7 unit test system data (Egan et al.

(1975))

Unit No. Unit Capacity 1 20 2 15 3 35 4 40 5 15 6 15 7 10 Installed Capacity (IC) (Sum of all Units Capacity)

No. of Intervals of Maintenance 2 2 1 1 1 1 1 150 MW

Interval

Peak Load, PL (MW)

Gross Reserve, GR (MW) = IC PL

1 2 3 4 Important Note:

110 120 85 100

40 30 65 50

Units under Maintenanc e (Refer Fig. 7) Egan et al - 75 4 1,7 1,2,5,6 2,3

Net Reserve during any interval (week) = Gross Reserve Capacity of unit Under Maintenance on that Particular Interval (week)