IMPACT MANAGEMENT PLAN

Proposed Vitali Water System (Source Development) Project


Sitio Kamalik, Vitali, Zamboanga City
Project Phase/Environmental Environmental Options for Prevention or Aspect Component Likely to be Potential Impact Mitigation or Enhancement I. PRE-CONSTRUCTION PHASE Source Verification Activity Spring source (water) disturbance of water quality, increase in limiting activities to measuring turbidity discharge of the source and sampling for water quality analysis Topographic Survey of the Residents fear of displacement from present conducted meeting with proposed pipe network settlement among nearby settlers affected settlers together with local barangay officials conflicting interests with lot/property identified proprietary rights of owners individuals over parcels of land that will be affected by the project Lot acquisition for 90 m Property owner acquisition of a parcel of land which undergo appropriate ground tank may or may not be acquired negotiations to arrive at the most reasonable price without going beyond or under fair market value Site inspection and source Ambient Air decrease in ambient air quality due to ensure regular preventive verification activities entrained dust from vehicles maintenance vehicles to transporting personnel prevent emission increases due to engine allow for settling of dust over a period of time limit engine idling time use of low sulfur and low aromatic fuel meeting the standards set motor vehicle as set by the Philippine Clean Air Act use of low-emitting Diesel engines meeting the emmissions standards for construction equipments as set by PCAA II. CONSTRUCTION PHASE Mobilization and Hauling of Ambient Air decrease in ambient air quality due to: Materials Entrained dust from material delivery allow for settling of dust over a trucks traveling on unpaved period of time roadsdecrease in ambient air quality use water flushing of unpaved dust entrained during aggregate and road every interval to reduce soil loading and unloading operations entrained dusts in the atmosphere and to remove buildup of loose material to control dust emissions Responsible Entity PDD Cost Guarantee/Financial Arrangements N/A

PDD, Vitali Barangay Council PDD, Admin. & LAC

ZCWD Funds

ZCWD Funds

Lot Acquisition Committe (LAC)

Php715,000 ZCWD Funds

ZCWD Transportation Maintenance Division

ZCWD Funds

ZCWD Transportation Maintenance Division Construction Division c/o Project Engineer

Final Staking/Lay-outing/Line and Grade

ambient air quality

Pipelaying works including land Operation of heavy equipments and other construction equipments, including hydrotesting and disinfection works, installation of valves/fittings and interconnection works; Installation of five (5) units of 75 mm fire hydrants and barricade; installation of four (4) unit of blow-off assembly ambient air quality

cover all trucks hauling soil, sand and other loose materials, or require all trucks to maintain at least two feet of freeboard limit traffic speeds on unpaved surfaces at 40 kph dust entrained during site preparation operational measures, such as and grading/excavation at the limiting engine idling time and construction site shutting down equipment dust entrained during onsite travel on when not in use unpaved surfaces regular preventive exhaust from the Diesel construction maintenance to prevent equipment used for site preparation, emission increases due to grading, and excavation engine problems Wind erosion of areas disturbed during Use either water application or construction activities; chemical dust suppressant Exhaust from automobiles and trucks application to control dust used by workers to commute to the emissions from unpaved construction site; surface travel and unpaved parking areas; generation of solid wastes prevention on site, segregation of waste according to recyclables, reusables and non-reusable/recyclable; all such solid waste generated shall be gathered at the temporary facility; nonreusable/recyclable for appropriate disposal after determination of whether classified as hazardous/toxic waste sprinkling of water at every construction equipment engine exhaust interval to reduce entrained Motor vehicle exhaust, brake and tire dusts in the atmosphere wear perform operational measures Entrained dusts from earth preparation such as limiting engine idling works time and shutting down the entrained dust from vehicles traveling equipment when not in use on unpaved roads entrained dusts from construction regular preventive workers transportation while traveling on maintenance to prevent unpaved roads during construction and emission increases due to pipelaying engine exhaust from the diesel construction use of low-emitting Diesel equipment used for site preparation, engines meeting the grading, excavation, and construction standards set by PCAA site of source collection box and ground tank exhaust from diesel-powered electric generators, air compressors, water pumps, etc.

ZCWD Transportation Maintenance Division Construction Division c/o Project Engineer

Construction Division c/o Project Engineer

Construction Division c/o Project Engineer Transportation Maintenance Division, ZCWD

Ambient sounds

increase in ambient noise levels at project site due to use of heavy equipments such as backhoe, dump truck, welding machine, bar cutter, hydrotesting machine, tamper hammer)

strategic location of project site allows for buffer zones; machine operators adviced to use ear plugs to avoid damage to hearing

Construction Division c/o Project Engineer

creek, spring or other adjoining or nearby water bodies, underground water

Construction of pipe support on creek crossings

decrease in water quality due to temporary disturbances due to construction activities or introduction of wastewater from disinfection works which may increase turbidity levels and temporarily alter chemical characteristics of the water body concerned creeks and other nearby temporary disturbance in water quality water bodies because of human activities and contruction of pipe support

monitoring of water quality by taking sample for analysis at the laboratory or conducting on-site testing before and after the hydrotesting and disinfection of pipes

Construction Division c/o Project Engineer or designated Project PCO

cement preparation will be Construction Division c/o made some distance from the Project Engineer creek to avoid contamination of water body and to allow natural treatment of the creek before resumption of domestic use allow settling to occur after maintenance activity has been performed as natural treatment for turbidity Production Department c/o Operator

III. OPERATION PHASE Regular maintenance of ground tank and source

nearest water body

disturbance of water quality due to increase in turbidity as a result of maintenance activities

IV. ABANDONEMENT PHASE Abandonment of pipelines land where pipelines have been installed

soil contamination due to corrosion of pipes

natural treatment of trace elements due to corrosion of pipes

Engineering Department

Prepared by:

Reviewed & Checked by:

Submitted by:

ANNE AUBREY R. DE GUZMAN-BUGTONG Researcher-Analyst A (J.O.) Planning & Development Section

MARIE CLAIRE C. BONGO Officer-In-Charge Planning & Development Section

MARLI P. ACOSTA-DE FIESTA Officer-In-Charge Planning & Design Division

Approved by:

Recommending Implementation:

Approved for Implementation:

CARLOS L. PEREZ, SR. Officer-In-Charge Engineering Department

ALEJO S. ROJAS, JR. Assistant General Manager for Operations

LEONARDO REY D. VASQUEZ General Manager