Explain Cutover Activities/Strategies in SAP FI.

Cutover Activities or Master Data Uploading Strategies Depending upon the when we are going live. As per that, you have to give the information to your core team. If you goling live at the middle you have to upload the all P&L Account items and B/S Items. If you going live at the financial year start, you have to only Upload the B/S Items. Activities for Golive: 1. G/L Master Upload Thru BDC or LSMW (TC-Fs00 and extended one co code to another company code Fs01) 2. Vendor Master Upload Thru BDC Or LSMW (Will be Taken Care By MM) 3. Customer Master Upload Thru BDC or LSMW (Will be Taken Care By SD) 4. Asset Master Upload(Thru As90) 5. Cost Element Master Upload 6. Cost Center Master Upload 7. Profit Center Master Upload 8. G/L Balances Thru F-02 10. Vendor Balances thru F-43 11. Customer Balances thru F-22 12. Customer Advances thru f-29 13. Vendor Advances thryu F-48 Before uploading Vendor Balances you have to take care of WHT(TDS) Information. -----------------------------------------------------the master data conversion how data will be provided, converted, uploaded? by who? when? the original system should runs any procedure before? -the planned data conversion -the gudget data conversion -the actuals -the purchase documents related to projects Consider that actuals, and purchase documents require a deep analisys regarding the integration with the FI/CO/MM modules. During the conversion is required any certification of the data? When the system will be available to users? Have the users the SAPguis installed and the network settings properly setted?

-------------------------------------------------------------------------------------------------------------------------Cutover plan is to plan the strategy for go-live regarding upload of master data, opening balances, dates, responsibilties, back up etc. Following are the diffrent cutover Activities... Communication to Vendor, Customer and Excise etc User Training by Core Team Cost Roll ups and Validations - Test Upload of Master Data in Sequence on Test Start entry of Open Sales Orders, Quotation, Enquiries, Purchase Orders in Prod Stock Taking Activity at Plant Stock Upload with SAP Material Code, Qty, Value and Storage Location as on Go-Live Date Enter Cash Balances as of Go-Live Dates Enter Excise balances as of Go-Live Dates with monthly duty payment for March Configure Cut off Excise Number Range (Excise Invoice, RG registers) as on Go-Live Dates Back up of Loaded Production Server Go Live Availability of all balances FI Balance uploads (For both ledgers/ subledgers/ assets/ customers/ vendors) Refer below sample cutover checklist.. http://hosteddocs.ittoolbox.com/KL122206.pdf ------------------------------------------------------------------------------------------------------Cut over activities to be followed (for PP - Discrete Manufacturing). Production Planning / Master data: For Production planning, only master data shall be migrated to SAP. In the 1st Stage, there is no master data. Following is the master data elements relevant for PP:

Bill of materials Routing. Work Centres.

Transaction data: As of the cut off date, ideally there should not be any work in process. All the open production orders should be closed and semi finished goods should be dismantled and should be added to Raw materials. This strategy should be followed for all production orders where lead time to complete the production order is not large. Since, the production orders are for longer duration and it is not possible to dismantle the product and add it to inventory, following can be the strategy for migrating the data to SAP:

Create a material master for the work in process and set the standard price as the cost incurred for that product (ie. Work in process) Create a bill of material (which will be used only for this production order) including this material and other materials still to be consumed. Create Routing for rest of the production process. Bring the work in process material into inventory as of the cut off date. Create the production orders in SAP for the Work in process and issue materials to production order.

Complete the production process after the cut off date of the project ----------------------------------------------------------------------------------------------------------http://sapdocs.info/2008/09/22/sap-go-live-strategy/

------------------------------It Involves deciding which tools you will use e.g. LSMW, CATT, ABAP etc. You need decisions on when you will cut off and establish these items and when you will do the physical transfer. You need to prioritize this. For example, I usually bring AR open items across before AP and GL and AA come last. Stock balances are also priority. If you have stock and AR OI in your system you can bill and do credit checks. Open sales and purchase orders also have to be brought across. You may have open WBS elements, Internal Orders and commitments to consider. You may also need to load your budget. If going live mid-year you need to consider the P & L account cumulative balances and cost centre / profit centre history. For all balance sheet items you need transit accounts which act as contra accounts for the OI and balances loads and zero out if everything is OK. Oh, and I always load in the last period of the old system and roll forward - i.e. for a January 1st Go-Live I load as at 31st December and use SAP standard functionality to bring balances and OI forward into the new year. You should also get someone working on data scrubbing as soon as possible so that you do not load a heap of rubbish. Year-end tends to be a time when people have vacation and then come back and go straight into year-end closing, so there is personnel planning to do to have the right people available at the right time. You need contingency planning for if things go wrong. You need to do test uploads in a QA system, etc., etc.

----------------------------------------------------------------------------------------------------------------------The process involved when the company is going live in mid year, how do we bring in the P&L balances from legacy to SAP. This varies from company to company and depends largely on how much history you want to keep. If you want to keep all the CO postings as well as FI then you have to analyze the first half year and summarize by GL account by month, and, within GL account, by profit centre / cost centre. This is usually done in a spreadsheet. On one project with an October 01 Go-Live we had a junior accountant doing this over a 6 month period before Go-Live. An accountant is the best person to do it because he can check the numbers as he goes and he knows his accounts. There is of course a mapping process between old GL and new GL, old profit centre / new profit centre, old cost centre / new cost centre. This has to be done first, obviously. Summarized numbers month by month are usually enough - you do not need individual transactions. There are several tools you can use to upload from Excel including LSMW and CATT. Once you have your spreadsheet it should fly into SAP without problems. You load into each monthly period separately. If all the above detail is not required, then you simply bring over the balances from the TB at the end of the last period before Go-Live. Usually the chief accountant wants the detail so that he has comparative figures for the first full year after Go-Live, but some people say to heck with that and do their comparisons in Excel. ------------------------------------------------------------------------------------------------------------http://sap.ittoolbox.com/groups/technical-functional/sap-acct/cutover-activities-and-openingbalances-1851354 could you plz, tell me what do you mean by cutover activites and what are the cutover activities are involved in final preparation phase plz, try to give me a detailed answer that to i can understand the basic idea and how do we upload opeing balances in to sap of GL AR AP AND Asset accounting 1st custover data means : the data you should cut the entering in legacy system and use the last figuers of this data as opening for sap. 2nd for openning balances you should do1-create contra accounts in your COA (create account group for it , esp. no. range ) 2-we'll take the open items for customers as example use the invoice in AR module so the debit will be customer and the credit will be the contra account related to ar open items. and so on for others fixed assets , vendors gl accouns and so on

3-you should care about the profit centers if it's required do not miss also for profitability analysis you should create internal order and link it to profit cenetr and send you entries incloding that Internal order no, and if you depend on the profit center concept for BS or p&l you should know the transaction 3keh and 1kek and the othe transactions so you can build the pc BS statment... yours hany refaat ---------------------------------------------------------------------------------Cutover activities the name itself tells you cut the business data ex: legacy transactions are stopped from today onwards means today is cut date and will take all balances as on todays date and upload into sap system by using LSMW, BDC, Ecatt etc., It is part of final preparation at 4th phase in the ASAP methodology. That includes upload the balances, sign off from end user, user acceptance test etc., Financial Accounting: The following account numbers will be used for the takeover of the opening data: Open balance assets <No.> Initial stock uploads <No.> Open balance GL <No.> Open balance of Receivables <No.> Open balance of Payables <No.> Trial Balance:1.The certified trial balance as on <date> will be taken over in the SAP system. 2.It may be noted that this trial balance needs to be broken down profit center wise for the balance sheet accounts and cost center & profit center wise for the revenue accounts (Profit & Loss Accounts) 3.The Balance sheet items excluding AR/AP/FA will be taken as the closing balance, whereas, open line item will be taken for AR/AP/FA respective sub-ledger wise. AR/AP line items will compulsory have payment terms. CWIP will be uploaded asset wise. So CWIP accounts will be broken up accordingly. Accounting Entries while data upload: 1.Inventory Takeover: When inventory will be uploaded, following entry will be generated by the system depending upon the valuation class specified in the material master. Inventory Account.Dr To Initial stock upload account 2.Receivable Takeover: Account Receivables will be uploaded customer wise and only the open items will be taken over to new system. At the time of upload following entry will be generated.

Customer Account (with actual reconciliation account Dr To Opening balance account receivables 3.Payable Takeover: Account Payables will be uploaded vendor wise and only the open items will be taken over to new system. At the time of upload following entry will be generated. Vendor Account Dr To Open Balance Account payables 4.Asset Takeover: The asset balances will be uploaded asset wise. This will not create any accounting entries initially and asset balances will be loaded. In case of Accounts Receivable, Accounts Payable, and Assets, it should be ensured that the sub ledger balances are tallying with the general ledger. 5.Other GL Takeover: All the GL Accounts (other than above) will be taken over by debiting / crediting to the account code <No.> (open balance GL) The closing balance of balance sheet accounts will be taken over and the profit and loss accounts will be taken cost center wise. At the end of the data takeover exercise, all takeover accounts together shall show a zero balance. These accounts shall be blocked for posting after the data take on activity. GR/IR account: It would be ideal to ensure that all invoices relating to goods received be booked in the legacy system before the cut off date. Alternatively, all provisions made in the legacy system relating to goods received but invoices not received will have to be adjusted against corresponding vendor invoices received after the go-live date. In case of invoices relating to goods that have been received before the go-live date, the following entry shall be passed in the production system: Corresponding Provision Account..Dr To Vendor Account The invoice for such receipts shall be passed using the FI invoice booking transaction and not through Materials Management. The verification of the invoice shall be manual. Apart from the above-mentioned data, the budget data for Cost center and Profit center also needs to be uploaded into the SAP system. ----------------------------------------------------------------------------------------http://www.sapfans.com/sapfans/asap/be_06_e.htm

Phase 4: Final Preparation


ThepurposeofthisphaseistocompletethefinalpreparationoftheR/3Systemforgoinglive.This includestesting,usertraining,systemmanagementandcutoveractivities,tofinalizeyourreadinesstogo live.ThisFinalPreparationphasealsoservestoresolveallcrucialopenissues.Onsuccessfulcompletion ofthisphase,youarereadytorunyourbusinessinyourproductiveR/3System. InPhase4,yourendusersgothroughcomprehensivetraining.Thelaststepwillbetomigratedatato yournewsystem.InparticularagoinglivecheckiscarriedoutandanR/3HelpDesksetup.
Fig.Xx:MainworkpackagesofPhase4

ThisphasebuildsontheworkdoneintheprevioustwophasessothatR/3canbehandedovertothe individualdepartmentsforproductiveoperation.Thisincludescreatingtheuserdocumentationand trainingtheendusers.Thetechnicalenvironmentisinstalledfortheproductivesystemandtheproject managersmakeplansforgoinglive,includingthetransferofdatafromlegacysystemsandusersupport inthestartupphase. Endusertrainingcanbetheareaanorganizationspendsthemosttimeandmoneytocomplete,since propertrainingiscriticaliftheprojectistobesuccessful.Ahighleveltrainingplanshouldhavebeen developedwithintheProjectPreparationphase,butnowmoredetailisadded.Thetrainingprogramis setupaccordingtothenumberofusers,theirlocationandtheirtasks.Oncethesiteofthecoursesandthe trainershavebeenchosen,thecoursescanbeheld. Toaccelerateyourtrainingactivities,youcanpurchasetheR/3InfoDatabase(InfoDB),ablendofR/3, multimediacontent,andtools.TheR/3InfoDBcontainsover250standardcoursesthatweuseinour SAPtrainingfacilitiesworldwide.ThesecoursesareavailableformultipleR/3releasesinupto14 languages.

Computing Center Management System


AspartofsettinguptheComputingCenterManagementSystem(CCMS),thesystemadministratorsare trainedandthenetworkadministration,backup,archiving,andcapacitymonitoringsystemsare preparedandtested.Someofthetasksinvolvedhereareconfiguringtheprintingfacilities,conducting systemvolumeandstresstestsandconductingagoinglivecheck. Furthermore,R/3logongroupsarenowsetup,enablingyoutoprovideapplicationserverswith improvedresponsetimeforparticularlyimportantworkgroupsusingtimesensitivetransactions. Operationmodes(resourceconfigurationsforeachinstanceoftheR/3System)nowneedtobedefined, withthetimesthattheservicesareavailable.Alertmonitorsandbackupschedulesaresetup.Productive systemprintingproceduresandspooladministrationproceduresaredefinedaccordingtotheSystems OperationsManualsetupintheBlueprintPhase.Finally,theR/3jobschedulingsystemneedstobe configured,aswellasalertmonitorsandbackupschedulesdefined. AlsoinPhase4,thesystemadministrationstaffneedstobetrainedinaworkshopsession.Topicsinclude troubleshooting,tapemanagement,andusermanagement,aswellasescalationprocedures.

FigXX:R/3technicalimplementationcycle

InPhase4yousimulatetheproductiveoperationofyourR/3System,astepofgreatimportance.Thetest plancontainsallthemostimportantsituationsthatariseinthenormalcourseofbusiness: Testingconversionproceduresandprograms Testinginterfaceprograms Conductingvolumeandstresstesting Conductingfinaluseracceptancetesting Developingafinalgolivestrategy

Thetestsituationsareselectedonthebasisofimportanceandfrequencyofexpecteduse.Printersand otheroutputdevicesarealsoincludedinthetests,inorderto,forexample,checkprintvolumesorprint layoutsinprintedinvoicesorpurchaseorders.Endusersareincludedintheplanningandexecutionof thetests. Volumetestingalsoinvolvescheckingthecriticalparametersforspecificbusinessprocedures,for example,adheringtoatwosecondaverageprocessingtimetocreateasalesorder.

CATT Test System


TheComputerAidedTestTool(CATT)canbeusedtoautomatetestsequencesforkeybusiness processes.Theresultsareloggedindetailandthenreviewed.CATTisalsousedforqualitytestsduring releasechangeoversandforsimulatingcompletebusinessprocesses. SystemadministrationtestinginvolvestestingtheactivitiesofaSystemAdministrator,suchasmanaging jobscheduling,administeringcorrectionsandtransports,reactingtoR/3Systemalertsandlogs. Phase4alsoprovidesforthetestingofthedisasterrecoveryplanandoftheproceduresdefinedforthe productiveenvironment.Ifathirdpartyproviderhasbeenengagedfortheseservices,theirservicesand responsivenesscanalsobetested.Disasterdowntimesareverifiedanddetailsondeescalation proceduresaredocumented. Nowthatthetechnicalconfigurationfortheproductivesystemisfinalized,plansaredrawnupfor transferringlegacydata.Atthispoint,thesystemsettings(Customizing)andR/3Repositoryobjectsare transferredfromthequalityassurancesystem,andautomaticandmanualdatatransferstothe productivesystemarecarriedoutandtested.

GoingLiveTM Check
TheGoingLiveTMCheckinvolvesananalysisofthemajorsystemcomponentsoftheR/3installationwith regardtosystemconsistencyandreliability.Forthis,SAPexpertslogonyourR/3Systemviaaremote connection,inspecttheconfigurationofindividualsystemcomponents,andprovidevaluable recommendationsforsystemoptimization.Byanalyzingtheindividualsystemcomponentsbefore productionstartup,SAPcanconsiderablyimprovetheavailabilityandperformanceofthecustomer'slive

system.Inaddition,thetechnicalapplicationanalysisprovidesinformationonhowtospeedupthecore processeswithinR/3. Inthesecondstepofoptimizationthetransactionswithhighresourceconsumptionaresearchedforand necessaryadjustmentsmade.Inthethirdstepofverification,thechangesfromthetwopriorsessionsare validated.Thischeckisperformedintheproductiveoperationsystem. Afterasystemgoeslive,somefinetuningandeliminatingofpotentialbottlenecksisstillnecessary.This iscarriedoutfourweeksaftergoinglivewiththeR/3System.

Refining the Cutover


AttheendofPhase4,itisnecessarytorefineandvalidatethecutoverplansgeneratedintheRealization phase.Amongotherthings,thisincludestaskssuchasthereviewingoftheruntimeoftestrunsto estimateruntimeforthecompletedatasize.Aconversionchecklistfortransportingallchangesintothe productivesystemisprovidedforalltheconfigurationsettingstobeimported. Atthisstage,itisimportanttoverifythatrequiredtaskshavebeensuccessfullycompleted,forexample, thatthetechnicalenvironmentisinplace,thecutoverprogramsarereadyandtheapplicationdatais verified.Approvalisnowsoughtfromprojectmanagementandcompanyseniormanagementtostartthe cutoverprocess. HereyoucanalsorefertotheDataTransferMadeEasyGuidebookcreatedespeciallyforthispurpose.Itis locatedintheKnowledgeCorneroftheASAPCD. Thehelpdeskisparticularlyimportantinthefirstweeksaftergoinglive,butyouwillrequirehelpdesk supportthroughouttheproductivelifeofyourR/3System.Aninternalhelpdeskshouldbestaffedand supportedmainlybyemployeesoftheenterprise.Settingupahelpdeskinvolves,amongotherthings, installingofficeandtechnicalequipmentanddefiningOSSusers.Problemswhichcannotbesolvedby thisinternalhelpdeskareforwardedtoSAPviatheOSSsystem. AssoonasyouknowwhenyouwillgolivewiththeR/3SystemorwithnewR/3applicationsyou shouldinformSAP.ThusyoucanensurethatSAPcanprovideoptimalsupportthroughoutyourgoing livephase.Forthelastweeksbeforeandfirstweeksafterthegolivedate,SAPofferstheR/3 GoingLive CustomerCareService,accessibleviaSAPNetandOSS.