INDENT :
MBB Indent 1
UPGRADE TYPE :
1 2
DAP Approval
Division Site Acqauisition Access Planning Civil Infra. Development Tx. Planning Power System Planning Approval Status Name Signature Date Remarks
Comments:
Dialog FTK
Site ID
GA0001
Site Name
Ahungalla
Surveyed By
Buddhika Krishantha
Surveyed Date
8-Dec-12
Dialog FTK
Basic Site Information
Site ID Site Name District Region Regional Manager Site Owner Site Type Coverage Tower Height Building Height
GA0001 Ahungalla Galle Southern
0777-333459
Urban Highway
Rural Port
Middaramulla, Ahungalla.
80 02 11.2 E Latitude 06 13 32.7 N
Dialog SPOC 777339026 MR.Nishantha Mobile Dialog Head Office Dialog Regional Office Site Key XFrom Landloard Other XNo Yes Additional Requirements for If Yes Description: Site Access Name Site Access Time Permitted Installation Time
X24 Hr
Transporation
Details : X24 Hr Specific Period Only Details : Manual If>50m Specify: 4WD Distance: XOther Specify: Comments: Medium Vehicle (Van, Lorry.) Stairs Elevator Crane Boom Truck Other Crane Arm Length Permitted Use Time Transport Promptly after removal Transport at other time
Remarks
Dialog FTK
Scope of Work & Site Survey Check List RBS/Antenna & Feeder System Scope of Work
Enclouser Type Upgrading Band
XIndoor
Band 1 (GSM) XBand 3 (3G)
Other
Upgrade Type Entire RBS(BTS/Node B) SWAP RBS(BTS/Node B) RRU Change RBS Base Band Capacity Change RBS Capacity Expansion-(Standalone) RBS Capacity Expansion-(Co-Cabinet) Antenna Network Change Band 1 RBS Configuration Existing Capacity Existing Mode Final Capacity Final Mode Existing RBS Type Existing RBS Qty Final RBS Type Final RBS Qty
Band 3
Band 2
Band 3
1+1+1 with HSPA 40W+40W+40W 2+2+2 with HSPA
40W/40W+40W/40W+40W/40W
1
RBS6601 With RRUS 11
1) Remove Existing Macro BTS and Install RRU-MU System. 2) Remove DTMA Connected to Antenna System before new RRUS-11 connect to the existing Antenna System List of Key Actions 3) Remove existing jumper cables and Connect New RRUS-11 with to be Performed Provided Antenna Jumper and Other RRU Installation Accessories 4) Remove,Repack and return the idling Macro BTS & BTS Installation Accessoroes 5) Remove,Repack and return the idling RF Cable & Accessories
Remarks
Dialog FTK
Scope of Work & Survey Check List RBS/Antenna & Feeder System Survey Check List - New RBS Installation
RBS Installation Details Fixed on floor Fixed to wall In 19" rack In Power Cabinet
Final RBS Installation Location
Existing
Final
X X
X Existing Cabin Different Cabin Position of Existing RBS Cabinet (after removal) On top of Existing RBS cabinet/ Auxiliary Cabinet Installation Position of New Macro RBS New Position in Cabin Other N/A XIn Existing 19" rack In New 19" rack Installation Position of Fixed to wall New Distributed RBSIn Power Cabinet Main Unit(MU) In Other RBS/Auxiliary Cabinet Other Install in Cabin(Wall/Floor) Install on Outdoor Wall Installation Position of New Distributed RBS- Install on Outdoor Antenna Pole Remote Radio XInstall on Tower Antenna Bracket Unit(RRU) Install on Tower Platform Other Existing BTS/MU Synchronization Data Band 1 Band 2 Band 3 Macro RBS Synch Yes No Yes No N/A MU TG Synch(Ext) Yes No Yes No N/A MU TG Synch(Int) Yes No Yes No N/A RRU Rx Combining Yes No Yes No N/A New BTS/MU Synchronization Data Band 1 Band 2 Band 3 Macro RBS Synch Yes No Yes No N/A MU TG Synch(Ext) Yes No Yes No N/A MU TG Synch(Int) Yes No Yes No N/A RRU Rx Combining Yes No Yes No N/A
Band 1 Sector 1 Sector 2 Sector 3 Remarks Band 2 Band 3 N/A N/A N/A
Dialog FTK
Scope of Work & Survey Check List RBS/Antenna & Feeder System Survey Check List - New RBS Installation
Current BTS/MU Sector Details Band 1 BTS #1 BTS #2 MU #1-DUx-1 MU #1-DUx-2 Final BTS/MU Sector Details Band 1 BTS #1 BTS #2 MU #1-DUx-1 MU #1-DUx-2 Current RRU Details Band 1 No of RRU in Sector 1 No of RRU in Sector 2 No of RRU in Sector 3 No of RRU in Sector 4 Final RRU Details Band 1 No of RRU in Sector 1 No of RRU in Sector 2 No of RRU in Sector 3 No of RRU in Sector 4 Is RBS Connected to External Alarm Yes Pannel Changing Details: Protective Grounding Cable Length(m) Band 1 MU/BTS RRU in Sector 1 RRU in Sector 2 RRU in Sector 3 Other RBS Cable Accessories Length(m) Band 1 RBS Synch Cable
External Alarm Cable RBS PCM Cable
Band 2
Band 3 S1,S2,S3 N/A N/A N/A Band 3 N/A N/A S1,S2,S3 N/A Band 3 No No No No Band 3 1 1 1 No
Band 2
Band 2
Band 2
XNo
Band 2
Band 2
Remarks
Dialog FTK
Scope of Work & Survey Check List RBS/Antenna & Feeder System Survey Check List -Antenna Installation
Existing Antenna System Antenna Type and Quantity Band 1 Sector 1 Sector 2 Sector 3
Antenna Height and Orientation
Band 2
Band 3
Kathrein-741990/1 Ant Kathrein-741990/1 Ant Kathrein-741990/1 Ant
Band 1 Sector 1 Sector 2 Sector 3 Antenna Tilt(M & E) Band 1 Sector 1 Sector 2 Sector 3 New(Additional/Replacing) Antenna System Antenna Type and Quantity Band 1 Sector 1 Sector 2 Sector 3
Antenna Height and Orientation
Band 2
Band 1 Sector 1 Sector 2 Sector 3 Antenna Tilt(M & E) Band 1 Sector 1 Sector 2 Sector 3 Space for New Antenna Band 1 Yes,Existing Infra Yes,New Infra No Other Remarks
Band 2
Band 2
Dialog FTK
Scope of Work & Survey Check List RBS/Antenna & Feeder System Survey Check List -Feeder & Other Installation
Existing Feeder System
1/2" Jumper Length & Connector-ANT End
Band 1
Band 2 3m 3m 3m
Sector 1 Sector 2 Sector 3 RF Cable or Fiber Length & Connector Band 1 Band 2 Sector 1 Sector 2 Sector 3 New Feeder System
1/2" Jumper Length & Connector-ANT End
Band 1
Band 2 2m 2m 2m
Band 3 Straight Straight Straight Band 3 85m 85m 85m 85m 85m 85m
Sector 1 Sector 2 Sector 3 RF or Fiber Cable Length & Connector Band 1 Band 2 Sector 1 Sector 2 Sector 3
RRU DC Power Cable Length & Connector
Sector 1 Sector 2 Sector 3 Cable Rack System Band 1 New Indoor Horizontal Cable rack required? New Outdoor Horizontal Cable rack required? New Outdoor Vertical Cable rack required? Yes No Details Yes No Details Yes No Details Yes No Details Yes No Details Yes No Details Band 2
Band 3 Yes XNo Details Yes XNo Details Yes XNo Details
Remarks
Remove existing 3G Feeder System and replace with new Fiber System using Down Time
Dialog FTK
Scope of Work & Survey Check List RBS/Antenna & Feeder System Survey Check List -Feeder & Other Installation
TMA and Other Passive Components Band 1 Current TMA Config Availability Model & Quantity Powered by Feeder
Powered by DC Inject Bias-T Type & Qty Injector Type & Qty TMA-CM & Cable Type
Band 2 Yes/No
Yes/No
X
N/A N/A N/A N/A Band 3 N/A
Band 1
Band 2
Current RF Combiners Availability Model & Quantity Indoor/Outdoor New RF Combiners Model & Quantity Indoor/Outdoor Combining Details Space for New Combiners. If No,Remarks: Remarks Yes/No Yes/No Band 1 Yes/No Band 2 Yes/No Band 3 Yes/No N/A N/A Band 3 N/A N/A
Band 1
Band 2
Yes/No N/A
Dialog FTK
Scope of Work & Survey Check List Civil Infrastructure Survey Check List -Equipment Room
Equipment Room Position Equipment Room Size Equipment Room Type Owner of Equipment Room Floor Type Feeder Window & Holes
Grounding Bar
X Greenfield Rooftop Shelter In the Building Outdoor Cabinet Other If Building,Details: Length(m) Width(m) Height(m) 3.66m 2.43m 2.78m Concrete Zinc-Aluminium XCement Other PU XDialog Other Operator Landlord Other XConcrete Cement Steel Other XPossible to use existing No of Used Holes 9 No of Unused Holes 5 Need New Feeder Window/Holes Mark proposed Location in Layout Grounding Points in Indoor Grounding Bar Used 14 Non Used 2 Grounding Points in Outdoor Grounding Bar Used 11 Non Used 0 Need New Grounding Bar Mark proposed Location in Layout
After the Existing BTS System is removed free grounding point can be used for the new system.
Remarks
Scope of Work
XNo Yes Mark proposed Location in Layout XNo Yes Mark proposed Location in Layout XNo Equipment Room Modification Yes Required Mark details in Layout XNo Other Modifications Required Yes Mark details in Layout List of Key Actions to be Performed
New Cellular Poles/Brackets Required New Microwave Poles Required
Remarks
Dialog FTK
Scope of Work & Survey Check List Power System Scope of Work
Upgrade Type
XNone
Battery Bank Upgrade Battery Bank Replacement Rectifier Upgrade Rectifier Replacement Site Power Supply Upgrade Other Comments:
X Three Ph
Existing E.T.N 75A 5 7 Final Oerlikon 4 150Ah Spare N/A 0 6 2 N/A 2 N/A 2 N/A Final
DC
Rectifier Details Model Capacity(A) No of Used Modules No of Unused Modules Battery Bank Details Model No of Banks Capacity of Each(Ah) No of DC Breakers Available 63A 50A 32A 25A 20A 16A 10A 6A Other
Other Power Cable Length(m)
15m 5m 5m Power Supply Plan for New RRUs XIncluded in Drawing/Photoes List of Key Actions to be Performed Proposed PDU will be installed on wall for RBS 6601 and RRU Power Remarks
DC Power Cable for new PDU Blue DC Cable for new RBS Black DC Cable for new RBS
Dialog FTK
Scope of Work & Survey Check List Transmission System Survey Check List
Transmission Equipment Type Transmission Provided by
XMicrowave
Fiber
XDialog
DBN Details: Transmission for New RBS X120 Ohm-E1 Type 75 Ohm-E1 Rack Space Availability
STM-1 FE
Other
No 7u/5u/3u
Yes
Pair Ref:
XNo
Comment: SMB Male BNC Male SMB Female BNC Female SMZ Male SMZ Female Quantity: Krone Module XCable Punch Down Cable Winding Other
XOther
Remarks
Dialog FTK
Site Photoes
Included
X X X X X X X X X X X X X X X X X X
Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken Photo Taken
Dialog FTK
Tower Panoramic A-B (0 to 315)
45
90
135
180
225
270
315
Dialog FTK
BS Panoramic A-B (0 to 315)
0o
135
180o
225o
270o
315
Dialog FTK
Site ID GA0001 Site Name Ahungalla Antenna Photo
3G Antenna
S1
S2
S3
GSM(900MHz) RRU
GSM(900MHz) RRU
Proposed
Site ID GA0001 Site Name Ahungalla Exterior view and interior view of the original cabinet
Dialog FTK
Site ID GA0001 Site Name Ahungalla Vertical Cable Ladder
Site ID
GA0001
Site Name
Ahungalla
Dialog FTK
Site ID GA0001 Site Name Ahungalla Installation position of new cabinet
Site ID
GA0001
Site Name
Ahungalla
Cabling rack
Dialog FTK
Site ID GA0001 Site Name Ahungalla Exterior view and interior view of the transmission equipment
Site ID
GA0001
Site Name
Ahungalla
Dialog FTK
Site ID GA0001 Site Name Ahungalla Exterior view and interior view of the equipment room
Site ID
GA0001
Site Name
Ahungalla
Dialog FTK
Site ID GA0001 Site Name Ahungalla Exterior view and interior view of the AC power distribution box
Site ID
GA0001
Site Name
Ahungalla
Dialog FTK
Site ID GA0001 Site Name Ahungalla Exterior view and interior view of the external alarm box
N/A
Site ID
GA0001
Site Name
Ahungalla
Dialog FTK
Site ID GA0001 Site Name Ahungalla Outdoor view and indoor view of the feeder window
Site ID
GA0001
Site Name
Ahungalla
Dialog FTK
Site ID GA0001 Site Name Ahungalla Jumper at the BS side
Site ID
GA0001
Site Name
Ahungalla
Dialog FTK
Site ID GA0001 Site Name Ahungalla Stairs, elevator, and other entries
Site ID
GA0001
Site Name
Ahungalla
N/A
Dialog FTK
Included
X Layout Attached
X X X X
Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached Layout Attached