Sei sulla pagina 1di 2

Pending Permit Progress Report by Program Interest ID

Click here for a detailed description Run At: 05/04/13 12:00 pm

Program: Land Use 215 AND 235 BIRCHWOOD AVE Cranford Twp NJ 07016

CRANFORD REDEVELOPMENT ASSOCIATES LLC (200308-0006.1)


FHA 110001 Flood Hazard Area
Program Description DEP Contact Name DEP Contact Phone Technical Suppport Land Use (609) 777 - 0454 Center Also known as Stream Encroachment, is a permit required when an activity is proposed within a river, lake or stream or their associated floodplains.

Individual Permit Clock


Ticking

Days Days Days Allotted Elapsed Remaining


90 16

Permit Review Status


74 In Process

Standard Tasks
Receive Application Start Administrative Review End Administrative Review Issue Notice of Technical Deficiency Receive Response to Notice of Technical Deficiency Issue Notice of Technical Deficiency Receive Response to Notice of Technical Deficiency Start Technical Review End Technical Review Final Decision awaiting from: Opara, Valda

Completed Date Assigned To


12/19/2011 12/20/2011 12/20/2011 1/17/2012 2/13/2012 3/8/2012 4/18/2013 Werner, Joanne Zigrand, Jeff Zigrand, Jeff Opara, Valda Opara, Valda Opara, Valda Opara, Valda Opara, Valda Opara, Valda

FHA 110002 Flood Hazard Area


Program Description DEP Contact Name DEP Contact Phone Technical Suppport Land Use (609) 777 - 0454 Center Also known as Stream Encroachment, is a permit required when an activity is proposed within a river, lake or stream or their associated floodplains.

Verification Clock
Ticking

Days Days Days Allotted Elapsed Remaining


90 16

Permit Review Status


74 In Process

Standard Tasks
Receive Application Start Administrative Review End Administrative Review Issue Notice of Technical Deficiency Receive Response to Notice of Technical Deficiency Issue Notice of Technical Deficiency Receive Response to Notice of Technical Deficiency Start Technical Review End Technical Review Final Decision awaiting from: Opara, Valda

Completed Date Assigned To


12/19/2011 Spera, Vickie Opara, Valda Opara, Valda 1/18/2012 2/13/2012 3/8/2012 4/18/2013 Opara, Valda Opara, Valda Opara, Valda Opara, Valda Opara, Valda Opara, Valda

HOW TO INTERPRET THE PENDING PERMIT PROGRESS REPORT


The content of this report provides the user with real time access to information regarding applications that are under review by the DEP. Land Use permit applications are available only if received January 1, 2006 or later. In conjunction with the DEPs permitting standardization process, this report displays standard tasks required during the review process of any type of permit application along with the completed date and person assigned to complete the task. The standard tasks are: Receive Application Start Administrative Review Send Notice of Administrative Deficiency (NAD) Receive Response to NAD End Administrative Review Start Technical Review Send Notice of Technical Deficiency (NTD) Receive Response to NTD End Technical Review Start Public Input End Public Input Issue Final Decision In addition, it provides a single point of contact for questions regarding each application as well a clock information tha t consists of the following data elements: Days Allotted The number of days, whether regulatory or Program commitment, DEP expects to reach a final decision on this application. Days Elapsed The number of days that have passed during the review process, that excludes any days during a public hearing or where DEP is waiting to receive deficient information. Days Remaining The number of days remaining for DEP to make a decision based on the Days Allotted. Permit Review Status This data element will display In Process or Backlogged. In Process indicates that a final decision has not been made and the DEP has not exceeded the Days Allotted to make a decision. Backlogged indicates that that a final decision has not been made and the DEP has exceeded the Days Allotted to make a decision. Lastly, the report incorporates color coding of Red to identify an event that would stop the clock and Green to identify an event that would start the clock.