Sei sulla pagina 1di 2462

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. Circle - Vasai Activity No.

0913 Name of Activity: LOCATION OF 11 KV 3 CORE X 300 sq. mm XLPE CABLE Division - Palghar

Boisar
Sr. No. 1 2 Sub Division Boisar (Midc) Boisar (Midc) From Gangotri 500 kva Contessa 33/11KV DTC Contessa Feeding Sub Station Location To Siyaram Colony Total Length in actual length KM(as per DPR) 0 0.7 Touched/ untouched Completed resource to bill Balance work for commissioned remarks

untouched 100 M Cable laying,4 nos end termination joint,03 straight joint,01 nos dp pole erection,

Not req

Boisar (Midc)

Contessa

Substation

JB Textile

1.1

Touched

Balnce work

contractor absent,

Boisar (Midc)

Contessa

Substation

Kepro Industries

2.4

1.5

Touched

1.5

Balnce work

contractor absent,laid cable 4 nos end termination have been damage during the joint,05straight joint,01 midc work,so 30*2 cable nos dp pole erection, should be replaced to be done

5 6 7 8

Boisar (Midc) Boisar (Midc) Boisar (Midc) Boisar (Midc)

kaneriia N-Zone N-Zone N-Zone

Viraj Substation Substation

Road Crossing Sahilendra N-30 /Near Sarex Overseas Aarti Drugs/Sahilendra

0.6 4 0 3.2 1 2

untouched Touched

0 0 Balnce work wip

recently trench work start,

Touched

Balnce work

wip

recently trench work start,

9 10 11 12 13 14 15

Boisar (Midc) Boisar (Midc) Boisar (Midc) Boisar (Midc) Boisar (Midc) Boisar (Midc) Boisar (Midc)

N-Zone TAPS Khairapada TAPS TAPS EHV-1 EHV-1

Substation Petrol Pump Khaira pada S/S Camlin Naka Substation

kolwade Athmasakthi Near Manse Bangalow MIDC Office Chowk Plot F-4

2.6 0.16 0.57 0 0 2 3.4

Touched untouched Touched

0 0 0.57

Balnce work

wip

recently trench work start, not req

0.57

Completed

untouched 3.4 Touched

0 3.4 Bay Requried End termination, DP pole erection Road crossing balance

work can not start due to need of HT feeder Piller bay not avilable

Sr. No.

Sub Division

Feeding Sub Station

Location From Substation Substation To Petrol Pump Near VIRAJ industries Vasundra Diary

Total Length in actual length KM(as per DPR)

Touched/ untouched

Completed

resource to bill

Balance work for commissioned

remarks

16 17

Boisar (Midc) Boisar (Midc)

EHV-1 EHV-1

10 2.4

untouched untouched

0 0 balance work in wip ,damage replacement End termination, DP pole erection cable balance work in wip , damage replacement End termination, DP pole erection cable balance work in wip , damage replacement End termination, DP pole erection cable

work can not start due to need of HT feeder Piller work can not start due to need of HT feeder Piller

18

Boisar (Midc)

EHV-1

Substation

Fibrosa

2.6

2.6

touched

2.6

Trench Requried

1. Substation 19 Boisar (Midc) EHV-1

1.BOC

2.2

2.2

touched

2.2

For commissioning 1 No HT feeder piller required

2.Substation

2.Khurana

touched

Bay Requried

Trench Requried

20

Boisar (Midc)

EHV-1

0 balance work in wip , damage replacement End termination, DP pole erection cable

21

Boisar (Midc)

EHV-1

Substation

Ankit Petro products

3.1

3.1

touched

3.1

Bay requried

Trench Requried

22

Boisar (Midc)

P-100

Substation

Hotel lalit

0.6

untouched

s/s deleated

23

Boisar (Midc)

N-Zone (EHV-1)

N-zone S/S

Galaxy

2.4

untouched

survay not clear

24

Boisar (Midc)

P-100

Substation

S-23

0.8

untouched

0 balance work in wip , damage replacement End termination, DP pole erection cable

s/s deleated

25

Boisar (Midc)

EHV-1

Near K-Plot

Near K-Plot

0.16

2.8

touched

2.8

Trench Requried

26

TOTAL

Sr. No.

Sub Division

Feeding Sub Station

Location From To

Total Length in actual length KM(as per DPR) 52.89 30.27

Touched/ untouched

Completed 24.17

resource to bill

Balance work for commissioned

remarks

Boisar (R)
27 28 29 30 31 32 33 34 35 Boisar (Midc) BOISAR R BOISAR R BOISAR R BOISAR R BOISAR R BOISAR R BOISAR R BOISAR R N-Zone TAPS TAPS TAPS Pathrali N-Zone N-Zone TAPS Substation Near Palm Panchyat KUMBAWALI 2.6 0.3 0.18 0.1 0.3 untouched touched for patrrale ss 0 touched Completed taken in midc bay not bay not nor req 60.97 5.374 0 bay not avilable

4.6 0.3

Total 36 Completed in Other Subdivisions Grand Total

5.374 0

66.344

2.7

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. Circle - Vasai Activity No.0913 Name of Activity: LOCATION OF 11 KV 3 CORE X 300 sq. mm XLPE CABLE, HT feeder Pillars required for commissioning of cable. Division - Palghar

Boisar
Sr. No. 1 2 3 Sub Division Feeding Sub Station EHV-1 EHV-1 EHV-1 Location From Camlin Naka Substation Substation To MIDC Office Chowk Petrol Pump Near VIRAJ industries Vasundra Diary Total Length in actual length KM(as per DPR) 2 10 2.4 2 10 2.4 Touched/ untouched Completed resource to bill Balance work for commissioned remarks work can not start due to need of HT feeder Piller work can not start due to need of HT feeder Piller work can not start due to need of HT feeder Piller balance work in wip , damage replacement End termination, DP pole erection cable 2.2

Boisar (Midc) Boisar (Midc) Boisar (Midc)

untouched untouched untouched

0 0 0

Boisar (Midc)

EHV-1

1. Substation

1.BOC

2.2

2.2

touched

2.2

For commissioning 1 No HT feeder piller required

16.6

16.6

Activity No.0913 Name of Activity: Laying & commissioning of Under Ground 11 KV 3 CORE X 300 sq. mm XLPE Cable

Sr. No.

Sub- Division

Scope

Completed/ WIP

Balance

Remarks

1 Boisar MIDC

52.89

30.27

For completing 16.6 Kms., 8 Nos.11 KV. HT 22.62 Pillars are required, for 6 Kms.alternate survey is required. For 4 Kms.Bay Required at TAPS S/s., for 3.6 7.68 kms. Alternate survey is reqd. 0

2 Boisar R

8.08

0.4

3 Palghar/ Dahanu

8.37

8.37

Total

69.34

39.04

30.3

Note: Cable received at site- 71 Kms. U/G. Cable.

Potrebbero piacerti anche