Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Sl. no. THE BASICS 1 2 3 4 5 6 7 Definitions Planning Process Project Scheduling Tools and Techniques used Terminology used Network Diagrams PERT Networks 3 4 5 6 7 8 14 Description Slide No.
THE PRACTICAL ASPECT OF SCHEDULING 8 9 10 How do we start development of a schedule Baselines updation and Tracking How to cope up with a delay 18 19 21
The Definitions
Project It is a temporary endeavor undertaken to create a unique product or service. Project Planning It is a part of Project Management, which relates to the use of schedules (e.g. Gantt Charts) to plan , report progress and subsequently control the project. project
Preparation of Schedule
Project Scheduling It is an integral part of Project Planning which is concerned with the techniques that can be employed to manage the activities that need to be undertaken during the development of a project. Objectives: Completing the project as early as possible by determining the earliest start and finish of each acti it activity Calculating the likelihood a project will be completed within a certain time period Finding the minimum cost schedule needed to complete the project by a g p p j y certain date Investigating the results of possible delays in activitys completion time Progress control Smoothing out resource allocation over the duration of the project
Milestone Chart
CPM
Terminology used
Float/ Slack The amount of time an activity can be delayed without delaying the project (total float) the (t t l fl t) or th early start of any successor activity (f l t t f ti it (free fl t) float) Milestone An activity with zero duration which indicates the start or finish of a major task ac y e o du a o c d ca es e s a o s o ajo as Work Breakdown Structure (WBS) The overall project is subdivided into smaller elements called Work Breakdown Structure (WBS) Its purpose is to divide the total project into (WBS). pieces of work called work packages which makes it easier to prepare project schedules, cost estimates and to assign management and task responsibilities p Critical Path It is a sequence of project network activities having zero float. It determines the shortest time possible to complete the project
6
Network Diagram It is a graphical representation of the project and it consists of a series of activities arranged in a logical sequence and show the interrelationship between the activities. Types: AON(Activity on node) or PDM(Precedence Diagramming method) A
START
D C
F
FINISH
Activity A Activity B y
Activity A Activity B
Activity B
Network Analysis
Forward Pass: It gives the earliest expected event times i.e. Early Start (ES) and Early Finish (EF) for each activity.
Backward Pass: It gives the latest allowable event times i.e. Latest Start (LS) a d a es and Latest Finish ( ) for eac ac s (LF) o each activity. y
10
105,110 110,115 C 5 115,129 115,129 115 129 F 14 129,149 129,149 129 149 G 20
149,170 173,194 H 21 149,177 166,194 166 194 I 28 149,194 149 194 149,194 J 45 194,204 194,204 194 204 K 10
11
Interpreting a schedule
The following parameters are essential to interpret a schedule
1.
BL1 Early Start or Early Finish Indicates when the activity should have started or finished BL1 Late Start or Late Finish Indicates maximum extent an activity can be delayed as per original plan Total Float Indicates how much float is available at a particular point in the schedule Free Float Indicates how much float can be actually used Schedule Percentage Complete How much should have been complete Actual Percentage Complete How much is actually complete
2.
3.
4.
5.
6.
12
The Baseline
Updated Schedule
Updated Schedule
13
Gantt chart The Bar or Gantt Chart is used as a visual aid for tracking the progress of project activities Appropriate percentage of a bar is shaded to document the completed work The manager can easily see if the project is progressing on schedule
14
Milestone Chart A Milestone chart is similar to a Gantt Chart with the emphasis placed on task completion Milestones allow project management to much more accurately determine whether or not the project is on schedule
14
Approved vendor reports Updated Approved schedules from the vendor Consultant reports on drawings and documents Vendor manufacturing data Package owner inputs Inputs from project owner
Vendor Reports Vendor reports are essential inputs for the updation process Standard report formats should be prescribed in the contract document Contact persons should be detailed out in the Co-ordination Procedure Vendor reports should be commented upon receipt and clarifications sought Vendor reports should at least contain the Engineering , Procurement and Construction data Reports have to be submitted at least on monthly basis
16