Sei sulla pagina 1di 27

Streamlining Shipyard Rigging Analysis June 2012

Ship Production Process Technology Panel

What is Shipyard Rigging?


Shipyard rigging involves the lifting, handling, and transportation of partially built structure, which is desired to be as massive as possible, that will undergo temporary loading conditions through orientations that may never occur again, for which the consequences of failure are severe.

References and Guidance

The Primary Goal is to Create Reference Material to Guide Shipyard Rigging Engineers on Proper Analysis of Lifted Ship Structure
Safety Defining the Problem, and its Variables Results in a Greater Likelihood of a Successful Lift Training Having Relevant Reference Material Increases the Versatility of Engineers Cost Greater Understanding Will Lead to More Efficient Solutions, and a Reduction of Overly Conservative Designs
3

Blocks Analyzed, Instrumented, Lifted

82-96 Ton deck and shell block: Lift, Lift and turn, Lift (53x 52x 13)

212 Ton Inner-bottom block: Lift (61x 51x 7)

Blocks Analyzed, Instrumented, Lifted

44 Ton small house block: Lift and turn (77x 38x 10)

44 Ton frame stiffened panel: Lift and turn (66x 20x 8)

Blocks Analyzed, Instrumented, Lifted

531 Ton Double Deck Block: Erection (106x 52x 32)

354 Ton Hangar Block: Erection (106x 59x 47)

Lifted Dynamics

Rigging is a Dynamic and Variable Event


There is Variation Seen in Shipyard Lifts Weight and COG (Estimate!) Operational Effects (Significant Percentage!) Dynamics Effects (Bouncing, Swinging, Twisting) Classic Sectional Analysis (Significant Error Possible!) Linear Finite Element Analysis (Simple, Detailed, Section) Category A is Engineered(DF=2) B is Standard (DF =3)

Match Structural Estimation of Unit Strength

ASME Below-The-Hook Bases Design Factor on Probabilistic Loading.

Lifted Dynamics

What are the Dynamics of a Typical Lift?


Historical Concern of Lifted Dynamics is Focused on the Effect on the Crane Previous Investigations in the 1940s and 1970s Created Data from Incrementing the Crane. Information Collected Pertained to Single Crane Lifts

Lifted Dynamics

Accelerometers Attached to Block


Acceleration of Block Scale of rigging results in very small accelerations, X, Y, and Z Lifted declivity of block, (<0.1 Deg) Global angle Local angle

Accelerometer

Lifted Dynamics

Vertical Bouncing of Block


Observed in accelerometer data during all movements recorded Mostly mass independent (The crane is causing it!) Periods of motion typically 0.25 to 4 (sec) Up to 5% g typically observed

10

Lifted Dynamic Loads

Pendulum Swinging of Load


First dynamic recorded in strain gauge Period of motion depends of crane boom height Period Periods of oscillation typically 11 to 16 (sec) {100-200 ft} Apparent swinging creating one degree of declivity or side load. Initiated when: cranes move, travel path changes, booming

11

Lifted Dynamic Loads

Twisting of Load
Along with Swinging, most prevalent dynamic recorded Coupled with swinging Periods of motion typically 4 to 30 (sec) Highly variable since depends on: Block mass Block mass moment of inertia Height of rigging Attachment location of rigging Lifted structure displays regular and chaotic motion

12

Eight Strain Gauged Lifts

Strain Gauges Allow Confirmation of Predicted Stresses and Show Variability of Stresses During Lift:
Dynamic Loads: Short Period Dynamic Oscillation of Structure Operational Effects: Long Erratic Period, or Variable

13

Operational Variables

Lift Specific Factors Can Heavily Influence Loads and Stresses


Slings: Exact Length Will Affect Angle, Elasticity, Load sharing Cranes: Travel Speed, Winch Speed, Separation Distance, Block Orientation Spreader bar: Exact Spread Will Affect Angles, Loads Weather: Wind, Rain Water Weight: What Exactly is on Block, Center of Gravity

14

Operation Variables

Weight and COG is The Most Important Thing in Rigging


Structural steel weight
Most likely to be accurate Plate substitutions possible Typically 60-99% of a blocks total weight Reliant on Vender Furnished Information 3D production modeling errors

Outfitting weight and COG is has more variability

15

Operation Variables

Lifted Weight and COG is Even More Complex


Weight control departments are mainly concerned with the completed vessel weight Individual blocks are subject to greater error What is on the block when it is lifted?
Temporary parts Missing parts Free ride

16

Operational Variables

Increases in Stresses Were Observed as Blocks Were First Lifted


Ground effects were found to be significant Global bending stresses significantly higher than the steady state lift values Occurred on all lifts Repeatable phenomenon Durations ranging from 5-60 sec Caused by: COG error Crane position tolerance Blocking arrangement

17

Operational Variables

The Turning of Units Have Significant Planned Loading Changes


Sling loads may swing through greater than 180 Tensions in slings will change as the operation is conducted Approximations to calculate are trigonometrically complex and require idealized assumptions

18

Rigging Engineering is Complex

If Operation is Complex and Difficult or Impossible to Project Exactly What Will Take Place, High Design Factors are Warranted.
Uncertainly for weight.
Small sampling of historical maximum errors

15% ~10% (?) 5% ~1 (Deg) 5 (Deg) 5 (Deg) ~100% ~100%

Uncertainly for center of gravity. (No Hard Data) Dynamic bouncing.


Max seen, other references similar, Typical seen during dynamic event in this project

Dynamics from swinging, twisting Two crane lift hook height variance Two crane lift positional tolerances (tug-o-war)
Typical seen in this project, similar found in references Doubling of sling tension possible but rare

Statically indeterminate lifting arrangements Ground effects on internal moments during first lift

Maximum seen for expected and significant bending moments


19

Structural Strength Estimation

Classic Assumed Section Analysis


Weight, COG and free body diagrams can estimate sling loads Forces impose moments in structure Assume an effective section which resist these moments Conservative assumption may project stress ~5 times higher Generous assumption may project stress ~5 times lower On a simple structures an estimates of (+/-) 50% is a reasonable expectation from a qualified and experienced structural rigging engineer

20

Structural Strength Estimation


Finite Element Analysis Can Create Accurate Estimates of Complex Structure. But How Much Detail Should be Included?
All structure and outfitting? Bulkheads, Frames, Longitudinal, Brackets, Foundations, Outfitting Bulkheads, Frames, Longitudinal, Brackets, Foundations Bulkheads, Frames, Longitudinals Bulkheads, Frames

All structure?

Primary and secondary planes of structure? Primary planes of structure? If an estimate of stress is all that is desired, modeling only primary and secondary planes of structure gives reasonable result. 50-80% of mass modeled with gravity increased
21

Structural Strength Estimation

Projecting Lifted Deflections and Wracking is Highly Complex


Rigging arrangements are nonlinear, the rigging will shift accompanied by the rotation of the many pin connections Model must be free to twist, deflect, and translate Fortunately there is little perceived need of precise lifted deflections If desired ~100% of mass and structure needs to be included

22

Structural Strength Estimation


Operation and Dynamics Stresses and Loading Vary Substantially


Hypothetically, loads or stress will be within 30% of projected, 90% of the time.

Detailed Finite Element Analysis Offers Relatively Accurate Analysis


Notionally, strength can be projected within 10% of actual, 90% of the time.

23

Structural Strength Estimation


Simplified Finite Element Analysis With 80/20 Rule


80% the accuracy, 20% the cost

Less Accurate Analysis


Strength can be projected within 20% of actual, 90% of the time.

Design Factor, or Margin Will Required to be Larger

24

Structural Strength Estimation

Conservative Assumptions Should Skew the Probability of Strength Prediction.


The odds are the strength will be higher than estimated if minimum size plates are assumed

Less of an Increase in Design Factor Would be Required

25

Summary

Shipyard Rigging is a Highly Variable Event


For safe rigging relatively high design factors are required

The Lift of Most Steel Ship Blocks Probably Does Not Result in Significant Global Stresses
Highest stresses are typically in the padeyes or near their attachment Highly outfitted lifts of units with minimal structure are exception

FEA Can Significantly Aid The Analysis of Large Complex Structures Simplification of FEA Can Significantly Reduce The Amount of Detail Required in a Structural Model Without Significant Sacrifice to Accuracy or Predicted Stresses

26

Questions?

27

Potrebbero piacerti anche