Sei sulla pagina 1di 2

KILN MAINTENANCE

I A better kiln coating?


by Guilherme Ferreira and After studying the kiln preheating and feeding procedures of
Luiz Pinho, Dynamis Ltda, hundreds of kilns around the world, Dynamis experts show two
Brazil opposite tendencies and examine the characteristics of each one. This
article discusses how the proper formation of kiln internal coating
can dramatically improve the life of refractory bricks.

S
ometimes one may face a pretty the kiln operation has reached a steady chamber (red dotted line), while in other
intriguing fact: two kilns constructed situation. The use of one of those fuels is cases the raw meal feeding starts at even
according to the same design, proper for a better combustion control, higher temperatures (solid blue line).
practically at the same time and fed with making it easier to adjust temperature Two main tendencies can be identified,
virtually the same raw meal and fuel peak position and to follow the heating not properly referring to the preheating
present different behaviour. When you ask curve through an accurate handling itself, but concerning the flame
the operators which kiln is best, they will of fuel flow. Additionally, those fuels adjustment after the desired smoke
be unanimous: kiln “A” is better than kiln make flame stability a lot easier under chamber temperature had been reached
“B”. Why do these things happen? cold secondary air conditions, even at and raw meal feeding had started.
Every equipment has its own history. relatively low excess-air rates. Also, it
Incidents that may have occurred to is important to control the combustion 1. Classical procedure
one may never happen to the other. We gases draft, which has an important role Most of kiln operators had the tendency
know that, depending on the kind of using a narrow and soft flame,
of incident that can occur to a kiln, in many cases a very long one.
its performance can be affected for Sometimes the flame length was a
a long time, if not for the rest of its requirement, but normally it was a
working life. Particular fails demand mere consequence of the combustion
specific maintenance solutions and the parameters that had been adopted to
succession of different events to each protect the bare lining and nothing
part of the kiln can lead to different could be done to shorten the flame,
behaviour with identical kilns. if so wanted. The lack of resources
This article deals with one of the in the main burner for shaping the
most important operations that will flame is often worsened by the cold
affect a clinker kiln performance, secondary air. Figure 2 presents a
especially concerning refractory lining diagram showing the evolution of the
Figure 1: kiln heating variations
life: the phases of preheating and protective coating over the refractory
feeding a new kiln or one that has brick lining in a kiln running under the
suffered a large lining change. During in the temperature profile, including both so-called classical procedure.
many years, Dynamis experts have been kiln and preheating tower. Normally, the
designing and putting to work hundreds oxygen content of those gases will vary What can we say about this
of combustion systems for rotary kilns. within 4-6 per cent at preheater exhaust, procedure?
During new burner start-up operations, depending on kiln characteristics (general • the operator must keep the flame away
normally following major refractory dimensions, number of cyclone stages, from the bricks even after a significant
maintenances, it was very common to false air infiltrations, etc). increase in fuel flow
hear from operation managers: “Let us Figure 1 shows some variations • as the flame tends to be long,
follow the recommended time multiplied concerning kiln pre-heating procedures. temperature peak will probably be located
by the temperature curve at the smoke The diagram indicates preheating can at upper transition zone
chamber” – and also: “Don’t allow that take 20 to 36 hours, depending on the • the hot meal reaches the upper
flame to impinge on the new bricks!”. type of refractory, as well as the extension transition zone and starts to form the
The manager was totally right. But were of the maintenance services. Mode 1 coating that protects the bricks there
those two recommendations enough to refers to short warm-up. Mode 2 refers to • the coating formation proceeds from
guarantee the desired performance of the a more conventional heating rate. Finally, upper to lower sections passing through
brand new bricks? – Certainly not. Mode 3 corresponds to extended warm- burning/clinkering zone and then to lower
We know that the preheating and up period, which is recommended after transition zone
feeding of a rotary kiln are critical large refractory maintenance or after the • lower transition zone bricks are put
operations. Normally, they are conducted cast of refractory concretes. In some cases under moderate to intense heat flux for a
either with natural gas or fuel-oil until the kiln is fed with 750˚C at the smoke long period of time.

ICR DECEMBER 2005


KILN MAINTENANCE

formation at burning/ may take 20-36 hours, depending on the


clinkering zone and then extension of refractory services. Equally
at upper transition zone; important is a non-interrupted preheating
• lower transition zone process, as break-offs during the operation
bricks are put under may lead to high temperature gradients
intense heat flux for a along brick thickness.
short period of time. Additionally, the smoke chamber (back
end) temperature at which the raw meal
Comments feeding starts is important and defines
The differences between how long the new bricks at lower kiln
the two opposite sections are kept under overheating
procedures become more risk. The use of kiln shell cooling fans
Figure 2: conventional coating formation process critical and take a more in combination with the readings of a
important role in the temperature scanner as important tools
2. Alternative procedure modern kilns, as SHL (Kiln Specific Heat to help operators to shape the internal
The alternative procedure is becoming Loading) increases. For reference, we can coating as required. Concerning those
more and more common and requires make a relation between dry-process kiln fans, both practical observation and
a very good flame pattern control. It technologies and SHLs as follows: theoretical studies show the superiority
consists of working with a shorter flame, Long Dry Kilns 1 to 2 Gcal/hm2 of the high-velocity air streams from
not only during warm-up, but mainly Preheater Kilns 2.5 to 4.5 Gcal/hm2 centrifugal fans over the low-velocity
during kiln feed. Naturally, the care Precalciner Kilns 2.5 to 4 Gcal/hm2 flows from axial fans.
for avoiding flame impingement over Short Precalciner Kilns 3.5 to 5 Gcal/hm2 Finally, adequate coating formation
refractory bricks remains a priority. It should not be a surprise to notice depends very much on the resources for
Figure 3 shows the evolution of the that some precalciner kilns have faced flame shaping offered by the kiln burner,
protective coating over the refractory brick refractory problems – for instance, a provided that raw meal composition is
lining in this case. 90-day basic brick campaign – either at adequate, refractory “coatability” is ok,
burning/clinkering or transition zones solid fuel fineness is according to the
What can be said about this since their start-up and rendered some specifications and a series of secondary
procedure? headaches to people involved until a requirements have been met. _________I
• the operator must have a good control solution was found. On the other hand,
on combustion conditions to place there are records of
temperature peak at lower transition zone; preheater kilns with quite
• once the kiln is fed, the hot meal must good refractory campaigns
reach the lower transition zone as fast as – 1200 days for aluminous
possible, to start coating formation at that bricks at calcining zone
point and protect the bricks; and 400 days for basic
• a little ‘cold blood’ and confidence in bricks at transition and/or
the combustion system resources are clinkering/burning zones.
necessary to the operators, who will see Other operational
the raw meal approaching – but not factors that may have an
passing through – the kiln discharge; influence on the refractory
• once initiated, the coating at lower performance refer to the
Figure 3: alternative coating formation process
transition zone ‘supports’ the coating warm-up period, which

DECEMBER 2005 ICR

Potrebbero piacerti anche