PROPOSED NACALA FLOUR MILL COMPLEX FOR M/S MIKOANI TRADERS LTD. DRAWING Nos.

QA-024-SE-AD1/AD2 & AD3 TAKE-OFF LIST 1) SITE PREPARATION Anti-termite treatment Over-site excavation Cutting trees Site clearance 2) EXCAVATION Foundation pits Foundation trenches Excavating in rock Backfilling Disposal of excavated materials 3) DISPOSAL OF WATER 4) PLANKING AND STRUTTING 5) HARDCORE FILLING 6) PLAIN & REINFORCED CONCRETE Blinding Strip foundations Column bases Column Surface bed Splash apron 7) REINFORCEMENT Y8 Y10 Y12 Fabric mesh reinforcement to surface bed 8) FORMWORK Formwork to foundations Columns Edges of slab 9) PRECAST CONCRETE UNITS 11) WALLING 12) FACEWORK 13) DPC Damp proof membrane Damp proof courses
Assignment III Take Off

Ass III - 1

SITE PREPARATION L 22,500 Add Apron 2/650 1,300 Add Wall 2/115 230 24,030 24.03 11.83 284.27 6.03 1.93 W 10,300 1,300 230 11,830

EXCAVATION External wall 12,228 22,500 2/ 34,728 69,456 External trenches 69,456 16,000 Ddt bases 16/1,000 53,456 Internal wall trenches Girth 4/4,500 18,000 Ddt bases 4/1,000 4,000 0 14,000

11.64 295.91

'Gladiator 4TC' or other equal and approved chemical anti-termite treatment to subsoil and filling applied in accordance with the manufacturer's instructions. & Excavating oversite to remove vegetable soil average 150 mm and spread and level where directed on site. & Clear site of all bushes, shrubs, undergrowth, small trees and the like generally, grub up roots and burn arisings on site. & Excavating to reduce levels 150 mm thick and remove from site. 20/ 1.00 1.00 1.20

24.00

Excavating pits to receive foundations commencing from stripped level: not exceeding 1.5 m deep. & Return, fill and ram. & Extra over all excavations for excavating in rock X 0.05 1.20 m3

Cut tree 600 - 900 mm girth (measured 1 m from ground); grub up roots and remove from site. & Cut tree 900- 1200 mm girth (measured 1 m from ground); grub up roots and

53.46 0.70 1.20 14.00 0.70 1.20

44.90

Excavating trenches to receive foundations commencing from stripped level: not exceeding 1.5 m deep. & Return, fill and ram. & Extra over all excavations for excavating in rock X 0.05 2.83 m3

11.76 56.66

Assignment III Take Off

Ass III - 2

DISPOSAL OF WATER 2/ Item Allow for keeping all excavations free from water (except spring and running water) by pumping, bailing or other means necessary. & Allow for provision and subsequent removal of planking and strutting to uphold and maintain all faces of excavations generally. Internal walls girth 4/4,500 18,000 Ddt 4/230 -920 0 17,080 HARDCORE 22.73 10.53 239.35 4.73 1.93 9.13 Ddt 69.46 0.23 15.97 18.00 0.23 4.14 228.36 150 mm thick hardcore filling to make up levels; deposit, spread and level and compact: 50 mm selected lake sand blinding. 20/ 1.00 1.00 0.30 REINFORCED CONCRETE 53.46 0.70 14.00 0.70 230 mm Reinforced in-situ concrete (1:1:3)/20 mm agg. - 25N/mm2; beds; strip foundation. & Ddt Return fill and ram x 0.23 = 10.86 m3 & Cart away x 0.23 = 10.86 m3 2/ 4/ 22.73 0.55 12.46 0.55 0.55 0.55 25.00 13.71 1.21 39.92 50 mm thick precast concrete paving slabs on and including bed of sand and bedded, jointed and pointed in cement and sand (1:3) mortar.

37.42 9.80 47.22

6.00

PLAIN CONCRETE 20/ 1.00 1.00 53.46 0.70 14.00 0.70 50 mm Plain in-situ concrete (1:3:6)/20 mm agg.; blinding to column bases.foundations. & Ddt Return fill and ram x 0.05 = 3.36 m3 & Cart away x 0.05 = 3.36 m3

Reinforced in-situ concrete (1:1:3)/20 mm agg. 25N/mm2; foundations to columns & Ddt Return fill and ram & Cart away

20.00 37.42 9.80 67.22

Hardcore + Floor Base

Height 1,500 50 -300 -350 900

Assignment III Take Off

Ass III - 3

20/

0.23 0.30 0.90

1.24

Reinforced in-situ concrete (1:1:3)/20 mm agg. 25N/mm2; columns & Ddt Return fill and ram & Cart away 126.00 126.00 15.80 15.80 349.82 349.82 491.62

REINFORCEMENT High yield tensile steel bar reinforcement to BS 4449 as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks

Y8 x 0.395 kg/m = 194.19 kg.

20/

0.23 0.30 0.15

0.21

Reinforced in-situ concrete (1:1:3)/20 mm agg. 25N/mm2; columns

308.00 308.00 200.00 200.00 508.00 22.73 10.53 239.35 4.73 1.93 9.13 248.48 Ddt 20/ 0.23 0.30

Y10 x 0.617 kg/m = 313.44 kg.

150 mm Reinforced concrete (1:1:3) / 20 mm agg. 25 N/mm2 in surface bed including tamping around fabric reinforcement.
&

259.20 259.20 28.80 28.80 288.00

Y12 x 0.888 kg/m = 139.06 kg.

1.38 247.10

Mesh fabric reinforcement reference A193 weiging 1.58 kg/m2 including 200 mm end and side laps. & 1000 gauge polythene damp proof membrane; 300 mm laps.

Assignment III Take Off

Ass III - 4

FORMWORK Sawn formwork 20/4/ 2/ 2/ 1.00 0.30 53.46 0.23 14.00 0.23 Vertical or battering sides of foundations, ground beams, machine bases.

WALLING Solid concrete block walling to BS 6078; laid in cement mortar (1:3); strength 3.5 N/mm2. Height 1,500 50 -300 -280 970

24.00 24.59 6.44 55.03

20/4/

0.23 0.90

16.56

Vertical or battering sides of columns.

Walls on columns 1,000 230 2) 770 385 230 mm walling. 67.37 16.57 & Ddt Return fill and ram x 0.23 = 18.36 m3 & 3.57 0.55 79.82 Cart away
x 0.23 = 18.36 m3

2/ 2/

22.73 12.46

45.46 24.92 70.38

Edges of beds; 75 - 150mm high.

69.46 0.97 17.08 0.97 Ddt

PRECAST CONCRETE Precast concrete class 35 (35 N/mm2) units; reinforced as necessary; finished fair face on all exposed sides; bedded and jointed in cement and sand mortar (1:4) including hoisting and fixing into position. 2/ 2/ 11.83 23.93 23.66 47.86 71.52 Concrete flat edging 50 x 200 mm on and including 350 x 150 mm plain concrete grade 20/15 mm bed with haunching one side and including all necessary excavation and disposal.

16/ 20/

0.23 0.97 0.39 0.07

69.46 0.15 17.08 0.15

10.42 2.56 12.98

230 mm walling.

Assignment III Take Off

Ass III - 5

FACING 2/ 2/ 22.73 0.05 12.46 0.05 50 mm Stone pitching to brick plinth walling and bedded, jointed and pointed in cement and sand (1:4) mortar. Ddt 24.00 56.66

2.27 1.25 3.52

Return, fill and ram selected excavated materials around foundations; deposit in 150 mm layers and compact to 98% MDD.

DAMP PROOF COURSE

'Hessian based bituminous felt damp proof course: horizontal; 200 mm wide: 150 mm laps, bedded and jointed in cement mortar (1:4).
69.46 17.08 Ddt 0.23 69.46 17.08 230 mm wide. -

10.86 6.00 3.36 1.24 18.36 40.84

10.86 6.00 3.36 1.24 18.36 39.82

Load, cart, deposit and spread surplus Excavated material approximately 10 km from site to a place approved by the local authority.

16/

3.68 82.86

Assignment III Take Off

Ass III - 6