Sei sulla pagina 1di 11

Chapter- 2

Land & Offshore Rigs

2.1 Introduction
Operations proceed in accordance with terms of a permit issued by the regulatory agency with jurisdiction. Normally, a drilling location is graded, a conductor pipe is set to support subsequent casing strings, blowout control equipment is installed and tested for well safety, the drilling rig and auxiliary equipment is moved in and set up, and drilling operations are underway.

2.2 Steps to drilling a well


Before drilling commences, certain arrangements and decisions have to be made. These may include: 1. 2. 3. 4. 5. Leasing of the land. Building of roads. Moving the equipment in. Drilling method. Depth and size of well.

2.3 Drill-site selection


The selection of the drill site is based largely on the geological evidence indicating the possible accumulation of petroleum. The exploration company will want to drill the well at the most advantageous location for the discovery of oil or gas. Surface conditions, however, must also be taken into consideration when selecting the drill site. There must be a nearly level area of sufficient size on which to erect the drilling rig, excavate reserve pits, and provide storage for all of the materials and equipment that will be required for the drilling program. All of the required legal matters need to have been attended to, such as acquiring a drilling permit, surveying of the drill site, and so on. When all of these matters have been resolved, the work on site preparation will begin.

2.4 Drill-site preparation


Once the drill site has been selected and surveyed, a contractor or contractors will move in with equipment to prepare the location. If necessary, the site will be cleared and leveled. A large pit will be constructed to contain water for drilling operations and for the disposal of drill cuttings and other waste. A large-diameter hole will be drilled to a shallow depth and lined with conductor pipe.

A large, rectangular cellar is excavated under the rig floor, dug before drilling to provide space for equipment at the top of the wellbore. The cellar serves to collect drainage water and other fluids which are jetted at intervals. A smaller-diameter hole called a "rat hole" is drilled near the main bore hole. The rat hole is lined with pipe and is used for the temporary storage of a piece of drilling equipment called the "kelly." When all of this work has been completed, the drilling contractor will move in with the large drilling rig and all the equipment required for the drilling of the well. After those actual drilling operations on the well is started. Start of the actual drilling usually called spud-in. The term is handed down from cable tool operations in the early days of the oil industry.

2-5 The Rig Crew

Drilling is usually done by a service company or drilling contractor. The drilling crew is composed of a toolpusher, a driller, a derrick man, and several roughnecks. The toolpusher

manages the drilling operation. The driller operates the rig. The derrick man helps with the drilling mud and in removing pipe from the hole. Roughnecks help with the drilling operation and maintaining the drilling equipment.

2-6 Rotary Drilling rigs


Drilling rig is a machine used to drill a wellbore. In onshore operations, the rig includes virtually everything except living quarters. Major components of the rig include the mud tanks, the mud pumps, the derrick or mast, the drawworks, the rotary table or topdrive, the drillstring, the power generation equipment and auxiliary equipment. Rotary drilling rigs are used for almost all drilling done today. The hole is drilled by rotating a bit to which a downward force is applied. The bit is turned by rotating the entire drill string, which consists of drill pipe and heavy, thick-walled pipe, called drill collars, which supply the downward force. The cuttings are lifted to the surface by circulating a fluid down the drill string, through the bit, and up the annular space between the hole and the drill string. The cuttings are filtered from the drilling mud at the surface by a device called a shale shaker.

A blowout prevention system is used to shut in the well in case of an emergency condition. Most rigs are powered electrically; diesel engines are used to generate the electrical power.

Figure 2-1 : Rotary drilling rig Generally drilling rig classified to two types, onshore and offshore rigs. Onshore rigs are different tan that offshore one. Figure 2-2 shows the classifications of rotary drilling rigs.

Figure 2-2: Classifications of rotary drilling rigs

2.6.1 Land (onshore) Rigs

Figure 2-3 land drilling rig

2-6-2 Offshore Rigs


Onshore rigs are different tan that offshore one as general layout. Both types (offshore and onshore) perform the same principles of operations (hoisting, circulating and rotating. A power system is required to perform those operations). There are different types of offshore rigs. A swamp barge is used in water depths of less than 20 feet. It is towed to the location and sunk in place. A jacket rig with tender is also used in shallow waters. The platform is fixed, and the drilling package is lifted onto the platform by the tender. For water depth less than 350 feet, a jack-up rig is often used. The rig is towed to the location with the legs elevated. On location, the legs are lowered and the rig is jacked-up above the wave action by means of hydraulic jacks. For deeper waters, a semi-submersible rig is used. The rig is towed to the location, and is partially submerged for stability. The rig is usually anchored over the hole. Once a large field has been discovered offshore, a large fixed platform may be employed to drill development wells.

Drill ships are used to drill in very deep waters. However, they are limited to areas where wave action is not severe.

Swamp barge

Jacket with tender

Jack-up

Semisub

Fixed Platfor m

Drillship

Figure 2-4: different types of offshore rigs

Potrebbero piacerti anche