Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2. Cost of foundation: The cost of the foundation consists of: Cost of excavation / levelling/ trimming/ disposal of material Cost of blinding Cost of base concrete. Cost of reinforcement. Cost of backfilling.
2.1 Cost of excavation / levelling/ trimming/ disposal of material The cost of excavation and disposal of material have been rated at Rs 490/m3 . The expected size of the pad foundation is 0.900m * 0.900m * 0.900m. But when excavating, the size were increased so as to remove loose soil.
width / m 1 depth of foundation/m 0.9 Volume of soil in pad foundation /m3 0.9 Number of pad foundation 14 Total volume of soil / m3 12.6
The expected size of the strip footing is 0.450 by 0.450 But when excavating, the width was increased to 0.6m so as to remove loose soil.
depth/m 0.45 width/m 0.6 perimeter of strip footing/m 71 Total volume of soil / m3 19.17
Total volume of soil excavated: 31.77m3. The cost rate for levelling and trimming is at: Rs32/m2 Total surface area of soil is : 56m2 . Total cost of Cost of excavation / levelling/ trimming/ disposal of material= ( 56*32) +( 19.17*490)= Rs 17475.
Cost rate for blinding: Rs 3500/m3 Cost of labour for blinding: Rs 20/m2 Total cost of blinding: ( 3500*2.8) +( 20*56) = Rs 10920. 2.3 Cost of base concrete.
Depth of base concrete for pad footing/ m 0.75 depth of base concrete for strip footing / m 0.3 width/m 0.9 perimeter /m 71 No. of pad 16 volume of base concrete/m3 10.8 volume of base concrete/m3 9.585
width/m 0.45
cost rate for concrete: Rs 4000/m3 cost rate for labour: Rs 125/ m3 Total cost of base concrete: ( 4000 *21) +( 125*21)= Rs 86625.
2.4 Cost of reinforcement. Total mass of reinforcement in pad foundation and combined footing:
Member Pad foundation Combined footing bar mark size/mm Y12 Y12 Y12 Y12 Y8 Y8 No of member 14 14 1 1 1 1 No of bar 6 6 14 6 4 4 total No. 84 84 14 6 4 4 Length of each bar/m 0.8 0.8 0.8 1.95 0.8 1.95 0.888 149.45 total length of bar/m 67.2 67.2 11.2 11.7 3.2 7.8 168.3
Size/ mm Y8 Y8
0.395 117.79
Cost of reinforcement :Rs 35/ kg Cost of labour( bar bender) : Rs 5/ kg Total cost of reinforcement: ( 40)( 267)= Rs 10680. 2.5 Cost of backfilling. For the backfilling, it will be assumed that 3 workers will be paid Rs 3000 for 2 days . 2.6 Total cost of Foundation: (3000+10680+86625+10920+17475) = Rs 128700.
The cost of ground floor slab consists: Cost of concrete Cost of labour. Cost of formwork used for shuttering. 3.1 Cost of concrete. Cost of concrete: Rs 4000/m3 Cost of labour for casting of slab : Rs 200/ m3 Surface area of ground floor slab: ((11.555*12.4)+(3.7*3))=155m2 Assume thickness of slab: 100mm Volume of concrete for ground floor slab: 155*0.1= 15.5m3 ( but we will use 16.5m3 to cater for wastage) Cost of concrete of ground floor slab: ( Rs 4200*16.5) = Rs 69300. Perimeter of ground floor slab: 56m Take depth of formwork to be 150mm Total area of formwork: ( 56*0.150) = 8.4m2 Cost of plywood marine: Rs 272/ m2 Cost of 10 timbers ( 3 by 2) use for curtailing: Rs 750. Cost of labour for shuttering of slab: Rs 150/m2 Cost of formwork used for shuttering: ( 8.4*272)+(150*8.4)=Rs 3545.
4 Cost of Block Work. The cost of block work consists: Material cost. Labour cost.
4.1 Material cost When we do block laying, we can consider the material cost to be comprised of: a) Cost of block b) Cost of mortar. 4.1 (a) Cost of Block. A unit block cost: Rs 17.00 In Mauritius blocks of length 450mm and depth 200mm are available. So it can be deduced that in 1 meter square we required 11 blocks. As such the cost of block per meter square: (17*11) = Rs 187.
Along grid line UGA UGB UGC UGD UG1 UG2 UG3 UG4 UG5 UG6 Interior block Wastage Total block / m2 Area of block/ m2 35 32 35 8 35 34 32 11 15 10 6 25 278
4.1 (b) Cost of mortar. The appropriate mortar for block laying required that 50kg of cement to be mixed with 175kg of rocksand( 0.4mm). 50kg of cement + 175kg of rocksand , we can lay 50 blocks.
50 blocks take an area of 4.5m2 So to lay 1m2 of block it costs Rs65 ( it is inclusive of the wastage) Cost of mortar for block laying: ( 278*65)= Rs 18070. Cost of labour for laying blocks: Rs 150/m2 Total cost of labour for block laying: (150*278) = Rs 41700.
10
5. Cost of columns. The cost of column consists: Cost of concrete Cost of reinforcement Cost of formwork.
Length of column/m 4
Width/m 0.2
No. column 16
cost of concrete: Rs 4000/m3 cost of labour of casting: Rs 200/m3 Total cost of concrete for columns: (4200*2.56) = Rs 10752 5.2 Cost of reinforcement. The wastage- overlapping and bending of bar at base of columns for reinforcement- used in column is taken as 30% of the height of column. 11
295.53
Cost of reinforcement bar: Rs 35/ kg Cost of labour: Rs 5/ kg Total cost of reinforcement: (40*296) =Rs 11840.
Area of a side to be shuttered: ( 4*0.2)= 0.8m2 Total area to be shuttered: ( 0.8* 29) = 26m2 ( inclusive of 10% of wastage) Cost of plywood marine: Rs 270/ m2 Cost of labour for formwork: Rs 125/ m2 Consider that plywood used for ground floor slab cannot be reused: Cost of formwork of column: ( 395*26)= Rs 10270.
12
6. Cost of beam The cost of beam consists of: Cost of concrete Cost of reinforcement Cost of formwork. 6.1 Cost of concrete. cost of concrete: Rs 4000/m3 cost of labour of casting: Rs 200/m3 Total length of beams used in the house: 95m Total volume of concrete required for beams: (0.450*0.200*95)= 8.6m3 Total of concrete: (4200*8.6)= Rs 36120
6.2 Cost of reinforcement. Here a wastage- overlapping, chairs and U-Bar- is taken as 40% of the total length of beams.
13
Cost of reinforcement bar: Rs 35/ kg Cost of labour: Rs 5/ kg Total cost of reinforcement: (40*473)= Rs 18920.
Member Beams Wastage Sum of bars, chairs and lapping Weight kg/m Total weight / Kg
size/mm Y12
No of member 1
No of bar 4
total No. 4
6.3 Cost of formwork for beams. Depth of formwork to be used for shuttering will be 600mm: it is more than 450mm, this allow the plywood to be nailed on the block. Area of formwork required: ( 2) ( 0.6*95)= 114m2 Consider the formwork used for columns to be in good condition, so the required formwork to be bought: ( 114-26) = 88m2 Cost of plywood marine: Rs 270/ m2 Cost of labour for formwork: Rs 125/ m2 Total cost of formwork for beams: ( 395*88) = Rs 34760. 6.4 Total cost of beams: ( 34760+18920+36120)=Rs 89710.
14
7 Cost of roof slab. The cost of roof slab consists of: Cost of concrete Cost of reinforcement Here there will be no cost for formwork because centers and scaffolding will be hired. 7.1 Cost of concrete. Surface area of roof slab: 160m2 Volume of concrete for roof slab: ( 160*0.150) = 27m3 ( inclusive of 10% wastage) cost of concrete: Rs 4000/m3 cost of labour of casting: Rs 200/m3 Total cost of concrete: (4200*27) = Rs 113400.
15
16
7.2 Cost of reinforcement for slab. Here a wastage- overlapping, chairs and U-Bar- is taken as 30% of the total length of slab.
Member Slab UG1 TO UG4 Slab UG4 TO UG6 Slab UG4 TO UG6 Slab UGC TO UGB Slab UGB TO UGD Slab UGD TO UGA Slab UGC TO UGB along UG1 Slab UG1 TO UG5 along UGC Slab UG1 TO UG6 along UGB Slab UG1 TO UG4 along UGA Slab UGA TO UGC along UG1 Slab UGA TO UGC along UG2 Slab UGA TO UGC along UG3 Slab UGA TO UGB along UG4 Slab UGD TO UGB along UG6 Slab UG1 TO UG3 Slab UG4 TO UG6 along UGD Sum Wastage Weight kg/m Total weight / kg bar mark 01-B1 01-B1 01-B1 02-B2 02-B2 02-B2 13-T1 03-T1 06-T1 10-T1 05-T1 07-T1 08-T1 09-T1 12-T1 04-T1 11-T1 size/mm Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 Y8 No of member 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 No of bar 82 7 31 86 24 15 40 87 114 79 80 80 80 41 27 20 29 total No. 82 7 31 86 24 15 40 87 114 79 80 80 80 41 27 20 29 Length of each bar/m 12 9.85 3.7 13 16 11.85 1.6 1.6 2.4 1.6 1.6 2.2 2.2 1.6 1.6 3.25 1.6 Total length of bar/m 984 68.95 114.7 1118 384 177.75 64 139.2 273.6 126.4 128 176 176 65.6 43.2 65 46.4 4150.8 1245.24 0.395 2131.45
17
Cost of reinforcement bar: Rs 35/ kg Cost of labour: Rs 5/ kg Total cost of reinforcement: ( 40*2132)= Rs 85280. 7.3 Total cost of slab: (85280+113400) = Rs 198680.
18
8.0 Cost of rendering. The cost of rendering consists: Cost of rendering compound ( will be made up of cement and rocksand 0.2) Cost of labour for rendering.
8.1 Cost of rendering compound. To render 1m2 , the appropriate rendering compound requires 7.5kg of cement and 20kg of 0.2 rocksand.
Cost / Rs 7.5 kg of cement 20kg of rocksand( 0.2) Cost of rendering compound to render 1m2 24 13 37
For this house both interior and exterior rendering will be done. Total area to be rendered: ( 278*2) = 556m2 Cost of rendering compound: ( 556*37*1.10) Rs 22630. 8.2 Cost of labour for plastering. For dotting both interior and exterior, 4 workers will be paid Rs 600 for a day. The dotting activities are expected to take 2 days. Cost for dotting: ( 600*4*2)= Rs 4800. Cost for rendering: Rs 110/m2 Total cost for rendering: ( 4800) +( 110*556) = Rs65960.
19
9 Final cost estimate. Final cost estimate is made up of : Total cost of Foundation Total cost of ground floor slab. Total cost of Block work Total cost of columns Total cost of beams Total cost of roof slab. Total cost of rendering Items Foundation Ground floor slab Blockwork Columns Beams Roof slab Rendering Final Cost estimate Cost / Rs 128700 72845 93686 32862 89710 198680 88590 705073
20
21
22
23
24