CHAPTER ONE 1.0 INTRODUCTION The Quantity surveying discipline is very practical in nature and mainly hinged on experience.

Hence there is a great need for any student aspiring to be a professional quantity surveyor to have some form of work experience while studying at school, in a reputable firm as related to his/her course of study. The Students Industrial Work Experience Scheme (SIWES) was designed and jointly put in place by the Federal Government, Industrial Training Fund (ITF), tertiary institutions, and other agencies like National Universities Commission (NUC), National Polytechnics Commission, and National Board for Technical Education and National Council for Colleges of Education. It is a program established in the year 1973 under the umbrella of Industrial Training Fund with the main aim of preparing and helping students of tertiary institution to obtain exposure on practical fields with respect to their profession. Through this exposure, students are expected to have better understanding of their profession and develop practical skill in addition to their acquired theoretical skills which they got from there institution. Students are exposed to some of the challenges in the industries and are supervised during their period of attachment to various organizations. It is a compulsory practical training that students must undertake as part of the requirement for the award of Bachelor in Technology, at the Federal University of Technology, Akure (FUTA). Since no study is complete without the practical experiences, the integration of a practical knowledge with the theoretical bases is necessary. Consequently, I had my work experience at the Philtola Engineering Limited. The Industrial training lasted from the 4th June November 15th 2012. My day to day activities were recorded in the log book.

1.1.1

PARTIES INVOLVED WITH THE SIWES PROGRAMME The following parties are involved in the successful completion of the students

work experience scheme; Tertiary Institution The institutions are expected to prepare their students for industrial attachment by organizing orientation programmes immediately before the commencement of the 1

training; pay regular visit to students during attachment with the view to producing effective supervision and guidance. Employers The employers are expected to work out relevant industrial attachment program with institutions ensuring that the attachment programme exposes students to real life working situation; inspects and signs students log book on weekly basis and make comments where necessary. Students The students on industrial attachment are expected to keep standard log book and clearly record all activities or work done on daily basis and other assignment before submitting for ITF approval. National Universities Commission The National University Commission [NUC] is expected to evolve minimum practical training programmes for supervision of industrial attachments. OBJECTIVES AND IMPORTANCE OF STUDENTS INDUSTRIAL WORK EXPERIENCE SCHEME (SIWES) i. To build and offer practical training opportunities to students in identified areas. ii. To make students to be aware and familiar with the industrial set up thereby making them to know their roles in industrial and national development process. iii. To encourage the involvement of employers especially the small scale industries in the organization and development of training programs and facilities including the establishment of group training scheme centre in some critical areas of the economy. iv. To make students learn how to manage the work environment effectively and to increase their interactive skills with colleagues, subordinates, superiors and clients. v. To make students aware of work related problems and learn how to cope positively in difficult situations.

1.1.2

1.1.3

SIWES GUIDELINES The guiding principles of the SIWES programme as issued by the Federal

government of Nigeria through the Industrial Training Fund (ITF) lists the qualities of a selected workstation such as: i. ii. iii. iv. v. Provision of a satisfactory good working environment Provision for experience in line with the students course of study Provision for job supervision by the employer Provision for opportunity to gain experience in various ways Use modern facilities, equipment, and literature appropriate for the various works. The above mentioned conditions were duly fulfilled as the organization.

1.2

THE QUANTITY SURVEYOR

A Quantity Surveyor (Q.S) is a Development and Construction Cost Adviser in Building, Civil and Engineering projects. The Quantity Surveyor is the Financial Expert in all matters relating to Buildings, Civil and other Engineering projects. The Quantity Surveyor is often referred to as a Cost Accountant of the Construction Industry.

1.2.1

DUTIES OF QUANTITY SURVEYOR The duties of a Quantity Surveyor are many but broadly, they include the

following: i. ii. Carrying out feasibility studies of capital project Cost modeling which means preparation of cost estimates, budgets, cost planning, monitoring and control cost, as well as cost research. iii. Contract documentation which include preparation of bills of Quantities and other tender documents, giving advice on tendering/bidding procedures, contractual arrangement and tender evaluation and analysis. iv. Contract administration which means management of construction work and cost during the execution of the project. v. Project Management which means the co-ordination of the efforts of all the consultants and contractors from the inception of the project to completion 3

in order to achieve desired result within pre-determined time and cost frame work. vi. Arbitration in case of disputes between the project owners i.e. the client and the contractors.

1.3

AIMS AND OBJECTIVE This report is aimed at summarizing the practical and additional theoretical

skills acquired during the period of the industrial attachment. It is also based on the relevance of the programme to field, the organizations chart and profile, site skills gained not excluding my own contribution to the progress of the organization.

1.3.1

AIM OF REPORT i. To put down in writing the record of the training experience gotten from Philtola Engineering Limited i.e. personal performance reflection. ii. To demonstrate my development of practical and professional skills in Quantity Surveying through technique experience and application of theoretical knowledge. Its also to training me in effective writing as a preparation for my final year project. This report covers every aspect of the practical skill I have built during my

iii.

industrial training at Philtola Engineering Limited. The company is situated in AdoEkiti, Ekiti State. The theoretical skill earned at school served as a foundation. Some of the skills built upon are; Measurement of civil engineering works Physical measurement on site for structural bridge works. Valuation of sub-contractors works Preparation of material (bending) schedule for reinforcement and; materials and labour schedules. Cost estimates of various elements of the bridge such as Precast Beams, Precast parapets and Precast Slabs. Supervision works and site meeting.

All these are written about in this report. 4

CHAPTER TWO 2.0 COMPANYS PROFILE Philtola Engineering Ltd. is an indigenous engineering firm situated at 68, Iworoko Road, Adebayo, Ado-Ekiti, Ekiti State. It was established by Engineer P.A Ajibade, a civil engineer by profession in the year 2008 and since then they have been engaged in consultancy services and civil construction works in majorly large scale projects. The Managing Director, Engr. P.A. Ajibade is a retired civil servant in the Ekiti State Civil Service with vast experience and knowledge in civil engineering works. The company engages mostly in Civil Engineering Works (both small and large scale projects) ranging from road construction, drainages, building works, bridges etc. The size of the workforce is about 30workers; 10 professionals.

Departments within the Organizational Includes; 1. Administration Unit: This unit co-ordinates the finances and operations of the company 2. Civil Construction Unit: This unit co-ordinates the various project been undertaken by the firm. A Project Manager heads the unit and is assisted by engineers, quantity surveyors and land surveyors. 3. Consultancy Unit: This unit takes charge of any project in which the company is to act as the project consultant; this unit is also assisted by the professionals in the civil construction unit. 4. General Services: This includes the receptionist, cleaners, drivers and security personnel.

Some of the services rendered by the company include; Consultancy services. Civil construction works Road rehabilitation Project management among others.

2.1

OBJECTIVES OF THE COMPANY Philtola Engineering ltd. specializes in delivering ambitious yet achievable

construction project that delight both clients and the community who uses them.

The major objectives of the company are listed below; To be the company of first-choice for all stakeholders. To continue to improve the image of construction worldwide To carry out the execution of every project without any flaws.

2.3

COMPANY ORGANIZATIONAL CHART During the six-month Industrial Training I was attached to the Project Quantity

Surveyor.

MANAGING DIRECTOR General Services Civil Construction Project Manager

Consultancy

Administration
Finance Operation

Receptionist Cleaners Drivers

Project Engineer

Project QS

Engineers Security Trainees

CHAPTER THREE 3.0 INDUSTRIAL WORK EXPERIENCE

3.1

BRIDGE CONSTRUCTION The construction of a Proposed Bridge (3x10.1m span @ 11+700), along Ado-

Ijan Road, Ado-Ekiti, Ekiti State... The proposed bridge is located at chainage 11+700 (km 11.7) along Ado-Ijan Road across a river called Ogbese River. The proposed bridge is to be located besides the existing bridge at 14metres centres from the existing bridge. The proposed bridge is designated to be 30metres (2x15.0m) but was later revised as a 30.3metres (3x10.1m) bridge to correspond spatially to the existing bridge. Also, one of the design specifications of the bridge is that it should be a 2x15m span bridge but during one of the site meeting, we took a tour to the bridge location to inspect the excavation for the bridge foundation. There, we observed that the proposed bridge is two (2) spans of 15m centres and since the existing bridge (3x10.1m span) will not be demolished, the difference in span arrangement of the two bridges will result in staggered piers across the river. This, we observed will not only be aesthetically unfit but will also prevent smooth flow of water along the river channel. The bridge designer (consulting engineers) was directed to review the bridge design to suit the existing arrangement and the revised bridge design (3x10.1m span) was made available within a week.

3.1.1

SIGNIFICANCE OF THE BRIDGE CONSTRUCTION The main purpose of the bridge construction work is to ease the traffic along

Ado-Ikare Road, as the existing bridge is one lane, that is, can only accommodate a vehicle at a time. Others purposes includes; 1. Minimize the rate of vehicular accidents along the route; the proposed bridge is two lanes which make it to accommodate several vehicles at the same time from both directions. 7

2. Allow ease of passage for pedestrians through the construction of walkway on the bridge in which the existing bridge does not accommodate in its design. 3. Construction of parapets walls (as against railings in the existing bridge) which offers more safety for both pedestrian and vehicular traffic. 4. Accommodation of drain pipes in the proposed bridge design as against what is obtainable in the existing bridge design.

3.2 3.2.1

BRIDGE WORKS PRECAST CONCRETE BEAM (BEAM 1) The proposed bridge is 3-span Bridge with each span length of 10.1m.

Therefore, each beam length is 10.1m but to allow for expansion joint, it was changed to 10.07m. The bridge beam are of two types Beam 1(precast) and Beam 2 (in-situ cross beam/diaphragm). Beam 1 is to span the length of the bridge and transmits the load from deck slab to the piers and abutment footing through to the bridge foundation. It also carries and supports the precast concrete slabs after it has been installed in position. During the construction work on site, the length of the beam was changed from the designed 10.1m to 10.07m to allow for the thorma expansion joint (25mm thickness) after installation.

Figure 1: Schematic diagram of the proposed bridge showing the expansion joints The full span of the proposed bridge; 10.1 x 3span = 30.3m Less the expansion joint (0.025m x 4) = - 0.10m 30.20m 8

For each beam, we have; 30.2m/3span = 10.07m (approx.) The width of the beam 1 is 400mm with height of 700mm. A total of 8 beams are needed for each span of the bridge width. The total number of beam 1 produced was; 8beams x 3span = 24 precast beam (Beam1). Beam size= 10.07m by 400mm by 700mm height.

CONCRETE MIX The concrete mix for the precast concrete beam differs in ratio from the one used to produce both precast slabs and precast parapets but both are of the same grade (concrete grade 30). This is because at the time of the production of the precast beams, a concrete mix design (Please see Table 7) has been produced which recommend a mix ratio of 1:1.8:2.5 for cement, sand and granite respectively. The sand consist of an equal mixture of both sharp sand and quarry (stone) dust due to the quality problem of the sharp sand supplied to site. 8bags per cubic metre of concrete was also recommended, but on site will make use of 9bags/m3 with water-cement of 0.47, that is, 185litre of water. CONCRETE BEAM PLATFORM Two concrete beam platforms were made; upon which the precast beams were casted. A beam platform of size 35m by 5m by 100mm thickness was first casted on a leveled surface (ground); fifteen (15) beams were casted on it. Also, a second beam platform of size- 33m by 4m by 70mm thickness was then casted, also on a leveled ground; it accommodates the other nine (9) beams. The space to be occupied by the beam platform was clear of vegetative elements. I worked with the surveying team using surveying instrument such as theodolite and pegs; where we got a level for a particular point and transfers the level to other points at 2metres intervals. (Please see Appendix 7) The pegs are nailed to the ground at regular interval of 2m and the theodolite is the used to travel level from a known height to the other pegs. Wooden planks were used as formwork to the sides of the platforms; laterite filling and compaction was done before the platforms were casted. 9

The height of each pegs represent the limit of the concrete to be poured at each interval length. The surface of the concrete is then rammed to give a uniform leveled surface for the beam platforms.

Also, a concrete beam camber-shape base for each precast beam was casted; size- 10.07m by 0.4m width and the height varies (1cm at the ends and 2.5cm at the centre of the camber base. This means that the height of the beam is slightly not uniform, as it casted on a camber (that is, slope at both ends; a slope of 2.5%). The beam bases are casted on the beam platforms at interval of 0.7metres.

The concrete beam camber-shape base is where each precast beam was casted. I was fully involved in the survey and casting of concrete for both the beam platforms and base.

Plywood boards are then placed and nailed using tornado nails (3inches nails) on top of the beam camber-shape base. The plywood boards come in sizes of 1.22m by 2.44m. The plywood boards were sawed into three pieces each of sizes 0.4m by 2.44m. Each beam base makes use of 4 and of such sawed plywood boards with chamfer placed at the formwork edges.

A total of 9 chamfers were used for each beam base. The plywood boards serves as formwork for the beam soffit to give use a fair-faced finish and the chamfer ensures chamfered edges for the beam.

The concrete beam platforms are made of unreinforced mass concrete of grade 20 concrete. (Ratio 1:2.5:5 of cement-sand-granite) and adequate water was used.

CONCRETE WORK The size of the beam 1 is 10.07m by 0.4m by 0.7m height; that is, 2.83 cubic metre of concrete were used for each beam. The concrete for the precast beam were mixed using an 8 cubic metre capacity transit mixer and an excavator is then used to pour the concrete into the beam formwork. (Please see Appendix 1) The concrete were poured into the excavator bucket, which then pour it inside the beam metal formwork. The concrete mix is then well vibrated using vibrator with

10

poker inside the beam formwork, so as to compact and fill the void between the reinforcement. I was actively involved in the casting of the precast concrete beams and the production of concrete cubes (6) for each beam casted. One beam per day is the production capacity. The soffit and the sides of the precast beams gives a fair-faced faced surface; only the top surface is rough cast according to its design in the working drawings. REINFORCEMENT The main reinforcement bars for the precast beam are 25mm, 20mm and 16mm diameter bars with 10mm reinforcement bars as the stirrups. Concrete spacers/kickers of 50mm are used to ensure an adequate concrete cover. The concrete kickers are placed on the plywood boards beneath the beam reinforcement and also tied at regular interval by its sides. 20mm diameter re-bars were placed and spaced across the beam at each end of the beam; as it serves as connectors/continuous bars for the diaphragm which is to be casted in-situ. (See Table 10 for the beam bending schedule) Also, attached to the beam reinforcement are 2-T20mm bars which serve as the lifting loop for the beam. This lifting loop are placed 2400mm from the ends of the beam. In Summary, Rebar type 12mm 16mm 20mm 25mm Number of lengths 634 192 120 384 Tonnes used 6.80 3.60 3.53 17.5

Table 1: Showing summary of reinforcement bars used for precast beams

11

FORMWORK The formwork used for the precast concrete beam is a metal formwork of size 1.22m x 2.45m which is adequately braced at 300mm c/c, aligned and well plumbed. A metal brace is also welded to the metal formwork at the 0.7m height which represents the height of the precast beam. The metal formworks are then bolted to each other using 19mm bolts and nuts. (Please see Appendix 1) Tie rods and U-Channels were then used to align, straighten and position the formwork; with top braces were also used to brace the metal formwork to ensure that the beam width is maintained throughout its length. A total of 8 of such metal formwork were used for each beam and the formwork is lightly oiled to ensure easy strike off of the beam formwork after the concrete have set. CURING Regular supply of water from a 15,000 litre water tank is used to cure the precast concrete after onion bags (24bags per beam) were placed on the beam to prevent quick evaporation of the water used to cure the beam. (Please see Appendix 1)

3.2.2

PRECAST CONCRETE PARAPETS The precast concrete parapets are of two types based on the working drawings-

Type 1 and Type 2. Type 1- Precast Concrete Parapets This is to be located within the proposed bridge span. They are of sizes 2.0m length and 1.85m width. The type 1 parapets produced are 30 in numbers. Type 2- Precast Concrete Parapets This is to be situated at the two approach slabs of the proposed bridge. They are of sizes 2.75m length and 1.45m width. The type 2 precast parapets are 8 in numbers based on the design specification.

12

However, the length of the type 2 precast parapets was reviewed from the initial design length of 2.75m to 1.83m to ensure ease launching. Also, due to the alteration, the number of type 2 parapets produced is now 12 in numbers. Both type 1 and type 2 precast parapets are of 150mm thickness.

CONCRETE MIX FOR THE PRECAST PARAPETS The concrete mix for both types of precast parapets is Grade 30 concrete, that is, the mix of cement-sand-granite in the ratio of 1:1.5:3 respectively with adequate water added. The volume of water used per m3 of the concrete mix (grade 30) is 150 litres. 5bags of cement were used for each type 1 parapets while type 2 parapets used up 4bags of cement each. (Please see Appendix 2) A transit mixer of 1 cubic metre capacity was used to mix the concrete mixture and also used to pour the concrete into the parapets formwork. The concrete is then vibrated using concrete vibrator with poker attached; the top surface of the parapets were surface dressed to give a fair faced finish. Concrete cubes were also produced from the concrete mixture, by pouring the concrete into six (6) cubes of sizes 150mm x 150mm x150mm. After the concrete cubes have set, they are immersed in water and are then taken out for crushing in a laboratory at Federal Polytechnic, Ado-Ekiti at 7days and 28days; three (3) concrete cubes each are crushed at both period. The minimum concrete strength at 7days and 28days which is 20N/mm 2 and 30N/mm2 was achieved and even surpassed at times. The results of such tests are the collected from the lab and a copy of such given to the supervising consultant. I was fully involved in the production of all the precast concrete parapets. FORMWORK The formworks for the precast parapets are marine boards which are well braced with 50mm x 100mm timber. The formwork is lightly oiled before casting to ensure easy strike off of such formwork from the sides and soffits of the parapets.

13

The formwork was also well plumbed and braced. The formwork is then placed on a concrete platform. Also, Chamfers were used and nailed to all the corners of the formwork, this helps to cancel out any deflection that may occurred at the edges. (Please see Appendix 2) Chamfers=> Nominal length= 2.44m; Cost= 650 each Marine boards=> 1.22m x 2.44m; Cost= 10,000 each

REINFORCEMENT The main reinforcement bars for both the type 1 and type 2 precast parapets is 16mm diameter bars with 12mm diameter bars used as the distribution bars. Concrete spacers (30mm) which have been produced prior to the production of the parapets are placed beneath the re-bars. (Please see Table 9 for the Parapets bending schedule) Continuous reinforcement bars, 16mm diameter bars were connected to the parapets, which were to serves as a connector to the reinforcement to be used for the pedestrian walkway and through which drain pipe will pass. Also, two 10mm diameter bars were attached to the re-bars of the parapets at the top side, which will serve as an anchor to launch the parapets. The concrete cover is 50mm.

In Summary, Rebar type T10 T12 T16 Number of lengths 5 170 250 Tonnes used 1.82 4.72

Table 2: Showing summary of reinforcement bars (in tonnes) used for precast Parapets (30 type 1 and 12 type 2 precast parapets) During the training program, I participated fully and supervised the placement of the reinforcement into the parapets formwork, casting for the precast parapets, production of the concrete cubes and surface dressing of the parapets surface to ensure

14

a good finish. I also observed how the formwork was strike off the precast concrete parapets. ASSEMBLING After, the parapets has set, two chains are attached to the parapet anchors which is hooked to any available lifting equipment (excavator and pay-loader were mostly used on site), which lift the precast parapets to an allocated portion/space within the site. Such precast parapets are adequately cured.

3.2.3

PRECAST CONCRETE SLABS (False Work/ Concrete Planks) The precast slabs or otherwise called concrete planks when launched onto the

bridge, is to serve as formwork for the in-situ deck slab and carries the load from it in a two way direction. The concrete are precast by design. The precast slabs are of two types based on the design specification and working drawings; Type A and Type B. Both types have a thickness of 50mm and concrete grade 30 was used. Precast Slab: Type A= 1000mm x 1100mm Type B= 1037.5mm x 1100mm By design precast slab type A is 147 numbers and type B is 42 numbers. However, the design lengths of both precast slab type was altered with due consultation with the supervising consultant; this was done to save time and reduce cost during the production, assembling and launching of the precast element. In essence, we redesign the concrete slabs to be 2300mm length while the width of 1100mm was maintained. Therefore, the precast slabs are now of the same type and size. Redesign size of the precast slabs= 2300mm x 1100mm x 50mm thickness The total number of precast slabs produced was eight-four, 84.

CONCRETE MIX The concrete mix for the precast slabs is grade 30; that is, the mix of cementsand-granite in the ratio of 1:1.5:3 respectively with adequate water added. The 15

concrete cover of the precast slab is 30mm. 1 bag of cement each was used for the 84 precast slabs produced. A 1m3 capacity concrete transit mixer was used to mix the concrete and poured into the slab formwork. I participated fully and supervised the concrete casting of the precast slabs and the placement of its reinforcement. The concrete was well vibrated and the surfaces of the precast slabs were roughcast surface as specified in the working drawings of the element. (Please see Appendix 3) The concrete was vibrated to prevent honey comb and have a fair-faced finish at the under-side of the precast slab. I also participated in the preparation of the concrete cubes. A total of eleven (11) concrete planks were produced daily with 24hour interval between successive castings. CONCRETE CUBES In preparing the concrete cubes, a short length (50cm) of 25mm bar was used to compact the concrete in the cubes. Each layer (three layers in all) is given 35 blows with a tapping rod of 25mm diameter bar. The cubes are left to dry for about five (5) minutes and a code and date of its production is written on each concrete cubes. (Please see Appendix 4) The concrete cubes were then taken to the lab for crushing at 7days and 28days and the strength must be close to 20N/mm2 and 30N/mm2 respectively.

REINFORCEMENT T10mm diameter reinforcement bars were used as both the main and distribution bars. The main reinforcement bars runs across the slab (shortest span) with shear connectors (T10mm bars) connected to the main bars at 150mm c/c. A total of 9shear connectors were used for each precast slab. The shear connectors were used in assembling the slabs and also the reinforcement to be used for the deck slab will run through the shear connectors. (Please see Table 8 for the precast slabs bending schedule) I supervised the placement of the reinforcement into the slabs formwork and the placement of the concrete spacers (biscuit). 16

In Summary, Rebar type 10mm Number of lengths 309 Tonnes used 2.30

Table 3: Showing summary of reinforcement bars (in tonnes) used for precast slabs (84 precast slabs) FORMWORK The precast slab soffit is to have a fair-faced finish while the top surface was to be rough-cast. Marine boards, size 2.44m by 1.22m were used as the soffit formwork, with 25mm x50mm planks used as the side formwork. The formworks were well aligned and plumbed. (Please see Appendix 3) The slab reinforcement is gently placed inside the slab formwork on top a 30mm thick concrete spacer (concrete biscuits).The formwork were lightly oiled and scrapped to ensure its suitability for subsequent use or casting.

ASSEMBLING The precast concrete cubes were removed 24hours after casting with the side formwork strike off. Two T10mm rods are passed through the shear connectors along the length of the precast slab, with which two chains are attached; with the other end of the chain hooked to a lifting equipment (Bob Cat was mostly used) which gently placed it in an allocated space/portion within the site and adequately cured. (Please see Appendix 3) (Please see Table 12- appendix for the cost analysis of the Bridge Beams, Slabs and Parapets)

3.2.4

BRIDGE FOUNDATION BLINDING AND BASE NAILING (FOR PIERS AND

FOOTING

ABUTMENTS) Due to the fact that the proposed bride spans across a river (Ogbese River), along Ado-Ijan road, Km 11.7; the blinding for the bridge footing was done in two phases- the footing blinding for the first pier and abutment was first carried out.

17

We were able to achieve this, by making an earth embankment to divert the river away from the excavated area where the casting of the blinding of both the pier and abutment was to take place. The excavation for the footing was about 2.5metres depth to reach an underlying rock layer (bed rock). The design specification for the blinding is has follows; Blinding for both Piers= 9m by 5m width by 300mm depth Blinding for both Abutment= 12m by 5m width by 300mm depth Also, due to the fact that the proposed bridge is on a rock base; Base nailing that is, a bored hole of 700mm depth filled with concrete and a 25mm reinforcement bar (1.5m). The purpose of the Base nailing is to ensure a homogenous bond of the bridge footing to the rock base and also to ensure the pier and abutment footings are well anchored. The bored hole is filled with grade 30 concrete and 1.5m length of 25mm rebar is also inserted in the bored hole. Piers: The piers have 15 numbers of such base-nailing at two [2] metres centres and at a depth of 700mm bored holes. (Please see Appendix 6) Abutments: The abutments have 18 numbers of such base-nailing at two [2] metres centres and at a depth of 700mm bored holes. (Please see Appendix 6) CONCRETE MIX FOR THE FOOTING BLINDING The concrete mix used for the blinding was Grade 20 concrete (that is, the mix of cement-sand-granite in the ratio of 1:3:6 respectively). 6bags per cubic metre of the footing blinding was used, with adequate water added. The concrete mix from the transit mixer was used to mix the concrete while we made use of excavator to convey the concrete to the excavated portion. Concrete cubes for the footing was also made.

18

FORMWORK Wooden formwork was used as side formwork to protect the areas that were to be blinded, from mud and earth materials. Before, we casted the blinding, the area was well cleaned, to ensure it is clear of any silt, mud water which may affect the concrete. The blinding was done to ensure the reinforcement for the footing for both the piers and abutments does not have contact with rock base and soil which could result to the re-bars getting rusted; and also to ensure the water from the concrete to be casted for the footings for both piers and abutments does not slip into the ground.

3.2.5

BOX-CULVERT [3.0m x 3.0m] The Box-Culvert is before the proposed bridge along Ado-Ijan road @Km 11+

660. The existing bridge has its own existing box-culvert of size 3m by 3m by 4m length. The proposed box-culvert is besides the existing box-culvert and is of size 3m by 3m by 12m length. It also has wing walls at the two openings or ends (4.5m length). EXCAVATION AND LEVELING The survey team marked out the area of the culvert to be excavated and the excavation for the culvert using an excavator to a depth of 900mm. The total surface of the excavated portion of the box culvert was filled with laterite and well compacted before blinding of the culvert base took place. (Please see Appendix 5) CULVERT BASE BLINDING Concrete blinding of 100mm thickness was achieved using grade 20 concrete (1:2:5 cement-sand-granite) with adequate water added. The concrete for the blinding of the culvert base was mixed and poured into the compacted base using 0.25m3 capacity widget concrete mixer. The concrete was evenly spread and tapped gently. (Please see Appendix 5) 19

Reinforcement: The reinforcement for the box culvert was then placed on the blinded base with concrete spacers (50mm) placed beneath the reinforcements. The reinforcements consist of top and bottom reinforcements separated using a 12mm shaped separator. BOX CULVERT BASE (Concrete works) The concrete mix for the box culvert base is grade 30 concrete with adequate water added. The thickness of the culvert base concreted floor is 250mm. The size 12 m lengths x 3m width The concrete was mixed using an 8m3 capacity concrete transit mixer and poured through a wooden funnel. The floor of box-culvert base was well tapped to give a fair faced finish. Also, concrete cubes (six) for the base casting were also produced and thereafter immersed in water. (Please see Appendix 5)

3.3

CONSTRUCTION MATERIALS AND EQUIPMENT As more and more advancement in technology is being witnessed globally, so

also is the development of existing building materials and invention of new ones. That is the main reason why I had intimated myself with as many construction materials as possible, in order to know the following Grades of products and their specification numbers Market prices and their long time economic advantage Uses of these materials, durability and their advantages over close substitutes With tangible knowledge in these areas, I was equipped with quality expertise advice which can be put into use when discharging professional obligations to clients and also a well-equipped and also a well-equipped insight of the nature of the business when dealing with dishonest and deceitful suppliers.

20

Construction Equipments Table 4: Showing various construction equipments available S/N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 EQUIPMENT/VECHICLE Grader Pay-Loader Bull Dozer Cat Low Bed Mack Tipper Mercedes Tipper Man Diesel Water Tanker Asphalt Cutting Machine Water Pump Generating Set Survey Instrument/ Instrument Pick-up Van Excavator Concrete Vibrator Hand Roller Tar Boiler Concrete Mixers (widget) Transit concrete mixer Bob Cat Cat 920 2 inches Bamatic Man Diesel 0.25m3 8m3 leveling 3 and 4inch nose MANUFACTURE/MODE QTY Cat-12G 966C D6 45 tonnes 30 tonnes 20 tonnes 15,000 litres 2 1 1 1 1 3 2 1 2 2 2sets 4 1 2 1 1 2 1 1

21

Construction Materials: These are the materials which were used up in the construction process. These materials and their cost are listed below.

Table 5: Showing various construction materials, their respective quantity and cost MATERIAL Sharp Sand Granite Cement Marine Boards Stone Dust Chamfer Onion Bags Tie Rods QUANTITY 10 tonne 30 tonne 50kg bag Each per tonne Each Each Each Reinforcement bars 10mm rebar 12mm rebar 16mm rebar 20mm rebar 25mm rebar 135 lengths/tonne 93 lengths/tonne 53 lengths/tonne 34 lengths/tonne 22 lengths/tonne 155,000 155,000 155,000 158,000 158,000 COST () 23,000 138,000 1,800 10,000 4,500 650 500 4,200

CHAMFER- size==> 2.44m; 45lengths/bundle (Please see Appendix 7) Chamfer helps to cancels any deflection that may occur at the edges of the beams and parapets apart from the aesthetic it adds to the elements MARINE BOARDS- size==> 2.44m x 1.22m x 0.025m (Please see Appendix 7)

22

Table 6: Showing various plants and their respective daily fuel consumption S/N PLANT DAILY FUEL CONSUMPTION 1 2 3 4 5 6 7 Diesel @ N170 per litre Petrol @ N97 per litre Excavator Pay loader Concrete Mixer (8 cubic metre) Concrete Mixer (1 cubic metre) Concrete Vibrator Bob Cat Pumping Machine 150 litres of diesel 120 litres of diesel 50 litres of diesel 25 litres of diesel 4 litres of Petrol 50 litres of diesel 6 litres of Petrol

3.4

CHALLENGES ON PROJECT SITE Challenges on site are inevitable but the way such challenges are managed or

solved will ensure the work progresses with minimal delays and in the long run, ensure the success of the project. Such challenges encountered on the bridge site during my training period include; 1. Supply of low quality materials by the sub-contractors and suppliers; For instance, materials such as Sharp sand; when supply is below the quality desired, such materials are rejected, with a caution and advice to the suppliers to ensure the supply of the desired quality and quantity needed. 2. Infiltration of water through the earth embankments: The earth embankment was used to divert the water along the river course away from the excavated foundation of both the piers and abutment. Due to the rising water levels of the river due to heavy rainfall, the earth embankment start collapsing; this effect was 23

reduced by the introduction of sand-filled jumbo bags, which are carefully placed to support the earth embankment. 3. Varying strength of concrete due to the quality of the sand: This was compensated for, by mixing the sharp sand and quarry (stone) dust in the same quantity together as a mono-mixture. This increases the sharpness of the sand mixture and gives a better result after such concrete cubes are crushed in the laboratory. (Please see Appendix 6) 4. Machine breakdown: The breakdown of machinery before or during operation on site tends to always delay the work. This was minimized by the employment of mechanics as companys staff and also the regular maintenance of such machinery. 5. Delay in supply of materials by suppliers: The delay in the delivery of some needed materials such as reinforcement bars tends to delay work progress leading to inevitable revision of program of work. 6. Flooding: Flooding of the site during heavy rainfall, makes some part of the site inaccessible and makes works in such parts to stop still the water subsidies. (Please see Appendix 6) 7. Theft: The issue of theft on site was a serious challenge in the initial stage of the project; for instance, theft of about 1.5tonnes of 12mm reinforcement bars. 8. Intimidation: Intimidation of domestic staffs by the foreign staff in the form of threat of being sack, pay-cut and non-payment of salaries, allowances as at when due. 9. Infiltration of water due to poor fixing of window seals: The solution was to replace the frame and do some builders work in adjusting the opening to make it flush properly with the installed window frame. 10. Delay in procurement of construction materials

24

3.5

ON

SITE

CONCRETE

MIX

CALCULATION

(FOR

1M3

OF

CONCRETE) During my Industrial Training, I was able to determine by calculation the volume of the various materials such as sharp sand, cement and granite needed to get a required grade of concrete using the concrete mix design produced from the laboratory of the Federal Polytechnic, Ado-Ekiti. We mainly make use of grade 30 concrete for major structural component of the bridge like the precast beams, precast parapets, and precast slabs among others. A concrete mix design was done in the laboratory using a gauge box of size 0.6m x 0.6m x 0.7m giving the gauge box a volume of 0.252m3. For instance, in the concrete mix design for grade 30 concrete, this table was extracted. Table 7: Showing the concrete mix design for concrete grade 30 Materials Cement Coarse aggregate 20mm 10mm Sand Water 697kg 327kg 722kg 185kg 2.5 1.82 23 2 1 Ratio by Weight 398kg 1 Ratio by volume 1

Site Gauge box- The size of our site gauge box is 0.33m x 0.33m x 0.33m with a volume of 0.035937m3. The number of site gauge box in one laboratory gauge box is calculated to be 7 boxes. = Volume of laboratory gauge box Volume of Site gauge box

25

In the concrete mix design done in the lab, the ratio by volume gotten for 1m 3 of Grade 30 Concrete is; 1box of cement to 1.8 box of sand to 2 boxes of granite (coarse aggregate) For site measurement; As 7boxes of site gauge box= 1box of laboratory gauge box I have; 7box of cement to 12.6 box of sand to 17 boxes of granite (coarse

aggregate.) for 1m3 of concrete For 3m3 of Concrete We have the following Sand= 12.6boxes x 3m3 = 37.8 gauge boxes Granite= 17.5boxes x 3m3 =52.5 gauge boxes

We make use of an Excavator bucket to convey the materials to a funnel into the transit mixer. The excavator bucket was measured to be 22gauge boxes (site gauge box). Sand= 37.8 gauge boxes = 1.72 buckets of sand (excavator bucket) 22 Granite= 52.5 gauge boxes = 2.39 buckets of sand (excavator bucket) 22 By using, this measurement values and results; we were able to minimize site

wastages and ensure that the minimum strength of concrete was gotten.

26

3.6

MATERIAL SCHEDULE FOR REINFORCEMENT BARS This is a table showing the needed information about the reinforcement bars to

be used at different parts or components of a structure, be it bridges or building structures. The provision, preparation and use of the bending schedule help me in the following aspects; 1. Helps to ease the taking off and determination of bar shapes of reinforcement bars from the working drawings. 2. Helps in ordering for the right quantity of reinforcement to be used for each section of work. 3. Aids visualization and determination of the cutting length of each bar shape, the number of each bar shape required and the off-cut per length of reinforcement cut. Based on site measurement, a length of reinforcement bar = 12m In most cases, the bending schedule of a component comes with the working drawing (except for the box culvert), I made conscious effort to ensure that the bar type, bar shape and the quantities of each bar type provided in the bending schedule of such component is accurate and corresponds to those in the working drawings. These are some of the material (bending) schedules for reinforcement I prepared for the various components of the bridge; Precast Slabs Precast Parapets and Precast Beams

27

A. MATERIAL SCHEDULE FOR REINFORCEMENT FOR PRECAST SLABS NUMBER OF SLABS = 84 Table 8: Material (bending) schedule for reinforcement for precast slabs
BAR MARK
NO THUS

DIA (mm)

BAR SHAPE & DIMENSION

CUTTING LENGTH
(nos per Length)

TOTAL QTY

NOS OF LENGTH

T1016 T1017

16 8

10mm
1040mm

1040mm
(11nos)

1344 672

123 135

Offcut from additional length used is 9818mm Offcuts per length used=800mm From additional length is 7200mm

10mm
2240mm

2240mm
(5nos)

T1015

12

10mm

75mm
200mm

675mm
(17nos)

1008

50 (plus
158 nos from T1016 & T1017 offcuts)

**Calculations
of the 158 nos below.

100mm

Number of Length= Total Quantity Number per length

SUMMARY
10mm = 309 lengths = 2.30 tonnes

Total Quantity= No thus x Number of Slab (84) Nominal Length of Reinforcement Bars= 12000mm **Calculations (for the shear connectors= T1015) 1. Offcut from T1016 9818 = 14nos 675 2. a. Offcut from T1017 800 =1 nos * 134 = 134 nos 675 b. Offcut from T1017 7200 = 10 nos 675 Total number of T1015 from offcuts = (14 + 134 + 10 nos) 3. Subtract answer from total quantity needed; 1008 158 = 850 nos 4. Number of T1015 per length = 12000 = 17nos 675 5. Since we need 864 nos more, we have; 850 = 50 lengths of 10mm bags 17

28

B. MATERIAL SCHEDULE FOR REINFORCEMENT FOR PRECAST PARAPET TYPE 1- 30numbers TYPE 2- 12numbers Table 9: Material (bending) schedule for reinforcement for precast parapets
BAR MARK
NO THUS

DIA (mm)

BAR SHAPE & DIMENSION

CUTTING LENGTH
(nos per length)

TOTAL QTY

NOS OF LENGTH

TYPE 1 T1210

2x1 3 13

12mm
1940mm
1420
90

1940mm (6nos) 3965mm

780

130

T1609

16mm
1790mm

390

130

100

90

315

100

240mm

T1611

13

16mm

440mm

(3nos) 1560mm (7nos) 700mm (17nos)

390

58

T1005

10mm

75mm 200 100mm

60

Offcuts from additional length is 6352mm

TYPE 2 T1213

2x1 3 12

12mm
1770mm
1390mm
90
100

1770mm (6nos) 3210mm

240

40

T1612

16mm

144

48

Offcuts per length used is 2370mm

140mm

T1614

12

16mm

100

240mm

440mm

(3nos) 1560mm

144

14 (plus
48nos from T1612 offcuts) 1 (plus 9nos from T1005 offcuts)

(7nos) 700 24

T1007

10mm

100mm
200

100mm

(17nos)

SUMMARY
10mm = 5 lengths 12mm = 170 lengths = 1.82 tonnes 16mm = 250 lengths = 4.72tonnes 29

C. MATERIAL SCHEDULE FOR REINFORCEMENT FOR PRECAST BEAM BEAM 1- 24numbers Table 10: Material (bending) schedule for reinforcement for precast beams
BAR MARK
NO THUS

DIA (mm)

BAR SHAPE & DIMENSION

CUTTING LENGTH
(nos per length)

TOTAL QTY

NOS OF LENGTH

10015mm

250

T2501

25mm

10515mm (1no) 10015mm

96

96

T2501 A T2002

12

25mm
10015mm 250

288

288

(1no) 10515mm 96 96

Offcuts per length used is 1485mm [1485 x 96] Offcuts per length used = 1985mm [1985 x 288]

20mm

10015mm

T1603

16mm
10015mm

(1no) 10015mm (1nos) 350mm (34nos) 3000mm

192

192

T2507

21

25mm
350mm

504

Lengths is taken and cut from offcuts of T2501A

T2004

20mm

250 1025 100

96

24

T1205

66

12mm

250mm 150mm

(4nos) 2230mm

1584

317

890mm

75

T1206

66

12mm
340mm 640mm
75

(5nos) 2110mm

1584

317

(5nos)

SUMMARY
12mm = 634 lengths = 6.80 tonnes 16mm = 192 lengths = 3.60 tonnes 20mm = 120 lengths = 3.53 tonnes 25mm = 384 lengths = 17.50 tonnes

30

3.7

SUPERVISION WORKS AND SITE RECORDS Supervision works and records taking is an essential aspect or activity in any

construction project site. It involves among many other things, ensuring that the specified standard of workmanship, materials and methods of construction are employed in order to achieve a desired output. In site supervision, I learnt that a one should be a good observer and have good background of construction works and practices; so that every work details were adhered to. Also, one must be able to translate working drawings on paper into a reality scheme on site. A site supervisor should have a good working relationship with the project manager and his dealings with the labourers on site. During the training program, I was opportune to supervise some construction works been carried out on site; this includes; 1. Placement of reinforcement bars for bridge culvert wall, base, wing walls and headwall. 2. Placement of reinforcement bars for precast concrete slabs/false work. 3. Placement of reinforcement bars for precast concrete beams. 4. Blinding of culvert base, abutment and pier blinding (300mm thickness). 5. Preparation and placement of marine plywood formwork to soffit and sides for the casting of precast slabs and precast parapets. 6. Placement of reinforcement bars for precast parapets.

7. Placement, coupling and aligning of metal formworks for the casting of precast concrete beams. 8. Preparation of concrete cubes. 9. Excavation works for piers and abutments footing 10. Preparation and alignment of formwork for beams, culvert, slabs, parapet etc. 11. Concrete casting and vibration of concrete used for the various bridge components. Another aspect that I gained some experience is the inspection of materials supplied to site by the suppliers or sub-contractors. To receive these materials to site, the following must be checked 1) Specification of the materials supplied. 31

2) Quantities of the materials supplied. 3) The sizes of the materials supplied. 4) The name of the producer and standard of materials supplied. 5) The date and time in which the materials was received. 6) The overall conditions of the materials. 7) The name of the supplier of the materials.

Also, during the training programme, I was solely charged with the responsibility of taking notes and records of activities within the site premises. Records taken include among other things; materials brought to site, those materials taken off site to other project sites, checking of suppliers weigh bills to ensure the contents corresponds with the material the suppliers brought to site. These activity generally helped me in intimating me with new materials that I do not know before my industrial training and those that I only have their theoretical knowledge, as well as giving me an overall knowledge of their various uses.

The materials which I received to site during my industrial training include; Sharp sand, cement and granite for concrete works. Reinforcement bars of various sizes (10mm, 12mm among others diameter bars). Plywood, marine ply boards and various sizes of wood for wooden formwork. 2 vibrators with pokers. Pumping machine (4 inch); among others. Drilling bits (19mm-2Qty). Plywood (sizes 1.22 X 2.44) Onion bags (for curing- 100pcs) Tornado concrete nails- 4inch and 3inch Emulsion paints (to mark reinforcement bars). Diesel, petrol, engine oil and kerosene for machinery Chamfer (4bundles, 45no/bundle) 10 metal plates (1.22m x 2.45m), angle bars, U-channels, and Tie rods (102 nos) used for metal formwork; among others.

32

3.8

SITE MEETING In the course of my training, I was privileged to be part of the site meetings,

where we have all the professionals involved in the project present, in order to have a look at how well the project is progressing. I noticed that Site meeting is one of the means used for effective coordination of projects because it is a platform whereby all the consultants do meet to discuss the performance of the contractors and the progress of the project. These site meetings were held monthly, first week of every month. The design consultants (bridge section), supervising consultants, Federal Roads Maintenance Agency (FERMA) representatives, the contractor, Site Engineer and the Quantity Surveyor and the client, Road Sector Development Team (RSDT), Abuja on behalf of World Bank are all seated to discuss, evaluate, inspect, ask questions, advice, recommend and plan on the progress of the project. During the site meetings, work progress is appraised, approvals are sought and given, advices are given, challenges faced are discussed, claims and payment are reexamined and laboratory tests carried out on materials during the month are presented by the contractor. The site meetings are held on a monthly basis at the contractor site office, before the meeting commences, inspections are carried out on various works ongoing or completed on site; video recordings and progress photographs are also presented by the contractor during the meeting proper. Progress Reports are also presented by the contractor which has to be verified by all the consultants of the project.

The agenda of the meetings is as follows: i. ii. iii. Opening Prayer/Introduction Amendment/Acceptance of the previous meeting minutes Main contractors Progress Report: The contractor do give the detail of the progress achieved since the previous meeting, account of various resources on site such as; number of trade and operatives, number and types of plant and quantities of materials on and off site. iv. Comment on Progress of work: During this time, general comment is pass on the progress by comparing it with the work programmed.

33

v.

Matters arising from the minutes: Any unresolved matters in the previous meeting are normally addressed.

vi. vii.

Anticipated progress in a month time Consultants Report/General Comment: Any outstanding matters among the consultants still awaiting further clarification or investigation are discussed; for instance, in one of the meetings, the bridge design was reviewed from 2x 15m span bridge to 3x10.1m span bridge. More so, if any of the consultants has any information to pass across apart from the normal instruction to the contractors or issues to be addressed.

viii. ix.

Adjournment Closing Prayer

3.9

PHYSICAL MEASUREMENT AND SURVEY WORKS Physical measurement is the measurement taken on site in respect of structural

components to determine the amount of work done so far on site for the purpose of valuation; ascertaining the exact number of materials used on site, also to check on the progress of work on site; the rate at which work is being carried out and what section of work is ongoing. It has to do with measuring work as built in order to make claim for interim payment and checking if there is any variation. I was opportune to carry out physical measurement of different parts and components of the bridge under construction. This enables us to get data for measurement to prepare interim valuation which are submitted and used to prepare payment to the sub-contractor. During the period of my training I carried out physical measurement of various bridge works which include a) Precast concrete beams b) Precast concrete parapets c) Precast concrete slabs d) Reinforcement works in preparation for casting for the various bridge works. e) Formwork (metal and wooden formwork) for the various members. f) Depth, width and length of the various excavation works

34

The measurement of each structural component of the 30.3metres Bridge is usually taking periodically as more and more works are being executed on site. The construction works being the largest part of the project is being handled by the main contractor and of which the payment arrangement between the client and the contractor is that valuation will be done monthly, which consequently necessitate continuous physical measurement as works progresses on site. And in order to avoid unnecessary delay in interim valuations, the senior quantity surveyor and I used to work together whenever we are taking physical measurement Also, I gained some experiences when we were measuring some other elements of the bridge like reinforcement works, excavation works, and various formworks in which at least a representative of the sub-contractors handling the element we are measuring will be present with us during the measurement. For the measurement of masonry work, we made use of tape rule; block works was measured taking the length and height; Excavation work taking the length, width and depth; Scarification of carriageway and shoulders taking its width and length etc.

3.9.1

SURVEY WORKS Also, during my training program I participated in some survey works which

include; 1. Taking levels/leveling of precast concrete beam platform. 2. Measurement of road length (approach road) using distance measuring wheel. 3. Rechecking of levels taken for the blinding of both piers and abutment and the underlying rock base. 4. Realignment of road at offset from existing road centerline. 5. Rechecking levels taken for precast beam platform. 6. Measurement of road chainages at 25m intervals. 7. Setting out and measurement of deflection angle. 8. Plotting of new road alignment to existing road. 9. Leveling of culvert base using surveying instrument.

35

3.10

APPROXIMATE ESTIMATING

Preparation of Materials Schedules The basis of material schedule is a material control scheme which itemizes all the materials necessary to complete a project. Ordering of materials or components required for the construction of a project for timely procurement, to meet the construction program becomes very easy for the contractor and the client; building directly with the available materials and labour schedules, ensures and aids adequate management of such resources. Grade 30 concrete was mostly used on site. For instance, the materials needed for 1m3 of reinforced in-situ concrete. (1:1.5:3 -20mm aggregate) are as follows.

A) Cement (50kg bag) Density of cement= 1442kgm-3 Therefore, 1m3 of cement=> 1442kgm-3/50kg = 28.84bags (approx. 29bags) Mixing ratio=>1:1.5:3 -20mm aggregate Concrete 1+1.5+3= 5.5 (1/5.5) x 29bags = 5.27 Add 50% for shrinkage and wastage =+2.64 7.91 Therefore for 1m3 of (1:1.5:3 -20mm aggregate) concrete, 7.91bags of cement (approx. 8bags) will be needed. This principle is still the same for 60m3 of concrete (for piers footing) which is 8bags x 60m3 which will give 480 bags of 50kg bag cement.

B) Sand There is a little difference, I observed in calculating this material due to the assumption that tonnage per haulage varies per trip. In the calculation for sand; Density of sand is 1650kgm-3 or 1.65Tm-3 (based on laboratory test) Volume of one bag of cement is 50kg/1442kgm3 = 0.035m3 With this result, 0.035m3, we can easily convert number of bas of cement to volume of cement and volume of sand subsequently by multiplying it with this factor

36

in the mixing ratio; which is later divided by the assumed mean volume of the said tonnage. Assumed mean volume for 20tonnage/trip =5.6m3 For 1m3 of (1:1.5:3 -20mm aggregate)concrete; [(8bags x 0.035m3 x 1.5) /5.6m3] = 0.08 load/trip of 20tonnes of sand C) Coarse Aggregate Unlike sand, coarse aggregate are normally supply in tonnage and therefore, our final schedule for coarse aggregate is in tonnes and not in trips, loads or haulage. Density of coarse aggregate, that is, granite is 1652kgm-3 or 1.652Tm-3 (as tested in the laboratory). We also got the aggregate volume from cement needed by multiplying it with its factor in the mixing ratio and its density, so in this case, [8bags x 0.035m3 x 3 x1.652Tm-3] = 1.39 tons

D) Reinforcement bars The schedule for reinforcement is always in tonnage since the suppliers normally supply it in tonnes; however, it is necessary for the clerk of work to convert it to numbers of length for proper recording. The length of the reinforcement bars are taken off from the working drawings and converted to metres. 1000mm=1metres. The total length of reinforcement of reinforcement bars for each bar type (that is, 10, 12, 16, 20, 25mm diameter bars) is calculated and converted to kilograms and then their equivalent in tonnes using the formula; = [0.222 x D2] * Total length 36 Where D= diameter of reinforcement bar. The result gotten is in kilogram (kg) which is then converted to tonnes by applying this => 1000kg= 1tonne For easy and quick calculation of tonnage of each bar type; the weight per metre (kg/m) of each bar type is calculated first; this is then multiplied by the total length (in metres) to get the total weight (in kg/tonnes). Using the formula => = [0.222 x D2] 36 37

Table 11: Showing the bar types, their respective weight per metre in (kg/m3) and the number of length per tonne. BAR TYPE WEIGHT PER METRE (kg/m3) 10mm 12mm 16mm 20mm 25mm 32mm 0.616 0.888 1.579 2.466 3.854 6.313 NUMBER OF LENGTH PER TONNE 135 93 53 34 22 Not supplied

E)

Formwork The schedule of materials needed for formwork (wooden planks or metal

formwork) of different sizes can be easily calculated by going through the sizes of such component in the working drawings. Marine boards and ordinary plywood comes in sizes of 1.22 x 2.44m and metal plates (formwork) come in sizes 1.22m x 2.45m. This formwork are adequately braced, plumbed and aligned in order for it to be able to withstand and support the weight and force of wet concrete. The metal formwork, for instance are braced at 300mm intervals. Therefore, for a 2.45m length metal plate, we have; (2.45/0.30m) + 1= 8.16+1 = 9.16 (approx 9 braces). U-Channels and tie rods are also supplied along the metal plates; these are used to hold the metal formwork in position and aligned them adequately. Also, the formworks are oiled before subsequent casting to ensure easy striking of the formwork after the concrete has set.

38

3.11

WORK PROGRESS REPORT In every construction project work, there is the need to constantly give the

client the progress report of the ongoing project in order for the client to measure the possibility of the contract or project meeting up with the stipulated time and also to compare the work progression to the program of work. This is a document that shows the extent of work done on site, the current stage of the work compared to overall program of works or the percentage of the work done in a project. The progress of works also reveals the pace at which the project is progressing. These progress reports are usually prepared by the contractor and submitted to the clients and consultants to provide them with all the needed information that will enable them to have a clear picture of what is currently happening on site. The subcontractors also prepares their own progress reports of their various aspects of work in the project and submit them to the contractor, the reports of these sub-contractors is also aimed at presenting a perfect knowledge on the current stage of their work and the pace at which the work is progressing on site. During the program, I was able to compile some site reports, by taking photograph of the work progress, drawing charts to represent the work progress. Sometimes, factors such as unforeseen events causes delays to the work progress; such includes, rainfall, public holidays, site flooding, delays caused by suppliers etc. This report is presented at the monthly site meetings for the client and consultants assessment, complains or request as the case may be. 3.11.1 PROGRESS PHOTOGRAPH The progress report is usually coupled with photographs of the various part of the bridge works under consideration. The photographs are arranged in a way that it will show the different phases of the bridge works, which will in turn enable anyone looking at the photographs to access the trend of the progress of the project. During the early period of my industrial training, it was part of my assigned duty to take the progress photograph of the various bridgeworks on site, which I did with enthusiasm and this gave me an unforgettable experience in packaging the project photographs in a way that it will easily be assessed by the client. 39

CHAPTER FOUR 4.0 4.1 CONCLUSIONS AND RECOMMENDATIONS CONCLUSIONS It is evident in every sense that the Industrial Training has been in every way a necessity for the acquisition of knowledge as well as building a bridge between the theory been taught in class and the practical world of reality. The Industrial Training was a successful programme as it has helped me to become more oriented in the practical aspect of my discipline and in general, the construction industry; introducing to a new sphere of knowledge on; Bridge construction, Production of precast concrete structures Experience on project site management and supervision work Interpreting engineering drawings People and Facility management Site records and cost estimating. Preparation of materials schedules among others.

This training therefore has helped me in appreciating my discipline and has prepared me on how to handle the challenges that may occur in the cause of practice in my discipline in the nearest future. In conclusion to rounding up this report, I will say that the lecturers in my department has not only taught me for the purpose of certificate, but have really imparted a high level of unquantifiable and qualitative knowledge into me which has processed me into a peculiar scholar in the field of cost engineering, also I acquired a lot of knowledge from the experiences gained both in regards to my discipline and with life generally within the working environment as a whole. The SIWES program has proved to be a vital aspect of my academic program as it gives me an extensive insight of the professional world of quantity surveying. As such, am grateful to my school (F.U.T.A) and the Industrial Training fund for this great opportunity.

40

4.1

RECOMMEDATIONS The Industrial training doesnt only gives the require knowledge to forge

ahead, but also teaches the students on how to interact with people. This is necessary in team work to enhance cohesiveness, synergy as well as objective achievement of the task given. The Students Industrial Work Experience Scheme (S.I.W.E.S.), though being a worthwhile experience for me, still has a few areas to give attention to in order to run a better and a more successful programme, so that future generations can have a more exciting and fulfilled training during their time. To this, I would recommend the following in my own humble view that: Industrial Training Fund and Government: The Government through the Industrial Training Fund should ensure that students on industrial training are supervised regularly which could be through a monthly, weekly visit to their place of work. This would awaken the consciousness that students are not on the training to play around but to acquire experience. The Department of Quantity Surveying The department of Quantity Surveying could make it essential for students from part two to part four to go for a three month Industrial Training at the end of each section to afford them to consistently put into practice their theoretical knowledge which will beyond any shadow of doubt produces a well-equipped set of professionals in the country and in the world at large. It would be okay if the department could acquire IT placements for students as this serves as a major heartache to many students as many students do not start on time limiting the time they have to learn relevant skills. The Students Students on the Industrial Training should be aware that the immense contributions of the various stakeholders in SIWES are geared towards ensuring that they (the students) acquire adequate relevant production skills before graduation. It will therefore be so unfortunate for one to see his/her participation in SIWES as an end itself (by considering irrelevant factors like comfort of placement and allowance paid) since it is actually only a means to a much greater end. 41

APPENDIX

42