CASPIAN CONSTRUCTION – CANADA POST MAIL PROCESSING PLANT


Caspian Construction’s $100 million Canada Post mail
processing plant project will become one of the first
high-tech facilities of its kind.

Working Together as a Team


Caspian Construction, in a joint venture with Toronto-based Aecon Buildings, is completing Canada Post’s
mail processing plant, which will stand out as a high-tech, LEED-certified facility.

By Kate Burrows “We also cannot build retention ponds that would attract

E arning LEED certification on any project requires


dedication and hard work, but earning credits on a
project located in close proximity of an airport –
such as the project Caspian Construction is currently build-
ing adjacent to the Winnipeg International Airport – repre-
wildlife or use highly reflective building materials such as
a light-colored roof or solar panels that may interfere with
aircraft movement above.
“For the LEED points, we are focusing on the credits that
actually add value to the project rather than attain the ones
sents an even bigger challenge. Caspian and its team are that have philosophical implications,” Babakhanians con-
up to the task as they build Canada Post’s $100 million tinues. “Our design is striving to attain all the credits under
mail processing plant in Winnipeg, Manitoba. According to water efficiency, energy and atmosphere, materials and
Program Manager Shaun Babakhanians, this high-tech mail resources and innovation and design process. While we are
sorting plant will be one of the few LEED-certified facilities of going for as many as we can under indoor environmental
its kind when it is completed in December. quality, some of the day-lighting credits are near impossi-
Babakhanians says earning LEED cred- ble to attain in the sorting plant area, for example, where
Caspian Construction –
Canada Post’s Winnipeg Mail its for this 275,000-square-foot project there is laser operated sorting equipment that is intolerant
Processing Plant requires many unique considerations. The of direct illumination.”
www.caspianconstruction.com project is unable to attain many of the Caspian is using regionally extracted materials where it
Project value: $100 million
Location: Winnipeg, Manitoba available credits because of the limita- can, especially Tyndall Stone. Also, in addition to using irri-
Employees at peak of con- tions of the site. “Since we’re located on a gation-free landscaping, the firm is reducing the water
struction: 250+ site that’s adjacent to the airport, we can- usage by more than 30 percent. “Canada Post’s mandate is
Specialty: Design/build
Shaun Babakhanians:: “We like not attract wildlife near the runways,” to get the project LEED-certified,” Babakhanians explains.
to maintain a family environment.” Babakhanians says. “LEED, as a concept, is not just about getting the plaque

56 ■ WWW.CONSTRUCTION-TODAY.COM ■ FEBRUARY 2009