Sei sulla pagina 1di 21

NTPC

Summer training report


At National Thermal Power Corporation AURAIYA (DIBIYAPUR)

ELCTRICAL SYSTEM IN POWER PLANT


Submitted by:

NIVEDITA PANDEY
ELECTRICAL AND ELECTRONICS ENGG.

AJAY KUMAR GARG ENGINEERING COLLEGE GHAZIABAD

Acknowledgement
First of all, I would like to thank the company NTPC (National Thermal Power Corporation) for giving me an opportunity to work and get experience and to know how much knowledge and how much hard work an engineer has to do for keeping the job proper. I would like to thank Mr. S.K. SINGH for his constant support and guidance. He taught me how to see the theoretical fundamentals in practical and how to apply the principles that we studied in books. He made me familiar with the latest trends coming up in the engineering field.

At last, I would like to thank once more all the people who were guiding either directly or indirectly for this training to become more successful.

Nivedita Pandey Ajay Kumar garg engineering college gzb

Summer training report At National Thermal Power Corporation AURAIYA (DIBIYAPUR)

ELCTRICAL SYSTEM IN POWER PLANT

Submitted by: NIVEDITA PANDEY ELECTRICAL AND ELECTRONICS ENGG. AJAY KUMAR GARG ENGINEERING COLLEGE GHAZIABAD

INDEX
INTRODUCTION DEMINERALISING PLANT.

PROCESS OF TREATME PRE -TREATEMENT PLANT..

MAIN PLANT...

COMBINED CYCLE TECHNOLGY.. BASIC PARTS OF POWER PLANT

DESCRIPTION OF ELECTRICAL EQUIPMENT/ SYSTEMS SWITCH YARD SINGLE LINE DIAGRAM..

INTRODUCTION
The reserves of natural gas in large quantity in the western off- shore region has influenced the government towards utilization of it for power generation. Earlier, gas use was restricted to fertilizer, petro-chemicals & extraction of LPG.It was found that amount of gas available for power generation, after meeting the gas requirements of fertilizer plant, could sustain power plants of 1000-1500 MW capacity in a combined cycle mode of operation. For high efficiency and early availability of power, the combined cycle has been preferred over conventional steam power plant cycle. Initially, NTPC was entrusted with the responsibility of setting up & operating three Gas Projects with an aggregate capacity 1610 MW. These projects are located at Auraiya near Etawah in Uttar Pradesh, Anta near Kota in Rajasthan & Kawas near Surat in Gujarat. The approval of Govt. of India for these projects was obtained in the month of October 86. The gross installed capacity of the Auraiya project is 663.36 MW. Award for the main plant package was placed On M/S Mitsubishi Heavy Industries of Japan. AuGPP has two combined cycle module each consisting of two gas turbines, two waste heat recovery boilers and one steam turbine. The capacity of each gas turbine and steam turbine is: Gas Turbine: 111.76MW (Each _Model MW. 701D Steam Turbine: 110.00 MW (each Model TC2F-28). Total capacity of each Module: 326MW The gas turbines at AuGPP are open cycle, single shaft, heavy duty, industrial type consisting of 19 stage axial flow compressor. 4 stage axial flow reaction type gas turbine (Model MW 701D) were manufactured by Mitsubishi Heavy Industries of Japan. Atmospheric air is drawn through the inlet manifold and inlet casing into the compressor where it is pressurized and forced into combustion chamber. Fuel delivered into the combustors, is burned which raises the temperature of the mixture of air and combustion products to around 1150 C. The compressed and heated mixture (gas) flows through the turbine dropping in pressure and converted into mechanical work of rotation.

DEMINERALISING PLANT
PLANT CAPACITY & SALIENT FEATURES
The plant was designed to supply 55 m3/hr polished water. The potable Water is supplied to the power station and colony whereas the polished water is consumed in boilers to produce steam (for power generation).The plant comprises of two chains in demineralization and 3 pressure vessels for potable water production section. There is a clarified water tank common to both sections. From the clarified water tank, water is pumped by Pumps to potable water filters. After filtration, the water is supplied for use as potable water. From the same tank, water is fed to DM water pressure filters, active carbon filters, cation exchangers and degasser by means of clarified water pumps. After degasification, the water is pumped to weak base anion, strong base anion; and mixed bed exchangers units working in series. After achieving the designed quality, the polished water is stored in DM water tanks, from where it is drawn for use in waste heat recovery boilers. Small amount of polished water is used for internal consumption in DM water plant i.e., regeneration in DM plant.

PROCESS OF TREATMENT
The process of demineralization consists of the conversion of salts like NaCl, CaSO4, Ca(HCO3)2 etc. to their corresponding acids like HCI,H2SO4, H2CO3 by cation exchange resin (in hydrogen form) and removal of these acids by anion Exchange resin (in hydroxide form), thus removing all dissolved ionic impurities from water & converting water in pure form. Ion Exchange Resins : Ion Exchange resins used in DM water plants are synthetic organic compounds made by copolymerisation of various organic compounds. Most commonly used are Styrene & divinyl benzine (for the basic resin beds). Cation Exchange Process : Two types of cation exchange resins are mainly used in DM water plants, weak acidic and strong acidic. Selection of any of these resins depends upon the feed water quality and final water quality desired from the plant. In softening plants, cation exchange resin is used in sodium form whereas in DM water plants, it is used in hydrogen form.The main cations in water are Ca ++, Mg++ & K+, These are exchanged with mobile hydrogen ion of cation resin and is represented by the followingequations: 1. Weakly Acidic Cation Resin : a. RH + NaHCO3 _ RNa + H2CO3 b. 2RH + CaCO3 _ R2Ca + H2CO3 c. 2RH + Mg (HCO3)2 _ R2Mg + 2 H2CO3

2. Strongly Acidic Cation Resin : a. 2RH + Na2SO4 _ 2RNa + H2SO4 b. RH + NaHCO3 _ RNa + H2CO3 c. 2RH + CaSO4 _ R2Ca + H2SO4 d. 2RH + Mg (HCO3)2 _ R2Mg +2 H2CO3 e. 2RH + CaSiO3 _ R2Ca +2H2SiO3 Water from cation exchangers is sent to degasser where carbonic acid breakes into water & CO2. H2CO3 _ H2O + CO2 In this way, Carbonic acid load is reduced. When the resins (weak or strong acid) are exhausted as indicated by leakage of cations in the outlet water. These are regenerated by Hydrochloric acid or Sulphuric acid to bring back the resin in hydrogen form Mixed Bed Unit When the water is passed through cation exchange resin and then to strongly basic anion exchange resin, it removes most of the dissolved ions present in the water. In order to produce still pure treated water having conductivity less then or equal to 0.02 ppm, a mixed bed unit is used. A mixed bed consists of mixture of strongly acidic cation exchange resin and strongly basic anion exchange resin. Good treated water quality can be obtained from a mixed bed unit using relatively lower quantities of regenerants.

PRE -TREATEMENT PLANT


This plant has the capacity to produce 3000 m3/hr of clarified water to meet the total requirement of DM Plant and softening Plant. The various processes involved are as below: AERATION The raw water from reservoir is being pumped through 750 mm dia inlet pipe to the aerator. Cascade aerator is used to remove volatile impurities from raw water. The raw water is discharged at the top of the aerator through a concentric pipe and flows down wards in steps. By aeration, the water absorbs O 2 from atmosphere which helps in oxidation of organic matters. The iron dissolved in the water is precipitated as Fe2O3. COAGULATION From the aerator, water flows directly to the flash mixer through open cannel; where chlorine, lime and alum (Aluminum Sulphate) are dozed by the pumps and then flows through a RCC channel by gravity. FLOCCULATION & CLARIFICATION The chemically treated water is fed to the two Clariflocculators each have capacity of 1500 M3/hr. The clariflocculators are circular tanks of 40.8 me. in dia. The clariflocculation consists of two zones for removal of impurities. First, the flocculation zone (dia=2 me) where the microflocs with the help of slow speed-agitator and the second clarification zone for solid liquid separation.

MAIN PLANT
COMBINED CYCLE TECHNOLGY
For decades, gas turbines were extensively used for aeronautical applications, peaking purposes and black-start facilities. With the oil crisis in the mid 70s, the operation of gas turbines in the open cycle mode (efficiency as low as 20 to 25 percent) had become less attractive to the power generation utilities. Technological advancements made it economically viable to adopt higher firing temperatures for gas turbine of the heat with the help of the waste heat recovery boilers (WHRB). These WHRBs generate sufficient steam to develop 45 to 50 percent of the power developed by the gas turbine. As the result, average efficiency achieved by a combined cycle project has gone up to 13 percent by 1985, whereas the most efficient conventional fossil fuel power plant couldnt cross the bench-mark of 38 percent even with the supercritical parameters. With the result of the detailed optimization studies carried out by NTPC, it was possible to arrive at parameters for evolving such waste heat recovery boiler and steam turbine that would give an over all plant efficiency of as much as 48 percent, a fact not many utilities could claim.

Advantages over Conventional Plant


1. The higher efficiency of combined cycle, saves well over 35 percent of the premium fuel. 2. On the capital investment side also, it is important to note that investment for the combine cycle plant is only two-thirds that of a conventional plant. 3. The gestation period for the combined cycle plant is as much as 40 percent less than that of a conventional plant. 4. Dust free and clean environment. 5. Substantially reduced requirement for water, land and operating and maintenance personnel.

Basic parts of power plants


1. Gas turbine:
In the gas turbine, the power for driving both the compressor and the generator is produced. The energy is supplied to the turbine in the form of hot gases as they come from the combustion chamber. The kinetic energy of the gases is transferred to the rotor in the turbine by means of rotating blades. The combustion gases, come from the preceding stage, are accelerated in the stator blade while, simultaneously the inlet pressure is reduced by vectorial addition with circumferential speed. The relative speed is obtained for starting the generator, there is a high torque requirement and therefore we used a starting unit for starting a gas turbine. Gas turbine starting unit consists of Pony motor, which provides starting torque to generator for rotation. There is a turning motor in starting unit, which provides lubrication of oil in the bearing. In this unit an oil tank is also present to provide oil. Here we use a pressure gauge for measurement of pressure. We use a pressure transmitter which transmits a current signal.The GT starting unit is joined to generator through a shaft. This generator is joined to a gas turbine which is joined to combustion chamber. This gas turbine exhaust has temperature from range 500 to 550 degrees Celsius. This exhaust is used for generation of steam for steam turbine through Waste heat recovery boiler (WHRB). This gas turbine operates on Brayton cycle.

2. Steam turbine: There are 2 steam turbines in number, present in the full
AuGPP (Auraiya Gas power project). The two waste heat recovery boilers combined their output to one turbine. The turbine gets its feed from two drums. These drums are low pressure (LP) and high pressure (HP) drums. The low pressure drums give its output directly to the turbine but the HP drums give its output to the supper heater and then to the turbine. In this way, steam turbine consists of two turbines. These are as followsa) Low pressure (LP) b) High pressure (HP)

The low pressure turbine also gets the raw material from the HP exhaust. The left out steam in the LP steam turbine goes to the condenser and then again to the drums. The numbers of stages that are present in the high pressure (HP) turbine are total 12 in number and that in the LP turbine are 6*2 stages. This low pressure turbine is directly connected to the generator. The steam turbine operates on Rankine cycle.

3. Fuels: In the plant, mainly two fuels are used. They are as follows:
a) Natural gas b) Naphtha Dual fuel systems are commonly used enabling the gas turbine to burn back up fuels. When the primary fuel source is not available, dual fuel systems can be used fire both fuels simultaneously.

4. Heat exchanger: It is a device in which heat is transferred between two


moving fluids. Heat exchanger may be parallel flow. Counter flow or cross flow, depending upon the direction of the motion of the two fluids. If both fluids move in the same direction, it is parallel flow heat exchanger and if fluids move in the opposite direction, it is a counter flow heat exchanger. If they flow normal to each other, it is a cross flow heat exchanger.

5. Compressor:

In the gas power plants, the main function of the compressor is to increase the pressure of the air and its temperature is also increased in the compressor room, first of all there is a silicon tank which is used for absconding the moisture contents of air and then this air is compressed and sent to the combustion chamber for the combustion.

6. Combustor: In the combustor chamber, combustion takes place between


fuel and compressed air from compression room. The combustion is a chemical reaction between a fuel and oxygen, which proceeds at the fast rates with the release of energy in the room of the heat. The temperature of the combustor chamber is usually 1100 degree Celsius. This temperature heat energy is sending to the turbine. thermocouples in the combustor chamber are used for the measurement of the temperature.

7. Condenser: The exhaust steam of the steam turbine condenses into water
in the condenser where cooling water circulates. After heat reflecting from the condenser chamber, this water is sent to the pump. A condenser could be a reversible constant pressure heat rejection.

8. Filters: For combustion process in the combustion, there is requirement of


oxygen. We take oxygen from atmosphere as air in the atmosphere contains impure particles (dust particles). Therefore we use a filter, for removal of dust particles from the atmosphere air and to get pure oxygen for combustion in the combustor chamber.

9. Generator:
a) Stator

In gas power plant, generators are used for generation of electricity. Basically generator has two parts: b) Rotor

Stator is the stationary part of the generator on which field winding is present. Rotor is the rotating part of the generator on which armature winding is present. When the rotor rotates, the flux linked with the conductors changes. Therefore EMF is induced based on the principle of Faradays laws. In gas power plant, total six generators are used (one for each turbine).

10. Valves: In gas power plant, valves are used to control the flow. 11. Pump:
After heat rejection, in the condenser the water is sent to the pump. For the pump, the ideal process would be reversible adiabatic compression of this liquid ending at the initial pressure (increase its pressure). In the gas power plant, there is centrifugal type pump. In this type of pump, inlet and outlet are connected to the peripheral of the pump. After pumping, outlet water is sent to the boiler.

12. Pipe: In gas power plant, there are different colours of pipe for easy
detection: a) Sky blue shows air pipe b) Yellow shows gas pipe c) Green shows water pipe d) Brown shows naphtha or fuel pipe

DESCRIPTION OF ELECTRICAL EQUIPMENT/ SYSTEMS


GENERAL
The Auraiya gas combine cycle power station has four gas turbines generating units and two steam turbine generating units. Each gas turbine generating unit can be operated independently on open cycle mode. In Auraiya project, there are two combined cycle modules, each module having two gas turbine units, two waste heat recovery boilers and one steam turbine unit. Each generator output is connected to generator transformer (235/11.5 kV) by isolated phase bus duct. HV side of generator transformer is connected to 220 kV open type switchyard by overhead line. GENERATOR SYSTEM

Generator
The generator is of hydrogen cooled (rated hydrogen pressure=2 Kg/cm 2) 3000 rpm, 50 Hz with static excitation system. The rated output of gas turbine generator is 141.08 MVA (at cooling water temperature 32 0 C) at power factor 0.8 with rated terminal voltage 11.5kV. The insulation of stator winding is of Class F (type of insulation: impregnated epoxy resin mica). The impulse voltage strength is 115 LVP.The insulation of rotor winding is of class F (type of insulation: impregnated epoxy resin mica).

Excitation System
Static excitation system (MEC-3400) is adopted for both gas turbine generator and steam turbine generator. Basically, the excitation system consists of the following cubicles: a) AVR cubicle (with Power System Stabilizer PSS) b) Thyristor cubicle. c) Surge absorber cubicle. d) Field breaker cubicle. The power for initial excitation of the generator is obtained from the station 220 V DC system.Under normal operation, the power source of the excitation system is from the associated excitation transformer, which is of dry type (natural aircooling) 11.5 kV/360 V star/delta connected and nominal output capacity 1200 kVA. The excitation transformer is protected by duplicated instantaneous and inverse time over current relays. The excitation system and PSS can be controlled and monitored from the electrical control board (ECB) in the central control room. The neutral point of the generator is earthed through

grounding transformer. Grounding resistor is connected at the secondary side of the grounding transformer. The grounding transformer is of single phase. The generator neutral grounding cubicle is rated at 12 kV with lightening impulse withstand voltage 95 Kv.

Generator Main Circuit


Isolation phase busduct (IPB) is used to transmit power produced by the generator to the generator transformer excitation etc., which consists of the following buses: a) Main Bus Between the generator and generator transformer. The aluminum conductor is of circular shape. b) Tee-off Bus : Between main bus and PT & SA cubicle. The aluminum alloy conductor is in channel shape. c) Tee-off Bus : Between the main bus and excitation transformer cubicle. The aluminum alloy conductor is in channel shape. d) Neutral Bus : Between the generator and generator NGR cubicle. The aluminum alloy conductor is in channel shape.

Generator Transformer
The gas turbine generator transformers are supplied by MELCO, which are rated at 148 MVA (at 270 C), 235/11.5 kV (Yd11) and with OFAF. The transformer is of shell type. The short time rating of the transformer is 31.5 kA 3 second. Each transformer has an automatic TCG (Total Combustible Gas) analyzer, which takes oil sample automatically from the transformer tank at preset time interval. The combustible gas content of the oil sample is analyzed. If the gas content or the trend of gas content exceeds certain level, an alarm would be given to the control center. The transformer has two radiator banks (each bank has 50% cooling capacity). Each bank has: - 6x10% fans (1x10% as spare ) - 3x25% oil pump (1x25% as spare) Impact recorder was mounted on the tank during transportation.The steam turbine generator transformers are supplied by Crompton greaves limited. They are shell type transformers (Rating =144.19). Each transformer has 2 radiator banks.

Potential Transformer and surge Absorber Cubicle


Surge absorbers are provided to protect the generator from lightening. The lightening surges flow through the transmission lines to the generatort ransformer. A surge absorber consists of a surge capacitor and lightening arrester. a) Surge Capacitor - Type : Synthetic liquid filled - Rated : 11.5/ 3 kV - Rated capacity : 0.13 F b) Lightening Arrester - Type : Metal oxide type - Rated Voltage : 12 kV - Power frequency-starting voltage: 15 kV (crest) - Max. discharge Voltage for : 25.2 kV (crest) 1500A discharge current There are 3 potential transformers for generator protection and metering purpose.
a) Potential transformer for voltage balance relay and reverse power

relay (or low forward relay for steam turbine generator and performance test at ECB). Connection : Star/star Voltage : (11500/ 3) 110/ 3V Capacity : 100 VA
b) Potential transformer for various protection and metering purposes

Connection : Star/star/Open Delta Voltage : (11500/ 3)/ 3/)(190/3) V Capacity : 100 VA/ 200 VA
c) Potential transformer for AVR :

Connection : Star/Star Voltage : 11500/ 3)/110/ 3V Capacity : 200 VA

STATION TRANSFORMER
The auxiliary power of the power station is supplied by two 220/6.9 kV (starstar connection) 27 MVA ONAF station transformers. The capacity of each station transformer is sufficient for all auxiliaries of the power station operating at the same time. So switching out of one station transformer will not affect the normal operation of power station. The station transformer is equipped with on load tap changer at HV side with range 10% in 1% step. Station transformer is of core type. HV side of the transformer is connected to 220 kV switchyard by overheadline. LV side is connected to 6.6 kV switchgear through nonsegregated bus duct. Neutral point of HV side is solidly earthed. Neutral point of LV side is earthed through neutral grounding resister.

6.6 kV NON-SEGREGATED BUSDUCT


6.6 kV 3-phase 3-wire non-segregated bus duct for each station transformer is terminated at the respective 6.6 kV bus section. Continuous rating of the bus duct is 2510 A at 50 C ambient temp.Bare aluminum conductor is used.The busduct is installed with space heater which are controlled by thermostat to prevent condensation.

6.6 kV SWITCHBOARD:
The 6.6 kV switchboard is consisting of two bus sections connected by bus coupler, using SF6 gas circuit breakers. Each bus section is fed from one station transformer. Besides, the black start gas turbine generator feed to both 6.6 kV busbars through GCB. The capacity of black start gas turbine generator is sufficient for starting up one generator unit during black-out condition.The nominal SF6 gas pressure (at 20 C) of GCB is 2.5 kg/cm2. The 6.6 kV switchboard is equipped with auto-changeover facility. When an incomer trips, the bus coupler will close automatically so that one station transformer feeds both bus sections without affecting the normal operation of the power station. The switchboard feeds to following equipment. a) 6.6 kV/ 415 V auxiliary transformers at 415 V power centers. b) Township transformer c) 6.6 kV C.W switchgear at C.W Pump House. d) 6.6 kV auxiliary motors consisting of: --- Gas turbine starting motor (4 nos., 1450 kW) --- Gas turbine main fuel oil pump (4 nos., 210 kW) --- Waste heat recovery boiler HP feed water pump (6 nos., 720 kW) --- Station service 6.6 kV/415 V auxiliary transformer

6.6 kV C.W Switchgear consisting of the following: a) Two incomers (from main 6.6 kV switchboard) b) Bus coupler c) Two feeders to 6.6 kV/415 V auxiliary transformers (500 kVA) of CWP MCC d) Five feeders to motors (770 kW) of circulating water pump

6.6 kV/415 V AUXILIARY TRANSFORMER AT 415 V POWER CENTER


(i) The auxiliary transformer is of encapsulated dry type for indoor purpose, class F insulation and AN cooling. The winding of transformer is delta/star (6.6 kV/415 V) connected. The neutral point at LV side is solidly earthed. HV side is connected to 6.6 kV switch board by cable. LV side is terminated with 415 V busbar. Each transformer has a winding temp. indicator and with the contacts for alarm and tripping. (ii) 6.6 kV/415 V station service transformers are of oil cooled outdoor type, class F insulation and having ON AN cooling.

415 V POWER CENTERS


The power centers are segregated on the basis of generating units and combined cycle modules. Basically, each power center has two bus sections. Each bus section is fed from one 6.6 kV/ 415 V encapsulated type auxiliary transformer. However, the rated capacity of each auxiliary transformer is adequate for the load requirement of both bus-sections. To improve the reliability of power center, the two auxiliary transformers of power center are fed from either bus section of 6.6 kV switch-board. Each power center has two incomer, a bus coupler and outgoing feeders to MCC and motors etc. 415 V air circuit breakers are used. Altogether there are six 415 V power centers. a) GT 415V Switch-gear 1 The continuous rating of bus-bar is 2100 A. This power center feeds to: i) 1GT-MCC ii) 2GT-MCC iii) Cooling water circulating pump motors for GT 1 & 2 (110 kW) 2 for each unit. b) GT 415 V Switchgear 2 Same as GT 415 V Switchgear-1 but it supplies for gas turbine 3 and 4.

c) WHRB/STG 415 V Switchgear The bus-bar rating is 2800 A This power center feeds to: i) 1 WHRB-MCC ii) 2 WHRB-MCC iii) 3 WHRB MCC iv) 4 WHRB MCC v) 1 ST-MCC vi) 2 ST-MCC vii) Auxiliary oil pump motor for ST 1 and 2 (140 kw)-1 for each unit d) Block common 1 415 V Switchgear. The bus bar rating is 2800 A and the It feeds the auxiliaries of No.1 combined cycle module. f) Station common 415 V Switchgear. The bus bar rating is 3500 It supplies to auxiliaries common to the power station. i) HVAC. ii) 2 X motor driver spray pump (150 kW). iii) FO unloading pump house MCC. iv) Raw/fire water pump house MCC. v) Outdoor/Misc. lighting DBB. vi) Lighting distribution board for switch-yard. vii) Distribution board for 220 kV switchyard. viii) Power house lighting DBB. ix) Station common MCC. x) Uninterruptible power supply (UPS)

415 V MOTOR CONTROL CENTERS:


MCCs are grouped on the basis of generating units, combined cycle modules, common auxiliaries for power station and the special function served by them. The name and function of individual MCC is listed below: 1) 1GT-MCC (fed from GT-415 V Switchgear-1) 2) 2GT-MCC (fed from GT-415 V Switchgear-1) 3) 3GT-MCC (fed from GT-415 V Switchgear-2) 4) 4GT-MCC (fed from GT-415 V Switchgear-2) 5) 1ST-MCC (fed from WHRB/STG-415 V Switchgear) 6) 2ST-MCC (fed from WHRB/STG-415 V Switchgear) 7) 1WHRB-MCC (fed from WHRB/STG-415 V Switchgear) 8) 2WHRB-MCC (fed from WHRB/STG-415 V Switchgear) 9) 3WHRB-MCC (fed from WHRB/STG-415 V Switchgear) 10) 4WHRB-MCC (fed from WHRB/STG-415 V Switchgear) 11) BC1-MCC (fed from Block Common-1 415 V Switchgear) 12) BC2-MCC (fed from Block Common-2 415 V Switchgear) 13) OSC-MCC

415 V AC DISTRIBUTION BOARD


For other station auxiliaries (such as lighting, space heater, oil heater), the supply is fed from 415 V AC distribution boards. Those distribution boards are fed from their respective 415 V power centers.

BACK-UP POWER SUPPLY


Basically, the Auraiya station is equipped with 3 back-up power supply sources, namely: a) Black-start gas turbine generator b) 220 V DC power system c) 110 V AC uninterruptible power supply system a) Black-start Gas Turbine Generator The capacity of black start generator is sufficient to meet the requirement during the complete black out of the power station, the black start generator is adequate to supply all important auxiliaries sufficient to start up one unit. The two terminal outputs of the generator feed to either bus section of the 6,6 kV switchboard directly. b) 220 V DC Power System : The 220 V DC system is a complete duplicated system with two sets of 5000 AH 220 V lead acid battery and battery charger. Each DC distribution board has 2 bus-sections with 2 incomer isolators and one bus coupler (which are with key interlock 92 out of 3) to avoid paralleling of the duplicated battery/ battery charger sets. Under normal condition, the 220 V DC system will supply to: 1) Various control and protection panels. 2) Alarm annunciation panel. 3) Excitation panel. 4) Initial excitation of GTG/ STG. Under black-out condition, the 220 V DC system will also supply to following auxiliaries as well: The capacity of each battery set (5000 AH) is sufficient to supply all the emergency auxiliaries, control and protection for not less than 10 hrs. under black-out condition.To improve reliability, each protection panel is fed by 2 DC feeders. The main protection relays and auxiliary relays are split accordingly to the 2 DC supplies. The fault breaking capacity of MCCB (220 V DC) is 40 kA. 220 V DC system is grounded through earth fault relay c) Uninterruptible Power Supply The ups system provides reliable and stable110 V 1-phase, 2-wire, 50 Hz power supply to important control/ microprocessor based equipment (which are sensitive to fluctuating electrical power supply from the grid). Basically, the system consists of the following with 100% redundant static charger and inverter. 1) Two rectifiers/chargers

2) One lead acid storage battery (9120 cells, 1000 AH) 3) Two inverters (90kVA) 4) One AC voltage regulator 5) Static transfer switch

6.6 kV AUXILIARY MOTOR AND 415 V AUXILIARY MOTORS


Motors with rating over 200 kW are fed directly from 6.6 kV switch-board, namely 1) Gas turbine starting motor (1450 kW) 2) Gas Turbine main fuel oil pump (210 kW) 3) Waste Heat Recovery Boiler HP feed water pump (720 kW) 4) Circulating water pump (770 kW) 6.6 kV auxiliary motors are with class F insulation and enclosure to IP54 PUBLIC ADDRESS SYSTEM PAS is composed of hand-set stations, loudspeakers and cable branching boxes.

13 ELECTRICAL CONTROL BOARD


The electrical control board is for remote control/supervision of major electrical equipment, and with the following devices/ equipment. a) Mimic diagram for the complete electrical system, from 220 kV to 415 V Power centers. b) Indication for electrical parameters c) Alarm annunciations d) Remote control of static excitation system e) Close/open of field circuit breaker
24

f) Governor control for GTG/STG g) Load limit control for GTG/STG h) Manual check sync. facilities i) Control of 220 kV GCB, 6.6 kV GCB and 415 V ACB for incomer/ bus coupler of power centers. j) Control of 220 kV bus bar isolators and line isolators k) Control of on load tap changer for station transformer l) Voltage regulation for black-start gas turbine generator m) Governor control for black start GTG

Switchyard

It is a medium for exchange of power from source to load or from one source to another. It consists of switching equipment, measurement, protection and control equipment required for power generation and utilization Components - Circuit breaker (CB) - Isolator - Earth Switch - Current Transformers (CT) - Capacitive Voltage Transformers (CVT) - Lightening Arrester (LA) - WAVE TRAP - Potential Transformers (PT) - Line matching unit (LMU) - Lightening Mast (LA)

Potrebbero piacerti anche