RELEASED MPI 84 / 1 7
All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from Alcatel.
2 / 30
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.1 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.2 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.3 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.4 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.2 Site Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4 Telecom / Supervision Outage and Operating Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.1 Before Going On-site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2 Before you start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3 Scenario Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.1 Perform initial checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2 Create Abis (Case 1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3 Create BTS(s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.4 Create Cell(s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.5 Insert BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.6 Call Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.7 Create Adjacencies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.8 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4 Reverse procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.1 Lock Cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.2 Disconnect BTS(s) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.3 Unlock Cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.4 Delete Cell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.5 Delete BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.6 Delete Abis (Case 1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.7 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 9 10 10 10 10 11 12 12 13 13 13 15 16 16 16 17 19 20 20 21 21 21 21 22 25 26 26 27 28 28 28 28 29 29 29 30
3 / 30
Figures
Figures
Figure 1: Grouped Task Sequence for Add BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
4 / 30
Tables
Tables
Table 1: Sites/Personnel/Duration in Minutes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 Table 2: Traffic Outage, Loss of Supervision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 Table 3: Software tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 Table 4: Forms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
5 / 30
Tables
6 / 30
Preface
Preface
Purpose Audience
To add a BTS. This document is intented for: Field service technicians Specialists Project managers Foremen.
Assumed Knowledge
You must have a basic understanding of the following: For planification purpose Network architecture and reshuffling principles Basic knowledge for scheduling. For realization purpose Alcatel operations and maintenance concepts for BSS Alcatel 1353RA OMC-R Equipment (BSC, BTS, MFS) hardware configurations Windows environment.
7 / 30
Preface
8 / 30
1 Overview
1 Overview
This chapter gives information needed for project managers and foremen, for presentation to the customer and site planning.
9 / 30
1 Overview
1.1 Presentation
Note:
The logical configuration can be activated completely independently from the physical connection of the BTS. Creating adjacencies and call tests must be conducted after the BTS is functional and connected to the network. Coordination is needed between BTS and OMC-R sites to define the initial settings. The Qmux address must always be set. For A9100/A910 BTSs, the transmission mode is configured via OML. The GPRS option is not applicable when the Abis chain to the BTS is passing through a satellite connection. G1 MKII BTSs can only be used if they have a BIUMD card (Chain) and if they are equipped with DRFU. They cannot be used if they have a BIU2M card (Star). If they have the BIU2M card, either the BTS or the card must be replaced. G2 BTSs can only be used if they have a FUMO or DRFU card. They cannot be used if they have a FUCO card, in this case either the BTS or the card must be replaced. In order to create a required configuration it is also possible to add more than one new BTS and more than one cell. In this case it is better to perform all the logical parameters modification into a single PRC.
1.1.1 Cases
The following cases apply: C1: BTS is installed on a new Abis. There is no traffic outage. C2: BTS is installed on an existing Abis with downstream BTSs. This case causes a traffic outage on the downstream BTSs. C3: BTS is installed at the end of an Abis chain (no downstream BTSs). There is no traffic outage.
1.1.2 Options
The method takes into account one option: O1 : Configuring the GPRS for the cells O2 : Abis connection via satellite. O3: Create cell(s) shared (applicable only for A9100 BTSs ).
1.1.3 Restrictions
None.
10 / 30
1 Overview
MSC
OMCR
Initial checks
BTS
Create BTS
Create cell
Insert BTS
Final checks
11 / 30
1 Overview
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply: BTS sites are clean, tidy and easily reachable. The Abis is installed and tested. For Case 2, the jumper linking the upstream and downstream BTSs has been installed. This jumper is removed during this scenario. BTS(s) is installed and commissioned. For option O3: Clock synchronization cable(s) must be already installed between BTSs involved into cell shared . BTS(s) must be configured with the correct initial settings. There are adequate resources to handle the new traffic channels and LapD. All BTS SW packages and OMU-CPF are loaded in BSC memory.
12 / 30
1 Overview
1.3 Scheduling
Table 1 describes the sites, personnel and duration of each Grouped task and the total time to perform the scenario. Time based on technical constraints The times in the following table do not take into account individual customer or safety requirements.
MSC
TSC
BSC
BTS
Imp. BTS -
OMC -R
Time/ Task
1 op 15
15
1 op C1:6
13 / 30
1 Overview
MSC
TSC
BSC
BTS
Imp. BTS -
OMC -R
Time/ Task
Create Cell(s)
1 op (3)
Insert BTS(s)
1 op 7/BTS+1/cell+1
7/BTS+1/cell+1 C1:+5
Call Tests
1 com 5/cell
1 com
1 op 15
15
TOTAL TIME
49+17/BTS+32/cellC1:+11 C2: +2/BTS*+13+5/cell C3: +7 O1: +7/cell O2: +3 O3: +3/ cell(shared)
14 / 30
1 Overview
Sup Out -
OM Out -
Impacts... None
None
1/30
None Sup.out. 130 during the PRC activation For C2, outage on downstream BTSs For O2+C2 telcom and GPRS outage for downstream BTSs (same value)
Insert BTS
2/BTS*+2/cell+10
10+2/BTS*
None None
None C2: 2/BTS*+2/cell+10 O2+C2:2/BTS*+2/cell+10 GPRS +telecom outage During the activation supervision outage:130.
C2: 2/BTS*+2/cell+10
15 / 30
1 Overview
1.5 Resources
1.5.1 Tools
The following tables describe the tools that are needed.
Hardware Tools
Item Wiring tools for disconnection and reconnection of PCM Mobiles for call testing PC with associated cables Part Number Use at ... BTS
BTS BTS
Item BTS Terminal for B7.2 LMT-CT (Craft Terminal) for B7.2
Part Number -
Item None
Part Number
Use at ...
Table 4: Forms
1.5.2 Supplies
The following table describes the supplies needed for this operation. Item Topology regarding operation Part Number Use at ... BTS
16 / 30
1 Overview
A1353-RA Configuration Handbook A1353-RA Surveillance Handbook B7 BSS Methods Handbook . Network Configuration Recommendations BTS Terminal User Guide Transmission Terminal User Guide BTS Site Master/ Slave Synchronization
17 / 30
1 Overview
18 / 30
2 Scenario
2 Scenario
This chapter presents all checks needed before beginning the scenario, and all detailed tasks to be performed on each site.
19 / 30
2 Scenario
Site Specific Information (Section 1.2.2) is available and ready for operation. Tools (Section 1.5.1) are available and ready for operation. Supplies (Section 1.5.2) are available and ready for operation.
Documentation is available and ready for operation.
Required Knowledge
Safety Rules and Precautions Telecom / Supervision Outage and Operating Impact (Section 1.4) Instruction for reverse procedure decision Grouped Task Sequence (Section 1.1.4) Operating Hints
How to document Faults and Anomalies.
20 / 30
2 Scenario
Note:
Case specific tasks are marked with a C1, C2 or C3 in the Note column. Detailed Tasks that do not have C1, C2 and C3 in the note column are common to all three cases and must be performed. To add a BTS to: A new Abis, use Case 1 (C1) An existing Abis with downstream BTSs, use Case 2 (C2) A BTS to the end of an existing Abis (no downstream BTSs), use Case 3 (C3). Options are marked with O1, O2, O3 in the Note column. Detailed tasks that have O1, O2, O3 are applied only if that option is choosen.
View Status of Managed Objects and Alarms on all the BTSs of the TSU and for the Abis, print it.
Create Abis Chain/Ring . Wait for the transmission programming flag to change from Abis to idle.
Note C2, C3
Task Description If the BTS(s) to add is G1 or G2, check if the Abis is set with a TS for Qmux. If not, reserve one Qmux TS by Modify Abis Chain/Ring Characteristics
Site OMC-R
To Do 2
Outage None
21 / 30
2 Scenario
Note
Task Description
Site OMC-R
To Do 7/ BTS
Outage None
OMC-R/BTS
1/ BTS
None
If the Abis is connected via satellite Check Cyclic OMC-R / BSC Redundancy at the BSC side using LMT-CT tool, and, if needed, Modify CRC4 Check that the newly created BTSs appear in the hierarchy view of the Radio Configuration Browser (SC). OMC-R
None
None
Note
Task Description
Site OMC-R
To Do 1
Outage None
Create PRC(PRC1). Enable the button Automatic opening in the Create PRC window. The PRC is opened once created.
O3
OMC-R
2/ cell
None
OMC-R
2/ BTS
None
O3
OMC-R
1/ cell
None
22 / 30
2 Scenario
Note
Task Description
Site OMC-R
To Do 2/ cell
Outage None
Create Provisioning Cell or Duplicate Cell . The cell is created/duplicated in the PRC1 and is in a locked state. Create one cell for each sector is necessary.
Use Set Cell Telecom Parameters.
Create Radio Frequency. Create Frequency Hopping System , if you use Frequency Hopping. Create TRX.
OMC-R
30/ TRX
None
Note : For O3 select the TRX in [Secondary] TRX on a shared BTS sector, if is necessary.
Configure TRX Channel Hopping Law , to hopping or no hopping. Specify TRX Preference. Configure Logical Channels.
O1
OMC-R
1 30/ cell
None
Set BSS/BSC Telecom Parameters in PRC1 to update GPRS parameters if needed. This task includes the modification of CAE data specific to the MFS.
Notice: the duration depends of the number of parameters to modify. Here is considered 10 parameters in different windows OMC-R 2/ cell None
O1
If GPRS parameters have to be modified on cell(s) then, Edit n Cells in PRC. Modify parameters such as Min_Pdch and Max_Pdch_High_Load, Max_Pdch, Routing Area Code or Routing Area Color
Notice1: To have GPRS on the cell GPRS Pref.mark must be different from 0. To modify it, use the java script Set/Update GPRS pref. Mark using script Notice2: to modify only one cell, the operator can use the edit cell command (see Set Cell Telecom Parameters ) Notice3:For O3 : GPRS Pref. mark =0, for secondary sector.
Click on <Apply and check> in the Edit Cell window to save cell modifications in the PRC1. Wait for the message No error or warning and click on &ok. If the check produces error messages, correct the configuration as required and re-attempt the check. Continue corrections and checks until no errors occur. Click on <Close> to exit from the Edit Cell window.
OMC-R
30/ cell
None
OMC-R
30/ cell
None
23 / 30
2 Scenario
Note
Task Description
Site OMC-R
To Do 1/ cell
Outage None
Note:map each new cell Use the Check All option ( without forcing cell administrative state) in Check PRC to check the parameters, hardware and telecom impact of your PRC1. If the check produces error messages, correct the configuration as required and re-attempt the check. Continue corrections and checks until no errors occur. Ask the MSC personnel to update the parameters in the MSC DB. OMC-R/MSC 3 None OMC-R 1 None
24 / 30
2 Scenario
Note C1, C3
Task Description If not done previously, the BTS must be physically connected to the new Abis link (use BTS Connection ). Inform the OMC-R you are ready to insert the BTS into the Abis link. In the Abis Interface View Window, select the Abis chain/ring where you insert the new BTS. Write down the BTSs that are downstream from the new BTS. Go to the SC and lock the cells, use Shut Down Cell of these downstream BTSs (WTC=3 min ). Inform the BTS site when the cells are locked.
Site BTS
To Do 5
Outage None
C2
None
C2
4/cell
C2
Lock BTS O&M Capability of the downstream BTSs. Inhibit Alarm Reporting on Abis TP, ( select Inhibit Alarm Reporting on TP Down) Jumper Disconnection. BTS Connection. Unlock BTS O&M Capability of the downstream BTSs.
Use Unlock Cell, to unlock the cells of the downstream BTSs. After connection the new BTS will enable its OML link. Unlock BTS O&M Capability of the added BTSs. It starts the download for each new BTS. After a time the OMC-R will automatically trigger a HW and alarm audit for the each new BTS. All the boards of the BTS must appear on OMC-R BSS equipment view. Wait until the end of BTS(s) audit.
OMC-R
1/ BTS*
OUTAGE 1
C2
OMC-R
OUTAGE 1
C2 C2 C2
5 5 1/ BTS*
C2
OMC-R
1/cell
END1
OMC-R
1/ BTS
None
OMC-R
6/ BTS
None
25 / 30
2 Scenario
Note
Task Description
Site OMC-R
To Do 5 / cell
Outage None
Activate PRC (PRC1). Choose to activate using the option Without forcing cell administrative state. This option keeps the cells locked.
The activation time depends on the number of cells activated. During the activation supervision outage(130).
Close PRC(PRC1).
C1, C2
OMC-R OMC-R
1 1
None None
Allow Alarm Reporting on Abis TP, ( select Allow Alarm Reporting on TP Down)
Use Unlock Cell , to unlock the cells of the new BTS(s).
OMC-R
1/ cell
None
Task must be done in parallel with the next task. . Unlock cell from Call Test detailed task not necessary here. CHECK
Display USD Detailed Cell Information . Check that the new cells are in traffic. If not, go to theReverse procedure (Section 2.4) .
OMC-R
None
Create Adjacency for the new cell with notes taken at preparation step assuming both adjacencies towards new internal cells and adjacencies towards new external cells.
For each cell on the same OMC that must be adjacent to the new added ones, Modify Adjacency to include the new added cells. For each cell on the neighbour OMCs that must be adjacent to the new added cells, Modify Adjacency on neighbour OMCs to include the new added cells.
OMC-R
2 /cell
None
neighbour OMC-R
2 /cell
None
26 / 30
2 Scenario
View Status of Managed Objects and Alarms on all the BTSs of the TSU. Compare this check to the initial check.
27 / 30
2 Scenario
OMC-R
4/ cell
C2
Lock BTS O&M Capability of the downstream BTSs. Lock BTS O&M Capability of the added BTSs.
OMC-R
1/BTS*
OMC-R
Inhibit Alarm Reporting on Abis TP, ( select Allow Alarm Reporting on TP Down) Jumper Connection.
C2
BTS
Unlock BTS O&M Capability of the downstream BTSs. Allow Alarm Reporting on Abis TP, ( select Allow Alarm Reporting on TP Down)
In the SC, use Unlock Cell to unlock all cells of the downstream BTSs. Traffic is restarted on the cells of the downstream BTSs.
C2
OMC-R
C2
OMC-R
Traffic Restarts
28 / 30
2 Scenario
Unlink Cell from a secondary BTS Sector , unlink the cell(s) which is shared with the added BTS(s) Delete TRX, to delete all TRXs for the secondary sector Delete Radio Fraquency, to delete all frequency for the secondary sector Delete OMC Cell from PRC, delete all the cell(s) from the added BTS(s). Activate PRC(PRC1).
The activation time depends on the number of cells activated.
O3
OMC-R
1/cell
O3
OMC-R
1/cell
OMC-R
1/ cell
OMC-R
5 / cell
1 2 3
Delete BTS(s) from OMC-R . Wait for the transmission programming flag to change from Abis to idle.
Delete Abis Chain / Ring you created. Wait for the transmission programming flag to change from Abis to idle.
29 / 30
2 Scenario
Display USD detailed Cell Information . Check that the downstream BTSs are in traffic.
Perform an Audit Alarm State on BSS.
OMC-R
10 5
View Status of Managed Objects and Alarms OMC-R on all the BTSs of the TSU. Compare this check to the initial check.
30 / 30