PROJEK LEBUHRAYA PANTAI TIMUR FASA 2, TERENGGANU PAKEJ 1A : DARI CH.0.00 KE CH.

3750
JABATAN KERJA RAYA PASUKAN PROJEK LPT FASA 2 Ref No. QBR/MS/PW/0212/02

MainContractor.
Q-BENA RESOURCES SDN BHD Date :

METHOD STATEMENT
Title:

PROOF ROLLING CH 0.00 CH 3750

07-02-2012

1. INTRODUCTION & PURPOSE

This method statement has been prepared for the work which carries out at location as highlighted in drawings. The purpose is to and to determine difference settlement in the placing the sub base. By locating repairs after the asphalt locate any soft spots

pavement structure before concrete surface has been placed.

soft spots early, proof rolling avoids costly

2. WORK SEQUENCE.

Perform proof rolling as directed.

Adjust the load and tire inflation pressures within the range of the manufacturers charts or tabulations, as directed.

Make at least 2 coverage with the proof roller machine within the width of the main carriageway.

Offset each trip of the roller by at most 1 tire width.

Operate proof rolling machine at a speed between 8-10 kilometres per hour or as directed by the S.O.

Rev.00 Page 1

of 3

PROJEK LEBUHRAYA PANTAI TIMUR FASA 2, TERENGGANU PAKEJ 1A : DARI CH.0.00 KE CH.3750
JABATAN KERJA RAYA PASUKAN PROJEK LPT FASA 2 Ref No. QBR/MS/PW/0212/02

MainContractor.
Q-BENA RESOURCES SDN BHD Date :

METHOD STATEMENT
Title:

PROOF ROLLING CH 0.00 CH 3750

07-02-2012

Proof rolling shall be carried out with proof rolling machine that have a weight of 50 tonnes. Tires shall be inflation pressures in between 0.5 N/mm to 0.7 N/mm.

Operate proof rolling machine in longitudinal direction and from lower to the higher edge.

The different settlement shall be measured with a long straight edge with the length similar to the width of the proof rolling machine.

If areas of subgrade upon proof rolling are found to be weak and/or fail, the area shall be demarcate and to be excavated to the depth of 600 mm and recompacted to required compaction by performing in situ CBR.

3. EQUIPMENT Proof Rolling Machine - 1 No Pneumatic Tyre Rollers -1 No Steel Wheel Tandem Roller - 1 No Tip truck - 1 No Power Broom - 1 No Motor grader - 1 No Back Pusher - 1 No 4. MANPOWER

Supervisor General Worker

- 1 person - 1 person

Rev.00 Page 2

of 3

PROJEK LEBUHRAYA PANTAI TIMUR FASA 2, TERENGGANU PAKEJ 1A : DARI CH.0.00 KE CH.3750
JABATAN KERJA RAYA PASUKAN PROJEK LPT FASA 2 Ref No. QBR/MS/PW/0212/02

MainContractor.
Q-BENA RESOURCES SDN BHD Date :

METHOD STATEMENT
Title:

PROOF ROLLING CH 0.00 CH 3750

07-02-2012

Machine Operator - 6 persons

5. RELEVANT DRAWING KPKR/J/R/130507 (LPT2)/1A/KL1A - KL34A 6. RELEVANT FORM Request for Inspection Form JKR SPK form 7. RELEVANT SPECIFICATION IN ACCORDANCE TO JKR/SPJ/2008-S4