Sei sulla pagina 1di 29

A PROJECT TO STUDY OPERATION OF NTPC SIMHADRI

SUBMITTED BY

ABINASH SAHU
ROLL NO. - 10CM60804 III SEMESTER, MBA (2009-2011)

BANGALORE SCHOOL OF BUSINESS BANGALORE

NTPC shimadri

IN

S.NO. 1. 2. 2.1. 2.2. 2.3. 2.4. 2.5. 2.6. 2.7. 2.8. 2.9 3. 3.1. 3.2. 3.3. 3.4. 3.5. 4. 4.1. 4.2. 4.3. 5. 6.

CONTENTS POWER SECTOR IN INDIA INTRODUCTION TO NTPC MAJOR ACHIEVEMENTS OF NTPC HISTORY OF NTPC VISION AND MISSION OF NTPC NTPC: CULTURE Simhadri NTPC NTPC: CORE VALUES &OBJECTIVES SWOT ANALYSIS DIVERSIFICATION SUBSIDIARIES BUSINESS MODEL OF NTPC OPERATIONS OF THE BUSINESS OPERATING STRATEGIES OF NTPC ORGANIZATION STRUCTURE CORPORATE OBJECTIVE SUPPLY CHAIN MANAGEMENT ISSUES AND CHALLENGES HUMAN RESOURCES FUTURE CAPACITY ADDITIONS CHALLENGES WITH COAL RESOURCES CONCLUSIONS/RECOMMENDATIONS BIBLIOGRAPHY

PAGE NO. 3 5 6 6 8 9 9 10 11 12 13 14 15 21 21 22 23 24 24 26 27 29 29

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

1.

POWER SECTOR IN INDIA

Power development in India is the key to economic development. The power sector has been receiving adequate priority ever since the process of planned development in 1950. Hydro power and coal based thermal power have been the main sources of generating electricity. Nuclear power development is at slower pace, which was introduced in late 60s. The concept of operating power systems on a regional basis crossing the place, the power supply industry have been under constant pressure to bridge the gap between supply and demand. Since Independence in 1947, Indian Power sector progress has been rapid. From mere 1713 MWs of Installed capacity in 1950 the capacity at the end of March 2007 rose to 124569 excluding capacity of renewable energy. Total generation in April2006- March 2007 was 659419 GWs in the utility sector. The per capita consumption of electricity increased from 15 KWHs in 1950 to 619 in 2006-07. Decades of economic planning in India following independence placed significant emphasis on the development of the power sector. Electricity generation capacity with utilities in India had grown from 1713 MW in December 1950 to over 124,287 MW by March 2006. However, per capita electricity consumption remains much lower than the world average and even lower than some of the developing Asian economies. Investment in the sector has not been able to improve access and keep pace with the countrys growing demand for electricity. India has the fifth largest generation capacity in the world with an installed capacity of 152 GW as on 30 September 2009, which is about 4 percent of global power generation. The top four countries, viz., US, Japan, China and Russia together consume about 49 percent of the total power generated globally. The average per capita consumption of electricity in India is estimated to be 704 kWh during 2008 -09. However, this is fairly low when compared to that of some of the developed and emerging nations such US (~15,000 kWh) and China (~1,800 kWh). The world average stands at 2,300 kWh. The Indian government has set ambitious goals in the 11th plan for power sector owing to which the power sector is poised for significant expansion. In order to provide availability of over 1000 units of per capita electricity by year 2012, it has been estimated that need-based capacity addition of more than 100,000 MW would be required. This has resulted in massive addition plans being proposed in the sub-sectors of Generation Transmission and Distribution. India is world's 6th largest energy consumer, accounting for 3.4% of global energy consumption. Due to Indias economic rise, the demand for energy has grown at an average of 3.6% per annum over the past 30 years. In March 2009, the installed power generation capacity of India stood at 147,000MW while the per capita power consumption stood at 612 kWh. The country's annual power production increased from about 190 billion kWh in 1986 to more than 680 billion kWh in 2006. The Indian government has set an ambitious target to add approximately 78,000 MW of installed generation capacity by 2012. The total demand for electricity in India is expected to cross 950,000 MW by 2030.

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

About 75% of the electricity consumed in India is generated bythermal power plants, 21% by hydroelectric power plants and 4% by nuclear power plants. More than 50% of India's commercial energy demand is met through the country's vastcoal reserves. The country has also invested heavily in recent years on renewable sources of energy such as wind energy. As of 2008, India's installed wind power genera tion capacity stood at 9,655 MW. Additionally, India has committed massive amount of funds for the construction of various nuclear reactors which would generate at least 30,000 MW. In July 2009, India unveiled a $19 billion plan to produce 20,000 MW ofsolar power by 2020. The Power sector in India is predominantly controlled by theGovernment of India's public sector undertakings (P SUs). Major PSUs involved in the generation of electricity are National Thermal Power Corporation (NTPC), National Hydroelectric Power Corporation (NHPC) and Nuclear Power Corporation of India(NPCI). Besides PSUs, several state-level corporations, such as Maharashtra State Electricity Board (MSEB), are also involved in the generation and intra -state distribution of electricity. The Power Grid Corporation of India is responsible for the inter-state transmission of electricity and the development of national grid. The Ministry of Power is the apex body responsible for the generation and development of power in India. This ministry started functioning independently from 2 July, 1992; earlier, it was known as the Ministry of Energy. The Union Minister of Power at present is Sushilkumar Shinde, who took charge of the ministry on the 28th of May, 2009.

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

2.

INTRODUCTION TO NTPC

NTPC Limited is the largest thermal power generating company of India. A public sector company wholly owned by Government of India, it was incorporated in the year 1975 to accelerate power development in the country. Within a span of 30 years, NTPC has emerged as a truly national power company, with power generating facilities in all the major regions of the country. Recognizing its excellent past performance and its vast potential, the Govt. of the India has identified NTPC as one of the 'Navratnas' - a potential global giant and also it is going to be identified as one of the Maharatna - giant among the 'Navratnas'. NTPC Limited is the largest thermal power generating company of India. A public sector company, it was incorporated in the year 1975 to acceleratepower development in the country as a wholly owned company of the Government of India. At present, Government of India holds 89.5% of the total equity shares of the company and the balance 10.5% is held by FIIs, Domestic Banks, Public and others. Within aspan of 30 years, NTPC has emerged as a truly national power company, with power generating facilities in all the major regions of the country. Based on 1998 data, carried out by Data monitor UK, NTPC is the 6th largest in terms of thermal power generation and the second most efficient in terms of capacity utilization amongst the thermal utilities in the world. The Group's principal activity is to generate and sell power to state utilities. It also provides consultancy to power utilities and maintains pow er stations. The Group operates in two segments, namely, Power Generation and Others. The Power generation segment includes generation and sale of bulk power to SEBs/State utilities. Other business includes providing consultancy, project management and sup ervision, oil and gas exploration and coal mining. In the Forbes list of World's 2000 largest companies, 2008, NTPC occupies 317th place. With a current generating capacity of 30,144 MW, NTPC has embarked on plans to become a 75,000 MW company by 2017. Presently, Government of India holds 89.5% equity in the company and the balance 10.5% is held by FIIs, Domestic Banks, Public and others. As on date, NTPC's total installed capacity is 27, 904 MW. NTPC's coal based power stations are at: Singrauli (Uttar Pradesh), Korba (Chattisgarh), Ramagundam (Andhra Pradesh), Farakka (West Bengal), Vindhyachal (Madhya Pradesh), Rihand (Uttar Pradesh), Kahalgaon (Bihar), NTCPP (Uttar Pradesh), Talcher (Orissa), Unchahar (Uttar Pradesh), Simhadri (Andhra Pradesh), Tanda ( Uttar Pradesh), Badarpur (Delhi), and Sipat (Chattisgarh). NTPC's Gas/Liquid based power stations are located at: Anta (Rajasthan), Auraiya (Uttar Pradesh), Kawas (Gujarat), Dadri (Uttar Pradesh), Jhanor Gandhar (Gujarat), Rajiv Gandhi CCPP Kayamkulam (Ker ala), and Faridabad (Haryana). NTPC's Power Plants with Joint Ventures are located at Durgapur (West Bengal), Rourkela (Orissa), Bhilai (Chhattisgarh), and RGPP L (Maharastra).
III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

Indias largest power company, NTPC was set up in 1975 to accelerate power devel opment in India. NTPC is emerging as a diversified power major with presence in the entire value chain of the power generation business. Apart from power generation, which is the mainstay of the company, NTPC has already ventured into consultancy, power tr ading, ash utilisation and coal mining. NTPC ranked 317th in the 2009, Forbes Global 2000 ranking of the Worlds biggest companies. The total installed capacity of the company is 31,134 MW (including JVs) with 15 coal based and 7 gas based stations, loca ted across the country. In addition under JVs, 3 stations are coal based & another station uses naptha/LNG as fuel. By 2017, the power generation portfolio is expected to have a diversified fuel mix with coal based capacity of around 53000 MW, 10000 MW thr ough gas, 9000 MW through Hydro generation, about 2000 MW from nuclear sources and around 1000 MW from Renewable Energy Sources (RES). NTPC has adopted a multi pronged growth strategy which includes capacity addition through green field projects, expansionof existing stations, joint ventures, subsidiaries and takeover of stations. NTPC has been operating its plants at high efficiency levels. Although the company has 18.79% of the total national capacity it contributes 28.60% of total power generation due o t its focus on high efficiency. In October 2004, NTPC launched its Initial Public Offering (IP O) consisting of 5.25% as fresh issue and 5.25% as offer for sale by Government of India. NTPC thus became a listed company in November 2004 with the government h olding 89.5% of the equity share capital. The rest is held by Institutional Investors and the Public. The issue was a resounding success. NTPC is among the largest five companies in India in e t rms of market capitalization. At NTPC people before Plant Load Factor is the mantra that guides all HR related policies. NTPC has been awarded No.1, Best Workplace in India among largeorganizations and the best P SU for the year 2009, by the Great Places to Work Institute, India Chapter in collaboration with The Economic Times. The concept of Corporate Social Responsibility is deeply ingrained in NTPC's culture. Through its expansive CSR initiatives NTPC strives to develop mutual trust with the communities that surround its power stations. Right from social to developmental work of the community and welfare based dependence to creating greater self reliance; the constant Endeavour is to institutionalize social responsibility on various levels.

2.1 MAJOR ACHIEVEMENTS OF NTPC


y y y y y

Largest thermal power generating company of India. Sixth largest thermal power generator in the world. Second most efficient utility in terms of capacity utilization. One of the nine P SUs to be awarded the status of Navratna. Provides power at the cheapest average tariffin the country.

2.2 HISTORY OF NTPC


1975  Incorporated in November 1977  TPC acquired the first patch of land at Sanghrauli
III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

 The first batch of executive trainees joined the company 1978  Takeover of management of the Badarpur project .  Construction of the first transmission network Sanghrauli- Korba- Kanpur of 400 KV systems started. 1982  Power Management Institute, Delhi, a centre for education was established 1983  In the very first year of commercial operation , NTPC earned a profit of Rs 4.51 crore in the financial year 1982-83 1985  This year marked the completion of decade (1975 -1985) of NTPCs existence. NTPC achieved a generating capacity of 220 MW by commissioning 11 units of 200 MW each at its various projects in country.  The government of India appr oved the setting of three gas based combine cycle projects by NTPC in Kawat in gujrat, Auraiya in Uttar Pradesh and Anta in Rajasthan. For these projects, the World Bank agreed to provide US$ 485 million, which was the largest single loan in the history of bank. 1987  1989  1990  1992  Crossed the 5000 MW capacity mark. Consultancy division launched Total installed capacity crossed 10000MW Acquisition by the company of Feroz Gandhi Unchahar Thermal Power Station (2x210 MW) from Uttar Pradesh Rajya Vidyut Utpadan Nigam Of Uttar Pradesh

1994  Crossed 15000 MW of installed capacity. 1995  NTPC celebrated 20 yrs of its existence.  A new logo was adopted.  NTPC took over the 460 MW Talcher Thermal power Station from Orrisa State Electricity Board. 1997  Achieved 100 million units generation in one year. 1998  Commissioned the first Naphtha based plant at Kayamkulam with a capacity of 350 MW. 2000  Commenced construction of a first hydro - electricity power project of 800 MW capacity in Himachal Pradesh

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

2002  Three wholly owned subsidiaries viz. NTPC Electric Supply Company Limited, NTPC Hydro Limited, NTPC Vidyut Vyapar Nigam Limited incorporated. 2004  NTPC became a listed company.  NTPC made its debut issue of euro bonds amounting to USD 200 million in international market. 2005  The company rechristened as NTPC Limited in line with its changing business portfolio and transforms itself from a thermal power utility to an integrated power utility. 2008  National Thermal Power Corporation is the largest power generation company in India. Forbes Global 2000 for 2008 ranked it 411th in the world.

2.3 VISION AND MISSION OF NTPC


VISION: To be one of the worlds largest and best power utilities, powering Indias growth. To realize this vision, NTPC has drawn up a detailed Corporate Plan for the period 1997 2012 which represents the company's collective optimism and enthusiasm, inspired by a glorious past, a vibrant present and a brilliant future. The Plan has been prepared in -house in consultation the committed, competent and confident members of the NTPC family. The road map that has been charted out was after a thorough scan of the strengths and weaknesses within the organization as well as opportunities and threats in the environment. Considering multidimensional opportunities in the energy sector, NTPC will adopt a multi-pronged growth strategy for capacity addition through Greenfield sites, expansion of existing stations, takeovers and joint ventures. The capacity addition plans that NTPC have drawn up for the fifteen-year period using all the above strategies to enable the corporation to become a 40,000 MW company by 2012 A.D. MISSION: Develop and provide reliable power, related products and services at competitive prices, integrating multiple energy sources with innovative and eco friendly technologies and contribute to society"  Make available reliable and quality power in increasingly large quantitie s at competitive prices and ensure timely realization of revenues.  Adopt a broad based capacity portfolio including Hydro Power, LNG, Nuclear Power, and non conventional and eco-friendly fuels  Plan and speedily implement power projects using state -of- the art technologies.  Be an integrated utility by implementing strategic diversifications in areas such as power trading distribution, transmission, coal mining, coal beneficiation etc.  Develop a strong portfolio of profitable businesses in overseas markets in cluding technical services, generation assets etc.  Continuously attract and develop committed human resources to match world standards.
III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

 Lead fundamental and applied research for adoption of the state -of-the-art technologies, breakthrough efficiency improvements and new fuels.  Lead developmental efforts in the Indian power sector including assisting state utility reform, policy recover etc.  Be a socially responsible corporate entity with thrust on environment protection, ash utilization, community development, and energy conservation.

2.4 NTPC: CULTURE


Core values are both intensely and widely shared Climate of high behavioral control Low employee turnover High agreement among the employees, for what NTPC stands for. All these point to the fact that strong cohesiveness, loyalty and organization commitment exist in NTPC lowering he attrition Rate.

2.5

Simhadri NTPC:

Address elephone ax Location Govt approved date Approved Capacity/Installed Capacity lant Configuration Land Availability Coal Source Water Source Beneficiary States Approved Investment Associated Transmission System
nits Commissioned

P.O. Simhadri-531 020, Dist. Vishakhapatnam, Andhra Pradesh (STD-08924,STD-Vizag-0891) 243001 243092 Near Pittavanipalem Village,Dist. Vishakhapatnam, Andhra Pradesh 24.07.1997 (Zero date 8.7.1997) 1000 MW 2X500 MW 3384.24 acres (entire land) Kalinga Block of Talcher Coal fields in Orrisa Yeluru canal for sweet water, Sea water for CW system. Andhra Pradesh (100%). Rs.3650.79 Cr. (I Qtr.97). Implemented by AP TRANSCO. Unit-I Commissioning: Feb 2002 Unit-II Commissioning: Aug 2002 JBIC

International Assistance

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

NTPC shimadri

Simhadri is the ambitious project of the National Thermal Power Corporation (NTPC) intended to provide the ever growing power need s of the state of Andhra Pradesh. Infact, NTPC comes to the rescue of about 20 million units of power consumed every day in Andhr a Pradesh. The construction work of the project is under way. Mr. R.C. Srivatsav has been appointed as the General Manager for the Simhadri Project Operations. With the completion of the project, the total power generation capacity of NTPC will reach to 3600 MW in Andhra Pradesh with NTPC Ramagundum already generating 2100 MW a day. The Project was developed near Parawada and 3384acres of land was allocated for the construction of the Thermal plant. The height of theChimney is 275-feet - a record in Asia for being the tallest factory chimney. Near to this are the 165- meter two cooling towers. The Coal for the project will be coming to the plan with a special rail line setup for this. Coal will be drawn from the Mahanadi Coal Fields in Orissa drawing over 6 Million tones of coal every year. The Coal transport f or the NTPC Simhadri Project is expected to begin in December 2002. The water intake for the project for cooling is done by sea water drawn from 8.9 kms away from the Bay of Bengal through an intake -well sized 9100 cubic meters. This intakewell is again the biggest well constructed in the entire India. The project also gets Sweet water from the Yeluru canal. The power generated at NTPC Simhadri will be bought by AP Transco- the power distribution arm of the Electricity Board in the state. The approximateselling price of power is expected to be at Rs. 2.10 as against to the price from private power generation companies which was at Rs. 3 - 4 per unit. The 500 MW First Boilers at the NTPC Simhadri, Boiler was ignited on November 6, 2001. This is a mile stone in the history of NTPC Simhadri. The commencement of the 500 MW first units was expected to begin in March 2002 while the second unit is expected to begin by December 2002. To save the environment from pollution, NTPC Simhadri has taken ample steps. Towards this is the project of planting trees and maintaining greenery around the site.

2.6 NTPC: CORE VALUES &OBJECTIVES


CORE VAL ES This corporate plan provides details of the overall agendafor NTPC. The successful delivery of this agenda would require a committed work force that identifies with and supports the vision. To ensure realization of this corporate agenda, a set of core values should be central to, and govern each activity of the organization. Known as one of the NAVRATAN S of the PSU S NTPC has its following core values. They are known as (BCOMIT) as follows: B-Business Ethics C-Customer Focus O-Organizational & Professional pride M-Mutual Respect and Trust I- Innovation & Speed T-Total quality for Excellence

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

10

NTPC shimadri

2.7 SWOT ANALYSIS


 y y y y y y y y y y y STRENGTHS Largest market share in domestic power generation and a broad customer portfolio across the country. Excellent track record of performance in project implementation and plant operation. Diversified thermal generation portfolio multiple sizes and fuel types. Highly skilled and experienced human resources, exposed to state -of-the art technologies in project execution and power generation. Navaratna status High brand equity among shareholders. Strong balance sheet ability to raise low cost debt. Engineering skills in project configuration and package design. Turnaround ability for old plants demonstrated in the takeover plants of Talcher, Tanda & Unchahar. High credit rating that is indicative of the confidence of lenders. In-house training facility (PMI), CENP EEP, R&D etc that assist in development of the sector. Thrust on reducing social costs of capacity growth strong execution of Resettlement and rehabilitation plans. WEAKNESS Low risk-diversification of business portfolio consists primarily of generation assets. Poor financial health of customers. Functional orientation hampering cross functional perspective in decision making. Long and multi layered procurement process leading to long lead times and process delay. Fragmented IT architecture. Gaps in HR systems such as performance management, rewards and incentives and career development.

 y y y y y y y

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

11

Inadequate deployment of a strong knowledge management system that could assist in improving efficiency and effectiveness in all aspects of the business. y Hierarchy for decision making that affects responsiveness. y Role ambiguity and dilution within different lends of the organization.  OPPORTUNITIES y Expand generation capacities by putting up thermal and hydrocapacities; maintain the position of a dominant generating utility in the Indian Power sector.

NTPC shimadri

y y y y y y y 

Broad base fuel mix by considering imported coal, gas, domestic coal, nuclear power etc with a view to mitigate fuel risks and maintain long run competitiveness. Expand services for EPC, R&M and O&M activities in the domestic as well a s international markets. Backward integrate into fuel management to exercise greater control and understanding of supply economics. Lead the development and commercial deployment of non -conventional energy sources especially in the distributed generationmode. Improve collections by trading, direct sale to bulk customers and the active ro le in allocation in new plants. Execute increased number of power plants that classify for Mega Power Projects status, thereby reducing the cost of the projects and pow er and power generated. Forward integrate into the distribution business in India.

THREATS y Limited experience of operating in a truly liberalized environment with competition. y y y y y y Limited experience of operating in an independently regulated system. Redirecting power may be constrained by inter -regional connectivity. Downward regulatory and competitive pressure on tariffs. Stringent norms for approval of increase in capital costs for projects in eve nt of time overrun. Stringent environmental norms in the future may add to the cost of generation. Absence of an independent regular for coal industry and the delay in private investments lending to the risk of low availability of coal in the future

2.8 DIVERSIFICATION
NTPCs quest for diversification started with its foray into Hydro Power. It has, since then, been moving towards becoming a highly diversified company through backward, forward and lateral integration. The company is well on its way t o becoming an Integrated Power Major, having entered Hydro Power, Coal Mining, Power Trading, Equipment Manufacturing and Power Distribution. NTPC has made long strides in developing its Ash Utilization business. In its pursuit of diversification, NTPC h as also developed strategic alliances and joint ventures with leading national and international companies.


III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

Hydro Power: In order to give impetus to hydro power growth in the country and to have a balanced portfolio of power generation, NTPC entered hydropower business with the 800 MW Koldam hydro projects in Himachal Pradesh. Two more projects have also been taken up in Uttarakhand. A wholly owned subsidiary, NTPC Hydro Ltd., is setting up hydro projects of capacities up to 250 MW.

12

NTPC shimadri

Coal Mining: In a major backward integration move to create fuel security, NTPC has ventured into coal mining business with an aim to meet about 20% of its coal requirement from its captive mines by 2017. The Government of India has so far allotted 7 coal blocks to NTPC, including 2 blocks to be developed through joint venture route. Coal Production is likely to start in 2009 -10. Power Trading: 'NTPC Vidyut Vyapar Nigam Ltd.' (NVVN), a wholly owned subsidiary was created for trading power leading to optimal utilization of NTPCs assets. It is the second largest power trading company in the country. In order to facilitate power trading in the country, National Power Exchange Ltd., a JV between NTPC, NHPC, PFC and TCS has been formed for operating a Power Exchange. Ash Business: NTPC has focused on the utilization of ash generated by its power stations to convert the challenge of ash disposal into an opportunity. Ash is being used as a raw material input for cement companies and brick manufacturers. NVVN is engaged in the business of Fly Ash export and sale to domestic customers. Joint ventures with cement companies are being planned to set up cement grinding units in the vicinity of NTPC stations. Power Distribution: NTPC Electric Supply Company Ltd. (NESCL), a wholly owned subsidiary of NTPC, was set up for distribution of power. NESCL is actively engaged in Rajiv Gandhi Gramin Vidyutikaran Yojanaprogramme for rural electrification and also working as 'Advisor cum Consultant' for Ministry of Power for implementation of Accelerated Power Development and Reforms Programme (APDRP) launched by Government of India. Equipment Manufacturing: Enormous growth in power sector necessitates augmentation of power equipment manufacturing capacity. NTPC has formed JVs with BHEL and Bharat Forge Ltd. for power plant equipment manufacturing. NTPC has also acquired stake in Transformers and Electricals Kerela Ltd. (TELK) for manufacturing and repair of transformers.

2.9 SUBSIDIARIES : NTPC Electric Supply Company Ltd (NESCL The company was formed on August 21, 2002. It is a wholly owned subsidiary company of NTPC with the objective of making a foray into the business of distribution and supply of electrical energy, as a sequel to reforms initiated in the power sector. NTPC Vidyut Vyapar Nigam Ltd (NVVN

The company was formed on November 1, 2002, as a wholly owned subsidiary company of NTPC. The companys objective is to undertake sale and purchase of electric power, to effectively utilize installed capacity and thus enable reduction in the co st of power. NTPC Hydro Ltd (NHL The company was formed on December 12, 2002, as a wholly owned subsidiary company of NTPC with an objective to develop small and medium hydroelectric power projects of up to 250 MW. Pipavav Power Development Co Ltd (PPDCL A memorandum of understanding was signed between NTPC, Gujarat Power Corporation Limited (GPCL) and Gujarat Electricity Board (GEB) in 2004 for development of a 1000 MW
III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

13

NTPC shimadri

thermal power project at Pipavav in Gujarat by forming a new joint venturecompany between NTPC and GPCL with 50:50 equity participation. Pursuant to the decision of Gujarat Government, NTPC Ltd. has dissociated itself from this company. PP DCL is under winding up. Kanti Bijlee Utpadan Nigam Limited (formerly known as Vaishali Po wer Generating  Company Limited To take over Muzaffarpur Thermal Power Station (2*110MW), a subsidiary company named Vaishali Power Generating Company Limited (VPGCL) was incorporated on September 6, 2006 with NTPC contributing 51% of equity and balance equity was contributed by Bihar State Electricity Board. This company was formed to renovate the existing unit and run the plant. The second unit has been successfully re -synchronized on October 17, 2007 after 4 years of being idle. Renovation and modernization of the first unit is under progress. The company was rechristened as Kanti Bijlee Utpadan Nigam Limited on April 10, 2008.  Bharatiya Rail Bijlee Company Limited (BRBCL A subsidiary of NTPC under the name of Bharatiya Rail Bijlee Company Limitedwas incorporated on November 22, 2007 with 74:26 equity contribution from NTPC and Ministry of Railways, Govt. of India respectively for setting up of four units of 250 MW each of coal based power plant at Nabinagar, Bihar. Investment approval of the proje ct was accorded in January, 2008.

3.

BUSINESS MODEL OF NTPC


1. Efficiency improvement includes both improvements in the existing process and through improvement in the technology used to increase the productivity of the company. Research & Development Centre is ISO 17025 accredited and provides high end scientific services to all the companys stations as well as many outside stations resulting in improving availability and reliability of stations by providing condition assessment, failure analysis, solving and analyzing specific problems, and helping our stations in increasing the availability and reliability of their units. 2. Cost efficiency i.e. providing power at reasonable prices so that they could provide power to all in need. Their ultimate aim is to reduce the cost because without being the cost leader they cant dominate the market. So as a market leader they are always aiming at reducing the cost.

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

14

NTPC shimadri

3. Technology enhancement i.e. to stay in competition they have to continuously enhance their technology. Technology enhancement is also a part of cost efficiency. That means by applying the new technologies the company can reduce the cost as well as improve the efficiency. 4. Eco friendly system: Driven by its commitment for sustainable growth of power, NTPC has evolved a well defined environment management policy and sound environment practices for minimizing environmental impact arising out of setting up of power plants and preserving the natural ecology.

3.1 OPERATIONS OF THE BUSINESS

LOCATION OF FACILITY FOR NTPC

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

15

The purpose of the location of NTPC in Visakhapatnam is to find an optimal location which will result in the greatest advantage to the organization. There is minimal wastage of resources because of this location. BHEL is the major supplier of equipment for NTPC Simhadri. It is located at a distance of 20 K ms from the plant. HPCL is the major supplier of FUEL. It is located at a distance of 20 K ms. The plant is quite near to Sea ports, Railway station (to handle coal from Australia and Talcher) and Airport. It distributes power to Power Grid which is just 10 K m away from the location of the plant and hence there is no wastage of power during transmission. Nearest water source is Yeleru Canal. 5 K ms from Seashore as it uses sea water as coolant in cooling towers.

NTPC shimadri

PLANT LAYOUT AND MATERIAL HANDLING

NTPC SIMHADRI OVERALL LAYOUT

 Coal is handled and processed. It is then sent to theunits 1,2,3,4.  Units 1 and 2 are linked with chimney 1 which consists of 2 chimneys internally. Similarly units 3 and 4 are linked with chimney 2.  Each unit is linked with cooling towers in order to cool the steam. Sea water pump house links with cooling towers in order to supply Sea water as a coolant.  DM plant links all the units in order to supply DM water.  Yeleru Reservoir Canal is linked with DM plant to supply water.  Every unit is linked with power handling and transmission station where power is transmitted to the power grid.  Also, each unit is linked with Ash pond through Ash dispenser.

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

16

NTPC shimadri

GENERAL THERMAL POWER PLANT LAYOUT

1. Cooling Tower 2. Cooling Water Pump 3. Transmission Line (3-Phase) 4. Step-Up Tra nsformer (3-Phase) 5. Electrical Generator (3-Phase) 6. Low Pressure Steam Turbine 7. Condensate Pump 8. Surface Condenser

10. Steam Control Valve 11. High Pressure Steam Turbine 12. Deaerator 13. Feedwater H eater 14. Coal Conveyor 15. Coal Hopper 16. Coal Pulverizer 17. Boiler Steam Drum

19. Superheated 20. Forced Dra ught (Draft) Fan 21. Reheater 22. Combustion Air I ntake 23. Economizer 24. Air Preheater 25. Precipitator 26. I nduced Draught (Draft) Fan 27. Flue Gas Stack

9.I ntermediate Pressure Steam Turbi ne 18. Bottom Ash Hopper

COAL PROCESS LAYOUT

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

D Coal is imported from Talcher and Australia which is transported to the plant through rail. D Coal wagons are handling at the Coal handling station.

17

NTPC shimadri

UNIT LAYOUT 1(IN ORDER TO OPERATION OF COAL FURNACE)

D From the coal handling station, coal is either stored in Stock Yard or directly sent to Coal Crushing mill, which crushes coal to 20mm size. D Through Conveyor belts, coal is sent to bunkers. D From bunkers it is sent to Coal mill where coal is milled to powdered state. D The powdered coal is mixed with air and sent to Coal Gun. D From Coal Gun, it is sent to the Coal Furnace. D

KNOW

THE

INTERNAL

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

18

 The coal furnace is surrounded by water walls which consist of DM water.  DM water is supplied from Boiler Drum to Coal Furnace which is more than 165 meters high from Coal Furnace.  Coal is supplied through coal gun.  Initially, the coal is burnt with the help of Diesel. Two kinds of Diesel are u sed: HSD (High Speed Diesel) and LSD (Low Speed Diesel). First LSD is used and then HSD is used. Later, Oil supply is stopped and coal is left for burning.  In order to ignite the furnace, DC supply is given by the DC inverters.  The heat generated by the coal furnace is more than 1200 degrees centigrade.  When water comes through the water walls, it gets heated upto 540 degrees and turns into steam.  This steam flows to turbines at various pressures.  These turbines are linked with generators which generate p ower and these generators supply power to power stations from where it is sent to power grid.  After the Coal is burnt, it turns into Ash. Bottom Ash is collected at Bottom Ashing and the Fly ash at the Induction Fans (IDF). Ash flows through IDF to ESP (Electro Static Priscribrators). In this ESP, 99% of Ash is sent to bottom Ashing. Less than 1% of the Fly ash goes through Chimneys which is 275 meters high. So, there is very less Air pollution.

NTPC shimadri

UNIT LAYOUT 2(IN ORDER TO KNOW THE INTERNAL OPERATION AND PROCESS OF TURBINE)

y y

y y

y y

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

19

Steam generated in the coal furnace is supplied to the Economizer. From there, it is sent to the Super heater which has an elaborate setup of tubing where the steam vapour picks up more energy from Hot Flue gases outside the tubing and its temperature is now super heated above the saturation temperature. The super heater steam is then piped through the main steam lines to the walls before the high pressure turbines. From High Pressure turbines (HP) steam is transferred to Super Heater again and then to IP (Intermediate pressure) turbine. The turbines are connected to generators where power is generated and sent to power grid. After this, the steam loses its pressure and hence is sent to low pressureturbine (LP). Then, steam has very low pressure which cannot be used for the turbines. Hence, it is sent to condenser which is in Vaccum. The condenser is a shell and tube heat exch anger in which cooling water is circulated through the tubes. The exhaust steam from the LP turbines enters the shell where it is cooled and converted to condensate (water) by falling over the tubes. Such condensers use steam ejectors for continuous remova l of air and gases from the steam side to maintain vaccum. This condensated steam is converted to water by the cooling towers in which coolant is sea water. The water from the cooling tower is sent to hot well. From hot well, the water will go through con denser pumps through low pressure temperature heater, then through High pressure temperature heaters. This is called Re-heating or Re-cycling system (Deaerator system) to Boiler speed pump. Each boiler speed pump consumes 10MW in 500MW generated power. Deaerators to boil speed pumps and to HP heaters and to FRS (Feed Regulating Station) to Boiler Drum.

NTPC shimadri

y y y

Hence whatever DM water was vaporized is again De-vaporized to DM water again. This comes back to Boiler Drum again. In cyclic process, this water goes down from Boiler drum to Furnace. In between the process of vaporizing and de-vaporizing of water, 10% of water is lost. This lost water is made up by make up pumps which are connected to the DM plant. DE-MINERALIZATION PLANT LAYOUT

 Water is supplied from Yeleru Canal to the reservoir. From here, this water is pumped to DM plant.  This water is purified with the help of Aulum and Chlorine in the first stage. This water is called Filter water.  Filter water is sent through gravity filters by which we get pure drinking water.  This pure water is sent to Cat-ion vessel and then to Cat-ion exchanges from here to the Degasser and then to An-ion exchanger and to mixed bed.  The water coming out of the mixer bed is 100% pure Dematerialized water (DM).  DM water is stored in DM water tank.  The DM water tank is linked with DM water make up pump which is again linked to boiler drum.

POWER STATION LAYOUT

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

 The power generated through the generators is 18 Kv.

20

NTPC shimadri

   

This 18 Kv power is stepped up by step-up generator to 400 Kv. This is done in order to avoid heavy Cabling for transmission of power. This is sent to power grid. From Power grid, the power distributions are 400 K v which is given to factories. In the same way 33 Kv, 11 K v are stepped onto 440v and again ste pped onto 230v which is used to household purpose.  Maintain its position as the leader: As the largest power Generation Company in India NTPC Ltd is looking to increase its capacity to 75000 MW by 2017.  Adopt the new technology: NTPC Ltd is also looking to utilize other sources of power generation in the next 5 years namely Hydel power and nuclear energy to generate electricity.  Resource management : The company will look to continue with their stringent recruitment an d retention policy which has provided it with the best minds in the country.  Environment management : Being the leader in its trade the company will look towards fulfilling its corporate social responsibility and contributing towards the environment.

3.2 OPERATING STRATEGIES OF NTPC

3.3 ORGANIZATION STRUCTURE:

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

21

NTPC shimadri

3.4 CORPORATE OBJECTIVE


 BUSINESS PORTFOLIO GROWTH y To further consolidate NTPCS position as the leading thermal power generation company in India and establish a presence in hydro power segment. y y To broad base the generation mix by evaluating conventional sources of energy to ensure long run competitiveness and mitigate fuel -risks. To diversify across the power value chain in India by considering backward and forward integration into areas such as power trading, transmission, distribution, coal mining, coal beneficiation, etc. To develop a portfolio of generation assets in internati onal markets.

y To establish a strong brand in the domestic & international market.  CUSTOMER FOCUS y To foster a collaborative style of working with customer growing to be a preferred brand for supply of quality power. y To expand the relationship with existing customers by offering a bouquet of services in addition to supply of power e.g. trading, energy consulting, distribution consulting, management consulting, management practices. y To expand the future customer portfolio through profitable diversification into downstream business, inter alia retail distribution and direct supply. y To ensure rapid commercial decision making, using customer specific information with adequate concern for the interests of the customer.  AGILE CORPORATION y To ensure effectiveness in business decisions and responsiveness to change in the business environment by y Adopting a portfolio approach to new business development. y Continuous and coordinated assessment of the business environment to identify and respond to opportunities and threats. y To develop a learning organization having knowledge based competitive edge in current and future businesses. y To effectively leverage information technology to ensure speedy decision making across the organization.  PERFORMANCE LEADERSHIP y To continuously improve on project execution time and cost in order to sustain long run competitiveness in generation. y To operate & maintain NTPC stations at par with the best -run utilities in the world with respect to availability, reliability, efficiencies. y To aim for performance excellence in the diversification businesses. y To embed quality in all systems and processes.  HUMAN RESORUCE DEVELOPMENT
III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

22

NTPC shimadri

To enhance organizational performance by institutionalizing an objective and open performance management system. y To align individual and organizational needs and develop business leaders by implementing a career development system. y To enhance commitment of employees by recognizing and rewarding high performance. y To build and sustain a learning organization of competent world -class professionals. y To institutionalize core values and create a culture of team building, empowerment, equity, innovation and openness which would motivate employees and enable achievement of strategic objectives.  FINANCIAL SOUNDNESS y To maintain and improve the financial soundness of NTPC by prudent management of the financial resources. y To continuously strive to reduce the cost of capital through prudent management of deployed funds, leveraging opportunities in domestic and international financial markets. y To develop appropriate commercial policies and processes this would ensure remunerative tariffs and minimize receivables. y To continuously strive for reduction in cost of power generation by improving operating practices.  SUSTAINABLE DEVELOPMENT y To contribute to sustainable power development by discharging corporate social responsibilities. y To lead the sector in the areas of resettlement and rehabilitation and environment protection including effective ash -utilization, peripheral development and energy conservation practices. y To lead developmental efforts in the Indian power sector through efforts at policy advocacy, assisting customers in the operations and management of power plants etc.  RESEARCH and DEVELOPMENTS y To pioneer the adoption of reliable, efficient and cost-effective technologies by carrying out fundamental and applied research in alternate funds and technologies. y To carry out research and development of breakthrough techniques in power plant construction and operation that can lea d to more efficient, reliable and environment friendly operation of power plants in the country. y To disseminate the technologies to other players in the sector and in the long-run generating revenue through proprietary technologies. y

3.5 SUPPLY CHAIN MANAGEMENT

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

23

 Coal is supplied from Talcher and Australia which is stored and maintained very well at the Coal Stock yard.  There are no retailers or distributors. Everything is taken care by the government since it is a State-owned company.

NTPC shimadri

 Supply of electric products are done by BHEL which is also a government owned enterprise.  Chief water source is Yeleru canal.

4. ISSUES AND CHALLENGES 4.1 HUMAN RESOURCES


People before P LF (Plant Load Factor)' is the guiding philosophy behind the entire gamut of HR policies at NTPC. NTPC are strongly committed to the development and growth of all our employees as individuals and not just as employees. NTPC currently employ approximately 24500 people at NTPC. Competence building, Commitment building, Culture building and Systems building are the four building blocks on which our HR systems are based.

RECRUITMENT NTPC believe in the philosophy of 'Grow your own timber'. Our 'Executive Trainee' scheme was introduced in 1977 with the objective of raising a cadre of home grown professionals. First Division Graduate Engineers/ Post graduates are hired through nation -wide open competitive examinations and campus recruitments. Hiring is followed by 52 weeks of fully paid induction training. CAREER ADVANCEMENT AND OPPORTUNITIES NTPC have a well established talent management system in place, to ensure thatNTPC deliver on our promise of meaningful growth and relevant challenges for our employees. Our talent management system comprises P ERFORMANCE MANAGEMENT, CAREER PATHS and LEADERSHIP DEVELOP MENT. REWARDS AND RECOGNITIONS We have, from inception, created a culture of rewards and recognitions through celebration of various achievements and events and recognizing the contributions behind such success. INNOVATE, CREATE, COMPETE We have introduced numerous initiatives which seek to enhance the creativity, innovation, functional aptitude and teamwork of our employees. These initiatives include National Open Competition for Executive Talent (NOCET), Professional Circles, Quality Circles, Business Minds and Medha Pratiyogita (a q uiz for our employees). A management journal
III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

24

NTPC shimadri

called Horizon is published quarterly to enable the employees to share their ideas and experiences across the organization. QUALITY OF WORK-LIFE NTPC is proud of its systems for providing a good quality of work-life for its employees. In addition to providing beautiful and safe work places, NTPC encourages a culture of mutual respect and trust amongst peers, superiors and subordinates. Away from hectic city life, NTPC townships provide an environment of sere nity, natural beauty and close community living. Numerous welfare and recreation facilities including schools, hospitals and clubs are provided at the townships to enhance quality of life & the well being of employees and their families. An entire range of benefits, from child care leave to post retirement medical benefits are extended to employees to meet any exigency that may arise in a person's life. KNOWLEDGE MANAGEMENT IN NTPC To meet our ultimate objective of becoming a learning organization, an integrated Knowledge Management System has been developed, which facilitates tacit knowledge in the form of learning and experiences of employees to be captured and summarized for future reference. TRAINING AND DEVELOPMENT NTPC subscribes to the belief that efficiency, effectiveness and success of theorganization, depends largely on the skills, abilities and commitment of the employees who constitute the most important asset of the organization. Our Training Policy envisages a minimum of 7 man days of training per employee per year. NTPC have developed our own comprehensive training infrastructure. EDUCATION UP-GRADATION SCHEMES To meet the academic aspirations of employees and match them with the needs of the organization, NTPC has tie-ups with institutes of repute like MDI, Gurgaon; IIT Delhi; BITS Pilani, etc. NTPC sponsors fixed size batches of employees who are inducted into these courses based on their performance rating in the company and their performance in the entrance exam conducted by the respective institute. Unlike other study leave and sabbaticals, employees undergoing these courses do not forego their salary or growth during the duration of the course. SEEKING FEEDBACK NTPC actively seek and encourage employee feedback to ensure that our HR interventions and practices remain relevant and meaningful. NTPC regularly conduct Employee Satisfaction and Organizational Climate Surveys. AWARDS NTPC derive immense satisfaction from the awards NTPC receive and the resulting recognition they bestow. The awards are key indicators and milestones on our HR journey, and reinforce our HR philosophy and practices. NTPC has been awarded No.1, Best

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

25

NTPC shimadri

Workplace in India among large organizations for the year 2008, by the Great Places to Work Institute, India Chapter in collaboration with The Economic Times.

4.2 FUTURE CAPACITY ADDITIONS


NTPC has formulated a long term Corporate Planup to 2017. In line with the Corporate Plan, the capacity addition under implementation stage is presented below: PROJECT Coal  1. NCTPP II ( 2 x 490  2 Korba III ( 1 x 500  3 Sipat I (3 x 660  4. Farakka III ( 1 x 500  5. Indira Gandhi STPP- JV with IPGCL & HPGCL ( 3 x 500  6. Simhadri II ( 2 x 500  7. Vallur I -JV with TNEB ( 2 x 500  8. Vallur Stage-I Phase-II -JV with TNEB ( 1 x 500  9. Bongaigaon(3 x 250  10. Mauda ( 2 x 500  11. Rihand III(2X500  12. Vindhyachal-IV (2X500  13. Nabinagar TPP-JV with Railways (4 x 250  14. Barh II (2 X 660  15. Barh I (3 X 660 Hydro  1. Koldam HEPP ( 4 x 200  2. Loharinag Pala HEPP ( 4x 150  3. Tapovan Vishnugad HEPP (4 x 130 Total STATE Uttar Pradesh Chhattisgarh Chhattisgarh West Bengal Haryana Andhra Pradesh Tamilnadu Tamilnadu Assam Maharashta Uttar Pradesh Madhya Pradesh Bihar Bihar Bihar MW 980 500 1980 500 1500 1000 1000 500 750 1000 1000 1000 1000 1320 1980

Himachal Pradesh 800 Uttarakhand 600 Uttarakhand 520 17930

NTPC Limited, countrys largest power generating company having an installed capacity of 30,144 Mw, is adding 6,500 Mw in the southern region. Of this, 1,000 Mw is for the Simhadri Super Thermal Power Station at Visakhapatnam, according to NTPC regional executive director (south) Ambarish N Dave. Of the two 500 Mw units planned to be added at Simhadri, one unit would be ready by November 2010 while the second would come up in the subsequent phase. The Simhadri power plant expansion is estimated to cost about Rs 5,130 crore. Andhra Pradesh would get about 35 per cent power from the new capacity addition at Simhadri. The remaining would be distributed in the southern region according to the

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

26

NTPC shimadri

agreements with the respective states. The entire power currently generated by the 1,000 Mw Simhadri plant is being used by the state. In Tamil Nadu, the company would add another 500 Mw once its 1,000 Mw plant at Vallur is complete. The plant is being set up at an estimated cost of Rs 5,123 crore in joint venture with the Tamil Nadu Electricity Board. This apart, the company is also in the process of conducting feasibility studies for the 4,000 Mw power plant at Kudgi in Bijapur district of Karnataka. The project would be executed together with Power Company of Karnataka Limited for which a memoran dum of understanding was signed in January this year. The project would have three units of 800 Mw each in Stage I and two units of similar capacity in Stage II. Feasibility studies for multiple locations for a 500Mw wind power project in Karnataka too would be conducted soon. NTPC was in talks with Gas Authority of India Limited for supply of liquefied natural gas (LNG) to the Rajiv Gandhi Combined Cycle Power Project at Kayamkulam in Kerala. The company would take up Stage II expansion of the project uponavailability of fuel (LNG) at a viable cost. The proposed expansion would not require additional land. The southern region achieved the highest -ever generation of 32,067.76 million units (mu) during the financial year 2008-09, surpassing the target of 29,775 mu.

4.3 CHALLENGES WITH COAL RESOURCES


The policy changes in coal sector provide an opportunity to NTPC to enter captive coal mining business. Production is expected by 2010 in one coal block already allotted (P akri Barwadih in the state of Jharkhand). Five more blocks (~40MTPA) have been allotted to NTPC, including two in JV with CIL. In addition to development of its own domestic coal mines NTPC is exploring various other options including acquisition of stake in coal mines abroad for sourcing of thermal coal for addressing fuel security concerns. Ash Utilization is one of the key concerns at NTPC. The Ash Utilization division, set up in 1991, strives to drive maximum usage from vast quantities of ash produced at its coal based stations. The division proactively formulates policies, plans and programmes for Ash Utilization. It further monitors the progress in these areas and works at developing new fields of Ash Utilization. The quality ash produced conforms to the requirements of IS 3812 2003. The fly ash generated at NTPC stations is ideal for use in cement, concrete, concreteproducts, cellular concrete, light weight aggregates, bricks/blocks/ tiles etc. this is attributed to very low loss on ignition value. To facilitate availability of dry ash to end users, all the new units of NTP C are provided with the facility of dry ash collection system. P artial dry ash collection systems have also been set up at the existing stations where these facilities did not exist earlier. Augmentation of these systems to 100% capacity is in under progress.

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

27

NTPC shimadri

As the emphasis on gainful utilization of ash grew, its usage over the years also increased. From 0.3 million tons in 1991 1992, the level of utilization during 2008 09 stood at over 24.40 million tons. The various segments of Ash Utilization currently includes use by a number of Cement, Asbestos Cement products & Concrete manufacturing industries, Land development, Road & Embankments, Ash Dyke Raising and Building Products. Such as bricks/ blocks / tiles, as a soil amender and source of micro nutrients in agriculture and backfilling of mines. AREA WISE BREAK-UP OF UTILISATION FOR THE YEAR 2008-09 IS AS UNDER:  Area of Utilization Quantity (in Million Tons Cement Industries 7.04 Ready Mix Concrete 0.33 Asbestos 0.20 Clay Ash/ Fly Ash Bricks 1.64 Land Fill 5.74 Ash Dyke Raising 6.24 Road/ Embankments 1.30 Mine Filling 1.14 Agriculture 0.002 Export 0.73 Others 0.02 Total 24 40 MAJOR INITIATIVES TAKEN BY NTPC TOWARDS ASH UTILISATION NTPC continually strives to evolve innovative and diverse means of AshUtilization to further broaden the scope. Prominent among the methods devised so far are:  Dry Flyash Extraction Systems  Use in cement & concrete  Use in Ash based products including setting up of o Ash Technology Park o Land Development/Wasteland Development, Roads & Emba nkments, Raising Ash Dykes'  Mine filling / Stowing  Agriculture NTPC Ash Utilization Division has published multiple literatures on the use of ash in various applications in the form of books & promotional brochures and documentary films to create awareness among the prospective users & entrepreneurs for use of ash. The booklets/ brochures/ films are: BROCHURES:
D D D

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

Fly Ash Bricks Clay Ash bricks Clay Ash Bricks with 60% Fly Ash

28

NTPC shimadri

Coal ash Environment friendly material - For fills, Embankments and Road pavement Construction D Fly Ash - a Resource for Cement & Concrete D Use of Ash in agriculture (In Hindi) FILMS:
D

Clay Ash Bricks Fly Ash Bricks Use of Fly Ash in Mine Filling Coal Ash As Fill Material

5. CONCLUSIONS/RECOMMENDATIONS
D NTPC Simhadri plant has created a benchmark in technology utilization, efficiency and effective utilization of resources. D It has been achieving records right from its synchronization. D It is the only Power plant in India where maximum Automation is done in its operations. D It is the first power plant which uses sea water as a coolant. D It has also achieved great environment standards through its infrastructure facilities like Tallest Chimneys in Asia (275m), Tallest cooling towers in Asia and maintaining an Ash pond which is eco-friendly. D It been maintaining excellent CSR(Corporate Social Responsibility) by providing jobs to the land losers along with good compensation, providing employment for the locals on a contract basis, construction of roads, drainage systems, drinking water supply, hygienic conditions, hospitals, schools, etc all within 8 K ms of the NTPC plant. D NTPC Simhadri has followed the principles of production and operation management quite well and also maintained good relationship within its Micro as well as Macro environments. D There should be more Involvement of management at all levels with effective creation of policies, vision, Mission, values, goals and support, communicated and implemented throughout the Organization. D There should be training of senior executives in managing for quality. D It should evaluate plans for expansion in order to meet the Power needs of India as well as to create more employment.

6. BIBLIOGRAPHY
Operations Management books from google e-book. www.ntpc.co.in www.ntpc.in www.google.com Wikipedia Forbes India Business World

III SEM MBA (2009-11), BANGALORE SCHOOL OF BUSINESS, BANGALORE (MS UNIVERSITY)

Page

29

Potrebbero piacerti anche