documents, including TM00100. For end of suite labelling, refer to CN1234-COM, Sh.46-1 2.6 Rubbish All rubbish, created by the above projects, is to be removed according to Telstras Procedures. 2.7 Dbors All relevant Dbors to be updated. The designer will ensure Cadlink is correct after receiving an As Built from the constructor. The area is to be left clean & tidy. 353/01599 KIT, SUITE END LABEL BRACKET FOR CN1234

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 9 of 11

Double Tie Bars as per CN1234-COM-36-1.

Stanchions.

Wall Bar. Dummy 150mm Signal Tray to facilitate Test Outlet. 240V Superstructure Test Outlet as per TM00100A03. Wieland Pendant Dropper for Test Outlets. Wieland Pendant Dropper for Lights.

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 10 of 11

Utilize Bend Side Plate to reduce the Tray from 450mm to 300mm.

Network Construction - Design Pack


Project Notes

6164128B0002
Attachment B

Issue: 1 Page 11 of 11

Network Construction - Design Pack


Cable Runway

6164128B0002
Attachment C

Issue: 1 Page 1 of 2

Cable Runway Details

Please note: Guidelines for Cable Runways and Risers should be constructed in relation to details from TM00181 and Design Guidelines for FSAM 576F Runway (ALT-6415).

1.1

Project Details: Work Required:


Refer to the attached drawings & Cadlink Drawing VX1055/11 (xii) Re-Route the Existing 150mm Earth Cable Tray

Re-route the existing 150mm Wall Mounted Earth Cable Tray to provide clear access for the new 450mm Cable Runway to the intended Cable Riser and Penetration.

(i)

Provide a new Wall Mounted Cable Tray

Provide a Wall Mounted 450mm Cable Tray. Please see the attached Buildings Request for a Structural Engineers report.

Network Construction - Design Pack


Cable Runway

6164128B0002
Attachment C

Issue: 1 Page 2 of 2

(ii)

Provide a Ceiling Suspended Continuation of the 450mm Cable Runway. Provide a Wall Penetration as per Buildings Request.

Ceiling Suspend a 450mm Cable Tray. Please see the attached Buildings Request for a Structural Engineers report.

Utilize bendside plate to reduce the Tray from 450mm to the 300mm Unidirectional Intra-Suite Tray.

(iii)

Wall Mount a 450mm Cable Riser and Floor Penetration.

Provide a Floor Penetration as per Buildings Request.

Provide a Wall Mounted 450mm Cable Riser. The existing 240V Wall Mounted GPO Outlet needs to be removed or relocated as per Buildings Request.

Network Construction - Design Pack


Integral Material List
Project def. WBS element Network Activity Material 353/01594 353/01799 353/01821 353/01822 353/01626 353/01590 353/01637 353/01650 353/01625 529/00051 353/01591 151/00796 151/00797 151/00798 151/00799 353/00469 353/01561 353/02527 353/02528 353/02526 353/01549 353/02407 353/02146 353/02211 353/02271 353/02405 353/02140 353/02409 353/01797 353/02403 353/02328 353/02329 353/01587 353/01588 353/00451 353/02520 353/02055 353/02270 353/02085 353/02536 353/02532 353/02177 353/02181 353/02179 353/02095 067/00478 353/02318 353/02172 353/02354 353/02322 067/00467 269/00092 269/00099 269/00102 -----N.10087.03 6164128 0001

6164128B0002
Attachment D

Issue: 1 Page 1 of 1

WP20003174 Nat NC CFC 11/12 V/T 10018832_78_VIC CSF EPGZ D&C Full 1. EPPING (EPGZ) Material Rqmts qty 9 EA 3 EA 9 EA 4 EA 4 EA 15 EA 10 EA 1 KIT 10 EA 15 EA 5 EA 5 EA 3 EA 2 EA 6 EA 6 EA 5 EA 8 EA 9 EA 14 EA 2 EA 120 EA 120 EA 120 EA 120 EA 50 EA 200 EA 30 EA 1 EA 3 EA 4 EA 4 EA 2 EA 17 EA 32 EA 4 EA 70 EA 1 EA 250 EA 250 EA 300 EA 16 EA 20 EA 32 EA 80 EA 2 EA 70 EA 20 EA 1 EA 60 EA 4 EA 1 PAC 2 PAC 2 PAC

Material text KIT,WALL BAR 3M CN1234 KIT,STANCHION FOR CN1234 FRAME,INTRASUITE FIBRE CABLE CN1234-MC FRAME,INTERSUITE CABLE CN1234-MC LABEL SET,HOT/COLD AISLE FOR CN1234 BRACKET,CABLE TIE OFF/OMF SUITE CN1234 BRACKET,CABLE HOOP 150MM W FOR ST3 TRAY KIT,SLIT PIPE 50MM FOR CABLE TRAY EDGING KIT,AISLE LIGHTING CONDUIT FOR CN1234 LIGHT UNIT,FLUOR EXCH RACK 40W SINGLE BRACKET,FOR 240V TEST OUTLET CN1234 OUTLET,DUAL 240V FOR CN1234 SUPERSTRUCT CABLE,4M FOR SUPERSTRUCTURE OUTLET CABLE,6M FOR SUPERSTRUCTURE OUTLET SOCKET,PENDANT WIELAND GST CONNECTOR FRAME,SUITE SUPPORT 600MM X 2.4M CN1234 FRAME,OFF/OMF SUITE SUPPORT 2.4M CN1234 TRAY,CABLE ST3 300MM X 3M AUG2A330 PC TRAY,CABLE ST3 450MM X 3M AUG2A345 PC TRAY,CABLE ST3 150MM X 3M AUG2A315 PC BRACKET,T JUNCTION 300MM ST3 TRAY PC BRACKET,HOLD DOWN ST3 TRAY AUG2HDC PC NUT,CHANNEL M8 TAPERED SPRING 1007 VZA SETSCREW,HEX HEAD M8X25 HHS0825 ZA WASHER,FLAT M8 FW08 ZA PLATE,SPLICE ST3 TRAY AUG2PFH PC SCREW,M10x20 & NUT ZA PLATE,LINK ST3 TRAY AUG2PLK PC BRACKET,150MM INFILL PC FOR 353/01549 PLATE,BENDSIDE 3M ST3 TRAY AUG2BS3 PC BRACKET,BRACED CANTILEVER 470MM CL300 ZA BRACKET,BRACED CANTILEVER 635MM CL450 ZA TRAY,FIBRE CABLE DROP RHS CN1234 TRAY,FIBRE CABLE DROP LHS CN1234 CHANNEL,SLOTTED 41X41MM X 3M 10003T CHANNEL,SINGLE 41X41MM X 3M 10003 ZA BRACKET,ANGLE 90 DEG 41X57MM 1068 ZA BRACKET,ANGLE 30 DEG 52X83MM 2101 ZA SETSCREW,HEX HEAD M12X30 HHS1230 ZA NUT,CHANNEL M12 TAPERED SPRING 1010 VZA WASHER,SPRING M12 SW12 ZA PLATE,FLAT 90X40MM 2 HOLE 1065 ZA BRACKET,U SHAPE 186MM 1377 ZA PLATE,FLAT 40X40MM HOLE 14MM 1064 ZA CAP,CHANNEL END 41X41MM 2240 PVC ROD,THREADED 12MM X 1M ZINC PLATED NUT,HEX M12 HN12 ZA CAP,CHANNEL END 2860-10 PVC PLANAR SHELF,150MM X 3M TELTRAY PC WASHER,FLAT M12 FW12 ZA ROD,THREADED 12MM X 3M ZINC PLATED TIE,CABLE SELF-LOCKING UV RES 2.5X100MM TIE,CABLE SELF-LOCKING UV RES 200 X 3.5 TIE,CABLE SELF-LOCKING UV RES 300 X 3.5

Network Construction - Design Pack


Equipment Layout

6164128B0002
Attachment E

Issue: 1 Page 1 of 1

Potrebbero piacerti anche