Sei sulla pagina 1di 3

1/10/2013

CLIENT : MAIN CONTRACTOR: CONSULTANT: MEP CONTRACTOR :

SH/KHALID BIN ABD AL RAHMAN AL-THANI ORIENTALS ENTERPRISES JAMES CUBITT & PARTNERS ENGINEERING CONSULTANCY ELECTROMECHANICAL ENGINEERING COMPANY

PROJECT TITLE: CONSTRUCTION OF KH RESIDENTIAL TOWER LOCATION: Onaiza -New Doha

PROGRESS MATRIX TABLE - MEP WORKS


1 2 3 4 5 6 6 7 8 Cable pulling for riser Cable trays (Main power cable riser) 9 10 11 Plumbing & Drain pump room works 12 Fire Fighting pump room works 13 14 Chilled water Connection @Qatar Cool 15 16 KAHRAMAA Power supply ( TF & HV Switch gear ) 17 18 19 20 21 HVAC Testing , Adjusting , Balancing & Commissioning Mhrs 90

TOWER AREA WORKS


Cable tray & trunking (Power & Low Current) Fire Fighting Tower area/ Plaza / Roof Chilled water Tower area/ Plaza / Roof Drainage riser Tower area/ Plaza / Roof Water supply Tower area/ Plaza / Roof Duct Apartment / Podium area / Roof Cable tray (GSM)

RISER WORKS
Cable pulling for riser Cable trays (Low Current) Bus bar (Vertical + Horizontal)

PUMP ROOM + SUB STATION WORKS


Electrical Substation room works Chilled water pump room works

PLOT UTILITY CONNECTIONS


Portable Water + Drain connection Structured Cabling system (Active Component/IDF MDF ) ENVAC ( Vacuum solid waste connection )

TESTING & COMM. WORKS


Fire fighting Sys testing & comm. 30 Plumbing testing & comm. works 15

Floor Levels

Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs

Plaza Level-1 Plaza Level-2 Plaza Level-3 Plaza Level-4 Tower Basement Floor Ground Floor Level - 1 Level - 2 Level - 3 Level - 4 Level - 5 Level - 6 Level - 7 Level - 8 Level - 9 Level - 10 Level - 11 Level - 12 Level - 13 Level - 14 Level - 15 Level - 16 Level - 17 Level - 18 Level - 19 Level - 20 Level - 21 Level - 22 Level - 23 Level - 24 Level - 25 Level - 26 Level - 27 Level - 28 ROOF -1

Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing

Days

Days Mhrs Days Mhrs Days

Mhrs

Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs ays ays Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs D D Mhrs

12 3

6 6

15 7 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6

25

24

7 7

3 3

8 1 No Design drawing 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 2 2 2 2 2 2 2 2 2 2 2

10

40

15

30

50

45

18

30

20

10

2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 4

15

1 8

3 3

4 7

15

Page 1 of 3

1/10/2013

CLIENT : MAIN CONTRACTOR: CONSULTANT: MEP CONTRACTOR :

SH/KHALID BIN ABD AL RAHMAN AL-THANI ORIENTALS ENTERPRISES JAMES CUBITT & PARTNERS ENGINEERING CONSULTANCY ELECTROMECHANICAL ENGINEERING COMPANY

PROJECT TITLE: CONSTRUCTION OF KH RESIDENTIAL TOWER LOCATION: Onaiza -New Doha

PROGRESS MATRIX TABLE - MEP 1st Fix WORKS


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Elec- wall Box's & conduits

Floor Conduits

Water supply pipes

Chilled water pipes

Power cables

Building wire

Plaza Level-1 Plaza Level-2 Plaza Level-3 Plaza Level-4 Tower Basement Floor Ground Floor Level - 1 Level - 2 Level - 3 Level - 4 Level - 5 Level - 6 Level - 7 Level - 8 Level - 9 Level - 10 Level - 11 Level - 12 Level - 13 Level - 14 Level - 15 Level - 16 Level - 17 Level - 18 Level - 19 Level - 20 Level - 21 Level - 22 Level - 23 Level - 24 Level - 25 Level - 26 Level - 27 Level - 28 ROOF -1

Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing 18 10 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 12 12 12 12 12 12 12 12 12 30 8 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 8 8 8 8 8 8 8 8 8 8

Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing 7 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 8 5 5 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 6

Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing 15 5 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 10 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 12 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 9 18 18 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 9 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 90 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 5 18 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 6 20 20 20 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 40 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 20 6 6 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4

Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing 30 5 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 20 10 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 8

Days Mhrs Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing 15 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 10 6 6 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 15 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 6 4 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2

Ceiling rose+flexible Cable


Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs No Design drawing

Fire Fighting pipes

No Design drawing

No Design drawing

No Design drawing

Low current Cable

Drain pipes

DFCU Units

Duct risers

Duct work

No Design drawing

Page 2 of 3

1/10/2013
CLIENT : MAIN CONTRACTOR: CONSULTANT: MEP CONTRACTOR : SH/KHALID BIN ABD AL RAHMAN AL-THANI ORIENTALS ENTERPRISES JAMES CUBITT & PARTNERS ENGINEERING CONSULTANCY ELECTROMECHANICAL ENGINEERING COMPANY

PROJECT TITLE: CONSTRUCTION OF KH RESIDENTIAL TOWER LOCATION: Onaiza -New Doha

PROGRESS MATRIX TABLE - MEP 2nd. Fix WORKS


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 26

Wiring devices

lighting fixture

Ele. Room D.B's Install. & termination

Water meters installation

Water supply P.R.V

Water supply risers

Water supply pumps

Chilled water valves

Chilled water riser

Chilled water pumps

Exhaust Fans

Air Handling units

Low current cables risers

BMS system

Low current system


25 15 4 4

Air terminal devices

F.H. cabinet

BTU meters installation

Bus bar installation

ZCV ( Zone Control Valves)

MCC &M.V panel

Elevator 's

Fire Alarm devices

Plaza Level-1 Plaza Level-2 Plaza Level-3 Plaza Level-4 Tower Basement Floor Ground Floor Level - 1 Level - 2 Level - 3 Level - 4 Level - 5 Level - 6 Level - 7 Level - 8 Level - 9 Level - 10 Level - 11 Level - 12 Level - 13 Level - 14 Level - 15 Level - 16 Level - 17 Level - 18 Level - 19 Level - 20 Level - 21 Level - 22 Level - 23 Level - 24 Level - 25 Level - 26 Level - 27 Level - 28 ROOF -1

Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing 3 3 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 7 7 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 6 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 7 3 3 3 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 3 4 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 7 4 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 7 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 2 2

Days Mhrs No Design drawing No Design drawing No Design drawing No Design drawing 15 10 5 4

Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs Days Mhrs No Design No Design No Design No Design drawing drawing drawing drawing No Design No Design No Design No Design drawing drawing drawing drawing No Design No Design No Design No Design drawing drawing drawing drawing No Design No Design No Design No Design drawing drawing drawing drawing 6 6 4 3 12 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 3 2 9 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 6 6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2 25 4 6 4 10 1 1 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 12 6 20 6 18 15 4 4 9 3 6 3 6 3 10 6

No Design drawing 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2

No Design drawing 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

No Design drawing 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

No Design drawing 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

No Design drawing 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 7 3 3 3 12 3 3

No Design drawing 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Page 3 of 3

Stand by Generator

Cable tray (GSM)

Sprinklers

F.Fighting Pumps

Core duct risers

Sanitary fixture

Potrebbero piacerti anche