A. Project Information:
Indicate name and location of the project; Ans: metro bus scheme is the name of our project.the location of our project is hajji camp, G.T road Peshawar khyber pakhtoon khawa.its cover various places of the city like sadder, city,hayatabad and university town. Provide name of District/Province; Ans: Khyber paktoon khawa (Peshawar). Attach a map of the area, clearly indicating the Project location.
Contact Persons information; Ans:the focal person of this project is mr.hasseb admin of our project .office address hajji camp , G.T road Peshawar city. His contact number is 0345-8978987 Email address. hasseb@yahoo.com
Project Start and end dates; Ans : 25 march 2013 to 30 march 2014
Information regarding organizations/authorities responsible for sponsoring, execution, operation and maintenance. Ans: World Bank, Chinese government, Turkish government and Asian development bank and ministry of planning and development will help us sponsoring the project. Peshawar development authority, sarhad development and authority will help us in executing our project. http://punjab.gov.pk/sites/punjab.gov.pk/files/BUS_RFP_Final-ver-12.pdf
B. Organizational Background In Peshawar PDA is people-friendly principal planning and development authority of the Peshawar Metropolis, they are aiming at providing and continuously improving metropolis-vide development works, providing facilities and services of acceptable standards to all without let or favor. PDA attempts to turn Peshawar into an "attainable city" with combined support of people, private sector and different level of the Government, where overwhelming majority enjoys convenient, healthful and satisfied living. Peshawar Development Authority is responsible for the planning, designing and implementation of various urban development projects in accordance with the function of Authority. Various directorates established for the purpose accomplish the assignment. From the inception of housing projects, planning and managing Water resources, designing Sanitation network, beautification of city area and planning of basic infrastructure of the city includes in objectives of PDA. PDA prepares and sanctions the town planning schemes, development plans, deals with urban transport, water supply, sanitation, development of new towns, roads, Infrastructure, parks and horticulture through execution of annual development projects to meet the civic requirements with highest life standards
Sarhad development authority is responsible for planning, promoting, organizing and implementing programmers for the establishment of industries and commercial ventures. This organization is responsible for tendering advice on the technical, operational and commercial feasibility of any programmed or scheme specified by government. The PDA has prior history in construction of flyover, street lighting, car parking, construction of sewerage system, construction of boundary wall in hayatabad police station, construction of ring road, construction of flush system.
Project Description
1. Goal & Objectives:
our project realizes the importance of providing safe, efficient, comfortable, and affordable Transport to the public and has therefore initiated construction of MetroBus Corridor from hajji camp G.T road to Hajji camp hayatabad along with university road ,Khyber road and sadder road. The MBS-PMU/PMA seeks to induct approximately 45Articulated 18m AC Diesel buses . The prospective investors/operator will procure, operate, and maintain buses for 8 years. Key locations throughout the city are targeted to maximize ridership from all surrounding areas. Roughly 20 stations have been planned to be built throughout the entire route . The GoPb is executing steps to engage an operator for provisioning of Automated Fare Collection and Bus Scheduling System (AFC-BSS) system, which will serve as a Management Information system. The AFC-BSS will be coupled with necessary hardware and software to authenticate entry/exit of passengers into bus stations, and to monitor adherence to bus schedules. The system will provide variety of fare media including throwaway cards, reusable RFID tokens, and smart cards. Smart cards may be recharged to a stated, agreed upon max limit,for travel onto MBS stations.The Driver Console Unit installed on buses shall be used to track buses accurately and reliably.The back-end system shall be able to produce MIS reports and bus-schedule adherence report and kilometers travelled by each bus of the operator. To accomplish this, GoPb will put in place an Operation Control Center (OCC) which will receive live passenger data, financial data, and Automatic Vehicle Location data.The total numbers of the registered motor vehicles estimated in Peshawar in 2013 are 1 approximately .The number will be doubled for the next coming generation. Talk about the experience old Peshawar transport most of the times. With the coming Peshawar Metro, common people specially the middle and lower middle class, students and women would be able to travel in a much more dignified manner.If successful, the Peshawar Metro Project has all the potential to become a transportation role model for replication in other major cities of the KPK like abbotabad .This can give rise to a healthy and desperately needed completion among the provincial governments.For governments, it gives them an indication that where there is a will there is a way. It proves the capability of local contractors and builders as well as public gets the clear message they can do it if they want to. According to a latest report from the Metro Bus lahore Service administration, something went wrong in the first hours of the service launch. Some women were harassed by men in Metro Bus Service, Women are complaining about the idea of mutual compartments in
the bus services, and highlighting the harassment moments by men during their traveling via Metro Bus Service.so we have planned to make a separate compartment in bus service in peshawar as to aviod the harassment moments by opposite gender.
a High tech innovation introduced for the first time in Pakistan. It has the capacity of 150 passengers.Their will be sperate compartment for males and females, for both gender there will be job opportunities. Safe and good quality of service, member ship cards for the both genders and their will be separate compartments for toll tickets. Security cameras for any mishaps. This project will bring Self Esteem to the Public .if we talk about old experiences of Peshawar transport its seem like you are traveling in rural area . With the coming Peshawar Metro, common people specially the middle and lower middle class, students and women would be able to travel in a much more dignified manner. We estimated total around 1000 per day people will be getting benefit of it .it will be 30 km good quality of road.Provide Passenger Information System equipment and software in buses.Advanced technology has been used in metro bus forexample automatic doors , verifying machine of membership customers and ticket toll machine.Led display the area people crossing and when you reached to destination announcements will be done and displayed too. Allotments of colors blue, green and red.(blue for sadar sunehri masjid road).( Red is for hayatabad university town, karkhano,) ( green Frrdos, Hashtnagri, Nishtarabad, Gulbahar and old haji camp. ) Buses with fully sitting arrangement having two compartment or cabin one for male and another one for female .its a 150 seater bus equipped with security camera, ticket machine, speaker with mike for the announcements of the area .LED for displaying the area name and fully air conditioner buses. Terminal will be build where MBS system , sercurity system , machine (for membership and toll ticket) . the terminal will be built in uch a way theit will be separation for both genders in entrance and exits. The headquarter of the metro bus controlling all the setup , updating and informing will be hajji camp , G.T road Peshawar city .
We have planned there should be separate road made for these buses which will be free from heavy traffic without any hindrance these buses will reach to their destination point
.the main features of these buses are designed in such a way they having a long turning radius so for the safe side open ended road separately construct . The main issue is insecurity and governance making strategy to resolve this issues as soos as possible. Except this road, fly over with lightening all these are relevant to this project, government will try to complete it simultaneously.
C.
2. Physical Phasing Year 1 jan - Mar - May- Julyfeb april june sept 100 % 100 % 60% 30% 10% 10%
item/description Infrastructure Terminals (15) Distributor Equipment (security camers,LED,sitting arrangement,AC,light s, computers and barriers) Solar plates Machines for tickets Software , design and components Buses total
Unit
oct
40%
260 %
30%
10%
50%
190 %
Financial phasing:
item/description Infrastructure Terminals (15) Distributor Equipment (security camers,LED,sitting arrangement,AC,light s, computers and barriers) Solar plates Machines for tickets Software , design and components Buses total
Unit
Year 1 jan - Mar - May- Julyfeb april june sept 100 100 60 30 10 10
oct
20
40
60 30 80
70 20 100 260
260
30
10
50
190
4. Annual Operating Cost Item-wise annual operating cost for 1 years. . Fuel salary Utility bills Stationary cost Maintenance cost Total Year 1 9800000 6200000 2800000 100000 3800000 22700000
(b) Debt:
On this project World Bank , 20 billion Asian development bank and ministry of planning and development 10 billion
Social:
Quantify benefit to the target Group Non-quantifiable 1) Easy pick and drop 2) Facility of transport 3) Oppourtunites for different advertisment agencies 4) Quick service 5) 24 hour service available 6) Covering main parts of the city 7) One ticket is for all stops
Environmental
Beautification of light Development of city
Implementation Schedule Indicate starting and completion date of the project: Ans: our project will start in january 1st and will end in december 31st .
Item-wise/year-wise implementation schedule in line chart correlated with the phasing of physical activities.
activities
Development of bid form
responsibility jan
feb
mar
apr
May
jun
july
aug
sep
oct
nov
dec
advertisement Submission of tender Selection of bider Ordering equipments installation Testing and checking Funds distribution
notify detailed specifications of the Metro Buses. All Buses to be introduced under this project would have to conform to these specifications. The detail of Urban Bus Specifications is attached as with this document. The Buses shall have system brand name and brand color only.
Monitor all activities of the METROBUS Operation to ensure its compliance with Environmental / municipal laws and regulations; and co-opt the representative of Environment Protection Agency to oversee the compliance of applicable environmental Laws, rules and regulations and their enforcement thereof by bidders. MBS-PMU /PMA may consider allowing advertisements inside the bus, in which case the size, nature, etc will be specified by MBS-PMU/PMA. Revenue proceeds of such Advertisements, if allowed, will be credited to the escrow account. Be responsible for the conduct and functioning of all staff employed in the MBS-PMU /PMA. The MBS-PMU staff shall provide efficient services, polite and courteous Behavior towards operator, and passengers. The MBS-PMU/PMA shall be liable for Any misconduct or unreasonable offense of its employees and shall take prompt and Appropriate action.Confirm ownership of buses in favor of the operator upon expiry of the contract.Through AFC-BSS, provide the bus drivers the required training of the use of the Driver Console.