Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Time Management
Text Book PMBOK 5E PMP Exam Prep Rita Mulcahy -7E
Procurement
Management
Management
Scope
Management
Time
Management
Risk
Integration
Management
Management
Cost
Communication
Management
Management
Quality
Management
HR
Stakeholder
Management
Planning
Planning Planning Planning
Planning
Planning
Control Schedule
Schedule Methodology SW to be used Rules of stating estimates Schedule Management Plan Schedule Baseline to control Identifying PIs to measure performance How to manage schedule variances Identify schedule control procedures Reporting formats to be used Formal/informal . But, A MUST
Hours/Days/Weeks/Months
Establish
Inputs
PM Plan Project Charter EEF OPA
Outputs
Schedule Management Plan
PM Plans
STQC management plans HR Management plans Risk management plan Procurement management plan Communication management plan Requirement management plan Stakeholder management plan Change management plan Configuration management plan Process improvement plan
Purpose and justification Measurable project objectives Success criteria High level requirements High level project description High level risks Summary mile stone schedule Summary budget Project approval requirements Assigned Project Manager PM: Authority level, responsibility Sponsor: Name, Authority Tools OPA Lesson learnt Historical Info Policies Templates Guidelines change , close Risk control procedures
Orgn. Culture, structure Resources, skills PM SW EEF Published data Authorisation system
Expert Judgment
Application area Knowledge area Discipline Industry
Analytical Techniques
Information exchange Brainstorming Evaluating options Deciding
Regression Grouping methods Causal analysis Root cause analysis Failure Mode Effect Analysis (FMEA) Fault tree analysis (FTA) Reserve Analysis Trend Analysis Earned value Analysis Variance analysis Crashing / Fast tracking
Contents
Methods, tools
Level of accuracy
Units of Measure Orgn. Procedure Links Schedule Model upkeep Control thresholds Rules of performance measurement Reporting formats Process descriptions/ flow charts
Process Owner/s
Work package
Activities
Inputs
Schedule Management Plan Scope Baseline EEF,OPA
Outputs
Activity list Activity attributes Milestone list
OPA
Contents
Activity planning related Policies, procedures Methodologies Lessons learnt from previous projects
Tools
Expert Judgement
SMEs Other departments Consultants Relevant stakeholders
For a given work package Activity identifier Scope of work involved Activity ID
Activity Attributes Activity ID WBS ID Activity name Activity code Activity description Predecessor activities Successor activities Logical relationships Leads/ Lags Resources needed Imposed dates Constraints/ assumptions Person responsible Location Level of effort
Sequence Activities
Inputs
Schedule
Management Plan
Activity list Activity attributes Project Scope statement Milestone list EEF,OPA
Outputs
Project Schedule network diagrams Project document updates
4 Dependencies
Finish to Start Finish to finish Start to start
Successor activity
Start Depends on Finish depends on Start depends on
Predecessor activity Finish of this activity Finish of this activity Start of this activity
Finish depends on
Execution Phase
N
Mech
N
OK ?
Initiating Phase
N N Y
Elec
N Y OK ?
OK ?
Y OK ?
Start
Concept
OK ?
Design
Electro
N
Integrate
N
Planning Phase
Civil
OK ?
Y Y
OK ?
SW
OK ?
OK ?
Transport
Instal
Y N
Commission
OK ?
Closing Phase
Project Document Updates Activity lists Activity attributes Milestones list Risk register
Network Diagram
P160,PMBOK 5E
Inputs
Outputs
Activity Resource requirements Resource breakdown structure (RBS) Project document updates
Inputs
People, machines, materials Availability: When and how long Experience required Skill level required At activity / project level
EEF
Market place situation Contract laws and regulations
OPA
HR Policies Rental policies : Suppliers/ equipments Historical information about: Types of resources used Duration of use
R44
R21
R7
Cost of resources influences Resource selection Activity duration More when we study cost.
Published data
By vendor companies
Bottom Up Estimating
Further decompose activities Start estimating at lowest level Aggregate upwards Most realistic Also time consuming
People, machines, materials Availability: When and how long Experience required Skill level required At activity / project level
Inputs
Outputs
Activity duration estimates Project document updates
SMP - Slides 15,16 Activity list, attributes Slide 15 Resource Breakdown structure slide 33 Activity resource requirements slide 33 Project scope statement explained in scope management Risk register slide 30
Inputs
Resource calendars EEF, OPA
People, machines, materials Availability: When and how long Experience required Skill level required At activity / project level
EEF
Duration estimate databases Productivity metrics Published data
OPA
Historical duration information Project calendars Scheduling methodology Lessons learnt
Project
Designers
Mechanical Electrical
Erectors
Skilled
Unskilled Specialists
Programmers
Painters
Based on similar data in the past Gross value estimating When information is limited Less costly and less accurate Type of expert judgment
Parametric Estimating
Based on activity parameters Time per unit of work Better accuracy
Reserve Analysis
Time reserves, buffers Provide for risks Needs constant review Rita book p193
Inputs
Activity list Activity attributes Network diagrams Activity resource requirement Resource calendars Activity duration estimates Project Scope statement Activity Resource Requirements Risk register Resource breakdown
Outputs
Project Schedule Schedule baseline Schedule data Project Calendars PM plan updates Project document updates
structure
EEF, OPA
Inputs
Activity list Activity attributes Network diagrams Activity resource requirement Resource calendars Activity duration estimates Project Scope statement Activity Resource Requirements Risk register Resource breakdown
OPA
Already explained
structure
EEF, OPA
Schedule Compression
Crash Fast track
Resource Leveling
When resources are over allocated Shared limited Often changes CP
2.Resource Smoothing
Control resource deployment No change in CP Delays < float Optimisation not possible
Modeling Techniques
What-if-analysis Simulation Monte Carlo analysis Show xl sheet
CostSlope
2. Select activity having smallest cost slope on CRITICAL PATH 3. Continue in ASCENDING order of Cost Slope 4. Crash other NON-Critical activities that may become critical 5. Continue till no further crashing possibilities exist
Project Management and Appraisal, Sitanshu Khatua. P51-62 For resource leveling Read p57
Milestone charts Bar charts Project Schedule Network diagrams Example P183,PMBOK 5E Schedule Baseline Version of schedule Approved by project management team Part of PM plan
Project Document Updates Activity resource requirement Activity attributes Project Calendar Risk register
Schedule data
Resources needed per time period Resource histogram Alternate schedule Best/Worst case Schedule of contingency reserves
G
B H
F,E
F G
5
5 7
C
End
H
C,B
8
0
D-End
Task 1 can start immediately and has an estimated duration of one week. Task 2 can start after Task 1 is completed and has a duration of 4 weeks. Task 3 can start after task 2 is completed and has an estimated duration of 5 weeks. Task 4 can start after task 1 is completed and must be completed when Task 3 is completed. It has an estimated duration of 8 weeks.
Time saved 2
1 1 2 2 3
A
B C D E F
14
9 3 7 7 11
12
8 2 5 5 8
10
17 25 14 14 27
14
27 26 20 20 36
4
10 1 6 6 9
2
10 1 3 3 3
If the project is to be crashed by exactly 3 months. Find : Activity to be crashed Cost of crashing What happens if activity C is on critical path?
B
F End
A,E
E B,F
5
3 0
M
L End
F,C
F H,M,L
4
5 0
2
3 0
6
8 0 72
8
12 0 127
Change Requests
Current status of the schedule Factors that influence changes Has the schedule changed? Managing the changes as they occur More on PMBOK 5E,p187,
Inputs
PM Plan Project Schedule Work performance
Outputs
Work performance information Schedule forecasts Change requests PM Plan updates Project document updates OPA Updates
Inputs
PM Plan Project Schedule Work performance data
Schedule control policies Formal Informal Schedule control tools Monitoring and controlling methods
Schedule data
Resources needed per time period Resource histogram Alternate schedule Best/Worst case Schedule of contingency reserves
CPM Critical chain method Earned Value Management Schedule Performance Index (SPI) Schedule Variance (SV) Buffer analysis Trend analysis Earned value management
Variance Analysis
Rest covered in previous slides For corrective action Total float analysis Compared to Schedule baseline
OPA Updates
Causes of variances Corrective actions Reason for choosing them Other lessons learnt
Additional Reading
www.youtube.com/watch?v=H58TPQNr2kM For a lecture on CPM method www.mindtools.com/critpath.html syque.com/quality_tools/toolbook/Activity/do.htm www.tutorialspoint.com/pmp-exams/pmp_mock_exams.htm www.preparepm.com/pmp/schedule.html http://hafeezrm.hubpages.com/hub/Case-Study-PERT--CPM---Calculating-Floats