PERT-CPM Two Storey Residential Building

ITEM OF ACTIVITIES( Months ) WORK ACTIVITIES ( Weeks) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Excavation Foundation Footing Tie Beam Column Floor Slab ( 2nd Floor ) Column/Wall layering Roof Beam Steel Trusses Plastering/Moulding Roofing Ceiling Floor Tiling Plumbing Electrical Painting

1 2 3 4 5 6 7 8 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

Prepared by: GUALBERTO D. BALLANO C.E. 038541