NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT AND RESEARCH COURSE TITLE COURSE NO : MANAGEMENT IN ORGANISATION : NCP 21

Your company has bagged a lucrative contract to construct a housing colony for an industrial group to be located in Western Maharashtra in a costal belt. You as a Project Manager have been asked by the company to evolve organisation structure with following conditions. i. Organisation should be as lean and thin as possible with bare minimum of personnel on company roll up to Junior Engineer level. ii. All Supervisors to down below will be temporary for project duration only to be recruited locally from 100 Km radius. Suggest and discuss an organisation structure denoting

responsibility, authority, communication control for all facets of construction work and management functions as visualised by you.

Housing consists of 10 Bungalows for senior executives, 20 Apartments in five buildings, 100 dwellings for white collar workers and 300 dwellings for blue collared workers. Colony will have market and entertainment complex.

NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT AND RESEARCH COURSE TITLE: PRODUCTIVITY AND WORK STUDY TECHNIQUES IN CONSTRUCTION PROJECTS COURSE NO : NCP 31

Write an essay on the role of motivation and incentives in productivity improvement. Elaborate in detail the role of human factor in productivity improvement. Give the role of incentive schemes with reference to your companys scheme.

NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT AND RESEARCH COURSE TITLE : CONSTRUCTION SAFETY MANAGEMENT COURSE NO : NCP 32 You have been appointed as a Project Manager of a 17- storied high rise building in Mumbai. The site is surrounded by many other sky-scrapers. Your company has prepared a safety manual for normal buildings since so far your company was engaged in the construction of townships and industrial buildings. Top management has asked you to revise the safety manual. Discuss the various aspects in this situation.

Following data is provided. Foundation - Partly pile foundation Partly rock cutting and dewatering R.C.C. Frame structure Tower cranes for construction Dozer and JCB machines for earthwork. Steel scaffolding, bucket lifts for concrete and automatic batching plant.

___________________________________________________________ _____ NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT AND RESEARCH COURSE TITLE: CONSTRUCTION AND ENVIRONMENT COURSE NO : NCP 33 A five star hotel of 300 rooms with adjacent golf course has been planned by your company engaged in project

development at the foothills of Kumaon hills. Project is spread over 1000 acres of foothills on land intermittently plain and intermittently hilly with streams. You have been asked by the management to make

environment impact assessment of this Project. Company wants to undertake the advertisement campaign to minimise the threat from environmentalists group. Discuss your plan.