Step By Step 2G RBS Commissioning 1. Local lock DXU & All DRU 2. Check Port A is Green Led 3.

Start Commissioning IDB without Connection to RBS by Software

4. commissioning/Create IDB

5. Check list All Parameter 6. Drop All Module on configuration Hardware

7. Connect to RBS Then Install IDB 8. After Finish, Unlock All DXU & DRU 9. make sure the RBS is Ready to integrate and then Call Integrator to load scripts.