COST ESTIMATION
Not an exact science WBS cost is a good starting point Do not leave anything out Estimating forms Estimators:
Optimistic estimators Pessimistic estimators Inconsistent estimators Accurate estimators
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
Other factors
Use of widely optimistic estimates Unawareness of good cost or time estimate practices Number of things producing errors in cost estimates are unlimited Allowance for waste and spoilage Bad luck: unpredicted delays
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
If labour is paid a wage of $12 per hr, and if benefits equal 28% of the wage rate, the estimated labour cost for 25 units is (1.28)($12/hr)(25 units)(70 hr/unit) = $26,880 Is this an underestimate or overestimate of actual labour cost?
Studies shown that human performance usually improves when a task is repeated.
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
Learning Curve
Tn T1n
Tn = time required for the nth unit of output T1 = time required for the initial unit of output n = number of units to be produced r = log decimal learning rate/log 2 Total time required for all units of a production run of size N is
total tim e T1 n r
n 1
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
Assuming that after producing the 20th unit, there is no significant further improvement. If Tn=70 hrs, the time required for the first unit is
Tn T1 r n
r = log 0.85/log 2 = -0.235
T1 = 141.3 hr The multiplier = 12.40
(12.40)(141.3 hr) = 1752.12 The last five units were produced in the stead-state time of 70 hrs each
1752.12 + 5(70 hr) = 2102.12 hr
Direct labour cost = 2101.12($12)!1.28) = $32,288.56 Difference with first estimate = $32,288.56 - $26,880 = $5,408.56 Accuracy = about 17%
Number of units
1
Order-of magnitude
Made without detailed engineering data May use past experience, scale factors, parametric curves or capacity estimates
Type of Estimates 3
Definitive estimate/Detaile d estimating
Prepared from welldefined engineering data including vendor quotes, fairly complete plans, specifications, unit prices, and estimate to complete.
2
Approximate estimate or top-down estimate
Made without detailed engineering data Prorated from previous projects similar in scope and capacity This is estimating by analogue, parametric curves, rule of thumb and indexed cost of similar activities adjusted for capacity and technology.
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
Project Estimating
Standard Project Estimating
WBS Level 1 2,3 4,5,6 Type of Estimate Estimate Method Accuracy -25%, +75% -10%, +25% -5%, +10%
Rough order of magnitude Parametric Approximate estimating Analogy Definitive Engineering buildup
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
BUDGET
Definition
An agreed and approved sum of money allocated for expenditure on a specific work scope
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
BUDGET
Budgets are the means by which project costs can be compared with financial resources, and they enable decisions to be taken concerning the provision and deployment of Company funds
(Shell Project Management Guidelines)
BUDGET
A budget requires a forecast of resources needed for the project, quantities, when needed, how much they will cost ..
The influence of history is strong in the budget of ongoing activity.
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
BUDGET
Many entries may become last years figure plus X percent
Guidance can be used from similar projects Project budgets are based on forecasts of resource usage and associated costs. This involves risk.
DR ASSEM AL-HAJJ, Univation, RGU Project Management and Economics. SITP-SPDC, NIGERIA
BUDGET TYPES
TOP-DOWN
Collecting judgements & experiences of top and middle managers, and available past data concerning similar activities Managers estimate overall project cost as well as costs of major subprojects.
Budget is broken down into successively finer detail, starting from Advantage 2 top Advantage 1 following small yet budgets the WBS costly tasks can be developed need not be quite individuall accurately y identified DR ASSEM AL-HAJJ, Univation, RGU
BOTTOM-UP
Follows the WBS People doing the work are consulted regarding times and budgets Estimates are made in terms of resources e.g. labour hours and materials Task budgets are aggregated to give the total direct costs Usually a more accurate method
Topdown is commo n