Sei sulla pagina 1di 63

INDUSTRIAL RING ROAD PROJECT Contract C1 & C2 Stay Cables and Bridge Deck Installation

Dr.Padipat Chaemmangkang VSL (Thailand) Co., Ltd.


1

CONTRACT NO.1
South Main Bridge

CONTRACT NO.3

North Main Bridge

CONTRACT NO.2
3

CONTRACTS C1 & C2

BASIC INFORMATION OF THE BRIDGES

South Main Bridge (Contract C1)


Span main span length 398m no. of segments 2x16 + 1 Alignment gradient max. 3.5% radius in plan straight crossfall (reversed V-shaped) constant 2.5% Segment width 35.9m depth 2.7-3.2m length/weight connectn box 7.0m/311t unit 1 10.0m/386t unit 2-15 12.0m/431-492t closure unit 10.0m/375t Max. Lifting Height 61.1m
6

North Main Bridge (Contract C2)


Span main span length 326m no. of segments 2x13 + 1 Alignment gradient max. 3.5% radius in plan straight crossfall (reversed V-shaped) constant 2.5% Segment width 35.9m depth 2.7-3.2m length/weight connectn box 4.95m/305t unit 1 10.0m/377t unit 2-15 12.0m/426-487t closure unit 10.0m/375t Max. Lifting Height 53.7m
7

10

HEAVY LIFTING TECHNIQUE

11

VSL Strand System


The main components of the system are the motive unit, the tensile member with the anchorage for the load, the hydraulic pump and its control.

12

Motive Unit
The motive unit consists of a hydraulic centre hole jack and the upper and lower anchorages. The upper anchorage is attached to the jack piston. During lifting the jack is extended, causing the individual strands of the tensile member to be gripped by the upper anchorage and thus to be moved upwards. At the start of the pistons downward movement the strands are immediately gripped by the lower anchorage, while at the same time the upper opens. The load is thus moved in a step-by-step process.
13

Motive Unit (continued)


For lowering operations, VSL motive units are equipped with an auxiliary device which automatically controls the opening and closing of the anchorages. Lifting and lowering operations can therefore be carried out with the same degree of safety and speed.

14

Tensile member
The tensile member consists of 7-wire prestressing steel strands with a 15.2mm nominal diameter. This tensile member is anchored to the load by a specially designed end anchorage.

15

Hydraulic Pump
The oil flow for the motive units is provided by electro-hydraulic pumps with either single or multiple outlets. The characteristics of these pumps guarantee synchronized jack movements, even if loads are different. Built-in pressure gauges or remote pressure control devices allow stresses to be monitored at all times. The size of the pump can be chosen to suit the load to be moved. Movement speeds vary according to the project and if required can be in excess of 20m /hour.
16

Control and Monitoring Systems


All VSL motive units, jacks and synchronized hydraulic pumps can be operated either manually or by remote control. When a precise coordination of lifting movements is required, specially designed, computer-based multi-point monitoring systems, which centrally control and monitor the operation up to final, precise height, can be applied. When loads from a number of different points are centrally monitored, custom designed equipment displays the pressures digitally and graphically, and provide print-outs of the results.
17

18

19

VSL SSI 2000 STAY CABLE SYSTEM

20

21

SSI 2000 SYSTEMS FEATURES


The system has been optimized to facilitate cable installation on site. Because it uses prefabricated anchorages, there is no anchorage component assembly on the deck or the pylon along the critical bridge erection path. The very compact anchorages permit easy installation in confined locations inside deck units and pylons. Singlestrand installation and stressing are standard features of the system.

22

SSI 2000 SYSTEMS FEATURES (continued)


The individual encapsulation of each strand avoids the risk of corrosion migration inside stay cable areas that cannot be visually inspected. Full individual strand encapsulation is achieved by providing each strand with its own protection tube and sealing details in the anchorages. This special sealing system ensures full protection of the strand during the construction phase. The performance of the seals can be checked at any time during the design life of the stay.
23

STAY CABLE & DECK INSTALLATION

24

Stay Cable Installation


The first stay cable was installed 16th November 2005 and following a tight 5 and 6-day cycle, the erection works was finalized within a record time of 4 months with the last stay cable erected 19th March 2006. The stay cables were installed using VSL Standard strand-by-strand installation techniques utilizing winches and were stressed by a combination of Manual and Automatic Stressing Systems.

25

Stressing
Before starting the stressing process, the stressing sequences and stressing force shall be predetermined for all cables. During stressing of the stay cables, the stressing force, the deflection of the deck segments and the pylon shall be closely monitored so that the tolerances are not exceeded.

26

Stressing (continued)
Essential data to be provided by the designer is as follows: 1 The construction sequence. 2 Coordinate of bridge after construction. 3 Tensile forces and correspondent deflections at deck and pylon in installation stage. 4 Tensile forces and correspondent deflections at deck and pylon in each adjustment stage. 5 Tensile forces and correspondent deflections at deck and pylon for final tuning of the stays.
27

General Procedure
1 Erection of cable-stayed segments 2 First bridge level is recorded and checked against the predicted theoretical level. 3 Strand by strand installation of the strands in the main span stays. 4 Strand by strand installation of the strands in the side span stays.

28

General Procedure (continued)


5 Pylon and deck deflection is checked and compared by the predicted values given by the designer. 6 Erection of segment. 7 Re-stressing of the stays simultaneously , e.g. main span pylon (MSP) and side span pylon (SSP) to be stressed simultaneously with four nos. of mono-strand jack. With mono-strand jacks, stressing force is evenly applied onto strands by stressing to a pre-calculated elongation rather than force. 8 New cycle.
29

30

31

32

33

34

35

36

37

38

39

40

41

42

Bridge Deck Installation


The composite bridge deck segments were prefabricated approximately 22-km down the ChaoPhraya River and transported to the site by barges. The segments were lifted from the barge to the final deck elevation using VSL Modular Self Launching Deck Erection Gantries. Due to Chao-Phraya River being extremely busy with commercial river traffic in the vicinity of the bridges, the lifting speed of the VSL System was set such that the lifting could be completed safely in approximately two hours.
43

Bridge Deck Installation (continued)


The key works of deck lifting and stay cable installation were carried out by VSL operating on a 24hours/7days schedule, where the coordination between the two disciplines resulted in an erection cycle two days faster than initially anticipated, allowing a gain of about a month in main decks erection program.

44

45

Strand Lifting Unit SLU 330/550

46

General Sequence
1 2 3 4 5 6 7 8 Delivery deck units to lifting location on site. Anchor the barge. Lower the SLB. Connect the SLB to the deck unit. Take up the initial tension in the strand. Confirm ready for lifting. Lift the deck unit. Remove the barge from site.

47

General Sequence (continued)


9 10 11 12 13 14 15 Lift the deck unit to final level. Pull the deck unit back to close gap. Make final level adjustments. Make connection between deck units. Install the stay cables. Release load from the erection gantries (EG). Launch EG forward.

48

49

Liftoff Procedure
1 The SLB is lowered to the deck unit on the barge. 2 The connection between the deck unit and the SLB is made with a typical pin connection. 3 A nominal portion of the expected load is introduced to the lifting system by building up the hydraulic pressure in the lifting system.

50

Liftoff Procedure (continued)


4 Upon confirmation that all relevant parties are ready, the load in the hydraulic system is built up in incremental steps of 25%, 505, 80%, 90%, 95% and 100%. 5 After reaching 100%, the unit is lifted off from the temporary supports on the barge by approximately one stroke length of the SLU 330/550, i.e. 500mm.

51

52

Lifting Operation
The lifting operation is a repetitive process of the jacks extending and retracting at the ends of each stroke. 1 The jack operations are controlled from the pump by the operator. While the jacks are extending the upper grippers will grip the strands and lift the load vertically. During the retract stage the load is held in the lower grippers mechanically while the upper gripper wedges allow the jack to reset for the next stroke.
53

Lifting Operation (continued)


2 The lifting of the deck units is a repetitive process 2.1 The deck units will be lifted in discrete steps of approximately 500mm 2.2 There will be a pause of approximately 1 minute while the pistons reset for their next stroke. The complete cycle time is dependent upon oil flow, which is adjustable. 2.3 The deck unit will move approximately 10mm while the load is transferred from the top anchor to the bottom anchor and vice versa in the reset phase of the jacking system.
54

Closing the Gap between Deck Units


For all of the deck units there is a nominal gap between that of the ones that had been previously erected and the one being lifted into position. This gap varies from unit to unit as follows: Connection box Units 1-15 Closure unit 1300mm 600mm 100mm

55

Closing the Gap between Deck Units (continued)


1 Upon lifting the deck unit to the required level, the gap closure jacks are connected to the SLB by a typical pin connection. A small footbridge is required for VSL personnel to cross the gap and work on the lifted deck unit. 2 After the jacks are connected, the deck unit is pull close, and at the required spacing the deck unit is held temporarily while the bolted connection and stay cables are installed.

56

Load Transfer onto Permanent Supports


After the connections have been made and all parties (TNNS, VSL and the design engineer) have agreed that load can be transferred to the permanent supports, the load is slowly released from the jacking system.

57

58

59

60

CONCLUSION

61

62

END

63

Potrebbero piacerti anche