Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
(CL01) ITEM Soil investigation The contractor shall implemented of exploratory drilling and mechanical test in all types of soil with on site testing and the issuance of the final report which contain the test results and recommendations of the foundation work. 01 Research and treatment for cavities Implementation through a perforating exploratory(cavity probing) In all types of rock to determined the horizontal and vertical elongation of cavities, the contractor will be responsible for treatment all cavities By injection and treatment for all cavities and voids of rock with all necessary work accordance with the technical specifications and instructions of the Supervising engineer SITE DEVELOPMENT The bidder is advised to visit the site before quoting the rates in order to get himself familiarized with the present site conditions Site clearance and demolitions 02 Demolish and clear away existing structures, pavings, electrical lighting, pavements or upstands, cut and plug or reroute existing service lines or utilities inside property line, clear site of rubbish or any impediments, loose top soil and as deemed necessary, for the total site cluster number 4 (CL04) area, approximately (22650m ), subject to engineer approval and as coordinated with public pension agency as shown on drawing CL04- XC-01 SITE DEVELOPMENT SITE GRADING Bulk excavate over site on unclassified ground including all hard and rock layers to reduced levels generally in cutting profiles the work shall include clear away to approved disposals. All additional excavation required for temporary works and spaces, shoring, dewatering, removal of surplus excavated materials, support, temporary spoil heaps and general compaction EXCAVATION AND EARTHWORK Necessary moving or transportation about the site excavation material including handling to temporary stockpile or ultimate disposal off site is to be included in the unit rate of excavation To Collection SR Note
2
DESCRIPTION
QTY
UNIT
RATE
AMOUNT SR
Note
M3
Item
Note
1 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION SITE PREPARATION AND GRADING 01 Excavation oversite on unclassified ground including all hard and rock layers (if any) to reduced levels generally in cutting profiles and forming depressions, falls and the like and clear away to approved disposal tip. Fill oversite with approved imported fill material according to site soil report recommendation including compaction in making up levels to required formations, embankments, contouring and the like as per drawings and spec. Note Work on proposed structural built-up areas from part of the Work pertaining to respective building or structure as measured elsewhere. QTY UNIT RATE AMOUNT SR
6300
M3
02
23275
M3
To Collection
SR
2 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION PAVING AND SURFACING 01 Supply and install precast concrete shotblasted pavers with photocatolytic titamium dioxide coating (beige color) size 400x400x60mm thk. including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, moisture barrier on compacted subgrade as per detail no. A1 on drawing CL01-XL301 Supply and install precast concrete shotblasted pavers with photocatolytic titamium dioxide coating (beige and light beige colors) size 400x400x60mm thk. including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, moisture barrier on compacted subgrade as per detail no.A2 on drawing CL01-XL301 Supply and install precast concrete shotblasted pavers with photocatolytic titamium dioxide coating (beige and brown colors) size 400x400x60mm thk. including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, on compacted subgrade as per detail no.A8 on drawing CL01-XL301 Supply and install precast concrete shotblasted pavers with photocatolytic titamium dioxide coating (grey and light grey colors) size 400x400x60mm thk. including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, on compacted subgrade as per detail no.A9 on drawing CL01-XL301 Supply and install precast concrete shotblasted pavers with photocatolytic titamium dioxide coating (beige, grey and brown colors) size 400x400x60mm thk. including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed on compacted subgrade as per detail no.A9 on drawing CL01-XL301 Supply and install precast concrete shotblasted pavers with photocatolytic titamium dioxide coating ( beige and light beige colors) size 400x400x60mm thk. with granite band ( grey color) size 200x200x30mm including 100mm thick cast-in-place concrete slab with A193-WWF reinforcement mesh, 20mm thick cement mortar setting bed, on compacted subgrade as per detail no. B3 on drawing CL10-XL301 To Collection QTY UNIT RATE AMOUNT SR
3900
M2
02
270
M2
03
690
M2
04
1400
M2
04
450
M2
05
3250
M2
SR
3 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION PAVING AND SURFACING 01 Supply and install polished granite pavers grey and dark grey color size 400x400x30mm including 20mm thick setting mortar bed, 100mm thick cast in place concrete base with A193WWF reinforcement mesh moisture barrier on compacted subgrad as per detail no. C4 on drawing CL01-XL301 Supply and install cast in place concrete with brick band 60mm thick including A193WWF mesh reinforcement, setting mortar bed for brick, moisture barrier, compacted subgrade as per detail no. D5 on drawing CL01-XL301 Supply and install rubber pavement 50mm thick with various colors, including adhesive mixture, cast in place concrete base with A193 W.W.F. reinforcement mesh , moisture barrier on compacted subgrade as per detail no. E6 on drawing CL01-XL-301 Supply and install timber decking 25 mm thick including adhesive mixture, smooth finished cast in place concrete base with A193 W.W.F. reinforcement mesh , moisture barrier on compacted subgrade as per detail no.F7 on drawing CL01-XL-301 Supply and install polished granite paving (light and dark colors)) size 400x400x30mm with granite band (dark color) size 200x200x30mm including 20mm thick setting mortar bed, cast in place concrete base with A193WWF reinforcement mesh, moisture barrier, on compacted subgrade as per detail no. H11 on drawing CL01-XL-301 Supply and install concrete screed with epoxy coat finish on 100mm thick cast In place concrete base with A193WWF reinforcement mesh, moisture barrier on compacted subgrade as per detail no. G on drawing CL01-XL-301 CURBS AND EDGING 07 Supply and install Precast concrete curb, size 300X500X150 mm with exposed aggregate finish including bedding, haunching, cast in place concrete base and concrete grout behind curb, 20mm thick cement mortar setting bed, on compacted subgrade, as per detail no.1 on drawing CL01-XL302 QTY UNIT RATE AMOUNT SR
120
M2
02
1160
M2
03
600
M2
04
420
M2
05
420
M2
06
15370
M2
1685
To Collection
SR
4 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION PAVING AND SURFACING CAST IRON TREE/PALM GRID 01 Supply anf formation of cast iron tree/palm pit surround including cast iron grate , 200x100x60 mm concrete edge pavers, cement mortar setting bed and all required to complete and finish the work as shown on detail no.2 on drawingCL01-XL302 WATER FEATURES Water fountain comprising reinforced concrete wall and base, 25x25 cm ceramic mosaic tiles dark and light blue color as per pattern for side wall and floor tiles finish, cement mortar setting bed, coping, water proofing & mositure barrier, subgrade compaction, fountain kit, supply and drainage pipework, fountain pump, electrical power and lighting, installation, ventilation and exhaust system and all associated works including builder's work and service installation as per deatil no.3 on drawing CL01- XL302 02 Water fountain, overall area 96 m2 area on plan, shape as shown on drawing CL10-XL101. Raised Planter Supply and install concrete raised planter with granite cladding brown color , including soil mix, drainage layer, filter , membrane, sealant , waterproofing membrane, protection board,and all required to complete and finish the work as per detail no. 5 on drawing CL01-Xl302 03 Raised planter, overall area 5 m2 on plan to suit required locations as shown on drawing CL01- XL101 TENT STRUCTURE 04 Supply and install tent staructure comprising columns, tent fabric, foundation, earthwork, and all required to complete and fix the work as per manufacturer's recommendations and subject to engineer's approoval to cover an area of 305 m2 as per detail no. 8 on drawing CL01-XL-302. Contractor shall submitt shop drawings for approval before supply QTY UNIT RATE AMOUNT SR
13
No.
Item
Item
No.
To Collection
SR
5 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION PAVING AND SURFACING EARTH MOUNT 01 Supply and formation of 500-1500 mm height earth mount including compacted sub base layer, 100 mmm thick layer of sand and gravel mix, and all required to complete and finish the work as shown on drawing CL01- XL101 and as per detail no. 11 on drawing CL01- Xl302 Softscape and planting soil mix are measured lsewhere WOODEN BENCH 02 comprising 50x75 mm interior wooden rails,comprising concrete walls, reinforced concrete slab with A 193 W.W.F reinforcement mesh smooth finished, (Softscape and planting soil mix are measured elsewhere), drainage layer, filter membrane, water proofing membrane, protection board, sealant and all required to complete and finish the work as per detail no.6 on drawing CL01- XL302 to suit required locations as shown on drawing CL01- XL101 and CL01-xl-304 215 HEIGHT FEATURE WALL AND WOODEN BENCH 03 Supply and install concrete raised planter with wooden bench, comprising 50x75 mm interior wooden rails,comprising concrete walls, reinforced concrete slab with A 193 W.W.F reinforcement mesh smooth finished, (Softscape and planting soil mix are measured elsewhere), drainage layer, filter membrane, water proofing membrane, protection board, sealant and all required to complete and finish the work as per detail no.7 on drawing CL01- XL302 to suit required locations as shown on drawing CL01- XL101and CL01-xl-304 RAISED CONCRETE PLANTER AND WOODEN BENCH 04 Supply and install concrete raised planter with granite cladding, and wooden bench, comprising 50x75 mm interior wooden rails,concrete walls, reinforced concrete slab with A 193 W.W.F reinforcement mesh smooth finished, (Softscape and planting soil mix are measured elsewhere), drainage layer, filter membrane, water proofing membrane, protection board, sealant and all required to compleet and finish the work as per detail no.9 on drawing CL01- XL302 to suit required locations as shown on drawing CL01- XL101 and CL01-xl-304 QTY UNIT RATE AMOUNT SR
Item Note
M2
60
M2
275
M2
To Collection
SR
6 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION PAVING AND SURFACING WOODEN BENCH STEPS SEATING 01 Supply and install concrete raised planter with wooden bench, comprising 50x75 mm interior wooden rails,comprising concrete walls, reinforced concrete slab with A 193 W.W.F reinforcement mesh smooth finished, (Softscape and planting soil mix are measured elsewhere), drainage layer, filter membrane, water proofing membrane, protection board, sealant and all required to complete and finish the work as per detail no.6 on drawing CL01- XL302 to suit required locations as shown on drawing CL01- XL101 and CL01-XL303 WOODEN SHADE STRUCTURE Supply and install wooden shade structure comprising concrete column size with polished granite cladding hibiscus pink color or approved equal, concrete beams size 200 x500 mm , louver abd louver frame size 50x150 mm and wooden rafter size 50x300 mm including concrete footings, earthworks, insulation, finishing, fixing, and all required to complete the work as per detail no.4 on drawing CL01-XL302 02 Wooden shade structure, approximate area 215 m2 on plan to suit required locations as shown on drawing CL01-XL101 ENTRANCE GATE Supply and install all required works for entrance gate comprisisng, concrete columns , watermist framing with stainless steel grade 316 including mist nozzles, and all required earthwork, concrete plumbing and mechanical works, as shown on drawings and according to water feature specialist drawings and specifications 03 Entrance gate with the required shape and color as per detail no. 13 on drawing CL01-XL302 and drawing no. CL01-XL304 1 No. 1 No. QTY UNIT RATE AMOUNT SR
120
M2
To Collection
SR
7 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM SITE SIGNAGE Manufacturer's standard outdoor sings, letters and plaques including fixings, finishes, accessories complete as detailed on drawing CL01-XC-09 to suit required locations as shown on drawing CL01-XC-07 and XC-08 and as per specifications REGULATORY SIGNS 01 Ref. type R5-1 ( ENTRY PROHIBTED ) INFORMATIVE SIGNS 02 03 Ref. type I-1 (PARKING) Ref. type I-2 (ENTRY ) Manufacturer's standard outdoor sings, letters and plaques including fixings, finishes, accessories complete as per details on drawing CL01-XL604 to suit required locations as shown on drawing CL01-XL601,602and 603 and as per specifications 04 05 06 07 08 09 10 11 12 13 14 15 RESIDENTIAL SIGN, as per detail (1) INFORMATION KIOSK SIGN, as per detail (2) DIRECTIONAL SIGN, as per detail (3) FLOOR DIRECTIONAL PANEL, as per detail (3) ADVERTISING PANEL, as per detail (5) SWIMMING POOL AREA SIGN, as per detail (6) COMMERCIALBUILDING SIGN, as per detail (7) COMMERCIALBUILDING PARKING SIGN, as per detail (8) CENTRAL PLAZA SIGN, as per detail (9) CENTRAL PLAZA PARKING SIGN, as per detail (10) SOUTH GATE SIGN, as per detail (11) EAST GATE SIGN, as per detail (12) To Collection DESCRIPTION QTY UNIT RATE AMOUNT SR
15
No.
5 12
No. No.
16 2 4 2 8 1 1 1 2 1 1 1
No. No. No. No. No. No. No. No. No. No. No. No.
SR
8 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION ROAD SIGNAGE & PAVEMENTMARKING Thermoplastic paint for traffic marking on drive way at basement/ground floor and ramps floor as per Manufacturer's standard as detailed on drawing CL01-XC-09, to suit required locations as shown on drawing CL01-XC-07 and CL01-XC-08, as per specification and as per engineer's instructions Pavement marking 01 02 03 03 04 05 06 White edge line, ref. detail (2) Lane marking, as per detail (3) Direction separation Line (Passing permitted), as per detail (4) Dotted line marking (Give way line), ref. detail (7) Through traffic arrow, ref. detail (9-1) Left turn arrow, ref. detail (9-3) Through and left arrow, ref. detail (9-5) QTY UNIT RATE AMOUNT SR
To Collection
SR
9 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM LANDSCAPING Palms including pit excavation, stakes and ties, soil planting mix, mulching, filter membrane and drainage layer all as details and planting schedule as per detail P1, on drawing CL01-XL-401 01 P/Wf Trees including pit excavation, stakes and ties, soil planting mix, mulching, filter membrane and drainage layer all as details and planting schedule as per detail P2 on drawing CL01-XL-401 02 03 04 05 04 05 06 T/Aa T/Af T/Fm T/Cl T/Po T/Tp T/Bv Shrubs including planting, site excavation as required, soil planting mix, mulching, filter membrane, screed sloped to drain and drainage layer all as per details and planting schedule as per detail P3,P5, on drawing CL02-XL-401 06 06 06 07 08 09 S/Ah S/Av S/Hs S/Iha S/lo S/Ld To Collection DESCRIPTION QTY UNIT RATE AMOUNT SR
24
No.
6 14 13 13 7 30 16
103 88 343 56 42 49
10 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM LANDSCAPING Shrubs including planting, site excavation as required, soil planting mix, mulching, filter membrane, screed sloped to drain and drainage layer all as per details and planting schedule as per detail P3,P5, on drawing CL02-XL-401 01 02 03 S/Ob S/Mc S/Ts Ground cover including planting, site excavation as required, soil planting mix, mulching, filter membrane, screed sloped to drain and drainage layer all as per details and planting schedule as per detail P3, on drawing CL01-XL-401 04 05 06 07 08 09 10 G/As G/Cgp G/Cm(O) G/Cm(R) G/Cm(Y) G/Cm(W) G/Rt Lawn planting, including soil planting mix, filter membrane and drainage layer, screed sloped to drain all as per details and planting schedule as per detail P4,P6 on drawing CL01-XL-401 11 L/Cd DESCRIPTION QTY UNIT RATE AMOUNT SR
110 322 10
2554
M2
To Collection
SR
11 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION PLUMBING INSTALLATION WASTE AND DRAINAGE INSTALLATION Supply, install and testing pipework, UPVC schedule 40, the work shall include but not limited to fittings, supports, cast iron pipes on roof for vent with caps, installation, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 01 02 03 04 50 mm dia. 75 mm dia. 100 mm dia. 150 mm dia. Construction work for briks inspection chamber, the work shall include bit not limited to earth work, plain concrete for foundation BED, concrete channel at chamber DED with standard cast iron manhole frame and double cover and all materials and equipments required to complete and finish the work according to specifications, drawings and code of practice 05 06 07 Inspection chamber, ref. (WIC) 600x600mm Inspection chamber, ref. (STIC) 600x600mm Inspection chamber, ref. (IC) 600x600mm Supply, installation and test drainage pipe work UPVC schedule 80 the work shall include but not limited to fittings, supports hangers, excavation, backfilling, cast iron pipes on roof for vent with caps and all materials and equipment required to complete and finish the work according to specifiactions, drawings and code of practice 08 09 10 50 mm dia 76 mm dia 100 mm dia 25 40 135 M M M 8 5 2 No No No 25 35 455 230 M M M M QTY UNIT RATE AMOUNT SR
To Collection
SR
12 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION Drainage installation to the external drainage network Construction work for briks inspection chamber, the work shall include bit not limited to earth work, plain concrete for foundation BED, concrete channel at chamber DED with standard cast iron manhole frame and double cover, UPVC pipework schedule 40 to nearest main sewer manhole and all materials and equipments required to complete and finish the work according to specifications, drawings and code of practice 01 02 Inspection chamber, ref. (IC) 600x600mm Slow down chamber 4 10 No No QTY UNIT RATE AMOUNT SR
To Collection
SR
13 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION MANHOLE AND COVERS Supply , install, testing and commissioning precast concrete sewer manholes with standard traffic (heavy duty) type cast iron manhole covers and frames, access ladders, concrete channel at manhole bed, foundation bed, drop pipe to manhole where required, all associated earthworks, damp proofing, and all materals, equipments required to complete and finish. the work according to specifications section 02605, 02730, drawings and code of practices 01 Sewer manhole, ref. (WIC) POTABLE WATER INSTALLATION Supply, install and testing pipework, UPVC Schedule 80 for potable water the work shall include but not limited to fittings, supports, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 02 03 04 32 mm dia. 05 mm dia. 100 mm dia. Reinforced concrete under ground water tank and pump room with proprietary cast iron manhole covers and frames the work shall include but not limited to earthworks, concrete works, sump pit, and submersible pump internal lining and water proofing, access ladders, pipework and valving, test main fold vent pipes, truck fill pipework with back flow preventer, ventilating fan and duct work within tank and pump room structure, and UPVC schedule 80 drainge pipe from submersible pump to the nearest sewer manhole and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 05 Potable water tank CAP 45 M3 1 No. 48 95 17 M M M 2 No. QTY UNIT RATE AMOUNT SR
To Collection
SR
14 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION POTABLE WATER SUPPLY SYSTEM Drainage installations Reinforced concrete gray water tank with proprietary medium duty cast iron manhole cover and frame, including sump pit, submersible pumps, internal lining, access ladder vent pipework within tank as detailed on drawing (Concrete work, earthwork & water proofing measured elsewhere) 01 Gray water tank CAP. 15 M3 1 Packaged type variable speed discharge pressure system Gray water lift pumps (one duty & one stand-by), including piping and valves network within pump chamber, complete with all controllers, accessories for automatic operation as scheduled on drawing as per spec. section 15453 02 Gray water lift pumps CAP. 3.7 KW Allow for the design, supply and installation of packaged type waste water treatment plant complete including filter, chemical feeders, air blowers controls, wirings, piping and all as associated works as per specifications section 02736 and scheduled on drawing 03 Packaged water treatment unit NON-POTABLE WATER INSTALLATION Supply, install and testing pipework, UPVC Schedule 80 for non-potable water the work shall include but not limited to valve boxes, fittings, supports, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification 04 05 06 07 40 mm dia. 50 mm dia. 63 mm dia. 75 mm dia. Accessories 08 Isolating & check valve assembly 100 mm dia. 3 No 60 50 6 15 M M M M 1 Item 1 Set No. QTY UNIT RATE AMOUNT SR
To Collection
SR
15 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION POTABLE WATER SUPPLY SYSTEM Supply, installation and test Packaged type constant pressure booster potable water pumps, set of one duty and one stand by pump, including piping and valving network within pump chamber, complete with all controllers, accessories for automatic operateion and all associate works as per code standard and as described on drawings and specification 01 02 Ref. PWP CAP 7.17 KW Ref. CP CAP 0.5 HP Accessories 03 04 05 06 Isolating & check valve assembly 50mm ida., Isolating & check valve assembly 75mm ida., Water meter assembly 50 mm dia., ref. WMA Back flow preventer assembly, 100mm dia., ref. BFPA FIRE WATER UTILITIES Supply, installation and test Pipework, UPVC class 5 including fittings, trenching, back fill supports system and all associate works as per code standard 07 150 mm dia. 10 M 1 1 2 2 No No No No 1 1 Set Set QTY UNIT RATE AMOUNT SR
To Collection
SR
16 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION IRRIGATION WATER INSTALLATION Supply, install and testing pipework, UPVC Schedule 80 for Irrigataion water the work shall include but not limited to fittings, supports, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 01 02 03 04 20 mm dia. 32 mm dia. 40 mm dia. 50 mm dia. Accessories 05 Supply and installation irrigation controller as detailed on drwings and as per specifications Supply and installation bubbler for trees Supply and install bubbler for shrubs, ground cover and succulents Supply and installation spray lawn sprinkler Gate valve W/valve box 20 mm dia., Gate valve W/valve box 32 mm dia., Gate valve W/valve box 40 mm dia., Gate valve W/valve box 50 mm dia., Supply and installation remote control valve assembly including piping complete with valve box, Y-strainer, accessories and all associated works as detail on drawing and as per specifications section 02810 13 14 15 16 Ref. RCV 20mm dia. Ref. RCV 32mm dia. Ref. RCV 40mm dia. Ref. RCV 50mm dia. 2 3 8 14 No. No. No. No. 1 No. 15 360 700 845 M M M M QTY UNIT RATE AMOUNT SR
06 07
200 1454
No. No.
08 09 10 11 12
71 1 1 14 13
To Collection
SR
17 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION SWIMMING POOL & PUMP ROOM including earthworks and reinforced concrete, finishings, water proofing, pipework, fittings, connection to grounding system, equipment and all associated works as detail A, drawing CL01-XP301 & detail 12, drawing CL01-XL302 lighting fixtures and necessary electrical works within swimming pool area (measured elsewhere) 01 Swimming pool no.1, 2 and pump room 1 Item QTY UNIT RATE AMOUNT SR
To Collection
SR
18 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM SITE DEVELOPMENT Collection Sheet -1 Sheet -2 Sheet -3 Sheet -4 Sheet -5 Sheet -6 Sheet -7 Sheet -8 Sheet -9 Sheet -10 Sheet -11 Sheet -12 Sheet -13 Sheet -14 Sheet -15 Sheet -16 Sheet -17 Sheet -18 DESCRIPTION QTY UNIT RATE AMOUNT SR
To Bill Summary
SR
19 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 2 - SITE WORK SITE GRADING All additional excavation required for temporary works and spaces, shoring, dewatering, removal of surplus excavated materials, support, temporary spoil heaps and general compaction EXCAVATION AND EARTHWORK Necessary moving or transportation about the site excavation material including handling to temporary stockpile or ultimate disposal off site is to be included in the unit rate of excavation Excavation in natural land consisting of solid rock formation, cracked rocks, bolders and natural contoured soil, temporary earthwork supports, dewatering ( if any ) as per specifications sections 02200 01 Excavation for foundations commencing from existing grade level Backfilling 02 Approved selected imported fill material including compaction in making up levels around and over foundations, beds and the like as per spec. sections 02200 Approved fill material selected from excavated material including compaction as per specification section 02200 Drainage layer 04 100 mm thick compacted coarse gravel to underside of slabs on grade as per specification section 02200 Soil treatment application for termite control 05 To subgrades of slabs and along periphery of building The work shall include all materials and equipments required to complete and finish the work according to specifications and code of practice Note QTY UNIT RATE AMOUNT SR
Note
183750
16600
03
price only
701
35265
To Collection
SR
20 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 2 - SITE WORK TRAFFIC MARKING DIMENSION Thermoplastic paint for traffic marking on parking pavement as detail 11 shown on drawing CL-GA-901 and specification 03 06 07 08 09 10 11 Straight arrows Parking lane marking Handicapped marking on floor ENTRY (text) NO ENTRY (text) EXIT (text) Lane numbers 169 No. QTY UNIT RATE AMOUNT SR
6330 37 4 9 3
685
SR
To Bill Summary
SR
21 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 3 - CONCRETE CONCRETE WORK CONCRETE TYPES Include in Unit Rates for concrete of the following types and locations: 20 Mpa a) Blinding concrete b) Catch basins and side walks 40 Mpa a) Footings b) Columns and R.C. walls c) Floor and roof slabs,stairs, beams, girders, stairs d) Concrete topping or structural screed e) Slab on grade f) water tanks QTY UNIT RATE AMOUNT SR
Note
To Collection
SR
22 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 3 - CONCRETE Plain insitu concrete, 20 Mpa, cement type V as per drawings and specifications section 03300 01 Supply and placing plain concrete under foundation. The work shall include soil compaction, concrete formwork, casting and curing for concrete and all required equipment and material for finish the work according to drawings and specifications, Supply and placing 50 mm thickc concrete screed including casting and curing and all requierd to complete the work Supply and placing Insitu reinforced concrete, 40 Mpa cement type V including formwork and steel reinforcements conforming to ASTMA615and A185 and all requiments to finish the work according to drawings as per specifications sections 03100, 03200 & 03300 , and code of practice in: 03 Raft foundation various thickening including formation depression areas, sump pits and elevators pits and electrical cables trench Retaining walls Slab on grade 125mm thick with A193 WWF mesh reinforcement including thicking where required QTY UNIT RATE AMOUNT SR
3100
02
2560
23300
04 05
2000 6
M M
To Collection
SR
23 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 3 - CONCRETE CONCRETE WORK Supply and placing of Insitu reinforced concrete, 40 Mpa type I cement including formwork and steel reinforcements conforming to ASTM A615 and A185 and all requirements to finish the work according to the drawings,as per specifications sections 03100, 03200 & 03300,and code of practice 01 02 03 04 05 06 07 08 09 10 11 Columns Reinforced concrete for tanks Shear wall Frame girder and column Beams Suspended flat slabs 220 mm thick including drop panels Suspended flat slabs 300 mm thick including drop panels Suspended flat slabs 320 mm thick including drop panels Suspended flat slabs 380 mm thick including drop panels Ramps Stairs including landings PRECAST CONCRETE Precast concrete wheel stopper including dowels, grouting and accessories for complete installation as per detail 21 on drawing CL-GA-901 and specification 12 Precast concrete wheel stopper including fixings QTY UNIT RATE AMOUNT SR
1310 1240
465 15 180 90 3950 2950 940 225 115
M M3
M3 M M M M M M M M
685
No.
To Collection
SR
24 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 3 - CONCRETE CONCRETE WORK Sundries 01 Allow for reinforced concrete equipment pads including upstand surrounds and anti-vibration accessories as required 150mm thick raised slabs, Handicapped`s ramps and curbs to suit required areas as per detail 10,14, 20 on drawing CL-GA-901 10 M QTY UNIT RATE AMOUNT SR
02
1275
SR
To Bill Summary
25 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 4 - MASONRY UNIT MASONRY Supply and fix concrete masonry blocks in courses with cement lime mortar including concrete lintels over openings , horizontal and vertical reinforcement, fixings, fillers, sealants and grout to complete the work according to specifications and drawings 01 02 03 200 mm thick wall, one hour fire rated Ditto, but one hour fire rated Ditto, but two hour fire rated QTY UNIT RATE AMOUNT SR
M M M
To Bill Summary
SR
26 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DIVISION 5 - METALS Steel cover as per details on drawings 01 02 03 To suit electrical cable trench Metal floor grill to suit basement`s ramps To suit sump pits as required dimensions at basement EXPANSION JOINT COVER Supply and install aluminium cover for expansion joints including, seals, fire barrier, stainless steel clip, gaskets and all required materials and equipments to complete and fix the work as shown on drawing CL-GA-902 and according to specifiactions, and code of practice 04 05 06 07 08 09 Floor to floor as per detail 1a Wall to wall as per detail 1b Ceiling to ceiling as per detail 1c Floor to wall as per detail 1d Wall to wall as per detail 1e wall to Ceiling as per detail 1h 3590 925 3200 270 605 1285 M M M M M M DESCRIPTION QTY UNIT RATE AMOUNT SR
95 49 16
M No
To Bill Summary
SR
27 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISON 6 - WOOD AND PLASTIC KITCHEN CABINETS Supply and install base and wall cabinets including doors, hardwares, shelves, decorations, and all required to complete, finish and fix the work as per detail no.7 on drawing CL-GA-601 and as per specifications 01 02 Ref. 01, wood base cabinet plastic laminated finish Ref. 02, wood wall cabinet plastic laminated finish 22 15 M M QTY UNIT RATE AMOUNT SR
To Bill Summary
SR
28 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 7 - THERMAL AND MOISTURE PROTECTION WATERPROOFING AND MOISTURE PROTECTION Membrane waterproofing 01 Supply and apply membrane waterproofing to "wet room" areas including upturn to abutting walls or upstands as per drawing CL-GA-601 to complete and finish the work according to specifiactions and code of practice MEMBRANE WATERPROOFING 02 Membrane waterproofing as per specifications to suit raft, tanks and retainig walls Protection board to suit raft, tanks and retainig walls VAPOUR BARRIER 04 Vapour barrier to underside of slabs, beds, and the like, specifications section 07100 705 M QTY UNIT RATE AMOUNT SR
87
75175
03
6115
M2
To Bill Summary
SR
29 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 8-DOORS AND WINDOWS DOOR SETS Supply and install all doors to suit masonry openings and approved samples including fixings, decorations, frames, architrave, hardwares and saddles and all required to complete and finish the work as detailed on drawing CL-GA-801 and according to specifications and code of practice TYPE A : 44mm thick panelled wood door 01 Type A1, single leaf door, size 800x2150mm TYPE B : 44mm thick painted hollow metal insulated door including door grill (where required) 02 03 04 05 Type B1, single leaf door, size 900x2150mm, 45 min. fire rated Type B3, single leaf door, size 800x2150mm Type B5, single leaf door, size 700x2150mm Type B6, double leaves door, leaf size 950x2150mm and 45 min. fire rated TYPE C: 44mm thk. fully louvered painted hollow metal door. motorized adjustable louvers panel working upon signal from fire alarm system for generator . 06 Type C1, double leaves door, leaf size 950x2400mm, 45 min. fire rated Type C2, double leaves door, leaf size 1050x2400mm, 45 min. fire rated TYPE D : 44mm thick painted hollow metal with 6 mm wired glass fixed vision panel 08 Type D2, single leaf door, leaf size 900x2150mm QTY UNIT RATE AMOUNT SR
Note
20
No.
17 1 10 13
10
No.
07
No.
No.
To Bill Summary
SR
30 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DIVISION 9 - FINISHES INTERNAL FINISHES Flooring including respective types of bounding materials, concrete screed sub-floor of required thickness, (if any) accessories for complete installations as per ID drawing and specification 01 02 03 Epoxy paint on cement screed. , ref. EC 600x600 ceramic floor tiles, ref.CR01 300x300 ceramic floor tiles, ref.CR02 Finishings : bases including sand-cement backing mortar and grout 04 100 mm high ceramic tiles base, ref. B03 Finishings : walls including metal angle beads and lathing at junctions of differing backgrounds 05 06 07 Cement plaster to suit walls Paint on cement plaster ,ref. W01 Ceramic wall tiles,ref. W03 Finishings : ceilings 08 09 Cement plaster to suit ceiling Paint on cement plaster, ref.C01 DESCRIPTION QTY UNIT RATE AMOUNT SR
M M M
460
M M M
32100 32100
M M
To Collection
SR
31 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DIVISION 9 - FINISHES EXTERNAL FINISHES Finishing : walls including metal angle beads and lathing at junctions of differing backgrounds 01 02 Cement plaster to suit external surface External Paint on cement plaster to suit external surface DESCRIPTION QTY UNIT RATE AMOUNT SR
795 795
M2 M2
To Collection
SR
To Bill Summary
SR
32 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 10 -SPECIALTIES TOILET AND BATH ACCESSORIES Supply and installation of following toilet and bath accessories as per schedule including fixings and trims as shown on drawings and specification section 10800 to suit locations as required 01 02 03 04 Ref. FM2, Clear glass mirror 400x600 mm with stainless steel frame Ref. RH, single robe hook Ref. SDH, wall mounted soap dish and holder Ref. TPH, Toilet paper holder CORNER AND COLUMN GUARD Supply and install rubber column guard including all required to fix the work as per detail no.18 shown on drawing CL-GA-901 and according to specifications 05 To suit required locations st basement and ground floor ALUMINUM LOUVERS SCREEN Supply and install fixed anodized aluminum sand trap louvers panels on anodized aluminum frames including finishes and all associated works to complete and fix the works as per details on drawing CL-GA-802 and specification 06 07 08 09 10 11 12 Ref. L03, size 3200x2500mm to suit required locations Ref. L04, size 3400x2500mm to suit required locations Ref. L05, size 1500x2500mm to suit required locations Ref. L06, size 2300x2500mm to suit required locations Ref. L8, size 400x700mm to suit required locations Ref. L9, size 5000x2500mm to suit required locations Ref. L10, size 1500x1500mm to suit required locations 2 6 2 1 7 1 1 No No No No No No No QTY UNIT RATE AMOUNT SR
11 22 11 11
1513
No
To Bill Summary
33 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 11 -EQUIPMENT TEA ROOM EQUIPMENT Supply and install the following equipment including necessary fixings and services connections required as shown on drawings and all required materials and equipments to complete and finish the works according to specifications section 11400 and code of practice 01 02 Ref. (07), upright refrigarator/freezer Ref. (14), washing machine SIGNAGE Manufacturer's standard indoor signs, letters and plaques including fixings, finishes, accessories complete as per interior design drawings CL01-i901 to CL01-i918 and all required materials and equipments to complete and finish the works according to specifications, drawings and code of practice 03 04 05 06 07 08 09 10 11 Ref. type S01 Ref. type S02 Ref. type S06 Ref. type S07 Ref. type S09 Ref. type S10 Ref. type S11 Ref. type S12 Ref. type S13 231 156 4 19 11 226 24 30 3 No No No No No No No No No 6 6 No No QTY UNIT RATE AMOUNT SR
To Bill Summary
SR
34 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 14 - CONVEYING SYSTEMS AUTOMATED WASTE COLLECTION SYSTEM Supply and provide all required to construct, test and operate automated waste collection system, consisting of the following items:01 Discharge valve room with basement floor including all required works as detailed on drawing no. STM - ITCCP2 - TD - 008. Contractor shall perform all required coordination with other trade to ensure proper installation and operation of the complete system to transport waste from tower chute to pipe networks as shown on drawings STM ITCCP2 - TD - 001 to 007 and 015, 016 and according to manufacturer's standards and specifications Outdoor Load station. including required earthworks, concrete works, masonry and electromechanical works for the vacuum room and PAI service box and all required works as detailed on drawing no. STM ITCCP2 - TD -013 and 014 Contractor shall perform all required coordination with other trades to ensure proper installation and operation of the complete system to transport waste from villas and playgrounds to pipenetworks as shown on drawings STM - ITCCP2 TD - 001 to 007 and 015, 016 and according to manufacturer's standards and specifications Full Vacuum Load station including required earthworks, concrete works, masonry and electromechanical works for the vacuum room and PAI service box located at the end of pipe work including all required works as detailed on drawing no. STM - ITCCP2 - TD - 010 and 011. Contractor shall perform all required coordination with other trade to ensure proper installation and operation of the complete system to transport waste kitchen areas to pipenetworks as shown on drawings STM - ITCCP2 - TD - 001 to 007 and according to manufacturer's standards and specifications PIPE WORK Supply and installation of Automated waste collection system piping. Item shall include the earth works, insulation, ,concentric reducer, puddle flanges ,inspection covers and all required materials and equipments to complete the transport pipe line from DV rooms , outdoor load stations and full vacuum load stations to waste plant 04 508mm under/above ground transport pipe 1425 M 14 No. QTY UNIT RATE AMOUNT SR
02
No.
03
No.
To Collection
SR
35 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 14 - CONVEYING SYSTEMS RC MANHOLE Supply and install cast insitu or precast reinforced concrete manhole ,the item shall include excavation, backfill insulation ,inspection cover, steel rungs and all required to complete the work. 01 RC manhole to suit required location in sitesas shown on drawings STM - ITCCP2 - TD 001 to 016 QTY UNIT RATE AMOUNT SR
40
No.
To Collection
SR
To Bill Summary
SR
36 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS SANITARY FIXTURES Supply and install sanitary fixtures, water mixers and accessories, as selection schedule, the work shall include but not limited to necessary fittings, trims, valves, traps, spouts and all materials and equipment required to complete and finish the work according to specifiactions, drawings and code of practice 01 02 03 Floor mounted water closet with flush tank, ref. (WC) Lavatory without pedistal, ref. LAV Counter top one bowel sink, ref. 03 19 19 10 No No No QTY UNIT RATE AMOUNT SR
To Collection
SR
37 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS WASTE AND DRAINAGE INSTALLATION Supply, installation and test drainage pipe work UPVC schedule 40 the work shall include but not limited to fittings, supports hangers, excavation, backfilling, cast iron pipes on roof for vent with caps and all materials and equipment required to complete and finish the work according to specifiactions, drawings and code of practice 01 02 03 04 05 06 32 mm dia 40 mm dia 50 mm dia 75 mm dia 100 mm dia 150 mm dia Supply, installation and test drainage pipe work UPVC schedule 80 the work shall include but not limited to fittings, supports hangers, excavation, backfilling, cast iron pipes on roof for vent with caps and all materials and equipment required to complete and finish the work according to specifiactions, drawings and code of practice 07 100 mm dia Accessories 08 09 10 11 12 Area drain 100mm dia., ref. AD Floor drain, 50 mm dia., ref. (FD) Parking drain, 150mm dia., ref. PD Cleanout, 50 mm dia., ref. (CO) Cleanout, 75 mm dia., ref. (CO) 3 75 101 13 139 No. No. No. No. No. 450 M 480 190 820 1715 2960 3090 M M M M M M QTY UNIT RATE AMOUNT SR
To Collection
SR
38 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS WASTE AND DRAINAGE INSTALLATION Accessories 01 02 03 04 05 06 07 08 Cleanout, 100 mm dia., ref. (CO) Cleanout, 150 mm dia., ref. (CO) Floor cleanout 50mm dia., ref. (FCO) Floor cleanout 100mm dia., ref. (FCO) Floor cleanout 150mm dia., ref. (FCO) Gully trap, ref. GT Trench drain outlet, 100mm dia., ref. TDO Running trap 32mm dai., Reinforced concrete sump pit including internal lining, proprietary galvanized steel manhole cover and frame, guide bar, lifting chain and all associated works, valves pipework within sump pit chamber as detailed on drawings (concrete work & earthwork, waterproofing measured elsewhere) 09 Sump pit Submersible pumps (one duty and one stand-by) including associated valves, pipework, valves controllers and accessories within sump pit chamber as described on drawings (sump pit measured separately) 10 11 Ref. SP1 capacity 1.5 HP Ref. SP2 capacity 2 HP 15 1 Set Set 16 No. 232 49 17 10 19 11 8 17 No. No. No. No. No. No. No. No. QTY UNIT RATE AMOUNT SR
To Collection
SR
39 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS POTABLE WATER INSTALLATION Allow for the design, supply and installation of packaged type waste water treatment plant complete including filter, chemical feeders, air blowers controls, wirings, piping and all as associated works as per specifications section 02736 and scheduled on drawing 01 02 03 Packaged water treatment unit. Cap. 31 m3/day Packaged water treatment unit. Cap. 38 m3/day Packaged water treatment unit. Cap. 47 m3/day 6 2 2 No. No. No. QTY UNIT RATE AMOUNT SR
To Collection
SR
40 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS POTABLE WATER INSTALLATION Supply, installation and test pipework, plypropylene for potable water the work shall include but not limited to installation, fittings, insulation for hot pipework, valves, supports and all materials and equipment required to complete and finish the work according to specifications, drawings and code of practice 01 02 03 04 05 06 07 15 mm dia. 20 mm dia. 25 mm dia. 50 mm dia. 63 mm dia. 75 mm dia. 100 mm dia. NON-POTABLE WATER INSTALLATION Supply, installation and test pipework, plypropylene for non-potable water the work shall include but not limited to installation, fittings, insulation for hot pipework, valves, supports and all materials and equipment required to complete and finish the work according to specifications, drawings and code of practice 08 09 10 11 12 20 mm dia. 50 mm dia. 63 mm dia. 75 mm dia. 100 mm dia. 80 1770 595 1015 485 M M M M M 225 1175 270 1320 475 150 670 M M M M M M M QTY UNIT RATE AMOUNT SR
To Collection
SR
41 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS HOT WATER INSTALLATION Supply, installation and test pipework, plypropylene for hot water the work shall include but not limited to installation, fittings, insulation for pipework, valves, supports and all materials and equipment required to complete and finish the work according to specifications, drawings and code of practice 01 02 15 mm dia. 20 mm dia. Accessories 03 04 05 06 07 08 09 10 11 12 13 14 15 Water meter assembly 63mm dia., Isolating valve 20 mm dia., ref. (IV) Isolating valve, 25 mm dia, ref. (IV) Isolating valve, 50 mm dia, ref. (IV) Isolating valve, 75 mm dia, ref. (IV) Isolating valve, 100 mm dia, ref. (IV) IV & CV assembly 50 mm dia., IV & CV assembly 63 mm dia., IV & CV assembly 75 mm dia., IV & CV assembly 100 mm dia., Hand spray with flexible hose and wall hook, ref. (HS) Wall mounted shower head with mixer, ref SH Hose bib 20mm dia., 19 20 19 50 38 1 11 2 4 11 19 19 52 No. No. No. No. No. No. No. No. No. No. No. No. No. 205 45 M M QTY UNIT RATE AMOUNT SR
To Collection
SR
42 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS Supply, install, testing and commissioning electrical water heaters the work shall include but not limited to short length pipework, valves, supports, controls, fixings, accessories and all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 01 Ref. EWH- 2 Drainage installations Reinforced concrete gray water tank with proprietary medium duty cast iron manhole cover and frame, including sump pit, submersible pumps, internal lining, access ladder vent pipework within tank as detailed on drawing (Concrete work, earthwork & water proofing measured elsewhere) 02 03 04 Gray water tank CAP. 31 m3 Gray water tank CAP. 38 m3 Gray water tank CAP. 47 m3 Packaged type variable speed discharge pressure system Gray water lift pumps, including piping and valves network within pump chamber, complete with all controllers, accessories for automatic operation as scheduled on drawing as per spec. section 15453 05 06 07 Gray water lift pumps CAP. 7 KW Gray water lift pumps CAP. 6 KW Gray water lift pumps CAP. 5 KW 6 2 2 Set Set Set 6 2 2 No No No 10 No QTY UNIT RATE AMOUNT SR
To Collection
SR
43 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS Packaged type duplex unit discharge pressure system potable water lift pumps, (one duty & one stand by) including piping and valves network within pump chamber, complete with all controllers, accessories for automatic operation as scheduled on drawing and specification section 15453 01 02 Potable water pump CAP. 7.17 KW Circulating potable water pump CAP. 0.5 HP Reinforced concrete under ground water tank and pump room with proprietary cast iron manhole covers and frames, including internal lining access ladders, pipework submersible pump, ventilating fans with exhaust and fresh air pipework, valves, vent pipes and truck fill pipework as detailed on drawings (concrete work & earthwork, water proofing measured elsewhere) 03 04 05 06 Potable Water tank CAP. 53 M3 Potable Water tank CAP. 105 M3 Potable Water tank CAP. 159 M Fire Water tank Supply, installation and test horizontal split case centrifugal fire pump, including piping network and valving within pump chamber,complete with all controllers, accessories for automatic operateion and all associate workks as per code standard and as scheduled on drawings and specification 07 08 Ref. FP1 CAP 75 KW electrically driven Ref. FP2 CAP 75 KW fuel diesel driven Supply, installation and test Electrically driven peripheral turbine Jockey pump, including piping network and valving within pump chamber, complete with all controllers, accessories for automatic operateion and all associate workks as per code standard and as scheduled on drawings and specification 09 Ref. JP CAP 5 KW To Collection 1 No SR 1 1 No No
3
QTY
UNIT
RATE
AMOUNT SR
10 10
Set Set
3 5 2 1
44 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL FIRE WATER UTILITIES Supply, installation and test Pipework, UPVC class 5 including fittings, trenching, back fill supports system and all associate works as per code standard 01 02 03 04 05 06 07 08 25 mm dia. 32 mm dia. 40 mm dia. 50 mm dia. 63 mm dia. 75 mm dia. 150 mm dia. 200 mm dia. Accessories 09 10 11 12 13 14 Pendent sprinkler head Upright sprinkler head Side wall sprinkler head 100mm Fire departement valve , ref. FDV Floor control valve assembly 150mm dia., ref. FCVA Fire department connection, 2 way fire department inlet connection type with gate and check valve 100mm dia. Fire department connection, 2 way fire department inlet connection type with gate and check valve 150mm dia. 244 2393 48 38 10 No No No No No 5455 1045 1830 745 85 20 1245 115 M M M M M M M M QTY UNIT RATE AMOUNT SR
No
15
No
To Collection
SR
45 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL FIRE WATER UTILITIES Supply, install, testing and commissioning proprietary integrated fire hose reel and fire extinguisher cabinet the work shall include but not limited to fire extinguisher, hose reel nozzle, fixings, isolating valve 40 mm dia., trims and all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 01 Ref. FHC Supply, install, testing and commissioning portable multipurpose fire extinguisher the work shall include but not limited to fixing to wall, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 02 03 Ref. PFE Ref. CO2 CO2 system Supply, install and test CO2 cylinders including pipe work, black steel seamless for CO2 fittings, supports valves, regulators, sleeves, as shown on drawings and as per specification 04 05 06 07 08 09 10 CO2 cylinders CAP 45 KG Control panel Remote manual release Abort switch Alarm bell 4-port nozzle Ioization detector To Collection 83 36 36 36 36 36 36 10 23 No No 41 No QTY UNIT RATE AMOUNT SR
46 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATION DIESEL FUEL STORAGE TANK INSTALLATION Allow for underground fiberglass diesel fuel storage tank with required capacity including concrete anti-flotation pad, heavy duty traffic type manhole ring and cover, pipework, valves duplex diesel fuel transfer pumps, steel ladder, pea gravel bed, earthworks, fixings and accessories all as detailed on drawings 01 02 03 Proprietary tank units CAP. 5675 Lit. Proprietary tank units CAP. 2800 Lit. Proprietary tank units CAP. 3800 Lit. 1 1 2 No. No. No. SR QTY UNIT RATE AMOUNT SR
To Collection Collection Sheet -37 Sheet -38 Sheet -39 Sheet -40 Sheet -41 Sheet -42 Sheet -43 Sheet -44 Sheet -45 Sheet -46 Sheet -47
To Bill Summary
SR
47 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS CHILLED WATER SYSTEM Supply, install and test black steel pipework including fittings thermal insulation, flexible connections and accessories as per required drawings and specification sections15050 to 15140 ,15510 01 02 03 04 05 06 07 08 09 10 11 12 15 mm dia. 20 mm dia. 25 mm dia. 32 mm dia. 40 mm dia. 50 mm dia. 100 mm dia. 150 mm dia. 200 mm dia. 300 mm dia. 400 mm dia. 450 mm dia. QTY UNIT RATE AMOUNT SR
M M M M M M M M M M M M
To Collection
SR
48 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS CHILLED WATER SYSTEM Supply and install valves / BTU meter Butterfly valve 01 Ref. MBFV 400 mm dia., Isolating valve 02 03 40mm dia., 32mm dia., Check valve 04 05 40mm dia., 32mm dia., BTU meters 06 07 40mm dia., 32mm dia., Supply and install heat exchanger including valves and short length piping as detailed on drawings and as per specifications 08 Ref. HEX-01 to 06, 2090 KW capacity QTY UNIT RATE AMOUNT SR
No.
12 26
No. No.
6 13
No. No.
6 13
No. No.
No.
To Collection
SR
49 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS CHILLED WATER SYSTEM Supply, install, test and commission, variable speed chilled water centrifugal inline pumps unit including valves, flexible connections, Y-striners, mounting and fixing to pads (measured separately) as detailed on drawing and specifications 01 Ref. SCWP-01 to 06, 55.4 L/S capacity 45 m TDH Supply, install and commission, expansion tank as detailed on drawings and specifications 02 Ref. ET, 1200 liter capacity Supply, install and commission, air separator tank as detailed on drawings and specifications 03 Ref. AS Supply, install, test and commission, chilled water Fan coil units ducted type including control valves, pressure & temperature, gauge, Y-strainer mounting and fixing as per drawings and specifications section 15781 04 05 06 07 08 09 Ref. FCU-02, 4.0 KW cooling capacity Ref. FCU-03, 2.4 KW cooling capacity Ref. FCU-04, 6.7 KW cooling capacity Ref. FCU-05, 5.1 KW cooling capacity Ref. FCU-06, 4.4 KW cooling capacity, Ref. FCU-07, 1.5 KW cooling capacity, Ref. FCU-08, 2.7 KW cooling capacity, Ref. FCU-09, 3.4 KW cooling capacity, To Collection QTY UNIT RATE AMOUNT SR
No.
No.
No.
6 11 2 6 11 3 15 4
50 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS Supply, install, test and commission, chilled water Fan coil units ducted type including control valves, pressure & temperature, gauge, Y-strainer mounting and fixing as per drawings and specifications section 15781 01 02 03 Ref. FCU-10, 1.5 KW cooling capacity Ref. FCU-11, 4.5 KW cooling capacity Ref. FCU-12, 17.1 KW cooling capacity Supply, install, test and commission DX-ducted split unit including control, pipes and fixing as per drawing and specifications 04 Ref. RAC-01, 3.51 KW nominal coollling capacity Supply, install, test and commission, DX-ducted split unit including control, pipes and fixing as per drawings and specifications section 15781 05 Ref. FCU-01/ACCU-01 , 4 KW capacity Supply, install, test and commission automatic chemical dosing unit as detailed on drawings and specifications 06 Ref. ACDU QTY UNIT RATE AMOUNT SR
24 6 2
18
No.
No.
No.
To Collection
SR
51 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS Supply, install, test and commission, Ventilating fans as details on drawings and specifications, section 15860 01 Ref. PEF- 01, 13500/22500 LPS capacity with exh. Duct and CAP. Ref. EF- 01, 50 LPS capacity Ref. EF- 02, 1600 LPS capacity Ref. EF- 03, 150 LPS capacity Ref. EF- 04, 125 LPS capacity Ref. EF- 05, 200 LPS capacity Ref. EF- 06, 85 LPS capacity Ref. EF- 07, 55 LPS capacity Ref. EF- 08, 30 LPS capacity Ref. EF- 09, 40 LPS capacity Ref. EF- 10, 30 LPS capacity Ref. EF- 11, 40 LPS capacity Ref. BIF-01, 3480 LPS capacity Supply, install, test and commission, Supply air round ceiling diffusers with opposed blade volume damper including frame trims & insulated plenum box as detailed on drawing and specification, section 15860 14 15 Ref. SD1 Ref. SD2 QTY UNIT RATE AMOUNT SR
10
No.
02 03 04 05 06 07 08 09 10 11 12 13
6 6 6 4 11 25 7 9 5 4 2 39
No. No. No. No. No. No. No. No. No. No. No. No.
2 59
No. No.
To Collection
SR
52 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS Supply, install, test and commission, Return round louver face ceiling diffusers as detailed on drawing and specification 01 02 Ref. RD1 Ref. RD2 Supply, install, test and commission, door grill as detalied and specificaitons 04 05 06 Ref. DG1 Ref. DG2 Ref. DG3 Supply, install, test and commission, exhaust air register as detailed on drawing and specification 07 Ref. ER 1 Supply and install Galvanized steel sheet rectangular ductwork, including supports and volume damper , and bill mouth opening as per drawings and specification 08 Various gauges Supply and install Duct insulation 09 Thermal semi-rigid insulation to rectangular ductwork Supply, install and operations supply motorized damber door louver as detailed on drawing and specifications 10 Size 950X2200 mm Supply, install and test generator exhaust ductwork with canvass connection QTY UNIT RATE AMOUNT SR
2 59
No. No.
11 8 65
45
No.
2100
Kg
580
No.
4
11 To suit generator room To Collection
No.
SR
53 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS Supply, install, test and commission, supply air square face ceiling diffusers as detailed on drawing and specification 01 02 03 Ref. SD1 A Ref. SD2 A Ref. SD3 A Supply, install, test and commission, Return square louver face ceiling diffusers as detailed on drawing and specification 04 05 06 Ref. RD1 A Ref. RD2 A Ref. RD3 A Supply, install, test and commission, Supply air register as detaild on drawings and spec. section 15891 07 Ref. SR1/RR1 Supply, install, test and commission, of electric works and motor control centers MCC C/W weather proof, magnetic starters, cabinets including power cables, wiring and conduits and cable trays from the MCC to HVAC equipment, interlocks, earthing ...etc, all materials and equipments required to complete and finish the work according to drawings, specifications and code of practices 08 Ref. MCC- CWP QTY UNIT RATE AMOUNT SR
12 79 4
12 79 4
12
No.
No.
To Collection
SR
54 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS BUILDING MANAGEMENT SYSTEM (BMS) Supply and install a BMS system consisting of, but not limited to: BMS equipment including BMS Monitoring and control server LAN TCP/IP operator terminal (PC), direct digital controllers DCC, IP/Routers , printer and power supply with UPS,as necessary to suit system network for the monitoring and control of electro-mechanical installations as indicated on plumbing, HVAC and electrical input/output schedules (all BMS as in the drawing and as in the specification section 15960 01 To suit building BMS system QTY UNIT RATE AMOUNT SR
Item
SR
To Collection Collection Sheet - 48 Sheet - 49 Sheet - 50 Sheet - 51 Sheet - 52 Sheet - 53 Sheet - 54 Sheet - 55
To Bill Summary
SR
55 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MEDIUM VOLTAGE INSTALLATION MVSWGR (medium voltage switchgear) Supply , install , testing and commissioning 13.8 KV, 3 phase, 60 Hz,SF6 MVSWGR with 3 cells (1 inputs + 2 outputs) including all associated works to complete installation as per drawings and specifications. The contractor shall prepare sketches and details for approval from SEC and shall make arrangement and required coordination with supervising engineer to complete the work 01 Ring Main Units ref(MVSWGR/CL-1) RING MAIN UNIT Only installation, testing and commissioning for 13.8 KV, 3 phase, 60 Hz SF6 ring main unit including all associated works for complete installation as per drawings and specifications and required coordination (supply will be by client) 02 Ring Main Units , ref (RMU1-CL1 ,RMU2-CL1 ,RMU3-CL1 ,RMU4-CL1,RMU5-CL1 &RMU6-CL1) Supply , install, testing and commissioning of the following equipment including grounding, all accessories and necessary works required for installation as per SEC regulation and as shown on the drawings and as described in specifications and required coordination 03 Dry type transformer 1600 KVA, 13.8KV -400/230V, 3PH, 60HZ , ref (TR1-CL1,TR2-CL1,TR3-CL1 ,TR4-CL1,TR5-CL1 &TR6-CL1) 6 No 6 No 1 No QTY UNIT RATE AMOUNT SR
To Collection
SR
56 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MEDIUM VOLTAGE INSTALLATION Supply , install and test medium voltage copper Cables 15KV/ XLPE/STA/PVC, between medium voltage equipments as shown on drawings and coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 Medium voltage cable comprising 3 core 70 mm CU / XLPE /STA/ PVC, cables route from RMU up to transformers Medium voltage cable comprising 3 core 300 mm CU / XLPE /STA/ PVC, cables Smart Metering System Supply, installation , testing and commissioning of Smart Metering System comprising of M-bus master controller ,M-bus IP router, complete with soft ware, including electronic KWH meter, interface with water meter& digital BTU meter, M-bus & 1 pair twisted cable # 22 AWG for each meter, and the necessary connection to TCP/IP net work and all associated works required as shown on drawing and as described in specifications To suit Building Smart Metering System as required to form a complete and fully operative system to link all project buildings with the existing data center at phase (1) 03 04 05 Electronic KWH meters M-bus master controller complete with software M-bus IP router 24 24 24 Note 30 M QTY UNIT RATE AMOUNT SR
02
650
No No No
To Collection
SR
57 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Sub-Main Circuit: supply , install , testing and commissioning 600/1000V XLPE multicore copper cable in conduit or cable tray (measured elsewhere ) , including earth cable, junction boxes, connection for feeders and various power loads as shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 4C-10mm2-CU/XLPE/PVC+10mm2G/ cable tray 4C-25mm2-CU/XLPE/PVC+16mm2G/ cable tray 4C-35mm2-CU/XLPE/PVC+16mm2G/ cable tray 4C-50mm2-CU/XLPE/PVC+25mm2G / cable tray 4C-70mm2-CU/XLPE/PVC+35mm2G / cable tray 4C-95 mm2-CU/XLPE/PVC+ 50 mm2G / cable trench 4C-120mm2-CU/XLPE/PVC+70mm2G / cable tray 4C-120mm2-CU/XLPE/PVC+70mm2G / cable trench 2(4C-150mm2)-CU/XLPE/PVC / cable trench 2(4C-150mm2-CU/XLPE/PVC)+150mm2G / cable tray 4C-185mm2-CU/XLPE/PVC+95mm2G / cable trench 2(4C-185mm2-CU/XLPE/PVC)+185mm2G / cable tray 4C-240mm2-CU/XLPE/PVC+120mm2G / cable tray 4C-240mm2-CU/XLPE/PVC+120mm2G / cable trench 3(4C-240mm-CU/XLPE/PVC)+240mmG/ cable tray 1230 105 1595 20 120 160 10 20 45 550 50 1405 550 40 135 M M M M M M M M M M M M M M M QTY UNIT RATE AMOUNT SR
To Collection
SR
58 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Sub-Main Circuit: supply , install , testing and commissioning 600/1000V XLPE multicore copper cable in conduit or cable tray (measured elsewhere ) , including earth cable, junction boxes, connection for feeders and various power loads as shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 4(4C-240mm-CU/XLPE/PVC) / duct bank 2(4C-300mm-CU/XLPE/PVC)+150mmG / cable trench 2(4C-300mm-CU/XLPE/PVC)+300mmG /cable tray 3(4C-300mm-CU/XLPE/PVC) / duct bank 4(4C-300mm-CU/XLPE/PVC) / duct bank 3(4x1C-630mm-CU/XLPE/PVC)+630mmG / cable trench The following items listed below shown in drawing AP05 - E701 , AP07 - E701 &AP08 - E701(inside each apartment building AP05, AP07 &AP08) 07 08 09 4C-10mm2-CU/XLPE/PVC+10 mm2G/ cable tray 4C-50mm+1C-25mmG-CU/XLPE/PVC / cable tray 4C-70mm+1C-35mmG-CU/XLPE/PVC / cable tray 200 95 95 M M M 20 10 135 20 20 10 M M M M M M QTY UNIT RATE AMOUNT SR
To Collection
SR
59 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply and install an Emergency Power Generating Sets including associated Generator Control Panel . In addition to circuit breakers, pads, supports, controls, daily and diesel fuel with necessary connections to earth as per the manufacture including all necessary equipment, accessories and associated works, as shown on drawings and as described in specifications. sections 01 02 03 (GEN.SET-4), 350 KVA, 400/230V, 3Ph, 4W, 60Hz,1800 RPM. (GEN.SET-2), 550 KVA, 400/230V, 3Ph, 4W, 60Hz,1800 RPM. (GEN.SET-1 & 3) 650 KVA, 400/230V, 3Ph, 4W, 60Hz,1800 RPM. MAN / HAND HOLE Supply, install, testing and commissioning reinforced concrete manholes and hand holes connected via UPVC conduit, complete with hand hole bolted type metal cover, drain pipe outlet, including trenching and backfilling for UPVC conduits for power and communication cables in UPVC conduit, tapes, , grounding, all as required to suit locations as shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 04 05 06 Power manhole (1800x1800x1800mm) ( Ref.PMH). Power hand hole (600x600x600mm) ( Ref.PHH). Communication hand hole (600x600x600mm) ( Ref.CHH). 14 14 2 No No No 1 1 2 No No No QTY UNIT RATE AMOUNT SR
To Collection
SR
60 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , testing and commissioning of panel boards including grounding, circuit breakers, grounding, fixings, markers and SAC switching actuator , DAC dimming actuators , other functional units and all associated works as required and shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 Ref. MDP-P1 Ref. DP51 Ref. DP52 Ref. DPS5 Ref. PPSD Ref. DPSB1 Ref. PPSB1 Ref. SLP1D ( listed in bill of site lighting package ) Ref. EDPSB1 with ATS (built-in ) Ref. EPSB1 Ref. EPMSB1A Ref. EPMSB1B Ref. EPP3 Ref. EMDP-P1 Ref. EDPS5 with ATS (built-in ) 1 6 6 6 6 1 1 1 1 1 1 1 1 1 6 No No No No No No No No No No No No No No No NIC QTY UNIT RATE AMOUNT SR
To Collection
SR
61 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , testing and commissioning of panel boards including grounding, circuit breakers, grounding, fixings, markers and SAC switching actuator , DAC dimming actuators , other functional units and all associated works as required and shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 Ref. EPSD Ref. MDP-P2 Ref. DP71 Ref. DPS7 Ref. PPSF Ref. DP72 Ref. SLP1C ( listed in bill of site lighting package ) Ref . MDP-P3 Ref. DPSB2 Ref. PPSB2 Ref. SLP1B ( listed in bill of site lighting package ) Ref. PPT Ref. EDPSB2 with ATS (built-in ) Ref , EPSB2 Ref. EPMSB2A 6 1 11 11 11 11 1 1 1 1 1 6 1 1 1 No No No No No No No No No No No No No No No NIC NIC QTY UNIT RATE AMOUNT SR
To Collection
SR
62 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , testing and commissioning of panel boards including grounding, circuit breakers, grounding, fixings, markers and SAC switching actuator , DAC dimming actuators , other functional units and all associated works as required and shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 Ref. EPMSB2B Ref. EMDP-P2 Ref. EDPS7 with ATS (built-in ) Ref. EPSF Ref. MDP-P4 Ref. DPSB3 Ref. PPSB3 Ref. SLP1A ( listed in bill of site lighting package ) Ref. PPSB4 Ref. EDPSB3 with ATS (built-in ) Ref. EPSB3 Ref. EPSB4 Ref. EPMSB3A1 Ref. EPMSB3A2 Ref. EPMSB3B 1 1 11 11 1 1 1 1 1 1 1 1 1 1 1 No No No No No No No No No No No No No No No NIC QTY UNIT RATE AMOUNT SR
To Collection
SR
63 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , testing and commissioning of panel boards including grounding, circuit breakers, grounding, fixings, markers and SAC switching actuator , DAC dimming actuators , other functional units and all associated works as required and shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 Ref.EMDP-P3 Ref. MDP-P5 Ref. MDP-P6 Ref. DP81 Ref. DPS8 Ref. SLPH ( listed in bill of site lighting package ) Ref. PPSH Ref. DP82 Ref. DPSB4 Ref. PPSB5 Ref. PPT1 Ref. EDPSB4 with ATS (built-in ) Ref , EPSB5 Ref. EPMSB4A Ref. EPMSB4B 1 1 1 2 2 2 2 2 1 1 4 1 1 1 1 No No No No No No No No No No No No No No No NIC QTY UNIT RATE AMOUNT SR
To Collection
SR
64 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , testing and commissioning of panel boards including grounding, circuit breakers, grounding, fixings, markers and SAC switching actuator , DAC dimming actuators , other functional units and all associated works as required and shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 Ref. EPP-IP54 Ref. EPP1-IP54 Ref. EPP2-IP54 Ref. EMDP-P4 Ref. EDPS8 with ATS (built-in ) Ref.EPSH Supply , install , testing and commissioning of circuit breaker including cables, conduits, fittings, supports, fixings, tapes, connections enclosures and all necessary works required to suit the locations shown on drawings and coordination & integration with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 07 200AT /250AF Rating. 1 No 1 1 1 1 2 2 No No No No No No QTY UNIT RATE AMOUNT SR
To Collection
SR
65 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Sub-Main circuit :Supply , install, Power & Communication distribution galvanized steel cable trays, including fittings, supports and all accessories as described on drawing Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 100 mm wide 200 mm wide 300 mm wide 400 mm wide 600 mm wide 800 mm wide 800 mm wide double layer 1000 mm wide 40 1100 2900 485 240 350 150 30 M M M M M M M M QTY UNIT RATE AMOUNT SR
To Collection
SR
66 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL POWER INSTALLATION The contractor is to insure that all power outlets mounted in wet areas and all service outlets for kitchens, bathrooms, laundry and water heaters are to be protected by central ground fault circuit interrupter (GFCI) Supply , install, testing and commissioning of power and sockets accessories including all necessary boxes, faces(according to the engineer approval ) comprising cables, conduits, fittings, connections, from the outlets to Panel boards feeder associated works as required to suit the locations shown on drawings Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 Above false ceiling disconnect switch, non-fused with pilot light, 20A, 1P, 230V for FCU-02,03,04,05,06, 11 Above false ceiling disconnect switch, non-fused with pilot light, weatherproof, 20A, 1P, 230V for EWH-01 Above false ceiling disconnect switch, non-fused with pilot light, 20A, 3P, 400V for BIF'S-01 Disconnect switch, non-fused with pilot light, weatherproof, 16A, 1P, 230V for waste collection Disconnect switch, non-fused with pilot light, 20A, 1P, 230V for active switcher for sec. network,FD'S,BD'S,FACP Disconnect switch, non-fused with pilot light, weatherproof, 20A, 1P, 230V for submersible , gray pump , fountain pump & fuel pump Disconnect switch, non-fused with pilot light, weatherproof, 20A,3P, 400V for 2potable pumps, gray pumps Disconnect switch, non-fused with pilot light, weatherproof,32 A, 1P, 230V for gray pump 42 No Note QTY UNIT RATE AMOUNT SR
02
No
03
39
No
04
24
No
05
62
No
06
25
No
07
20
No
08
No
To Collection
SR
67 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL POWER INSTALLATION Supply , install, testing and commissioning of power and sockets accessories including all necessary boxes, faces(according to the engineer approval ) comprising cables, conduits, fittings, connections, from the outlets to Panel boards feeder associated works as required to suit the locations shown on drawings Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 Disconnect switch, non-fused with pilot light, weatherproof, 32A,3P, 400V for Sw. pool pump Disconnect switch, non-fused with pilot light, , 50A,3P, 400V for PEF-01,02 Disconnect switch, non-fused t, weatherproof, 200A, 3P, 400V for fire pump & jockey pumps Disconnect switch, non-fused t, weatherproof, 630A, 3P, 400V for fire MCC-CWP Disconnect switch, fused with pilot light, 20A, 1P, 230V for RAC-01,FDA,FDBFCU-07,08,09,10 Disconnect switch, fused with pilot light ,weatherproof, 20 A, 1P, 230V for RAC-01,FDA,FDB Disconnect switch, fused with pilot light ,weatherproof, 25 A, 1P, 230V for RAC-01 Disconnect switch, fused with pilot light, 32 A, 1P, 230V for FCU-01 Disconnect switch, fused with pilot light ,weatherproof, 50 A, 3P, 400V for PEF-01 Floor mounted ,Junction box, 1 No QTY UNIT RATE AMOUNT SR
02
No
03
No
04
No
05
75
No
06
11
No
07
No
08 09
8 2
No No
10
No.
To Collection
SR
68 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL POWER INSTALLATION Supply , install, testing and commissioning of power and sockets accessories including all necessary boxes, faces(according to the engineer approval ) comprising cables, conduits, fittings, connections, from the outlets to Panel boards feeder associated works as required to suit the locations shown on drawings Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 Ceiling mounted junction box Wall mounted junction box Single socket outlet, 10A, 230V, grounding type Single socket outlet, weatherproof , 10A, 230V, grounding type Single socket outlet, weatherproof , 16 A, 230V, with ground fault circuit interrupter ,ref. GF Duplex socket outlet,16A,230V, grounding type Single phase power socket outlet ,20A\230V,grounding type Single phase power socket outlet ,weatherproof ,20A\230V,grounding type 88 70 510 265 31 No No No. No. No. QTY UNIT RATE AMOUNT SR
06 07 08
81 8 12
To Collection
SR
69 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL LIGHTING INSTALLATION Supply, install , testing and commissioning of switches lighting accessories including all necessary boxes, switches, faces, conduits, wires (according to the engineer approval ) associated works as required to suit the locations shown on drawings .Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 Single pole one-way switch (13A) Single pole one-way switch weatherproof (13A) Single pole , two gang, switch (13A) Three-way switch(13A). Three-way , two gang, switch (13A) Four-way switch(13a). Push button switch Motor switch with built-in overload protection (tumbler switch) Supply, install , testing and commissioning of lighting fixture outlets and including conduits, wires and all boxes belong to Lighting Panel boards and associated works as required to suit the locations shown on drawings .Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 09 10 Lighting fixture outlets Lighting fixture outlets type FT1 (cove light ) 2,507 36 No No 211 4 39 8 4 4 57 81 No. No. No. No. No. No. No. No. QTY UNIT RATE AMOUNT SR
To Collection
SR
70 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL LIGHTING INSTALLATION Supply ,install, testing and commissioning of lighting fixture (furnished with lamp and electronic blast, accessories and internal wires) mounting accessories.(according to the engineer approval ) associated works as required to suit the locations shown on drawings .Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 Ref. EX (Exit light wall mounted, single sided) Ref. EX (Exit light ceiling mounted, single sided ) Ref. F1 Ref. F1E Ref. F2 Ref. F2E Ref. F3 Ref. F3E Ref. F4 Ref. F4E Ref. F5 Ref. F5E Ref. F7E Ref. UW1 Transformer 1000VA, 220 /12V , 60 HZ for under water lighting fixtures UW1, as shown on drawings 68 81 984 281 334 129 7 5 156 51 19 19 144 7 2 No No No No No No No No No No No No No No No QTY UNIT RATE AMOUNT SR
To Collection
SR
71 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL LIGHTING INSTALLATION Supply ,install, testing and commissioning of lighting fixture (furnished with lamp and electronic blast, accessories and internal wires) mounting accessories.(according to the engineer approval ) associated works as required to suit the locations shown on drawings .Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 Ref. N Ref. NE Ref. WL3 Ref. WL4 Ref. WL4E Ref. FT1 2 51 76 36 56 996 No No No No No M. QTY UNIT RATE AMOUNT SR
To Collection
72 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL COMMUNICATION SYSTEMS DATA AND VOICE SYSTEM INSTALLATION Supply, install , testing and commissioning of integrated data and voice system with inter-link with CCTV camera, comprising equipment rack consisting of building data distribution, outlets, patch panels, patch cords including cabling (including fiber optic cable all UTP CAT 6A cable, switches) , in conduits, connection/ extension and interfacing all as shown on drawings .Coordination, integration with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications To suit system network equipped with: 01 02 Wall mounted telecommunication outlet, 1 ports ( one data ) ref. (T0 ) Ceiling mounted telecommunication outlet, 1 ports ( one data ) ref. (T0 ) Wall mounted telecommunication outlet for intercom system Ref. (T0 )I Wall mounted telecommunication outlet, 1 ports ( one tel ), Ref. (T01) Wall mounted telecommunication outlet, 1 ports ( one tel ),at 1500 mm A.F.F.L Ref. (T01)W Wall mounted telecommunication outlet, 1 ports ( one data, one tel ) Ref.( T02 ) Wall mounted telecommunication outlet, 1 ports ( oneTV. ) Ref.( T03 ) Wall mounted telecommunication outlet, 3 ports ( two data,one telephone. ) Ref.( T04 ) 42 108 No No QTY UNIT RATE AMOUNT SR
03
34
No
04
42
No
05
106
No
06
No
07
46
No
08
19
No
To Collection
73 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL COMMUNICATION SYSTEMS DATA AND VOICE SYSTEM INSTALLATION Supply ,install, testing and commissioning of integrated data and voice system with inter-link with CCTV camera, comprising equipment rack consisting of building data distribution, outlets, patch panel, patch cords including cabling (including fiber optic cable all UTP CAT 6A cable, switches) , in conduits, connection/ extension and interfacing all as shown on drawings .Coordination, integration with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 Floor Distributor includes : 19",standard rack , fiber optic patch panel (F. O. P. P) , data switch CAT6 a 1x36 RJ45 ports ,UTP patch panel CAT6 a 1x36 RJ45 ports, with fans ,UPS,power supply and all accessories to complete the work as per drawings and specifications according to latest technology Ref (FDA,FDB ,FDC &FDD ) The following items listed below shown in drawing AP05- E801 , AP07 - E801 &AP08 - E801(inside each apartment building AP05, AP07 &AP08.) 02 Building distributor (BD5,BD7&BD8) ( Includes main F. O. P. P. and all necessary works required for installation as shown on drawings, on single line diagram in AP -05-E801,AP -07-E801&AP -08-E801) to form a complete and fully operative system Floor Distributor includes : 19",standard rack , fiber optic patch panel (F. O. P. P. (2 x 4 port)) , data switch cable 1x24 RJ45portss ,UTP patch panel (24 ports) with fans ,UPS,power supply and all accessories to complete the work as per drawings and specifications according to latest technology Ref (FD5G ,FD7G &FD8G) Data and voice system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system 19 No 4 No QTY UNIT RATE AMOUNT SR
03
19
No
04
Item
To Collection
SR
74 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL FIRE ALARM SYSTEM
Supply, install , testing and commissioning of fire detection /alarm system comprising of analogue addressable fire alarm panel , detectors, alarm bell, break glass, modules including associated cable wires, ear thing for equipment and conducting, interfacing with other systems as shown on drawings and .Coordination, integration with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications
QTY
UNIT
RATE
AMOUNT SR
To suit fire alarm system network equipped with: 01 02 03 04 05 06 07 08 09 10 11 Ceiling mounted optical smoke detector, Ceiling mounted heat detector Sounder with strobe light Fire alarm bell Fire alarm manual call station Fire alarm interface module Ceiling mounted multi sensor ( heat , smoke ) Ceiling mounted multi sensor ( CO ,heat , smoke ) Fire fighting telephone panel ref (FFT) Fire man's telephone jack Master analogue fire alarm control panel-MFACP comprising of TCP-IP interface and power supply unit with complete PC work station , interfacing to auto - dialer to local fire department, Analogue terminal adapter (interfacing with auto - dialer ) 253 10 24 38 103 63 79 228 19 38 1 No No No No No No No No No No No
12
No
To Collection
SR
75 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL FIRE ALARM SYSTEM
Supply, install , testing and commissioning of fire detection /alarm system comprising of analogue addressable fire alarm panel , detectors, alarm bell, break glass, modules including associated cable wires, ear thing for equipment and conducting, interfacing with other systems as shown on drawings and .Coordination, integration with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications
QTY
UNIT
RATE
AMOUNT SR
The following items listed below shown in drawing AP05- E801 , AP07 - E801 &AP08 - E801(inside each apartment building AP05, AP07 &AP08.) 01 Analogue addressable fire alarm control panel-FACP comprising of TCP-IP interface and power supply unit, automatic dialer ,analogue terminal adapter interfacing to auto - dialer to local fire department, Fire alarm system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system IP TV SYSTEM Supply, install, test and commissioning of television system connected to TCP/IP (LAN) comprising for RJ 45 outlet (measured elsewhere ) set top box , power supply , and all associated works as shown on drawings and .Coordination, integration with other systems disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 19 No
02
Item
46
No Item
1 IP TV system network including coaxial cabling/wire and all required accessories to form a complete and fully operative system To Collection
SR
76 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL VOICE EVACUATION SYSTEM Supply , installation, testing and commissioning of voice evacuation system complete with all accessories required for installation including distribution panel for voice evacuation system , pull boxes, loudspeaker , microphone, cable/ wire and conducting supports, fittings, interfacing units , and all required to suit the locations shown on drawings. Coordination and integration with other systems shall be conducted during work execution, as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications To suit evacuation system network equipped with: 01 Master voice evacuation distribution panel ref. MVP complete with fire phone, power supply unit with battery backup (3-hours continuance operation), including master mic with zone selection, master mic control, 96 switch control, dual channel , integrated fire phone & interface to fire alarm control panel (FACP). Voice evacuation distribution panel (ref.VDP) with3x100W amplifier, and power supply unit Voice evacuation distribution panel (ref.VDP) with 2x100W amplifier, and power supply unit 2 Watts, voice evacuation speaker, ceiling mounted 2 Watts, voice evacuation speaker, wall mounted Voice evacuation system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system 1 No. QTY UNIT RATE AMOUNT SR
02
No.
03
19
No.
04 05 06
59 123 1
To Collection
SR
77 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL AUDIO / VIDEO IP INTERCOM SYSTEM Supply , installation testing and commissioning of audio / video IP intercom system comprising of outdoor station unit with built-in color camera, indoor station units with built -in monitors, electrical door lock , AC power supply, cables and conduits and associated works as required to suit the locations shown on drawings and coordination & integration & communication kit with other systems shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications To suit audio /video phone IP intercom system network equipped with: The following items listed below shown in drawing AP05- E801 , AP07 - E801 &AP08 - E801(inside each apartment building AP05, AP07 &AP08.) 01 Waterproof outdoor station unit (48 lines) including but not limited to color camera, mic, speaker, push buttons, power supply, , etc. in drawing AP05- E801 Waterproof outdoor station unit (72 lines) including but not limited to color camera, mic, speaker, push buttons, power supply, etc.in drawing AP07- E801 , Waterproof outdoor station unit (96 lines) including but not limited to color camera, mic, speaker, push buttons, power supply, etc..in drawing AP08- E801 , Electric door lock Network controller with power supply Exit push button Electric door strike Audio / video IP intercom system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system To Collection 12 No QTY UNIT RATE AMOUNT SR
02
22
No
03
No
04 05 06 07 08
38 19 38 36 1
No No No No Item
SR
78 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL INTEGRATED SECURITY SYSTEM Supply , installation testing and commissioning of integrated security system comprising of CCTV IP cameras, network video recorder with built in motion detection, CCTV monitors, video display unit, keypad, system controllers, readers, readers interface modules, push buttons, electro magnetic locks, encoders, security server, workstations, wire, power supplies, conduits, interfaces and all accessories required for the system as per drawings, riser diagrams and specifications To suit system consisting of ,but not limited to: 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Intelligent security controller (ref. ISC) Reader interface module (ref. RIM) Double reader interface module (ref. DRIM) Card reader ref. (CR) Exit push button (ref. PB) Electromagnetic lock Magnetic door contact(ref. DC) Electromagnetic lock for double side door with electric lock (D) Ceiling mounted indoor IP CCD day / night camera Outdoor ceiling mounted IP CCD day / night camera Outdoor wall mounted IP CCD day / night camera Ceiling mounted IP fixed dome camera Outdoor type motion sensor Security system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system 21 40 76 No No No QTY UNIT RATE AMOUNT SR
192
116
No.
No
82
82 34 22 47 34 38 74 1
No.
No No No No No No No Item
To Collection
SR
79 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN TELECOMMUNICATION SYSTEM NETWORK Supply, installation, testing and commissioning distribution network for data and telephone system to connect all buildings/floor distributers BD/FD to the primary/secondary active switch as shown on drawings. Item includes cables\ wires in conduits or cable tray( measured elsewhere )and all associated works as required for the whole network in the site. Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings by making arrangement with supervising engineer according to manufacturer's recommendations to achieve the complete work to the best possible 01 To suit all network system MAIN FIRE ALARM SYSTEM NETWORK Supply, installation, testing and commissioning distribution network for fire alarm system to connect all FACPs in all buildings with each other as shown on drawings. Item includes cables\ wires in conduits or cable tray( measured elsewhere )and all associated works as required for the whole network in the site. Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings by making arrangement with supervising engineer according to manufacturer's recommendations to achieve the complete work to the best possible To suit all network system 02 Supply and install a fire alarm system to suit external feeder network 1 Item 1 Item QTY UNIT RATE AMOUNT SR
To Collection
SR
80 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN VOICE EVACUATION SYSTEM NETWORK Supply, installation, testing and commissioning distribution network for voice evacuation system to connect all voice evacuation distribution panels. in all buildings with master voice evacuation panel. as shown on drawings. Item includes cables\ wires in conduits or cable tray( measured elsewhere )and all associated works as required for the whole network in the site. Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings by making arrangement with supervising engineer according to manufacturer's recommendations to achieve the complete work to the best possible 01 To suit all network system BUILDING MANAGEMENT SYSTEM (BMS) Supply, install, testing, commissioning and integrating the building / cluster BMS system or sub system items (equipment controllers, routers, cables inside the building between system items, conduits, boxes, fiber optic cables,..etc) with phase 1 main BMS system (located in the data center)via LAN network as shown on the building drawings, indicated in plumbing, HVAC and electrical input/ output schedules (all BMS schedules) and as described in the specifications, consisting of but not limited to: 02 To suit building BMS system network and the system should be applicable to linked with existing operating system in phase one after getting approval from service and operation team in phase one to complete the work to the best possible 1 Item 1 Item QTY UNIT RATE AMOUNT SR
To Collection
SR
81 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL GROUNDING SYSTEM Supply, install, test and commissioning a grounding system for cluster comprising bare copper conductors for grounding all electrical and mechanical equipments in the cluster and all required works for connecting in one grounding system In addition to all earthwork, connections, clips, copper clad steel rods in ground test wells with cast iron covers situated around the building as required and all associated works as necessary to provide a complete grounding system, all as shown on drawing . Coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 To suit grounding system for network of cluster 1 Item QTY UNIT RATE AMOUNT SR
To Collection
SR
82 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL Collection Sheet - 56 Sheet - 57 Sheet - 58 Sheet - 59 Sheet - 60 Sheet - 61 Sheet - 62 Sheet - 63 Sheet - 64 Sheet - 65 Sheet - 66 Sheet - 67 Sheet - 68 Sheet - 69 Sheet - 70 Sheet - 71 Sheet - 72 Sheet - 73 Sheet - 74 Sheet - 75 Sheet - 76 Sheet - 77 Sheet - 78 To Collection SR QTY UNIT RATE AMOUNT SR
83 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL Collection Sheet - 79 Sheet - 80 Sheet - 81 Sheet - 82 To Collection Collection Sheet - 83 Sheet - 84 SR QTY UNIT RATE AMOUNT SR
To Bill Summary
SR
84 / 85 REVISED PAGE
PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL01) ITEM DESCRIPTION AMOUNT S.R.
BILL SUMMARY Sheet - 19 Sheet - 21 Sheet - 25 Sheet - 26 Sheet - 27 Sheet - 28 Sheet - 29 Sheet - 30 Sheet - 32 Sheet - 33 Sheet - 34 Sheet - 36 Sheet - 47 Sheet - 55 Sheet - 84 SITE DEVELOPMENT SITEWORK CONCRETE MASONRY METALS WOOD AND PLASTIC THERMAL AND MOISTURE PROTECTION DOORS AND WINDOWS FINISHES SPECIALTIES EQUIPMENT CONVEYING SYSTEMS PLUMBING HVAC ELECTRICAL 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
To Tender Summary
SR
0.0
85 / 85 REVISED PAGE