Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Discussion Topics
The Program Managers Dilemma CCPM Project Management - A Different Focus
Comparison of Traditional PM to CCPM Buffer Management
pg. 2
Pre-requisite We must
Do Whatever It Takes
The GOAL
Conflict
We mu st
Necessary Condition
.
We must
pg. 3
A new method of Project Management based on Theory of Constraints. It is an alternative to the Critical Path Method.
Planning
Plan worked backward from completion with each task starting as late as possible Task durations are planned at the 50% probability duration and evaluated at the 90-95% level. Resource leveling leads to the critical chain with the identification of schedule buffers to handle normal schedule variations
Execution
Critical chain is the race, and the resources on the critical chain are the runners, so pressure is put on the resources to complete the critical chain tasks as quickly as possible
Based on a book entitled, Critical Chain. Copyright 2009 The Boeing Company. All rights reserved.
pg. 4
A1 AB1
B1
Resources start as early As possible
B2
B3 B4
Resource Conflicts Ignored
C1 AB2 B6
AB3 A2
B5
10
12
A1
Buffer AB1 B1 B2 B3
C1
AB2
B4
AB3
A2
Buffer
No Resource Conflicts
This buffer is needed to protect the project for normal task variation. pg. 5
Management action taken Management action taken To assist team recover To assist team recover
d d tifie n e i e f i d it re en a d s i n plaare n o s ti iga an Mit n pl o ati g i t Mi
50
Team members actively work Team members actively to recover buffer work to recover buffer
50 Percentage of Critical Chain Completed Copyright 2009 The Boeing Company. All rights reserved.
100
pg. 6
Resolution Approach
Develop software code and put the program under Configuration Management Execute project using Critical Chain Project Management
Results
Project completed 12-42% ahead of schedule Chief Engineer praised the quality of the software program and support specification and verification documents
pg. 7
Project Buffer, %
Reflects Special Cause variation Team chose not to re-baseline the project.
Critical Chain, %
Copyright 2009 The Boeing Company. All rights reserved.
pg. 8
Resolution Approach
CIH team identified potential execution issues and mitigated them All functional managers and team members were introduced to CCPM and their support to use this method was obtained Team established Execution Run Rules to ensure the team stayed focused Team members subordinated their work to the effort on the critical chain and actively managed the buffers
Results
Hardware delivered early, under budget and exceeded quality expectations
Copyright 2009 The Boeing Company. All rights reserved.
pg. 9
pg. 10
Resolution Approach
Team adopted CCPM believing it offered them the best opportunity for finishing on schedule All of the required updates were identified for each data book Knowledge resources were identified for each data book update in order to establish aggressive durations and define the critical chain for the project All resources were trained on CCPM processes and procedures Execution Run Rules were established and executed by the team Weekly buffer management meetings were conducted and actions taken as needed
Results
All data book updates completed within five months, a 58% schedule reduction. Customer expectations were exceeded
Copyright 2009 The Boeing Company. All rights reserved.
pg. 11
pg. 12