Introduction: This guide can be used as quick reference for Nokia Flexi BTS Indoor Cabinet installation.
Checking the delivery

Contents of delivery

Checking the site

Changing the door opening direction

Lifting the cabinet

Installation

Grounding the cabinet

Installing the modules

Clearances

Minimum clearances Fixing points

Changing the door opening direction

Lifting the cabinet

Installing the cabinet

Grounding the cabinet

Installing the modules

Lifting the cabinet with a rope Lifting the cabinet with handles

Anchoring the cabinet

Recommended installation order Installation example

Cabling principles

Cabling principles

Cable routing

Routing cabinet external cabling

Checking the installation

10

Installation check list

-2-

The information in this document is subject to change without notice and describes only the product defined in the introduction of this documentation. This document is not an official customer document and Nokia Siemens Networks does not take responsibility for any errors or omissions in this document. This document is intended for the use of Nokia Siemens Networks customers only for the purposes of the agreement under which the document is submitted. No part of this documentation may be used, reproduced, modified or transmitted in any form or means without the prior written permission of Nokia Siemens Networks. The documentation has been prepared to be used by professional and properly trained personnel, and the customer assumes full responsibility when using it. Nokia Siemens Networks welcomes customer comments as part of the process of continuous development and improvement of the documentation. The information or statements given in this documentation concerning the suitability, capacity or performance of the mentioned hardware or software products are given as is and all liability arising in connection with such hardware or software products shall be defined conclusively and finally in a separate agreement between Nokia Siemens Networks and the customer. IN NO EVENT WILL Nokia Siemens Networks BE LIABLE FOR ERRORS IN THIS DOCUMENTATION OR FOR ANY DAMAGES, INCLUDING BUT NOT LIMITED TO SPECIAL, DIRECT, INDIRECT, INCIDENTAL OR CONSEQUENTIAL OR ANY LOSSES SUCH AS BUT NOT LIMITED TO LOSS OF PROFIT, REVENUE, BUSINESS INTERRUPTION, BUSINESS OPPORTUNITY OR DATA, that might arise from the use of this document or the information in it. THE CONTENTS OF THIS DOCUMENT ARE PROVIDED "AS IS". EXCEPT AS REQUIRED BY APPLICABLE MANDATORY LAW, NO WARRANTIES OF ANY KIND, EITHER EXPRESS OR IMPLIED, INCLUDING, BUT NOT LIMITED TO, THE IMPLIED WARRANTIES OF MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE AND NON-INFRINGEMENT, ARE MADE IN RELATION TO THE ACCURACY, RELIABILITY OR CONTENTS OF THIS DOCUMENT. NOKIA SIEMENS NETWORKS RESERVES THE RIGHT TO REVISE THIS DOCUMENT OR WITHDRAW IT AT ANY TIME WITHOUT PRIOR NOTICE. This document and the product it describes are considered protected by copyrights and other intellectual property rights according to the applicable laws. The wave logo is a trademark of Nokia Siemens Networks Oy. Nokia is a registered trademark of Nokia Corporation. Siemens is a registered trademark of Siemens AG. Other product names mentioned in this document may be trademarks of their respective owners, and they are mentioned for identification purposes only. Copyright Nokia Siemens Networks 2010. All rights reserved.
DN70490819 version 1

Warning
Danger of eye damage due to invisible laser radiation from LTE, WCDMA, or Flexi Multiradio System Module or the EDGE Optical Converter Unit. Always switch off the laser before detaching the optical fibre from the connector.

Caution
Incorrect cables and seals may not provide secured weather protection. In outdoor installations, including the outdoor cabinet, use only tested IP65 class outdoor cables with seals provided by Nokia Siemens Networks. This is also recommended for indoor installations. Electrostatic discharge (ESD) may damage the modules. Wear an ESD wrist strap or use a corresponding method when handling the modules. Overbending the optical damages the cables and can detach or damage the connectors. Do not bend the optical cables beyond the minimum radius of 70 mm.

1 Contents of delivery
Delivery
Nokia Flexi Cabinet for Indoor Cabinet key Cage nuts (62 pcs)

-3-

Contents

Version

Codes
470152AA 6490006

Site package 1 Guide plates (30 pcs) Site package 2 Loose cage nuts (28 pcs) 6332594 822083

Check list Delivery is complete. Equipment is not damaged.

-4-

2 Clearances
Fixing points
71.5 mm (2.8 in) 457 mm (18.0 in) Back stop 71.5 mm (2.8 in)

Minimum clearances
Isometric view
300 mm (11.8 in) Depth 600 mm (23.62 in)
Width 600 mm (23.62 in)

Facility wall

179 mm (7.0 in)

Height 1800 mm (70.87 in)

300 mm (11.8 in)

570 mm 620 mm (22.4 in) (24.4 in)

Front
Front

Maintenance space 500 mm (19.7 in)

600 mm (23.6 in)

Top view
600 mm (23.6 in)

570 mm (22.4 in)

Door swing radius 600 mm (23.6 in)

900 mm (35.4 in)

50 mm (2.0 in)

Check list Site meets the minimum clearances.

NOTE: Maintenance space is not included.

3 Changing the door opening direction


NOTE: If you do not need to change the handedness of the door, skip section 3.

Principle of changing the door opening direction

2
Loosen the hinge screw Remove the hinge

1. Remove the ground wire and hinge pins, and detach the door. 2. Loosen the hinge screws and remove the hinges. 3. Install the hinges on the opposite side of the cabinet.

Tip: Remove the lower hinge first

3
Install the hinge on the opposite side of the cabinet Tighten

4 Changing the door opening direction (continued)


4

-5-

4. Remove the door lock-plate. 5. Install the door lock-plate on the opposite side of the cabinet.

Loosen screws

6. Flip the door end-to-end. 7. Mount the door on the opposite side. Reinstall the ground wire after attaching the hinge pins.

180o

Check list Door opening direction and magnetic sensor is changed.

-6-

5
2

Lifting the cabinet


Lifting the cabinet with WLHA handles

Lifting the cabinet with a rope

Minimum 500 (19.6)


4xM5

1 1

2
4xM5

NOTE: Dimensions: mm (in.)

1. Attach the 4 x M12 lifting eye bolts to the lifting points. 2. Attach the hoisting belt or rope to the lifting eye bolts. 3. Lift the cabinet carefully to the desired installation location. 4. Remove the lifting equipment.

1. Align the handle screw holes with the four M5 srew holes on the side of the cabinet. 2. Fix the handles to the cabinet with four M5 screws provided with the kit. 3. Lift the cabinet carefully to the desired installation location. 4. Remove the lifting equipment.

TIP: It is possible to lift the cabinet with modules installed and internal cabling completed.

6 Installing the cabinet


Anchoring the cabinet

-7-

Note that the cabinet should be attached to the base with M10 or M12 anchor bolts, nuts, and washers (4 pcs each). The recommended anchor bolt length is 60 mm (2.36 inches). Anchor bolts and nuts are not provided with the Flexi BTS delivery and must be acquired locally. 1. Mark the anchoring bolt holes with the help of the drilling template.
Cabinet feet adjustment (use a flathead screwdriver) Anchor hole

2. Drill the anchoring bolts holes on the base. 3. Attach the anchoring bolts to the base. 4. Position the cabinet on the anchoring bolts. 5. Fix the nuts on the anchoring bolts. 6. Check that the cabinet is level. 7. Tighten the nuts properly (recommended 49.0Nm (36.1 ft-lb)).

Adjustable feet (4pcs)

Cabinet fixing nut Cabinet spring washer Anchor bolt Floor

Check list Cabinet is anchored according to instructions.

-8-

7 Grounding the cabinet


Side view of cabinet Top view of cabinet

A
M5
Star washer
Cabinet ground cable

3.5-4.2 Nm (2.58-3.10 ft-lb)

Bolt Lug

Front
B

Cabinet ground cable

grounding points
M8
8.0-10.0 Nm (5.9-7.37 ft-lb)

1. Make sure the grounding cable is fixed to the site grounding point. 2. At the top of the cabinet, remove the screw and star washer. 3. Strip approx. 2 cm (0.79 in.) of the main ground cable. 4. If this is a NEBS installation, bring the mating surfaces of all unplated ground connections to a bright finish, using emerycloth -

(or other suitable method). Then coat the exposed ground cable conductor with antioxidant. 5. Insert the stripped end of the cable into a cable shoe lug and crimp. 6. Fit the lug to the grounding point in the cabinet and fix with a star washer and screw. Tighten M5 to 3.5-4.2 Nm (2.58-3.10 ft-lb). Tighten M8 to 8.0-10.0 Nm (5.9-7.37 ft-lb).

Check list Cabinet is correctly grounded.

8 Installing the modules


Recommended installation order
1 2
3

-9-

Installation example
Module installation order in a 1+1+1/2+2+2 configuration.

B A
6U

ERxA EXxA ESMA

2U ERxA EXxA 2U

Front view

ERxA EXxA

1. Push the front part of the guide plate in place first, and then the back part. 2. Fix the cage nuts according to the configuration. 3. Slide the first module in. 4. Fix the module to the cabinet with screws. 5. Repeat for each subsequent module.

Check list Modules are installed according to instructions.

- 10 -

Cabling principles

Cabling principles

Power cable clamp

Cable entry hole

Routing external cables. (1+1+1/2+2+2 FCIA configuration)

For instructions on connecting EDGE cables, see the Creating FCIA Configurations document.

NOTE: The appearance of the modules may vary depending on product or the module type.

Check list Cables are correctly routed. Cables are correctly connected.

10 Installation check list


Perform these checks to make sure that the installation is complete:
Delivery is complete and undamaged. Cabinet is anchored according to instructions. Cabinet is grounded. Modules are installed according to instructions. External power feed cable is connected. External antenna feeder cables are connected. External transmission cables are connected. Cables are routed, connected and tied correctly. All cable rubber seals are firmly in place. Cables are routed downwards from modules.