Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
VDC
Descriptions
Unskilled Labour
Skilled Labour (Mason)
cement
Sand
Stone
Mud
Gravel
Local wood sukath
Reinforcement
CGI sheet 26 Gauage
Unit
md
md
mt
m3
m3
mt
m3
m3
kg
Sqm
Rate
150.00
200.00
15000.00
500.00
250.00
200.00
275.00
15000
70.00
300
Remarks
Scheme:
VDC:
Description of work
S.No
1 E/W/ in excavation in foundation in OS
10 m lead, 1.5m lift
(Analysis for 1 m3)
Sub total Rs
With 15 % for O/H and profit
Total
Rate per m3
2 E/W/ in excavation in soft rock, box
cutting in trench
(Analysis for 1 m3)
Sub total Rs
Total
Rate per m3
3 E/W/ in excavation in hard rock,
cheiseling
(Analysis for 1 m3)
Sub total Rs
With 15% for O/H and profit
Total
4
Rate per m3
Back fill
Sub total Rs
With 15% for O/H and profit
Total
1.58
150.00
237.00
237.00
0.00
237.00
237.00
1.90
150.00
285.00
285.00
285.00
285.00
3.95
150.00
592.50
592.50
0.00
592.50
0.50
150.00
Rate per m3
592.50
75.00
75.00
0.00
75.00
75.00
Mason (md)
Unskilled Labour (md)
cement (mt)
1.50
4.50
0.15
200.00
150.00
15000.00
300.00
675.00
2,250.00
Sand (m3)
0.40
500.00
200.00
1.05
250.00
262.50
3,687.50
0.00
3,687.50
3)
Stone (m
Sub total Rs
With 15% for O/H
Total
Rate per m3
5.2 Stone masonary with mud mortar
(Analysis for 1 m3)
3,687.50
Mason (md)
Unskilled Labour (md)
mud (mt)
1.00
2.50
0.42
200.00
150.00
200.00
200.00
375.00
84.00
Stone m3
1.10
250.00
275.00
934.00
0.00
934.00
Sub total Rs
With 15% for O/H
Total
Rate per m3
6.1 Plaster 12 mm thk
for 100 m2)
Amount Rs
934.00
(Analysis
Mason (md)
Unskilled Labour (md)
18.00
17.50
200.00
150.00
3,600.00
2,625.00
6.1
Cement (mt)
0.80
15000.00
12,000.00
Sand m
1.20
500.00
600.00
18,825.00
0.00
18,825.00
188.25
1.00
3.50
0.30
200.00
150.00
15000.00
200.00
525.00
4,500.00
Gravel (m3)
40mm
20mm
10mm
0.51
0.20
0.10
275.00
275.00
275.00
140.25
55.00
27.50
Sand (m3)
0.42
500.00
Sub total Rs
With 15 % for O/H
Total
210.00
5,657.75
0.00
5,657.75
Rate per m3
5,657.75
Sub total Rs
With 15% for O/H
Total
Rate per m2
0.75
6.50
0.31
200.00
150.00
15000.00
150.00
975.00
4,650.00
Gravel (m3)
40mm
20mm
10mm
0.50
0.20
0.10
275.00
275.00
275.00
137.50
55.00
27.50
Sand (m3)
0.42
500.00
Sub total Rs
with 15% for O/H and profit
Total
210.00
6,205.00
0.00
6,205.00
Rate per m3
6,205.00
Sub total Rs
Add 15% for O/H and profit
11.50
11.50
1.00
10.00
200.00
150.00
70000.00
60.00
2,300.00
1,725.00
70,000.00
600.00
74,625.00
0.00
74,625.00
74.63
1.00
3.25
200.00
150.00
200.00
487.50
Stone ( m3)
Sand ( m3 )
1.05
0.70
250.00
500.00
262.50
350.00
1,300.00
0.00
Total
1,300.00
3
Rate per m
10 Dry Stone Wall
m3
1,300.00
Analysis for 1
Skilled Labour (md)
Unskilled Labour (md)
1.00
3.50
200.00
150.00
200.00
525.00
Stone ( m3)
1.10
250.00
275.00
1,000.00
0.00
1,000.00
Sub total Rs
Add 15% for O/H and profit
Total
Rate per m2
11 Gabion works ( mesh wire 10 swg,
salvage wire 7 swg and bind wire 11swg )
including netting, positioning, boulder
collection and filling all complete.
Skilled Labour (md)
Analysis for 2 m3
Unskilled Labour (md)
GI wire ( kg )
Sub total Rs
Add 15% for O/H and profit
Total
Rate for m3
12 Door and Window frame of sal wood
(Analysis for 1 m3)
Unskilled Labour (md)
1,000.00
0.40
9.10
24.00
200.00
150.00
75.00
80.00
1,365.00
1,800.00
Binding Wire ( kg )
3.10
60.00
186.00
Salvage Wire ( kg )
1.05
40.00
42.00
3,473.00
0.00
3,473.00
1,736.50
3.30
3.30
200.00
150.00
660.00
495.00
1.05
91.50
182.00
1500.00
10.00
0.38
1,575.00
915.00
69.16
3,714.16
0.00
3,714.16
200.00
150.00
15000.00
500.00
1900
1950
4575
305
8730
0
8730
87.3
200.00
150.00
300.00
500.00
50.00
1,200.00
300.00
3,600.00
500.00
50.00
5,650.00
0.00
5,650.00
565.00
Sukath ( m3)
Holdfast ( no )
Screw ( no )
Sub total Rs
with 15% for O/H and profit
Total
13 Rate analysis for cement pointing on boulder for 100 Sq.m.
Skilled Labour (md)
Unskilled Labour (md)
Cement(mt)
Sand
Sub total Rs
Add 15% for O/H and profit
Total
Rate per m2
14 Door and Windowshutter of sal wood
Skilled Labour (md)
(Analysis for 10 m2)
Unskilled Labour (md)
Unskilled Labour (md)
Sukath ( sqm)
Nails
Machine
Sub total Rs
with 15% for O/H and profit
Total
Rate per sqm
9.5
13
0.305
0.61
6.00
2.00
12.00
LS
LS
Sub total Rs
with 15% for O/H and profit
Total
Rate per sqm
(Analysis
Skilled Labour (md)
Unskilled Labour (md)
CGI sheet( sqm)
Nails
1.10
1.25
12.00
LS
200.00
150.00
300.00
100.00
220.00
187.50
3,600.00
100.00
4,107.50
0.00
4,107.50
410.75
No
Total
Unit
1.00
1.00
1.00
5.00
3.00
9.59
4.74
1.7
0.4
1
0.5
1.2
23.70
2.55
4.60
30.85 m3
1.00
3.00
3.00
3.00 m3
1.00
1.00
1.00
1.00
1.00
6.73
3.00
0.30
5.00
0.30
1.7
0.9
0.3
0.9
1.66
0.3
1.6
1.6
1.6
11.17
1.53
0.43
2.40
0.43
1.00
1.00
1.00
0.45
1.1
0.1
1
1
1
4.48
4.48
4.48
2.30
2.30
2.30
1.80
0.10
0.30
18.55
1.03
3.09
18.55 m3
1.03 m3
3.09 m3
4.78
0.55
1.40
3.68
3.68 m3
1
1
3.50
4.10
14.35
14.35 m2
Set
1
1
100
100
0.5
50
1
1
1
1
1
11
6
2.4
0.7
0.8
0.5
21.12
2.1
23.22 m3
11.00
6
2.40
0.7
0.10
0.1
2.64
0.42
3.06 m3
1
1
11.00
6
2.40
0.7
0.30
0.30
7.92
1.26
11.18 m3
1
1
1
1
1
1
1
1
1
1
3.50
6.00
2.50
3.50
6.00
2.50
0.30
10.70
1.00
0.30
0.30
0.30
0.35
0.40
0.40
1.00
3.80
0.75
1.00
1.30
1.30
1.00
1.30
1.00
0.50
1.05
2.34
0.98
1.23
3.12
1.00
0.15
40.66
0.08
c/s area=6.73
15.97 m3
0.05 m3
Set
Set
0.10
Remarks
100 m
50 m3
9.86 m3
40.66 m2
0.08 m3
Set
No
2
2
2
2
1.5
1.5
1.5
1.4
1.4
1.4
0.75
0.3
1
LS
3.15
1.26
4.2
20
24.25
0.60
1.00
14.55
2
1
2
5.00
4.00
4.90
0.60
0.60
0.60
1.00
1.00
1.00
6.00
2.40
5.88
long wall
partion wall
short wall
2
2
2
5.00
4.00
4.90
0.45
0.45
0.45
3.35
3.35
3.35
15.08
Doors
Windows
1
2
1.00
1.00
0.45
0.45
2.40
1.00
-1.08
-0.90
42.15
Total
3.15
1.26
4.2
40
Unit
Remarks
m3
m3
m3
kg
14.55
m3
42.15
m3
Superstructure
14.77
Deduct openings
2
2
2
1
4.00
4.00
4.90
5.00
3.35
3.35
3.35
4.00
26.80
26.80
32.83
20.00
Deduct openings
Doors
Windows
7 Wood work
Door and window framme
Door
Windows
Door and window shutters
Door
Windows
7 CGI Sheet roofing work
8.0 Tailrace Canal
1
2
2
2
1.00
1.00
5.80
5.00
2
2
2.25
1.00
39.32
2.40
1.00
0.07
0.07
0.10
0.10
-2.40
-2.00
102.03
102.03 m2
0.08
0.07
0.15
0.15
4.50
2.00
6.50
39.32
m3
plan area=2.40m2
6.50
39.32
m2
m2
1 Earthwork in excavation
15.00
1.00
0.65
9.75
9.75 m3
2 stone soling
15.00
1.00
0.15
2.25
2.25 m3
3 PCC (1:2:4)
15.00
1.00
0.08
1.13
1.13 m3
15.00
0.30
0.40
3.60
3.60 m3
(6.50*5.5)*1.1
Scheme
VDC
Bill Of Quantities
A. Civil Components
S.No
1
1.1
1.2
1.4
1.6
1.8
1.9
2
Description of work
INTAKE AND WEIR
Site clearance
Earth work in Ordinary Soil
Gabion Works
1:4 c/s Stone Masonry work
P.C.C for R.C.C 1:2:4
Wooden Stop Log
Coarse Trash Rack
Sub Total 1 :
2
2.1
2.2
2.3
2.4
2.5
HEADRACE CANAL/PIPE
Site clearance
Rennovation of Existing earthen canal
250 mm HDPE Pipe, 2.5 kgf/cm2
Patch Works
Back filling
Sub Total 2:
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
GRAVEL TRAP
Site clearance
Excavation
Stone soaling
PCC in 1:2:4
1:4 c/s Stone Masonary
1:4 c/s plaster of 12 mm thk
MS flusing gate
Sub Total
4
4.1
4.2
4.3
4.4
4.5
4.6
Unit
LS
Cu.m
Cu.m.
Cu.m.
Cu.m.
No
No.
LS
m
m
LS
m3
1.00
350.00
100.00
1.00
50.00
1000.00
LS
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Sq. m
no
1.00
18.55
3.09
1.03
3.68
14.35
1.00
500.00
237.00
2335.00
1,050.00
2,625.00
43.50
75.00
300.00
700.00
10000.00
0.00
250.00
5,641.00
2,260.00
175.50
7000.00
Non-local
Amount
3000.00
7312.21
2355.00
41910.23
0.00
2000.00
0.00
56577.43
0.00
3621.00
36082.71
307.15
0.00
4000.00
44010.86
3,000.00
7,312.21
5,976.00
77,992.93
307.15
2,000.00
4,000.00
100,588.29
1000.00
0.00
0.00
0.00
3750.00
1000.00
0.00
105000.00
70000.00
10000.00
0.00
185000.00
1,000.00
105,000.00
70,000.00
10,000.00
3,750.00
186,000.00
772.80
5,812.49
8,318.16
2,518.43
7,000.00
24421.87
500.00
4,395.69
7,990.75
6,894.41
17,979.73
3,142.65
7,000.00
47,903.23
500.00
4,395.69
7,217.95
1,081.92
9,661.58
624.23
23481.36
LS
Cu.m.
Cu.m.
Cu.m.
Cu.m.
Sq. m
1.00
23.22
11.18
3.06
9.86
40.66
1500.00
316.00
2,335.00
1,050.00
2,625.00
41.00
Cu.m.
Cu.m.
3.15
1.26
316.00
2335.00
Cu.m.
Cu.m.
kg
4.20
0.80
40.00
1830.00
LS
Cu.m.
1
12.5
LS
Cu.m.
Cu.m.
Sq. m
LS
Cu.m.
Sq. m
L.S.
Sq. m
Cu.m.
Cu.m.
Cu.m.
Cu.m.
1
14.55
42.15
102.03
1.00
0.15
6.50
2.00
39.32
9.75
2.25
1.13
3.60
250.00
5,745.00
3,030.00
183.60
250.00
5745.00
900.00
96.00
Total
1,500.00
7,337.52
26,105.30
3,213.00
25,882.50
1,667.06
65,705.38
2,795.00
17,579.70
29,875.80
7,465.18
57,715.68
1,500.00
7,337.52
28,900.30
20,792.70
55,758.30
9,132.24
123,421.06
995.40
2,942.10
315.00
995.40
3,257.10
7,686.00
11,623.50
24,129.00
720.00
3,840.00
29,004.00
31,815.00
720.00
500.00
316.00
500.00
3,950.00
4,450.00
2000.00
316.00
1760.00
43.50
2,000.00
4,597.80
74,181.36
10,537.13
2,000.00
4,597.80
84,718.49
561.58
3,672.50
3,081.00
5,253.75
1,186.50
9,450.00
94534.49
257,372.16
12,000.00
4,000.00
16,150.69
562.50
6,374.33
8,136.00
49,624.65
389,777.04
12,000.00
561.58
3,672.50
4,000.00
16,150.69
3,081.00
5,816.25
7,560.83
17,586.00
144,159.14
647,149.21
250.00
175.50
12,000.00
3,714.16
565.00
2,000.00
410.75
316.00
2335.00
1,050.00
2625.00
250.00
5,641.00
2260.00
40,627.50
500.00
3,950.00
4,450.00
Scheme
VDC
Bill Of Quantities
B.
Mechanical Components
S. No Description of Items
1 Penstock Pipe
Type:HDPE
Diameter: 250mm OD
Thickness/Pressure:4kg/cm2
2 Penstock Pipe
Type: MS Steel
Diameter: 225mm Internal Dia,
Thickness:3mm
3 Pipe Clamps & tar paper
With Nuts & bolts
4 Butterfly Valve
Size: 225mm dia
5 Turbine
Type: Cross flow, T12
Gross Head:25 m
Design Discharge: 80 lps
6a Turbine Base frame
6 b Generator Base frame
7 Coupling system
Type: Havasit Belt drive
8 Trash rack
Type: Fine
Coarse
9 Flushing Mechanism
Type: 300 mm dia Cone flushing
10 Vent Pipe
11 Expansion joint
12 Flange joint
Total B:
Units Quantity
m
40
10
Rate
1300
Amount
52000
1700
17000
Set
450
1800
Set
35000
35000
Nos
325000
325000
Set
Set
Set
1
1
1
4500
4500
6500
4500
4500
6500
Set
Set
Set
1
1
1
3500
2600
5600
3500
2600
5600
Set
Set
Set
1
1
2
3000
15000
7000
3000
15000
14000
505000
Remarks
Scheme
VDC
Bill Of Quantities
C. Powerhouse Electrical Component
S. No Description of Items
Units Quantity
Rate
Amount
1 AC Generator
Type: 20KVA,Synchronous brushless, 400v, 50Hz
Phase: 3
2 Governing Mechanism (ELC) with ballast heater
with tank & control panel, switch gears & Over
voltage and under voltage trip mechanism with 12
kW ballast load
3 Power cable,10 mm2 4 core Aromred Copper cable
Power cable 16 mm2 4 core Aromred Aluminium
cable
4 Power House Wiring
Transmission & Distribution Line
6 ACSR Conductors
a. Squirrel
b. Weasel
7 Insulators
a. Medium Shackle type with D-clamp, nut, bolts &
washers complete with 5 % spares
b. Small Shackle type with D-clamp, nut, bolts &
washers complete with 5 % spares
8 Poles ( Wooden Poles)
Length: 7m
9 Stay set including guy wire, turn buckle, Rod & plate
complete
10 Earthing Set
(Including Salt, Coal & lime)
Material: Copper or GI
Type: Plate
Size: 600x300x3mm plate & 8mm dia. copper wire
in case of cu plate earthing
11 Lightning arrestor
0.5 kVwith mounting accessories
12 Service cable [4mm2]
13 0.5 Amp MCB for household connection
14 MCCB (3 phase, 30 amp)
Total C:
Nos.
140000
140000
Set
114000
114000
m
m
15
27
725
275
10875
7425
LS
5000
5000
m
m
Nos.
3100.0
5700.0
194
19
25
130
58900
142500
25220
Nos.
32
120
3840
Nos.
56
700
39200
Set
16
1100
17600
Set
2975
20825
Sets
15
1000
15000
3120
18
56160
Nos.
no
104
1
325
8000
33800
8000
698345
Remarks
Scheme
VDC
Chilli Khola II
Kolki, Lamjung
Cost Summary
S.N
1
2
3
4
5
6
7
Description of Items
Cost of Civil Component
Cost of Mechanical Component
Cost of Electrical Component
Spare Parts & Tools
Transportation Cost
Installation
Commissioning Charge
Sub Total
VAT @ 13% on non local cost
Total Project cost
Contingencies (5%)
Grand Total of the Project Cost
Per Kw project cost
Local Cost
Non-Local Cost
257,372.16
389,777.04
505000.00
698345.00
20000.00
90400
55000.00
35000.00
347,772.16
1,703,122.04
Amount
647,149.21
505,000.00
698,345.00
20,000.00
90,400.00
55,000.00
35,000.00
2,050,894.21
221,405.87
2,272,300.07
113615.00
2,385,915.08
238,591.51
Remarks
Scheme
VDC
Bill Of Quantities
D. Installation and Supervision charge
S.No.
Description of Items
1
Electro-Mechanical installation & supervision
Charge
2
Transmission/ Distribution line erection &
supervision charge
Units
Quantity
Rate
Amount
LS
30000
30000
LS
25000
25000
Total D:
55000.00
Description of Items
Truck charge
Transportation of easy loads
Transportation of difficult loads
Total E:
Units
Trip
Kg
Kg
Quantity
2
12000
800
Rate
10000
5
13
Amount
20000
60000
10400
90400
Units
Quantity
Rate
Amount
20000
LS
20000.00
20000.00
Mechnical Parts
Electrical Parts
Total G:
LS
LS
1
1
20000
15000
20000
15000
35000.00
Tariff
Monthly
Annual Remarks
Income
Income
NRs./watt/Mont NRs.
NRs.
h
1 104X95=9880
1.5
14820 177840
Grand Total 1,77,840
Hence, Total Annual income from domestic lightening and business load is Rs.3,39,840
Expenditure:
S. Post
N.
Office
1 Expenses
2 Manager
3 Operator 1
4 Operator 2
Operation&
4 Maintenance
5 Miscellaneou
Grand Total
Salary/Month Annual
Remarks
cost NRs.
LS
10,000.00
1500
3000
3000
LS
Source of Finance
S.N
Total Subsidy:
1325000
312000
Equity:
347772
2 VDC Investment 200000
Bank Loan Project 201,143
3 Total
2,385,915
4 Cost:
1
NRs. 10*125000+15*10*500
Cash ( @ 3000/HH)
Kind
Finanacial Analysis
Annual OCF,
Oa
% of Annual
OCF,O%
Actual OCF,
Oy=Oa*O%
Cumulative Cash
flow, C=Cy+Cy1
NPV Divisor,
Dy=(1+K)y
NPV, N=Cy/Dy
@K%
201,143
Actual ICF,
Iy=Ia*I%
180,000
Bank Loan
6%
% of Annual
ICF,I%
Discount rate, K =
Annual ICF,
Ia=St
2,385,915
1,325,000
1,060,915
339,840
Year
1060915
100
1060915
-1060915
-1060915
1.00
-1060915
339840
70
237888
180000
100
339840
80
271872
180000
100
180000
91872
-911155
1.12
81766
339840
90
305856
180000
100
180000
125856
-785299
1.19
105671
339840
100
339840
180000
100
180000
159840
-625459
1.26
126608
180000
159840
-465619
1.34
119442
180000
57888
-1003027
1.06
54611
339840
100
339840
180000
100
339840
100
339840
180000
100
180000
159840
-305779
1.42
112681
339840
100
339840
180000
100
180000
159840
-145939
1.50
106303
339840
100
339840
180000
100
180000
159840
13901
1.59
100286
180000
159840
173741
1.69
94609
339840
100
339840
180000
100
10
339840
100
339840
180000
100
180000
159840
333581
1.79
89254
11
339840
100
339840
180000
100
180000
159840
493421
1.90
84202
12
339840
100
339840
180000
100
180000
159840
653261
2.01
79436
180000
159840
813101
2.13
74939
13
339840
100
339840
180000
100
14
339840
100
339840
180000
100
180000
159840
972941
2.26
70697
15
339840
100
339840
180000
100
180000
159840
1132781
2.40
66696
4893696
3760915
1600
3760915
1132781
-716465
26
306285
Total:
NPV Rs.
IRR %
306,285
10%
7.91
1.55
Page - 15 of 17
B/C Ratio
Annual
Annual
Income Expenditure
237888
241431
271872
241431
305856
241431
339840
241431
339840
241431
339840
180000
339840
180000
339840
180000
339840
180000
339840
180000
339840
180000
339840
180000
339840
180000
339840
180000
339840
180000
Total
B/C Ratio =
Discounted
Income
224422.64
241965.11
256802.60
269185.11
253948.22
239573.79
226013.01
213219.82
201150.77
189764.88
179023.47
168890.07
159330.25
150311.56
141803.36
3115404.66
6%
Discounted
Expenditure
227765.03
214872.67
202710.07
191235.91
180411.24
126892.90
119710.28
112934.23
106541.72
100511.06
94821.75
89454.49
84391.02
79614.17
75107.71
2006974.25
Remarks
1.55
Page - 16 of 17
Annuity Payment
Principal
Remaining
201,143
171,895
137,967
98,611
52,958
-
Annuity
Payment
61,431
61,431
61,431
61,431
61,431
-
Principal
Interest of
Payments
29,248
33,928
39,356
45,653
52,958
-
32,183
27,503
22,075
15,778
8,473
-
16.0%
5
61431
0
241431
98409
0
Remarks
Years
Subsidy deducted
Page - 17 of 17