Sei sulla pagina 1di 28

Building B ildi Infrastructure: I f t t Challenges and Opportunities

- Gajendra Haldea Planning Commission


March 23 , 2010 Vigyan Bhawan, New Delhi

Infrastructure Deficit
Highways
70 70,548 548 Km of NH (2% of network, network 40% of traffic): only 17% Four Fourlane; 53% Two-lane; and 30% Single-lane

Ports
Inadequate I d t berths, b th rail il / road d connectivity ti it and d draft d ft are constraints t i t

Airports
Inadequate q capacity: p y Runways, y aircraft handling g capacity, p y p parking g space & terminal buildings

Railways
Old technology; saturated routes: slow average speeds (freight: 22 kmph; passengers: 50 kmph); low payload to Tare ratio (2.5)

Power
14% peaking ki d deficit fi it and d 11% energy shortage; h t 27% T&D losses; l absence of competition; and inadequate private investment

Projected Investment in Infrastructure


140.0
XI Plan:

120.0 100.0
US $ Bn.

Revised Projections: US $ 514 bn. (Rs.20,54,205 cr.)

X Plan

80.0
X Plan:

60.0 40.0 20.0 0.0

Actual: US $ 226.5 bn. (Rs. 9,06,074 cr.)

Business us ess as Usual: Usua : US$ 408 08 b bn (Rs. 16,32,436 cr.)

XI Plan: Business as Usual

XI Plan: Projected

Projected Investment in Infrastructure (Revised) (at 2006-07 prices)


X Plan Sectors Electricity (incl. NCE) Roads and Bridges g Telecommunication Railways (incl. MRTS) Irrigation (incl. Watershed) Water Supply & Sanitation Ports Airports Storage Oil & Gas Pipelines Total Rs. crore 340,237 127 107 127,107 101,889 102,091 106,743 60,108 22 997 22,997 6,893 5,643 32,367 906,074 Share (%) 37.55 14 03 14.03 11.25 11.27 11.78 6.63 2 54 2.54 0.76 0.62 3.57 100 XI Plan Rs. crore 658,630 278 658 278,658 345,134 200,802 246,234 111,689 40 647 40,647 36,138 8,966 127,306 2,054,205 Share (%) 32.06 13 57 13.57 16.80 9.78 11.99 5.44 1 98 1.98 1.76 0.44 6.20 100

Revised Mid-Term Projections j


Compared to original Eleventh Plan projections, the revised projections are:
Telecom: (+) 34% Irrigation: (+) 3% Power: (-) 1% Roads: (-) 11% Water Supply: (-) 23% Railways: (-) 23% Ports: (-) ( ) 53%

Investment by Centre, States & Private Sector


(Rs. crore at 2006-07 prices) (per cent share in brackets)

Tenth Plan Centre States Private Total


370,381 370 381 (41) 310,473 310 473 (34) 225,220 225 220 (25) 906,074

Eleventh Plan
690,926 690 926 (34) 620,367 620 367 (30) 742,912 742 912 (36) 2,054,205

Investment in Infrastructure as % of GDP


9.00 8.00 7.00 6.00 % of GDP P 5.00 4.00 3.00 2.00 1 00 1.00 0.00 200 02-03 200 03-04 200 04-05 200 05-06 2006-07 2007-08 2008-09 2009-10 2010-11 11-12 201

Total Public Private

Projected figures for 2009-12

Growth of Private Investment


(Rs. crore at 2006-07 prices)
250,000 208,413 200,000 (Rs. cr rore)

150,000 121,138 100,000 59,533 50,000 23,384 -

Projected figures for 2009-12

Relative Share of Private Investment (%)


90 80 Private 70 60 % Share 50 40 30 20 10 2002-03 2003-04 2004-05 2005-06 -07 20062007-08 2008-09 2009-10 2010-11 2011-12 Public

Projected figures for 2009-12

Sector-wise share (%) of private investment d i the during th Eleventh El th Plan Pl


90

82
80 70 60

80

64

per cent

50 40 30 20 10 -

44

16 4
Electricity Telecom Roads Railways Ports Airports

Telecom: A spectacular success story


Private investment increased from Rs. Rs 5 5,936 936 cr. cr in 2002-03 to Rs. 51,019 cr. in 2009-10 (8.6 times) Share of p private investment increased from 28 % in 2002-03 to 80% in 2009-10 Target of 15% tele-density by 2010 was achieved 3 years ahead of schedule Over 1 crore mobile connections added every month; total of 54 5 crore by 54.5 b February Febr ar 2010 Lowest tariffs in the world C Competition i i and d access to consumers seems the h d driving i i force

Power: Constrained growth g


T&D losses exceed 27%; provisional losses of Rs. 40,000 cr. in 2008-09; 2008 09; 14% peak shortage & 11% energy shortage About 5,900 cr. units sold by traders to utilities at average price of Rs. 5.9 p per unit for Rs. 33,000 cr.- highest g tariff in the world Traded power is purchased by state-owned utilities only; public sector is the sole buyer of this high-cost power Unregulated trading will increase consumer tariffs and utility losses Complete lack of open / last mile access to consumers despite the mandatory provisions of the Electricity Act Ab Absence of f competition titi and d access to t consumers seems the th principal cause for inadequate investment and shortages

Projected j Investment in Twelfth Plan


300.0 250 0 250.0

XI Plan: Revised projections:

XII Plan: Projected: US $ 1,025 bn. (Rs. 40,99,240 cr.) XI Plan

200.0 US $ Bn n.

US $ 514 bn. (Rs. 20,54,205 cr.)

150.0 XII Plan 100.0 Business as Usual: US $ 857 bn. (Rs. 34,28,918 cr.) 50 0 50.0 XII Plan BAU

0.0

Share of Private Investment in Twelfth Plan


(Rs. crore at 2006-07 prices)
700,000

Total Projected Investment: Rs.40,99,240 crore


600,000

Public
500,000

Private

Rs. crore

400,000

300 000 300,000

200,000

100,000

Policy Challenges
Large capacity addition
Time-bound delivery under budgetary constraints World class y yet cost effective Commercially sustainable yet affordable

Attracting private investment


Policy and regulatory framework for PPPs Institutional restructuring and reorientation Financial support to PPPs

Division of Labour
Public Sector to continue, and even expand
- Especially in segments that cant be commercialised, such as rural roads

Increased reliance on PPPs for additionality & improved efficiency


- In segments that can be commercialised, eg. roads, ports, airports & rail concessions

Independent private investment whenever feasible


- Enable competition in power generation, airlines, container trains etc. etc

Stages of PPPs
I. Public sector provision of Infrastructure: Command & Control
- PPP by exception

II. Introduction of PPPs: The Transition - still on in some sectors/states


- Largely negotiated, often opaque - Often driven by private beneficiaries (eg. (eg Dhabol, Dhabol NOIDA bridge)

III. PPPs gain acceptability: Enhancing welfare & efficiency


- T Transparent, t competitive titi and d fair f i - Driven by the government; good governance becomes the key j is to attract p private capital p in p public p projects j - Objective

Indian PPP projects are mostly in Stage III

Governance: Typical Issues


Unwillingness of incumbents to cede control over construction & operation of projects Denial of level playing field Inadequate and inefficient roll out of projects
- The demand for PPP projects is far greater than their supply

Incumbent mindset constitutes a major challenge

The Paradigm Shift: Wider Ownership


Line Ministries/Departments: p
- often encumbered by incumbent pressures & conflicts of interest against PPPs - have inadequate inter inter-sectoral/ sectoral/ inter inter-disciplinary disciplinary exposure

Successful reform initiatives have universally relied on:


- political liti l leadership l d hi - creation of independent & inter-ministerial processes

PPP has gained wide ownership and support across the government. A paradigm shift has occurred.

Governance Structure for PPPs


Constitution of a Cabinet Committee on Infrastructure (CCI) Prime Minister is the Chairperson Ministers of Infrastructure Ministries, Finance Minister and Deputy
Chairman, Planning Commission are members

PPP Appraisal Committee Appraises & recommends all PPP projects of the Central Government Chaired by y Finance; ; appraisal pp by y Planning g Commission Cleared 144 projects with an investment of Rs. 1,30,915 cr. (US$ 33 bn) Empowered Committee Approves proposals for Viability Gap Funding (upto 20% of capital costs) Chaired by Finance; appraisal by Planning Commission Cleared 55 projects with an investment of Rs. Rs 39,736 39 736 cr cr. (US$ 10 bn)

Governance Structure for PPPs (contd.) (contd )


PPPs have been integrated g in the p planning gp process Ministries retain their role but work closely with CCI to develop & implement the vision for world world-class class infrastructure Greater reliance on inter-ministerial and inter-disciplinary dialogue to enrich outcomes and eliminate conflicts of interest. interest Consultations with stakeholders, including users and investors Simplification & standardisation of documents and processes

Framework Documents
Model Concession Agreements published for PPP in:

National Highways State Highways Ports Operation & Maintenance of Highways Urban Rail Systems (Metro rail) Container Train Operation Redevelopment of Railway Stations N Non-metro Ai Airports Greenfield Airports Procurement-cum-Maintenance Procurement cum Maintenance of Locomotives Transmission of electricity

Framework Documents (contd.)


Model Bidding Documents for PPP projects

Request for Qualification Document (RFQ) for pre-qualification of bidders Request for Proposal (RFP) for selection of bidder RFP for Selection of Technical Consultants RFP for Selection of Legal Advisors RFP for Selection of Financial Consultants

Guidelines for Appraisal, Approval and Assistance for PPP projects

Guidelines for Financial Support to PPPs in Infrastructure (VGF Scheme) Guidelines for Appraisal and Approval of PPP Projects (PPPAC) S h Scheme f for Fi Financing i th through hI India di Infrastructure I f t t Finance Fi Co. C (IIFCL) Guidelines for establishing Joint Ventures (JVs) in Infrastructure

Financial support s pport to PPPs


Viability Gap Funding (VGF) upto 20% of capital costs based on bidding 159 central and state projects with an investment of Rs. 177,365 cr. (US$ 44 bn) cleared with a VGF commitment of Rs. 51,629 cr. (US$ 13 bn) India Infrastructure Finance Company (IIFCL) provides upto 20% of f capital it l costs t as long-term l t debt d bt for f viable i bl projects j t IIFCL has sanctioned Rs. 21,000 cr. (US$ 5 bn) for 125 projects

Some illustrative PPP projects


Delhi, Mumbai, Hyderabad & Bangalore airports Jaipur-Kishengarh and Delhi-Gurgaon Highways Two T metro-rail il projects j in i Mumbai M b i Four Ultra mega Power Projects: Sasan(MP), Mundra (Gujarat), Krishnapatnam (AP) and Tilaiya (Jharkhand) Container terminals at JNPT, Chennai & Tuticorin 15 concessions for operation of container trains

Initiatives at State level


States have initiated several PPP projects State PPP projects are availing upto 20% of capital costs as VGF grant from Central Government They are also availing upto 20% of capital costs as long-term loans from IIFCL Technical assistance being provided by Planning Commission Assistance for capacity building being provided by the Finance Ministry

Way y forward
Reinforce the enabling environment for private investment Improve the delivery of public sector projects Ad Adopt standardised d di d documents d and d processes for f accelerating l i competitive investment flows Leverage budgetary resources & multi-lateral loans for PPPs Accelerate the roll-out roll out of PPP projects Objective is to create world class infrastructure

Thank You

For further details please visit http://infrastructure.gov.in

Potrebbero piacerti anche