Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ocated 275 miles inside the Arctic Circle on Alaskas North Slope, Prudhoe Bay knows cold. Cold is winds up to 70 miles per hour, temperatures down to -80 F and daylight, or more accurately, twilight only an hour or two a day. In this almost unworldly cold, the ground stays permanently frozen, a solid mixture of soil and ice.
foundation to settle. To prevent this, a network of steel c u l ve rts was permanently installed in the 6-foot-deep g ra vel subbase beneath the footings and floor slab. Aft e rw a rd, cold outside air was constantly circulated through the culve rt s, preventing the ice lenses in the soil from thawing and thus keeping the building from settling. When the weather turns warm, the thermostatically controlled circulation system automatically shuts off, enabling the ground beneath to stay frozen. Covering a 25,000-square-foot floor area, this unusual refrigeration system required over 4000 lineal feet of 12-inch-diameter steel culve rt . To reduce the amount of heat loss into the ground, closed cell extruded polystyrene foam insulation was also placed under the slab and footings, a 6-inch layer of 30-psi foam under the slab and 6-inch layers of 60-psi foam under the footings and grade beams. The bearing capacity of the polystyrene itself exceeds that of the 6foot-thick, compacted gravel subbase.
Arctic concreting
Four hundred thirty yards of 3000-psi concrete was needed for footings and grade beams. Howe ve r, to withstand the severe Alaskan cold, a 7-sack mix with an effective 4000-psi strength was used. Aggregate was
Closer spacing of smaller wires at the edges of fabricated reinforcing mats helped save steel costs. Minimum lap for 12x12 welded wire in this case became 8 inches instead of 14 inches. screened from local river gravel; maximum aggregate size was 112 inches. During placement of the footings, a make-shift tent of plastic, parachute fabric and old tarps was erected over the site and heated by portable, dieselfueled heaters to +40 F. After the footings were cast, the building shell was erected, heated by the same heaters, and the floor slabs were cast.
Reinforcement economies
The garage facility was designed for maintenance of all types of heavy equipment, including both rubbertired and -tracked vehicles. Slabs for the tracked-vehicle bays were constructed 12 inches thick with wide flange structural steel beams inlaid flush with the floor surface. Thus vehicle tracks could ride on steel beams, steel on steel. Slabs for the rubber-tired vehicle bays were placed 10
Steel placer positions 12x12W12xW12 mats on concrete block prior to pouring concrete. Six-inch spacing of edge wires on these mats saved steel in all of the lap zones.
inches thick. The main slab areas required 950 cubic yards of concrete. All were reinforced with 12x12 W12xW12 high strength welded wire fabric mats. In these mats, 0.4-inch-diameter smooth wires are spaced 12 inches on center each way. Mats were 7 feet wide and 19 feet 8 inches long, with special lengths provided to accommodate pour line configurations of the slab. Two W6.0 edge wires were provided 6 inches apart on each panel edge to provide continuous steel area throughout the pour and to reduce steel buildup in the lap zones. The required minimum lap splice length was one space plus 2 inches. Since the manufacturer provided a 6-inch edge spacing as a stock feature of the 12x12 W12xW12 mesh, an 8-inch lap could be used. This reduced the weight of steel needed in the lap by 7.6 percent, compared with mats having 12-inch spacing extended to the edge. Reinforcement mats had to be supported 2 inches from the top of the slab. Two-man crews placed these structural mats at a rate of 4.8 tons per man per day.
PUBLICATION #C820780
Copyright 1982, The Aberdeen Group All rights reserved