Sei sulla pagina 1di 87

Add your company slogan

DISTRIBUTION SYSTEM PLANNING: PRINCIPLES , CRITERIA & METHODS, ISSUES & WAY FORWARD

By: Halim Osman General Manager Asset Management TNB Distribution


1 ILSAS

PRESENTATION OUTLINE Distribution Business & ESI Regulatory Framework- Standards, Codes, Acts & License Performance Standards Design Principles/ Considerations/Criteria Issues & Challenges in Distribution Planning Evolution of Planning Methodologies Summary & Conclusions

ILSAS 2

www.themegallery.com

Add your company slogan

DISTRIBUTION BUSINESS & ELECTRICITY SUPPLY INDUSTRY

3 ILSAS

TYPICAL INDUSTRY STRUCTURE & PARTIES


External Parties External Parties

THE GRID SYSTEM

Directly Connected Customers

Directly Connected Customers

DG

DG Consumers

Generators

Transmission

G G

Main Interconnected Transmission System (500kV and 275kV)

Transmission System at 132kV and 66kV

Distribution System at 33kV and below Consumers

G Generation System Network Operators

Embedded Distribution

Transmission System
Network Operators

Distribution DG System

TOTAL POWER SYSTEM

Grid Code

Distribution Code www.themegallery.com

DISTRIBUTION NETWORK BUSINESS


Grid System Grid System Operator (GSO)

MV Consumers With DG DG

Distributor Distributor

Distributed Generator

MV Consumers Consumers DG MV Consumers

Embedded Distributor

DG

LV Consumers
5 www.themegallery.com

ESI ON DISTRIBUTION BUSIENSS


MORE PLAYERS THUS REQUIRING CONSISTENT, TRANSPARENT, GUIDED ACTIONS BY MANY PARTIES TO ENSURE SYSTEM PERFORMANCE SAFETY, ADEQUACY, RELIABILITY & ECONOMICS OF SYSTEMS. NEEDS FOR CODES, STANDARDS & COMPLIANCE DSITRIBUTION BUSINESS REGULATED MONOPOLY
RELIABILITY PERFORMANCE MONITORING & REPORTING INDUSTRY TRENDS IN PERFORMANCE STANDARDS
RELIABILITY LIMITS /SEGMENTED TO RURAL & URBAN REPETITIVE FAULTS/CUSTOMERS AFFECTED IMPOSITION OF GUARANTEED STANDARD OF PERFORMANCE(GSOP)

ILSAS 6

www.themegallery.com

Add your company slogan

REGULATORY FRAMEWORK - CODES, ACTS, STANDARDS

7 ILSAS

Relationship between Systems, Standards, and Codes


TOTAL POWER SYSTEMS Generation

G
Generation Reliability Standards Transmission System Reliability Standards Transmission Reliability Standards
Sufficient generation capacity and connections to deliver full generation output for normal and Specific contingencies

Main Interconnected Transmission System


Transmission

Transmission radial network and demand points

Criteria for planning, designing and operating of transmission system to meet reliability and power quality standards

Transmission Power Quality Standards


DG

Sufficient transformer capacity to meet demand Power quality limits at interfaces

Distribution System
DG

Distribution

Embedded Distribution

SYSTEMS

Customers

8 STANDARDS

Distribution Supply Security and Power Quality Standards

Criteria for planning, designing and operating of distribution system to meet supply security and power quality standards

CODES www.themegallery.com

DISTRIBUTION CODE

GRID CODE

Sufficient transmission capacity to meet demand for specified contingencies Meeting standards performance limits

EXAMPLE OF ACT (AKTA) (AKTA)

Cover Page
ILSAS 9

First Page
www.themegallery.com

EXAMPLE OF RULES (PERATURAN) (PERATURAN)

Contoh daripada Akta Bekalan Elektrik 1990

ILSAS10

www.themegallery.com

EXAMPLE OF INDUSTRY CODE

Cover Page of Distribution Code


ILSAS11

Contents Page of Distribution Code


www.themegallery.com

PERFORMANCE STANDARDS ~ SUPPLY SECURITY


1. Normal MV Breakdown: a.) For single circuit outage (except busbar) 50% restoration within 2 hours (syarat 15) restoration time 4 hours b.) For rural areas or MD < 1MW restoration time 24 hours 2. Normal LV Breakdown: restoration time 24 hours 3. Extra-ordinary Breakdown (Force De Majoure): restoration time may be > 24 hours
Reference : Distribution Planning Code 5.4.2.3
ILSAS12
www.themegallery.com

PERFORMANCE STANDARD- VOLTAGE LIMITS STANDARD-

Voltage Regulation (Normal Condition): MV of 6.6/11/22/33kV : 5% of nominal voltage LV of 240V & 415V : +5% & -10% of nominal voltage Voltage Regulation (Contingency Condition): MV : 10% of nominal voltage LV : 10% of nominal voltage

ILSAS13

www.themegallery.com

PERFORMANCE STANDARD- FREQUENCY LIMITS STANDARD-

Frequency Regulation (Normal Condition): System Frequency : 1% of nominal value of 50Hz Frequency Regulation (Exceptional Circumstances): System Frequency : within 47Hz & 52 Hz

ILSAS14

www.themegallery.com

PERFORMANCE STANDARD- SECURITY LEVELS

LEVEL 1

RESTORATION TIME Less than 5 seconds

DESCRIPTION Customer who specially request for the service Selected urban areas, industrial areas, hospitals & places of national importance All areas except for rural areas & any areas or circuit with group peak demand of < 1MW Rural area having total demand < 1MW

Less than 15 minutes

Less than 4 hours

Less than 1 day

15

PERFORMANCE INDEX SAIDI (1/2)


System Average Interruption Duration Index It provides information about total average time the customers are interrupted. Measures of reliability of supply Records the frequency and duration of outages that customers may experience. Only loss of supply exceeding 1 minute will be counted
16 www.themegallery.com

PERFORMANCE INDEX SAIDI (2/2)


Average Interruption time / customer / year

SAIDI =

Customer Interruptions Duration No of Customer Served


n

C d
Where: Ci di n N

i i

(= SAIFI x CAIDI)

i=1

= No of interrupted customers = Restoration time of each interruption event (in min) = No of interruption event = No of customers served
17 www.themegallery.com

PERFORMANCE INDEX - CAIDI


Customer Average Interruption Duration Index Average time required to restore service to the average customer per sustained interruption. (Average duration per interruption)

CAIDI =

Customer Interruption Durations No of Customer Interrupted


n

C d

i i

Where: = i=1 n Ci = No of interrupted customers Ci di = Restoration time of each interruption event (in min) i= n = No 1 interruption event of
18 www.themegallery.com

PERFORMANCE INDEX - SAIFI


System Average Interruption Frequency Index Average frequency (no.) of sustained interruptions per customer.

SAIFI =

No of Customer Interruptions No of Customer Served


n

C
i=1

= Where: N No of interrupted customers Ci = N = No of customers served n = No of interruption event


19 www.themegallery.com

SUBSTATION FIRM CAPACITY

System must be operated below firm capacity

Substation uses (PMU/PPU/SSU/PE)

Uses n-1 CONCEPT

20

www.themegallery.com

FEEDER FIRM CAPACITY & DESIGN CRITERIA (1/2)


Feeder uses 50% loading concept First leg cables from PMU/PPU must be at least of size 240 mm2 3C Al XLPE or any equivalent capacity. No more expansion of cable 70 mm2 Al or equivalent in the system. No bottle-necks in the system.

21

www.themegallery.com

FEEDER FIRM CAPACITY & DESIGN CRITERIA (2/2)


No spur feeder in the system except for rural domestic load that is less than 1 MW & it is economically far away from the source. Feedback should be from different source where possible. MV Overhead insulated cables can be used & strung on the same pole as LV cost-effectiveness. MV Overhead lines system (33kV in particular) should be equipped with auto-recloser & sectionaliser.
22 www.themegallery.com

Add your company slogan

PQ STANDARDS

23

TNBS LIMITS ON QUALITY OF SUPPLY (1/2)


1. Voltage Regulation (at Customers Terminal) LV : 415/240 V; -10% < VOLTAGE <+5% HV : 6.6/11/22/33 KV; -5% < VOLTAGE < +5% 2. Voltage Unbalance Definition: negative phase sequence voltage, positive phase sequence voltage Causes: Unbalance phase impedance and loads Acceptable Unbalance Voltage level is < 2%

24

www.themegallery.com

TNBS LIMITS ON QUALITY OF SUPPLY (2/2)


3. Loads Affecting Supply Quality Steel Making ARC furnaces, rolling mills, welding equipment, induction furnaces, power semiconductors rectifiers, computers, railway traction, etc. 4. Harmonics Caused by nonlinear loads such as rectifiers and other power semiconductors Acceptable limits based on the electrical regulation MS IEC 61000 Series

25

www.themegallery.com

CAUSES, EFFECTS & MITIGATION OF PQ EVENTS (1/2)


EVENTS CAUSES Electromagnetic disturbance (by components failure fault clearing, utility power system, trees, animals, lightning, 3rd party digging) EFFECTS MITIGATION System improvement (utility), power conditioner (customer), improvement of equipment immunity (manufacturer) Harmonic filter (shunt passive/active filter), ensure minimum harmonic emission on network design stage

Sags & Swells

Equipment trip / process interrupted

Harmonics

Electronic gear (3 rectifier, power regulator, customers capacitive component), welders, arc furnaces, fluorescent ballasts, pc

CB tripping, unexplained fuse operation, capacitor failure, electronic equipment malfunction, flicking lights & telephone interference

26 MFuad

www.themegallery.com

CAUSES, EFFECTS & MITIGATION OF PQ EVENTS (2/2)


EVENTS CAUSES Mainly by huge arcing generated by furnaces in steel mill (cause health problem such as epilepsy), electronic gears, motors EFFECTS Equipment trip / process interrupted MITIGATION Flicker compensator

Flickers

Voltage Fluctuation Frequency Deviations Transients

Ferranti effect, Cap bank, cable Generation voltage, load end, long line- voltage violation, sizing, transformer customer equipment length capacitance tap, booster affected Generation Vs load Generation Load (freq unstable) Maintain healthy spinning margin

Animals, lightning, vegetation

27 MFuad

www.themegallery.com

PQ PERFORMANCE INDEX - SARFI


System Average RMS Variation Frequency Index To show event frequency of supply interruption, voltage sag & swell 2 ways of index representation: SARFIX SARFICURVE

28 LimCY

www.themegallery.com

SARFIX
SARFIX event frequency of supply interruption, voltage sag & swell under a defined voltage level within short-duration RMS variation events (with duration < 60s) Example: a) SARFI90 = 5 5 events of voltage sag & supply interruption occur below 0.9 p.u. or 90% of nominal voltage. b) SARFI70 = 3 3 events of voltage sag & supply interruption occur below 0.7 p.u. or 70% of nominal voltage. c) SARFI110 = 2 means 2 events of voltage swell occur above 1.1 p.u. or 110% of nominal voltage.

29 LimCY

www.themegallery.com

Add your company slogan

LOADING CRITERIA

30

LOADING CRITERIA
Feeders Maximum of 50% loading of its rated capacity (for n-1 contingency). Transformer Initial / Optimum loading 60% (Refer LV Planning Guideline) Maximum loading of 90% for 24 hours Operation. Can load higher than 90% for cyclic loading (E.g: 100kVA ONAN Transformer can be loaded to 1420kVA for 2 hours.

31

www.themegallery.com

Add your company slogan

MV NETWORK CONFIGURATION

32

TYPICAL DISTRIBUTION SYSTEM


11kV PPU 33kV U/G & O/H

TRANSMISSION LINE 132kV

33kV

POWER STATION

12 kV

132kV U/G & O/H PE 415V/240V DISTRIBUTION


33

PMU

11kV

PE 415V/240V

www.themegallery.com

TYPICAL MV NETWORK CONFIGURATION


Types of Network Radial circuit Mesh Loop from same supply source Loop from different supply sources Petal configuration Twin loop 2-1-2 configuration for 33kV urban

34

www.themegallery.com

TYPICAL NETWORK STRUCTURE


PMU
BULK SUPPLY

X X

X
B/S

Network Description Parallel feeders supplying bulk customer, 11kV , 22kV or 33kv

Security Level Level 1 attainable with feeder unit protection

Normal State Bus-section 'ON'

X
ON

Figure 1 (a): Parallel feeders with n - 1 elements


PM U 1
PPU / C U STO M ER

PM U 2

X X X

X X X X

off

X X
B /S 2

X X X

B /S 1

F ig u re 1 (b ). P a rallel fe e d er w ith n - 2 ele m e nt N etw o rk D e scriptio n 3 fe e de r in to a P P U bu lk custo m e rs sw itch ing statio n 2 fe e de r a re pa ralle l N o rm al S ta te B re ake r 'A ' is in 'O F F' p osition B u s se ction 1 a nd B u s se ction 2 a re 'O N '
35

S e curity L evel L evel 1 e staina b le

www.themegallery.com

TYPICAL NETWORK STRUCTURE


PMU 1 PPU / CUSTOMER
PMU 2

OFF

X X X

X X X X X
A B

X X X

X X X

OFF

Figure 1 (c). Parallel feeders with n - 3 element

Network Description 4 feeder into a PPU or bulk customer switching station 2 feeder are parallel

Normal State Breaker A and B are 'OFF' Bus section 1 and 2 are 'ON'

Security Level level attainable

36

www.themegallery.com

TYPICAL NETWORK STRUCTURE


X
PMU 1

Network Description Simple - looped network from one PMU/PPU with n - 1 element

Security Level level 1 not attainable with SCADA/DA Level 3 without SCAD/DA

off

X
Figure 2(a). Looped, configuration from one PMU with n -1 element
PM U 1

o ff

X X

X X

PMU 2

F ig u r e 2 ( b ) . L o o p e d fr o m tw o P M U w ith n - 1 e le m e n t N e tw o r k D e s c r ip tio n L o o p c o n fig u r a tio n fro m tw o P M U / P P U w ith n - 1 e le m e n t N o r m a l S ta te Level 1 not a tta in a b le L e v e l 2 a tta in a b le w ith S C A D A /D A L e v e l 3 w ith o u t S C A D A /D A
37 www.themegallery.com

TYPICAL NETWORK STRUCTURE


PMU 1

off

X
off

PMU 2

X X
Network Configuration Loop configuration from two PMU / PPU with n - 2 element Normal State Level 2 attainable with SCADA Level 3 attainable without SCADA / DA

38

www.themegallery.com

TYPICAL NETWORK STRUCTURE


PMU 1

X X

X
F ig u r e 3 ( c ) .R a d ia l C o n fig u r a tio n , n - 0 e le m e n t
N e tw o r k C o n fig u r a tio n s p u r fe e d r fr o m P M U / PPU S e c u r ity L e v e l Level 4 L e v e l 1 ,2 & 3 n o t a tta in a b le

39

www.themegallery.com

APPLICATION GUIDE ~ SECURITY & CONTINGENCY CRITERIA (1/2)


SECURITY CONTINGENCY CRITERION n-1 feeder element Level 1 n- 1 transformer element n-1 bus-bar element n-1 feeder element n- 1 transformer element n-1 bus-bar element n-1 feeder element Level 2 n- 1 transformer element n-1 bus-bar element n-2 feeder element n-1 transformer element n-1 bus-bar element APPLICATION (YES/NO) Yes Yes No Yes Yes No Yes Yes Yes Yes Yes Yes Looped radial feeders with 33kV,22kV and 11kV sub-systems open points and fed by SCADA, Sub-station for towns and sub-urban areas and same PMU or PPU source and feeder low demand density industrial but from different secondary automation estates buses ( see fig.) 33kV, 22kV and 11kV for urban areas or similar areas (industrial estates) with high demand intensity and readily available reserve capacity - PMU /PPU sources Application to 33kV network in Penang & Klang Valley or similar supply areas with high demand density and readily available reserve capacity
40

APPLICATION POLICY / GUIDELINES

NETWORK MODELS

OPERATIONAL CONTROL No network control or automation SCADA/DA

Parallel feeders into a For supply schemes to bulk 11kV customer's bulk supply & 33kV customers switching station ( see fig. )

Looped radial feeders with open points and fed by different PMU or PPU source ( see fig.

SCADA, Sub-station and feeder automation

Network configuration with three (3) feeders into a PPU, SCADA, Sub-station PPU supplied from two and feeder different PMU sources ( see automation fig. )
www.themegallery.com

APPLICATION GUIDE ~ SECURITY & CONTINGENCY CRITERIA (2/2)


SECURITY CONTINGENCY CRITERION n-1 feeder element APPLICATION (YES/NO) Yes APPLICATION POLICY / GUIDELINES 33kV,22kV and 11kV for lesser important urban areas of low demand intensity NETWORK MODELS OPERATIONAL CONTROL n- 1 transformer element Yes n-1 bus-bar element n-1 feeder element Level 3 No Yes Looped radial feeders with open points fed by same No SCADA/DA PMU or PPU source but different bus-bars

n- 1 transformer element Yes n-1 bus-bar element n-2 feeder element Yes Yes

33kV, 22kV and 11kV network for Looped radial feeders with urban areas and industrial estates open points and fed by the with medium load density different PMU sources Application to 33kV sub-systems for supply areas with high demand density and readily available reserve capacity - PMUs & PPUs Highly selective and customized application to LV schemes e.g commercial areas Applicable to 33kV, 22kV & 11kV feeders supplying into remote rural areas with less than 1 MVA Generally LV networks are operated in radial and standby capacity through gen-sets
41

No SCADA/DA

n- 1 transformer element Yes n-1 bus-bar element n-1 feeder element n-1 feeder element Level 4 No Yes No

Network configuration with three(3) feeders supplying No SCADA/DA load points namely PPU with two PMU sources Looped LV network with open points No network control or automation

n- 1 transformer element Yes n-1 bus-bar element n-1 feeder element No No

Radial MV network from a single PMU source

No SCADA/DA

Radial low-voltage network

No network control or automation


www.themegallery.com

DESIRED 33 KV NETWORK ~ INFANT STAGE WITH 1 PMU Option


PPU for (n2) elemen t PPU

PPU

PMU
FEEDE R L1 L2 SOURCE (n-1) L2 L2

PARALLE L X

Network with (n-1) element ~ Not withstanding loss of PMU, security level 1 & 2 is attainable with SCADA in PPU place
42 www.themegallery.com

PPU

DESIRED 33 KV NETWORK 2ND STAGE WITH 2 Network PMUS source with (n-1)

PPU

PMU

PPU

PPU

PMU

PPU

PPU

Security level 1 & 2 is attainable with SCADA in place under (n-1) source contingency
43 www.themegallery.com

DESIRED 33 KV NETWORK - MATURED STAGE WITH MORE THAN 2 PMUS


PPU PPU

PMU

PPU

PPU

PMU
planned.

PPU

PPU

PMU

Network with more than 2 sources with (n-1) concept

Security level 1 & 2 is attainable with SCADA emplaced under (n-1) source contingency
44 www.themegallery.com

33 KV SYSTEM DESIGN OPTIONS TO ACHIEVE SECURITY LEVELS 2 & 1


PMU
PPU PPU

PMU

PARALLEL

FEEDER L1 L2 FEEDER L1 L2 FEEDER L1 L2 FEEDER N/A L2

SOURCE (n-1) L2 L2 SOURCE (n-1) L2 L2 SOURCE (n-1) L2 L2 SOURCE N/A L2


www.themegallery.com

Level 2 attainable with SCADA

X PARALLEL

PMU

PPU

PPU

PMU

X PARALLEL

Level 1 & 2 attainable with SCADA PMU PMU

PPU

PPU

X PARALLEL

Level 1 & 2 attainable with SCADA

PMU

PPU

PMU

X
45

Level 2 attainable with SCADA

MV NETWORK CONFIGURATION (3/4)


Selection election of network - Based on the reliability & security levels

Design criteria Safe, fast & easy operation No overloading of remaining circuit after single cable outage Feedback for any single outage contingency

46

www.themegallery.com

MV NETWORK CONFIGURATION (4/4)


Performance Criteria
Worst requirement (Base on Syarat 15) 50% restoration within 2 hours Full restoration within 4 hours Loading of feeders must be less than 50% to reduce distribution losses Reduce number of substations per feeder wherever possible Reduce number of customers per feeder

47

www.themegallery.com

MV FEEDER CAPACITY & DESIGN CRITERIA (1/2)


MV feeder uses 50% loading concept First leg cables from PMU/PPU must be at least of size 240mm2 Al XLPE 3C or any equivalent capacity No more expansion of cable 70mm2 Al or equivalent capacity in the system No bottle necks in the system No spur feeder in the system except for rural domestic load that is less than 1MW and it is economically far away from the source Feedback should be from different source where possible

48 LooCK

www.themegallery.com

MV FEEDER CAPACITY & DESIGN CRITERIA (2/2)

MV overhead insulated cables can be used and strung on the same pole as LV cost effectiveness MV overhead bare line system (33kV in particular) should be equipped with auto-recloser & sectionaliser

49 LooCK

www.themegallery.com

Add your company slogan

DISTRIBUTION PROTECTION

50

DISTRIBUTION PROTECTION (1/2)


OBJECTIVES
Ensure distribution network can operate within preset

requirements for the safety of the public, staff and overall network including equipment items. Isolate faults on the network in a minimum time in order to minimise damages

51

www.themegallery.com

DISTRIBUTION PROTECTION (2/2)


Radial U/G cable operated circuit (6.6, 11 & 22kV) Use over-current & earth-fault protection Radial O/H lines operated circuit (6.6, 11 & 22kV) Use over-current & earth-fault protection With auto-recloser Parallel circuits (Loop from same PMU/PPU) Use directional earth-fault & over-current Parallel interconnector Use pilot wire / fibre optic cable unit protection Use over-current / earth-fault as back-up

52

www.themegallery.com

Add your company slogan

SYSTEM FAULT LEVEL

53

IMPORTANCE OF FAULT LEVELS


Fault level in the distribution system must be identified To decide on fault rating of equipment. Magnitude of fault current depends on the infeed arrangement and the impedance of the network configuration. Fault level must not exceed short circuit rating of equipment (e.g. circuit breaker interrupting the fault current). Too low fault current (long & highly loaded feeder) may unable to operate the protective device Need to configure the system to reduce the system impedance.

54

www.themegallery.com

INTRODUCTION OF FAULT LEVEL


Analysis of power system electrical behavior under different fault conditions Effects of these conditions on the power system current & voltage. Equipment rating Under maximum fault, the system components must be rated such that the resultant heat can be dissipated & mechanical forces withstand.

55

www.themegallery.com

FAULT LEVEL IN TNBS DISTRIBUTION SYSTEM


Maximum fault level allowed in the distribution system Nominal System Voltage (kV) 33 22 11 6.6 0.415 Rated Voltage (kV) 36 24 12 7.2 1 / 0.415 Fault Current (kA) 25 20 20 20 31.5

Withstand the rated fault current for a duration of 3 seconds.

56

www.themegallery.com

Add your company slogan

DISTRIBUTION SYSTEM LOSSES

57

DISTRIBUTION SYSTEM LOSSES (1/2)


Technical & non-technical losses Technical losses reduce to optimum level Refer to A Guidebook on Reduction of Distribution Losses Non-technical losses reduce to minimum level MV Losses management MV Feeder loading must be less than 50%. Install shunt capacitor bank near the load. Optimising network (Off-point) Bring injection point to the load Load management

58

www.themegallery.com

DISTRIBUTION SYSTEM LOSSES (2/2)


LV losses management Reduce feeder loading Load transfer Use larger size conductor/cable Add new feeder Reduce feeder length Reduce volt-drop losses (long lines/feeder) Load balancing

59

www.themegallery.com

WHY VAr MANAGEMENT

Voltage regulation Optimize distribution capacity Reduce losses Can Cap Bank reduce harmonics ?

60

www.themegallery.com

VAr MANAGEMENT
Cap Bank sizing/locating - CAPO LV Load profiling (include Amp, Volt, VAr, Pf) Sub-station Pole top Customer end Other advantages of cap bank Points to note with cap bank operation safety maintenance

61

www.themegallery.com

SYSTEM STUDIES & TECHNICAL PROPOSAL

62 Rosemi

www.themegallery.com

DISTRIBUTION SYSTEM STUDY


Performance Diagnosis Capacity/demand Loading Losses Security Off points Reliability-SAIDI (Good to have) Fault level Protection Others- PQ (sensitive customer) Network regime-SCADA,EFI Operational planning

Network data + loading (Existing & New)

Modeling of Existing cct,Yr0

New Standard New network structure Security level Configuration Criteria Losses

Yr1
63 Rosemi

Yr2
www.themegallery.com

STEP 1: RECEIVE APPLICATION FROM CONSULTANT VIA PK/PC


Check for:
Year 1999 2000 2001 2002 2003 2004

Plan Load details TNB Specs compliant Date Supply required Expected Demand Yearly Estimated 24hrs load profile Site Visit
Yr Yr0 Yr1 Yr2 Yr3 Yr4 Yr5 MDMW 0.3 0.5 0.9 1.5 2.1 2.7
3 2.5 2 1.5 1 0.5 0 1999 2000 2001 2002 2003 2004
64 Rosemi

Projected Customer Demand Growth

MDMW

www.themegallery.com

STEP 2: CHECK FOR SUPPLY VOLTAGE LEVEL


LOAD < 800kW* 800kW to 5MW 5MW to 25MW VOLTAGE LEVEL LV MV 11kV MV 33kV

> 25MW

MV 132kV

65 Rosemi

www.themegallery.com

STEP 3: CHOOSE DESIGN FORMAT FOR (n-1) SYSTEM (nA B C

D
Plan A B C D E Security Criteria Element (n-1) (n-1) (n-1) (n-2) (n-2)
66 Rosemi

Loading Criteria <50% <50% <50% <50% <50%


www.themegallery.com

LOSSES IN CABLES
% Arus Amp % Loss I^2 Act Loss

Loss= I2R

IRON LOSSES IN CABLES


12

10

0 10 20 30 40 50 60 70 80 90 100

0 100 400 900 1600 2500 3600 4900 6400 8100 10000

0.0 0.1 0.4 0.9 1.6 2.5 3.6 4.9 6.4 8.1 10.0

Losses

0
% Arus Amp 0 10 20 30 40 50 60 70 80 90 100

% Current flow of 100%

67 Rosemi

www.themegallery.com

STEP 4: FIND SITE LOCATION & ELECTRICAL LOCATION

Site Location

Electrical Location
68 Rosemi www.themegallery.com

STEP 5: SUPPLY ADEQUACY CHECK, FOR CURRENT SYSTEM, WITHOUT NEW LOAD
Check For 100% Feedback w/out Current Violation ie no Overload Voltage Violation ie no Vdrop <10% I I1
Overload

Vd <-10%
Check Limit Figures 300mmp=330A 240mmp=350A 185mmp=250A 150mmp=280A 120mmp=200A 95mmp=210A 70mmp=140A 9.9kV
www.themegallery.com

I I1
Voltage Drop
69 Rosemi

<100%

<100%

If the system complies, proceed, if not, redesign

Vd

<10%

STEP 6: SUPPLY ADEQUECY CHECK, WITH NEW LOAD INJECTION


Check For 100% Feedback w/out Current Violation ie no Overload Voltage Violation ie no Vdrop <10% I Vd <-10%
Check

Inject new load with maximum MD in final year with load scaling factor considered
Limit Figures 300mmp=330A 240mmp=350A 185mmp=250A 150mmp=280A 120mmp=200A 95mmp=210A 70mmp=140A 9.9kV
www.themegallery.com

I1
Overload

I I1
Voltage Drop
70 Rosemi

<100%

If the system complies, proceed, if not, redesign

<100%

Vd

<10%

STEP 7: SUPPLY ADEQUACY CHECK, WITH NEW LOAD INJECTION & LOAD SCALING
I
Start with load in year 5, if comply, proceed, if not go to year Vd <-10% 4. Find in what year the system complies the standard criteria (I,V). Suggest improvement for future year yr3,yr4,y5 if any.
Load in MW PE2 PE3 PE4 PE5 0.20 0.15 0.20 0.15 0.21 0.16 0.21 0.16 0.22 0.16 0.22 0.16 0.23 0.17 0.23 0.17 0.24 0.18 0.24 0.18 0.25 0.19 0.25 0.19
71 Rosemi

I1

Year 2005 2006 2007 2008 2009 2010

Yr NewPE PE1 Yr0 0.3 0.10 Yr1 0.5 0.10 Yr2 0.9 0.11 Yr3 1.5 0.11 Yr4 2.1 0.12 Yr5 2.7 0.13

Total Growth 1.10 1.33 4% 1.77 4% 2.41 5% 3.05 5% 3.70 5%


www.themegallery.com

STEP 8: SECURITY LEVEL SELECTION


Redesign to include all features. System design to follow (n-1) source and element

Select security level for The customer or The area

Level ResTime System Design L1 5 Sec 2 dedicated parallel Cables, Unit protection, DOC,VCB,SCADA L2 15 Min VCB,SCADA, Unit Protection L3 L4 4 hr 1 day RMU + VCB RMU, H Pole
72 Rosemi

L2,L3 L4 L2,L3 L4 L1,L2,L3

e.g. Penang Island


www.themegallery.com

STEP 9: LOAD FLOW ANALYSIS


a) Contingency Criteria (Vd<-10%, I<100% for 100% Feedback) Test for single contingency (n-1) I I
Vd<-10% Vd<-10%

and
I1

I1
Check Limit 1st leg A 1st leg B OK/NOK Figures 300mmp=330A 240mmp=350A 200A 198A OK 185mmp=250A 150mmp=280A 120mmp=200A 95mmp=210A 70mmp=140A 9.9kV 11.55kV 10.01kV 10.02kV No
73 Rosemi

I
Overload

<100%

I1
Voltage Drop Over Voltage

<100%

Vd Vover

<10% >5%

OK OK

No

If comply, proceed, if not, redesign. Eg. New injection, reconductor or reconfigure.


www.themegallery.com

STEP 10: TIE OFF POINT OPTIMIZATION (TOPO)


Run load flow to find the lowest losses , with different off point, or use TOPO (just an option)

Off Point PE1 PE2 PE3 PE4 PE5 PE6

% Loss Best 2.00% 2.20% 2.40% 1.65% MinLoss 2.00% 2.30%

Choose PE4 as OFF Point. It gives min loss

74

www.themegallery.com

STEP 11: LOAD FLOW ANALYSIS (2)


b) Steady State (Vd <-5%,I< Cable Cap, <50%Feeder Loading, Loss<5%,pf>0.85 ) Ia Ib
Check Limit <50% <50% <-5% <-5% >+5% >+5% <+5% >0.85 Targeted Actual Actual Figures Figure A Figure B 195A 195A 105A 100A 100A 102A 10.92kV 10.93kV

I1 Vd1

I2 Vd2

Load 50% of feeder Voltage Drop Over Voltage Losses Power Factor

Ia Ib Vd1 Vd2 Vd1 Vd2 Loss pf

>10.45kV 10.91kV >10.45kV 10.94kV <11.55kV <11.55kV lowest 1.0 2.30% 0.89

2.30% 0.89

75 Rosemi

www.themegallery.com

STEP 14: IDENTIFY SYSTEM LIMITATION



Year Yr0 Yr1 Yr2 Yr3 Yr4 Yr5 2005 2006 2007 2008 2009 2010

Increase load 4%-5% each year (based on load forecast) Test for steady state and contingency Find in what year, the system max Propose system improvement for that year
Steady State Growth Total Total Loss Power % Load(MW) Loss(kW) % O/Load Vd<-10% O/Load Vd<-10% O/Load Vd<-5% Factor 2.52 50.400 2.0 No No No No No No 0.85 0 2.62 52.416 2.0 No No No No No No 0.86 4 2.73 54.513 2.5 No No No No No No 0.86 4 2.83 56.693 2.6 No No No No No No 0.89 5 2.95 58.961 2.7 Yes No Yes No Yes Yes 0.76 5 3.07 61.319 2.7 Yes Yes Yes Yes Yes Yes 0.71 5 Contingency 1st legA 1st legB

This system can withstand load growth until Yr3. System improvement is required in Yr4, by laying 240mmp 11kV 1200m from PPU A to PE5.
76 Rosemi www.themegallery.com

STEP 15: ANALYSIS SUMMARY


Yr0 Load Forecast %Growth
Condition

Yr1 2.62 4
Yr0 No No No No No No No No No No No No No No No Yr1 No No No No No No No No No No No No No No No

Yr2 2.73 4
Yr2 No No No No No No No No No No No No No No No

Yr3 2.83 5
Yr3 Yes Yes Yes Yes No Yes Yes Yes Yes No Yes Yes Yes Yes No

Yr4 2.95 5
Yr4 Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
www.themegallery.com

2.52 0

Test Ia>50% Ib>50% Steady state I o/load Vd<-5% pf <0.85 Ia>50% Ib>50% Contingency I o/load A Vd<-10% pf <0.85 Ia>50% Ib>50% Contingency I o/load B Vd<-10% pf <0.85

77 Rosemi

Add your company slogan

ISSUES & CHALLENGES

78

DISTRIBUTION PLANNING & ASSET MANAGEMENT


DISTRIBUTION PLANNING FUNCTION SCOPE & METHODOLOGY TO SUPPORT ASSET MANAGEMENT OBJECTIVES OPTIMIZE PERFORMANCE , COST & RISKS

DISTRIBUTION RELIABILITY

PLANNING

TO

UNDERSTAND CYLCE

EQUIPMENT COST OF

PERFORMANCE,

EQUIPMENT/SYSTEMS.

INVESTMENT ANALYSIS TO PROVIDE DEAL WITH PERFORMANCE, COST AND RISK ASSESSMENT SO NEED FOR SUPPORTIVE METHODOLOGIES.

79 LooCK

www.themegallery.com

DISTRIBUTION PLANNING ISSUES(1)


VOLTAGE SELECTION FOR HIGH GROWTH AREAS

SECURITY STANDARDS & CONTINGENCY CRITERIA

SERVICE LEVEL DIFFERENTIATIONS

DETERMINISTIC VS PROBABLISTIC CRITERIA.

NETWORK STRUCTURE & CONFIGURATION

80 LooCK

www.themegallery.com

DISTRIBUTION PLANNING ISSUES(2)


PROTECTION & AUTOMATION

EQUIPMENT DESIGN, SELECTION & STANDARDIZATION

ASSET REPLACEMENT DECISIONS & PLANS

DG CONNECTIONS

LOAD FORECASTING

81 LooCK

www.themegallery.com

DISTRIBUTION PLANNING ISSUES(3)


SYSTEM STUDIES: METHODS, TOOLS & DATABASES

INVESTMENT APPRAISAL METHODS

82 LooCK

www.themegallery.com

Add your company slogan

EVOLUTION IN PLANNING METHODOLOGIES

83

EVOLUTION IN PLANNING METHODOLOGY

RISK-BASED PLANNING

RELIABILITY-BASED PLANNING

VALUE-BASED PLANNING LEAST-COST PLANNING


84 LooCK www.themegallery.com

SUMMARY & CONCLUSIONS


TRADITIONAL DISTRIBUTION PLANNING FUNCTION REALIGNED TO FIT OVERALL ASSET MANAGEMENT OBJECTIVES OF UTILITIES

DISTRIBUTION

PLANNERS

TO

DEVELOP

&

APPLY

METHODOLOGIES THAT COULD

EFFECTIVELY DEAL WITH

RELIABILITY AND RISK ASSESSMENT, LIFE CYCLE COSTING FOR ASSET DEVELOPMENT AND REPLACEMENT DECISIONS.

85 LooCK

www.themegallery.com

SUMMARY & CONCLUSIONS

PLANNING & DESIGN CRITERIA REMAINS UNCHANGED BUT STILL LINGERING ISSUES THAT NEED TO BE DEALT WITH PLANNERS ARISING FROM ENHANCED ROLES & DELIVERABLES.

OPPORTUNITIES FOR DEVELOPMENT OF NEW METHODS RISK ASSESSMENT AND OPTIMIZATION TOOLS FOLLOWING IMPLEMENTATION OF INTEGTRATED UTILITY IT APPLICATIONS ( GIS-BASED NETWORK MGT SYSTEM, OMS, CBM, SCADA ETC)

86 LooCK

www.themegallery.com

THANK YOU!

87 LooCK

www.themegallery.com

Potrebbero piacerti anche