SN A-1 A.1.

DESCRIPTION OF ITEMS FOUNDATION Piles & Pilecaps Providing and installing bored cast-in-situ vertical piles of 1000 mm diameter in M-35 grade of Reinforced Cement concrete using Ordinary Portland Cement of grade 53 all complete (including cost of all materials labour etc except reinforcement steel, which will be paid as per item A 1.4), as per specifications

UNIT

QTY

RATE

A.1.1.1

In all types of soil except hard rock. i) 1000mm dia piles. A.1.1.2 Empty boring from working platform to cut off level including provision of Temporary guide casing if necessary at contractors own cost and extra cutting and taking away the same after the casting of pile.

Meter

2,000.00

10,883.00

A.1.1.3

i) 1000mm dia piles. Manufacturing, bending, welding supplying and driving in position 6mm thick M.S. Liner (permanent) including the cost of M.S. Plate. Rate includes cost of all labour and materials. i) 1000mm mm dia piles. Note: This item A 1.1.3 shall be operated only where the MS Liners are required as per site condition, to be left permanently in the work. Payment will be made from the cut off level to bottom of Liner.

Meter

160.00

652.00

MT

36.00

59,926.00

A)The scope of work in the above items include: 1)The cost of all initial layout of piles and setting out, initial excavation, if any. 2)The cost of boring through all types of soils/existing road/pavement, removal of all obstruction like boulders, old foundation concrete by chiseling or any other method as approved by the Engineer-in-Charge. If a bore is abandoned for any reason no payment shall be made for such incomplete boring and shifting of the equipment's. The cost of filling up of the empty bore, if required. will be borne by contractor

3)The cost of preparation, circulation and handling of bentonite slurry is included in this rate. 4)The cost of disposal of all spoils, bentonite waste to keep the work area neat. 5)The cost of providing temporary liner and its withdrawal, if required below adjoining ground level (irrespective of the R.L. of the adjoining ground level) for vertical piles. 6)The cost of providing and mixing all ingredients of cement concrete (except reinforcement steel) including admixtures, with batching plant, transportation, placement of concrete by tremie pipe for the required lengths of pile including providing cover blocks, stiffeners, handling bars etc. for safe handling of reinforcement cage.

7) The cost of breaking of pile head not earlier than 3 days after concreting and to remove spoil concrete to bring the pile head to the socketing level including cleaning and arranging the extended reinforcement bars as per drawings. 8)The cost of working for all leads, lifts, pumping / bailing out of water, labour, material and equipment etc.

9)The cost of mobilizing to site, installation at different locations transferring / dismantling, shifting, reinstalling and removal from site of the piling rigs and/or other equipment's and all accessories including working platforms.

AMOUNT (in Rs)

21,766,000.00

104,320.00

2,157,336.00

10)The cost of identification, protection and maintenance of existing services, if any, which in the opinion of Engineer-in-charge are likely to be affected by piling operation incl. temporary shifting of such services to facilitate piling job shall also have to be done, if so required by the Engineer-in-Charge and the cost for the same as assessed by the Engineer-in-Charge shall be reimbursable.

11)The contractor has to be made baricadding with G.I. Sheet / steel sheet with vertical post by suitable section of steel angle/ pipe at minimum height of 1.5m from the existing road level during the execution of the work . The contractor has to be manage the all traffic safety requirements during the execution period.

12)The cost of all incidentals, labour, material, equipment and works required to execute the job. The item also includes any other incidental expenditures for completing the job as per the direction of the engineer-incharge. 13)The item includes the cost of testing of all the materials involved in the execution of the item as per QAP. 14) Temperory diversion road if any constructed shall be paid seperately as per Non scheduled items. B) Mode of Measurement : 1) Length of pile shall be measured from cut off level to the tip of the pile correct to a cm in case where the pile is terminated. 2) Reinforcement steel shall be measured & paid separately under relevant schedule item A 1.4. A.1.2 Load test of piles A.1.2.1 Initial vertical Load testing of test piles as per the specifications duly supplemented with IS: 2911 (Part IV) with latest amendments thereto all complete. . i) 1000 mm dia piles. Nos. A1.2.2 Horizontal Load testing of test piles as per the specifications duly Nos. supplemented with IS: 2911 (Part IV) with latest amendments thereto all complete. i) 1000 mm dia piles. A)The scope of work in the item includes: 1) The cost of making of pile head ready for testing at the desired level. 2) The cost of mobilizing, fabrication / making of test set up, its dismantling, removal and making good, if any, after the test is over. 3) The cost of supplying all labour, materials, equipment, instrumentation etc. including its transportation complete. 4) The cost of Recording and presentation of data as required by the Engineer-in-Charge. (Refer Appendix D IS: 2911 (Part I/Sec I) for sample Data Sheet). 5)The cost of supporting / reaction arrangement (including reaction piles, if any) for the kentledge load (kentledge load shall be 1.25 times the test load). 6) No working pile shall be used as a reaction pile. B) Mode of Measurement : 1) Measurement shall be made for each complete set of testing and reporting. 2.00 2.00 306,690.00 101,687.07

2) Initial test piles also shall be measured for payment like normal piles. A.1.2.3 Routine vertical testing of working piles as per the specifications duly supplemented with IS: 2911 (Part IV) with latest amendments thereto all complete. i) 1000mm dia piles. A)The scope of work in the item includes: 1) The cost of making of pile head ready for testing at the desired level. 2) The cost of mobilizing, fabrication / making of test set up, its dismantling, removal and making good, if any, after the test is over. Nos. 2.00 113,000.00

613,380.00 203,374.14

226,000.00

3) The cost of supplying all labour, materials, equipment, instrumentation etc. including its transportation complete. 4) The cost of Recording and presentation of data as required by the Engineer-in-Charge. (Refer Appendix D IS: 2911 (Part I/Sec I) for sample Data Sheet). 5) The cost of supporting / reaction arrangement (including reaction piles, if any) for the kentledge load (kentledge load shall be 1.25 times the test load). 6) No working pile shall be used as a reaction pile. B) Mode of Measurement : 1) Measurement shall be made for each complete set of testing and reporting. Mode of Measurement: Measurement shall be made for each successfully complete set of testing and reporting per pile. A.1.3 A.1.3.1 Pile cap Earth work in excavation for casting pile cap in all type of soils, weathered CUM rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts, and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap. The cost of backfilling around the pile cap and restoration of road, if required shall be included. 1,092.00 41.00

A.1.3.2

Providing and laying plain cement concrete M15 (aggregate 20mm CUM nominal size) under the pile cap / foundations and below approach slab. The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer in charge. Payment shall be made based on approved plan dimensions for PCC.

77.00

6,646.00

A.1.3.3

Providing and laying reinforced cement concrete for construction of pile CUM caps and foundations in M-35 grade concrete using Ordinary Portland Cement of grade 53, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), as per approved drawings supplied by the Engineer-incharge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, which will be paid as per item number A 1.4).

706.00

8,856.00

A)The scope of work in the item includes. 1)The cost of all initial layout and setting out work including identification of existing services, if any. 2)The cost of all pumping/Bailing out of water, including its labour, material and equipment's.

3)The cost of providing centering and shuttering including its erection, dismantling and removal of formwork including all leads and lifts with all required tools and plants to the required line and level..

4)The cost of providing and mixing all ingredients (except reinforcement steel) including admixtures etc., with batching plant, transportation, placement, finishing and curing of concrete.

44,772.00

511,742.00

6,252,336.00

5)The cost of maintenance and protection of existing services, if any which in the opinion of Engineer-in-charge are likely to be affected by any related activities including temporary shifting of such services to facilitate construction of pile cap work shall also have to be done, if so required by the Engineer-in-charge, and the cost for the same as assessed by the Engineer-in-Charge shall be reimbursable.

6)The cost of installation of any fixture into the pile cap (cost of only fixture to be paid separately). 7)The contractor has to be made baricadding with G.I. Sheet / steel sheet with vertical post by suitable section of steel angle/ pipe at minimum height of 1.5m from the existing road level during the execution of the work . The contractor has to be mange the all traffic safety requirements during the execution period.

8)The cost of testing of all the materials involved in the execution of items as per QAP. 9)The cost of all incidental labour, materials, equipment and works required to execute the job as per directions of engineer-in-charge. B) Mode of Measurement: 1) Measurements shall be made for the finished volume of reinforced cement concrete restricted to volume as per approved drawing (excluding cost of reinforcement steel only). Quantity of concrete of piles, which has gone into the pile caps shall be deducted. Reinforcement shall be measured & paid separately as per item A 1.4.

A 1.4 Reinforcement: Supply, cutting, bending, with all leads, lifts and depths, fixing in position reinforcement of any diameter, HYSD or TMT as per relevant BIS specification and drawing in all RCC/PSC works of this schedule A-1. The rate shall include cost of all material including laps, tying wire, binding wire, cover block, provision of stools, chairs, spacer bars, support bars , labour, transportation, storing and all other incidental charges, tools & plants etc complete. Payment shall be made as per theoretical requirement and no wastage shall be paid. Rate shall include all costs.

MT 249.00

57,379.00

SUB TOTAL - A-1 A-2 SUBSTRUCTURE Piers, Abutments and bearings A.2.1 Providing and laying reinforced cement concrete for construction of piers, pier caps, abutment, abutment caps, and dirt wall in M-35 grade concrete using Ordinary Portland Cement of grade 53 , appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, which will be paid as per item number A 2.5). CUM 623.00 9,615.00

A) The scope of work in the item includes

1)The cost of all incidental work required including providing, placement and removal, shifting of shuttering, cleaning, oiling & maintenance, erection & removal of staging, scaffolding and form liner etc, for piers, pier caps, bearing pedestals and other works as stated in other parts of the tender document.

2)The cost of casting of a mock pier at casting yard true to line, level and shape as per the direction of the Engineer- in-Charge.

14,287,371.00

46,166,631.14

5,990,145.00

3)The cost of casting of pier, pier caps, abutment, abutment caps etc. including providing and mixing all ingredients and admixtures etc. in Batching plant, transportation, placement, compaction, finishing and curing, placing in position inserts with pier/pedestals as per specification and the direction of the Engineer-in- charge.

4)The cost of disposal of all spoils and to keep the work area neat and tidy during the work and thereafter. 5)The cost of Barricading and all safety requirements as mentioned elsewhere in the tender document. 6)Installation of any fixtures into pier/pier cap etc (cost of onlyfixtures if any, to be paid separately). 7)The cost of all incidentals, labour, material, equipment and works required for the executions of the job as per the direction of Engineer-incharge. 8)The cost of testing all materials involved in the execution of the item as per QAP. 9)The cost of working for all leads, lifts, pumping / bailing out water, labour`, material and equipment etc. B) Mode of Measurement : 1) Measurement shall be made for the finished volume of concrete only and will be restricted to the dimensions shown in the approved drawings. 2) Reinforcement steel shall be measured & paid separately as per item A 2.5. A.2.2 Providing and laying reinforced cement concrete for construction of CUM bearing pedestal in M-40 grade concrete using Ordinary Portland Cement of grade 53 , appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), inculding placing & fixing of Bearings in position as per drawings (Bearings shall be supplied by IRCON free of Cost at its store at Patna or elsewher in Bihar, the contractor has to transport the same to the work site from IRCONs Store at its own cost) the as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, which will be paid as per item number A 2.5). 50.00 9,831.00

A) The scope of work in the item includes 1) Scope of work in this include the scope of work as mentioned in item no. 2.1 above except clause (2) of A.2.1.(A) above. B) Mode of Measurement : 1) Measurement shall be made for the finished volume of concrete and will be restricted to the quantity as per approved drawings. Reinforcement steel shall be measured & paid separately as per item A 2.5.

A.2.3

Painting below GL: Providing anticorrosive treatment to the parts of substructure in contact with earth upto GL with one coat of primer and two coats of Anticorrosive Coal Tar Epoxy Paint below the ground level on Pile caps, Piers, abutments etc with all labour material tools and plants complete job.

SQM

870.00

39.00

A.2.4

Painting over exposed surfaces: Painting the surfaces with SQM Anticarbonation/Anticorrosive Acrylic Paint above the ground level on Piers, pier caps, etc. with all labour material tools and plants complete job including surface preparation at joints in approved colour.

1,414.00

132.00

491,550.00

33,930.00

186,648.00

A.2.5 Reinforcement: Supply, cutting, Bending, fixing in position reinforcement of any diameter, HYSD or TMT as per relevant BIS specification and drawing in all RCC/PSC works of this schedule A-2. The rate shall include cost of all material including tying wire, labour, transportation, storing and all other incidental charges, tools & plants etc. Payment shall be made as per theoretical requirement and no wastage shall be paid. Rate shall include all costs.

MT

188.00 58,455.00

SUB TOTAL - A-2 A-3 SUPERSTRUCTURE A.3.1.1 Providing and laying reinforced cement concrete for construction of precast Prestressed super structure girders / prestressed solid slab / diaphragm in position in M-45 grade concrete using Ordinary Portland Cement of grade 53, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel & HT Steel, which will be paid as per relevent items respectively).

CUM

1,021.00 10,548.00

A) The scope of work in the item includes 1)The cost of initial layout ensuring correct levels. 2)The cost of all incidental works required including providing casting yard, casting bed, providing, placement and removal or shifting of shuttering, staging, scaffolding etc. and other works as stated in other parts of the tender documents.

3)The cost of design of the job mix. 4)The cost of providing and mixing all ingredients including admixtures etc. with batching plant, transportation, placement, compaction, steam curing and finishing etc., which shall also involve preparation of surface, placing in position with anchorages as per specification and the direction of the Engineer in charge, complete job.

5) The item includes the cost of disposal of all spoils and to keep the work area neat and tidy during the work and there after. 6)The item includes the cost of barricading and all safety measures including management of traffic as desired by the Engineer-in-Charge and as specified elsewhere in the tender document. 7) The item includes the cost of foundation preparation for staging of solid slab staging and making casting bed to take care of loads and settlements. 8)The cost of all incidentals, labour, material, equipment and works required for the executions of the job as per the direction of Engineer-incharge. 9) The cost of testing all materials involved in the execution of the item as per QAP. 10)The cost of working for all leads, lifts, pumping / bailing out water, labour, material and equipment etc.

B) Mode of Measurement : 1) Measurement shall be made for the volume of finished concrete only and will be restricted to the quantities as per the dimensions shown in the approved drawings. The reinforcement steel shall be measured & paid separately which will be paid as per relevent item .

10,989,540.00

17,691,813.00 10,769,508.00

A.3.1.2 Launching (by Crane), Side Shifting & placing, temporary restraining of precast girder in position true to line and level including pulling, pushing, lateral shifting, loading, unloading, complete in all respect as per drg & specification observing all safety measure, obtaining block of train movement/ road traffic movement from appropriate authority, providing suitable diversion if required etc complete job. Rate shall include cost of all labour ,lead, lift ascent, decent, crossing of tracks.

CUM

1,021.00

3,500.00

A.3.1.3 Supplying, making into cables and fixing in position H.T. steel cables made from high tensile low relaxation strands (any dia) in PSC girder including cutting making into cables with necessary spacers encasing in HDPE sheathing placing of cable as per drawing provision of anchorage's end blocks stressing, cutting blocking, grouting etc complete job. Payment shall be made for the weight of HTS wire consumed from end to end . However rate shall include cost of all prestressing material, tools for stressing, grouting etc. Nothing extra shall be paid for jacking length.

MT

73.00

85,388.59

A.3.2 Providing and laying reinforced cement concrete for construction of deck slabs, diaphragms, cross beams, cantilever footpath / slab etc in M45grade concrete using Ordinary Portland Cement of grade 53, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, which will be paid as per relevent item ).

CUM

438.00

11,328.00

A.3.3 Crash barrier: Providing & laying reinforced cement concrete for the construction of crash barrier including supplying & fixing of the 65 NB G I pipe steel railing, providing 150 mm dia PVC Pipe along with 12 dia mesh around it as detailed in the sketch enclosed in tender document in M-40 grade concrete using 53 grade cement and appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), as per approved drawings supplied by Engineer in charge, including all types of shuttering, scaffoldings/staging, necessary tools, plants, machinery and all related operations as required to complete the work with all lead, lifts, depths, true to line, level and position but excluding the cost of reinforcement steel (which shall be paid as per relevant item under this schedule) all complete. The item includes supplying, fabricating and fixing Metallic railing on top of the concrete crash barriers, conforming to IS standards.

RM

434.00

4,822.00

A) The scope of work in the item includes 1)The item includes the cost of preparation and submission of detailed shop drawings, fabrication, casting fixtures, placing and fixing in position using required fasteners and pickling.

2)The item includes the cost of two coats of painting along with one coat of anticorrosive primer for steel portion only. 3)The item includes the cost of testing of all the materials involved in the execution of the item as per QAP. 4)The item includes all other incidental expenditure for completing the jobs as per the directions of Engineer-in- charge. B) Mode of Measurement : 1) The measurements shall be made in Running Meters of the completed railing.

3,573,500.00

6,233,366.82

4,961,664.00

2,092,748.00

A.3.4 Painting over exposed surfaces: Painting the exposed surfaces of SQM superstructure with Anticarbonation / Anticorrosive Acrylic Paint with all labour material tools and plants complete job including surface preparation at joints in approved colour.

434.00

132.00

A.3.5 Providing and installing Single strip seal expansion joints as per Clause 2607 of MORTH specifications for Road and Bridge Works (Fourth Revision) 2001 supplemented with manufacturers recommendations. Entire installation is to be carried out strictly in the presence of manufacturer's representative only, at all times. The seal of the expansion joint shall be such as not to permit any dust collection at all times.

(i) with a total allowable movement upto 140 mm A) The scope of work in the item includes: 1)Cost of all materials, labour, equipment and other incidental charges for execution of this item. Supervision during installation by the manufacturer is also included. 2)Installation & fixing of expansion joints as per manufacturers specifications and design / drawing approved by the engineer-incharge including chipping of concrete, cleaning of concrete and reinforcement bars, leveling, necessary shuttering, pre-setting, welding etc.

RM

96.00

7,508.00

3)Item to include necessary provision and filling of recess for the expansion joints at no extra cost. 4)The item includes the cost of testing of all the materials involved in the execution of the item as per QAP and testing of completed and installed joints as per the acceptance criteria of MORTH. B) Mode of Measurement : 1) The expansion joints shall be measured in running meters. The length payable is the actual length provided at site including vertical parts of kerbs / crash barriers, footpath etc. A.3.6 Drainage System: Providing and laying G.I drain pipes, spouts, GI steel gratings over formed holes in deck slab, fixing 100 mm dia G.I runner pipes and 100 mm dia G I downtake pipes of approved quality at every pier etc. as per approved drawings including bends, collars, clamps, fasteners, threading etc., complete.

a) 100 mm dia water spout with GI grating. b) 100 mm dia P.V.C runner pipes / downtake pipes. A)The scope of work in the item includes: 1)The providing, placing, joining and fixing the drainage pipes with all necessary fittings, tools and tackles, bends,clamps, screws etc., complete as per the approved drawing. 2)The cost of works to make taping all points to be leak proof, tested etc. including all couplers, materials, manpower and tool and tackle etc. complete as per the direction of Engineer-in-charge.

Nos. M

73.00 599.00

910.00 1,212.00

B) Mode of Measurement : 1) The measurement shall be made in numbers for the drainage port supplied and installed at site. The payment for the pipes will be made in Running meters. The quantity will be restricted to the length as shown in the approved drawings.

A 3.7 Reinforcement: Supply, cutting, Bending, fixing in position MT reinforcement of any diameter, HYSD or TMT as per relevant BIS specification and drawing in all RCC/PSC works of this schedule A-3. The rate shall include cost of all material including tying wire, labour, transportation, storing and all other incidental charges, tools & plants etc. Payment shall be made as per theoretical requirement and no wastage shall be paid. Rate shall include all costs.

145.00

59,064.00

SUB TOTAL - A-3 A.4 STAIRCASE IN RAILWAY SPAN

57,288.00

720,768.00

66,430.00 725,988.00

8,564,280.00

17,189,166.00

A.4.1

Earth work in excavation for casting foundation of stair case in all type of CUM soils, weathered rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts, and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap/foundation. The cost of backfilling around the pile cap/foundation and restoration of road, if required shall be included.

875.00

54.00

A.4.2

Providing and laying plain cement concrete M15 (aggregate 20mm CUM nominal size) under foundations. The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer in charger. Payment shall be made based on approved plan dimensions for PCC.

58.00

6,912.00

A.4.3

Providing and laying reinforced cement concrete for construction of CUM staircase in M-35 grade concrete using Ordinary Portland Cement of grade 43 or 53, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, which will be paid as per item number A 4.4).

448.00

8,787.00

A 4.4

Reinforcement: Supply, cutting, bending, with all leads, lifts and depths, fixing in position reinforcement of any diameter, HYSD or TMT as per relevant BIS specification and drawing in all RCC/PSC works of this schedule A-4. The rate shall include cost of all material including tying wire, binding wire, cover block, provision of stools, chairs, spacer bars, support bars , labour, transportation, storing and all other incidental charges, tools & plants etc complete. Payment shall be made as per theoretical requirement and no wastage shall be paid. Rate shall include all costs.

MT

54.00

58,455.00

A.4.5

Supplying and fixing non-skid tiles/ chequered tiles (25mm thick) on the SQM steps of staircase as per drawings and specification complete as directed by engineer Total of A-4 schedule =

568.00

903.00

47,250

400,896

3,936,576

3,156,570

512,904.00

8,054,196.00

A-5 FOOT OVER BRIDGE A.5.1 Earth work in excavation for casting foundation of stair case in all type of CUM soils, weathered rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts, and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap/foundation. The cost of backfilling around the pile cap/foundation and restoration of road, if required shall be included.

660

54.00

A.5.2 Providing and laying plain cement concrete M15 (aggregate 20mm CUM nominal size) under foundations. The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer in charger. Payment shall be made based on approved plan dimensions for PCC.

40

6,912.00

CUM A.5.3 Providing and laying reinforced cement concrete for construction of staircase in M-35 grade concrete using Ordinary Portland Cement of grade 43 or 53, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design (proposed by contractor), as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, which will be paid as per item number A.5.4.

341

8,787.00

A 5.4 Reinforcement: Supply, cutting, bending, with all leads, lifts and depths, fixing in position reinforcement of any diameter, HYSD or TMT as per relevant BIS specification and drawing in all RCC/PSC works of this schedule A-5. The rate shall include cost of all material including tying wire, binding wire, cover block, provision of stools, chairs, spacer bars, support bars , labour, transportation, storing and all other incidental charges, tools & plants etc complete. Payment shall be made as per theoretical requirement and no wastage shall be paid. Rate shall include all costs.

MT

45

58,455.00

A.5.5 Supplying and fixing non-skid tiles / chequered tiles (25mm) on the steps SQM of staircase as per drawings and specification complete as directed by engineer Total of A-5 Schedule = TOTAL SCHEDULE A1+A2+A3+A4+A5

952

903.00

(RS)

35,640

276,480

2,996,367

2,630,475

859,656

6,798,618.00 95,900,424.14