Sei sulla pagina 1di 150

ADJUSTED PRICE

Republic of the Philippines


DEPARTMENT OF AGRICULTURE
MINDANAO RURAL DEVELOPMENT PROGRAM-Phase II

Province of Zamboanga Sibugay


Municipality of Imelda
OFFICE OF THE MUNICIPAL ENGINEER

SUB-PROJECT PROGRAM OF WORK


Project No.
Project Title
: Water Supply System Level II
Category
:
Physical Target :
Location
Barangay
: Barangays
San jose
New Sagay, Casacon, Katipunan, Ali Alsree, Kulambugan and Magsaysay
Total Project Cost:Php
8,737,321.03
Equipment Needed:
Implementation Mode:
Project Description:
Project Duration
Const. Of San Jose, Imelda LEVEL II
Equipment Needed:
WATER SYSTEM
Technical Personnel:

Item No.

1
2
3
4
5
6
7
8

Scope of Work
Trench Excavation
( Transmission/Distribution)
Construction of Pump house
Installation of Submersible pump
Drilling
Transmission Line
Cylindrical Storage tank (24,000.0 ltrs.,
cap)
Distribution line
Tapstand
Total Direct Cost

Breakdown of Estimates
A. Direct Cost

% Weight

Quantity

Unit

3.33%
5.09%
3.10%
8.62%
3.01%

498.70
1.00
1.00
180.00
352.00

units
unit
unit
feet
ln.m.

473.73
361,803.71
220,000.00
3,403.00
606.71

18.47%
49.92%
8.46%

1.00
4,635.00
25.00

unit
ln.m.
unit

1,311,486.55
764.92
24,039.43

Unit Price

100.00%

Grant
3,551,018.03

Materials
Equipment
Labor

By Contract
200 calendar days
DT, BackhoeLoader, Staketruck
Civil Engr, Foreman.Plumber,
Pipefitter, Carpenters, Laborers

SOURCES OF FUNDS
LGU Equity
Cash
Non-Cash
3,551,018.03
7,102,036.06

Total

2,248,881.40
207,015.00
1,095,121.63

2,248,881.40
207,015.00
1,095,121.63

817,642.48

817,642.48

1,63

32,867.50
3,551.02
426,122.16

32,867.50
3,551.02
426,122.16

Quality Control (1% of direct cost)


Taxes (12% of the direct cost)

85

Contractor's Profit (10% of the direct cost)

355,101.80

355,101.80

71

C. Total Direct & Indirect Cost

4,368,660.51

4,368,660.51

8,737,321.03

E. TOTAL PROJECT COST


Percentage Sharing

4,368,660.51
50%

4,368,660.51
50%

8,737,321.03
100%

B. Indirect Cost
Plumbing Tools(Threaders,Pipe Wrench, Pipe
Cutter)

Prepared by:

Recommended Approval:

Municipal Engineer

Approved:

4,497,762.80
414,030.00
2,190,243.26

Reviewed by:

Mun. Planning & Dev. Coordinator

RPCO - RIE

Approved by:

Municipal Mayor

OSCAR O. PARAWAN, DVM


DA - Regional Executive Director

days
Loader, Staketruck
Foreman.Plumber,
Carpenters, Laborers
Total

236,250.00
361,803.71
220,000.00
612,540.10
213,563.25
1,311,486.55
3,545,406.60
600,985.85
7,102,036.06

Total
41,063.77

6
4,497,762.80
414,030.00
2,190,243.26

1,635,284.97

50304.44

###
65,735.00
7,102.04###
852,244.33###
710,203.61###
8,737,321.03
8,737,321.03
100%

PARAWAN, DVM
al Executive Director

79.32

ADJUSTED PRICE
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
Mindanao Rural Developement Program-Phase II
San Jose, Imelda, Zamboanga Sibugay
PROJECT
LOCATION

:
:

Water Supply System Level II at San jose


San Jose, Imelda, ZSP
DETAILED APPROVED AGENCY ESTIMATE
Item/Description

Spl I: Trench Excavation


Q=
498.70 cu.m

Unit

Unit Cost

Note: Slope correction and wastage factor of 20% Applied

Transmission line L = 352.0 ln.m.


Distribution Line L = 4635 ln.m.
Total

V=
V=

A. Labor:
15.0 Laborer

35.20 cu.m.
463.50 cu.m.
498.70 cu.m.

days
total

45.00

350.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost
II

Quantity

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

SPL II: Construction of of Pump house (1 unit)


Q=
1.000 unit
A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
4" x 8" x 16" CHB
4" x 8" x 4" Fixed Louver
10mm x 6.0m Def. Bars
8mm x 6.0m Def. bars
0.90m x 2.45m Corr. G.I. Sheet Ga #26 Roofing
0.90m x 2.45m Plain G.I. Sheet ga.#26 ridge roll
6mm x 1.22m x 2.44 Marine Plywood
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire
#7.75cm Roofing nails ( umbrella type)
Door Knob Yale
3/16" x 4" hinges
Vulcaseal
10pcs 2" x 4" x 10' Gem. Lumber
11pcs 2" x 4" x 10' Gem. Lumber
5 pcs 1" x 8" x 10' Gem Lumber
B. Electrical
25mm ID x 3.0m PVC Pipe
25mm ID x 90 PVC bend
25mm ID male threaded adaptor
25mm ID entrance cap
25mm PVC Clip
Solvent Cement Eslon blue 150G
12mm TW stranded wire
Electrical tape
50 Kva Transformer
Sub total

bags
m
m
pcs
pcs
pcs
pcs
pcs
pc
pcs
kgs
kgs
kgs
kgs
set
pair
can
bd.ft.
bd.ft.
bd.ft.

35.00
4.00
5.00
173.00
28.00
32.00
18.00
6.00
2.00
5.00
6.00
18.00
3.00
3.00
1.00
3.00
2.00
80.00
86.66
40.00

280.00
1,000.00
1,000.00
15.00
28.00
204.00
90.00
280.00
280.00
520.00
100.00
100.00
100.00
120.00
980.00
95.00
250.00
30.00
30.00
30.00

pcs
4.00
185.00
pcs
10.00
36.00
pcs
2.00
25.00
pcs
2.00
89.00
pcs
18.00
25.00
can
2.00
250.00
mtr
10.00
87.00
roll
2.00
90.00
pc
1.00
200,000.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor:
total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost
3

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

DETAILED APPROVED AGENCY ESTIMATE


Item/Description
III

Unit

Quantity

Unit Cost

SPL III: Installation of Submersible Pump


Q=
1.00 unit
A. Material
Goulds submersible Pump Stainless Steel
casing close coupled to a 4.5 HP 1 phase 230v
60 Hz, Franklin submersible motor, with built-in
lighting protection, original brand new, made in USA
to include the foll.
- Motor lead assy
- Built-in check valve and strainer
190ft. Submersible cable wire no.14
380ft Suspension wire No.14
- Panel board metal enclosure consist of the
foll.
- magnetic starter w/ overload
B/W Water level cut-off control w/ levelelectrodes
- on/off push button switch
- lightning arrester
1 set water roof splicing tape
1.00 unit
220,000.00
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
material
labor
B. Labor:
total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost
IV

SPL IV: Drilling (180ft depth)


Q=
180.00 ft.

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

Note: Including peremeter fence

A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire
Gravel (25mm in size) Gravel packing
burb wire

bags
m
m
pcs
kgs
kgs
kgs
cu.m.
m

Pipes:
150mm x 6.0m uPVC Pipe Class 150 (casing)
38mm x 6.0m G.I. Pipe sch 40 w/ coupling (suction)
"thk x 20mm x 38mm discharge plate
5/8" x 12" Stainless bolt w/ nut
38mm x 90 G.I. elbow
38mm G.I. Tee
38mm x 13mm G.I. bushing reducer
Pressure gauge
38mm G.I. Union
38mmx 0.20m G.I. Nipple threaded sch 40
38mm G.I. Gate Valve
38mm G.I. Swing Check Valve
25mm Wide thread tape
50mm GI Water meter
Sub total
B: Equipment Rental
Driling machine 180ft drill halo w/
casing installation

52.00
4.00
5.00
12.00
3.00
6.00
2.00
6.00
290.00

280.00
1,000.00
1,000.00
204.00
100.00
100.00
100.00
1,000.00
25.00

pcs
13.00
7,020.00
pcs
13.00
520.00
pcs
2.00
670.00
pcs
5.00
190.00
pcs
2.00
75.00
pcs
3.00
80.00
pcs
2.00
75.00
pcs
2.00
2,300.00
pcs
2.00
75.00
pcs
10.00
130.00
pcs
3.00
350.00
pcs
2.00
380.00
pcs
6.00
45.00
pc.
1.00
2,400.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

feet

180.00

2,200.00

C. Labor:
total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

DETAILED APPROVED AGENCY ESTIMATE


Item/Description

Unit

Direct Cost
Unit Cost
V

SPL V: Transmission Line (352 ln.m.)


Q=
352.00 ln.m.
A. Material:
50mm
50mm
50mm
25mm

Quantity

Unit Cost

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

Note: Slope correction and wastage factor of 20% Applied

ID x 6.0m G.I. Pipe sch. 40 w/ coupling


x 45 G.I. Elbow
G.I. Union
Wide Thread tape
Sub total

pcs
75.00
1,900.00
pcs
6.00
185.00
pcs
12.00
175.00
pcs
35.00
45.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor: (including pipe laying & embankment)


total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost

VI

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

SPL VI: Cylindrical Storage Tank (24,000.0 liters cap)


Q=
1 unit
A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
Sahara Cement
16mm x 6.0m Def. bars
12mm x 6.0m Def. Bars
12mm x 6.0m Stainless steel
10mm x 6.0m Def. Bars
#16 Tie Wire
#3.75 cm CWN
#10.02cm CWN
1/8"thk x 1.22 x 2.44 Steel Plate
Hacksaw Blade
Shovel
Welding Rod
6mm x 1.22m x 2.44 Marine Plywood
100 pcs 2" x 4" x 12' Gem. Lumber
528 pcs 2" x 2" x 10' Gem. Lumber

bags
m
m
pcs
pcs
pcs
pcs
pcs
kgs
kgs
kgs
sht
pcs
pcs
box
pcs
bd.ft.
bd.ft.

Plumbing:
150mm ID x 0.50m G.I. Nipple Threaded sch 40
150mm G.I. Elbow 45
100mm ID x 0.50 G.I. Nipple Threaded sch 40
75mm ID c 0.20m G.I. Nipple Threaded sch 40
50mm ID x 0.30m G.I. Nipple Threaed sch 40
150mm CI Gate Valve MJ/F NRS w/ bolts and
nuts & Gasket
150mm CI Adaptor MJ/F NRS w/ bolts and
nuts & Gasket
150mm CI Tee 150mm x 150mm F/F w/ bolts
and nuts
150mm CI 90 F/F w/ bolts and nuts
100mm G.I. Gate Valve screw end
75mm GI Elbow 90
50mm GI Elbow 90
50mm GI Union
25mm Wide Thread tape
50mm Water meter

C: Painting:
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
5

406.00
25.00
36.00
406.00
42.00
617.00
5.00
67.00
118.00
33.00
190.00
2.00
18.00
7.00
3.00
83.00
920.00
2,026.00

280.00
1,000.00
1,000.00
150.00
510.00
288.00
2,100.00
204.00
100.00
100.00
100.00
3,780.00
85.00
690.00
2,940.00
520.00
30.00
30.00

pcs
pcs
pcs
pcs
pcs

10.00
5.00
5.00
3.00
4.00

750.00
220.00
650.00
575.00
490.00

pcs

4.00

6,345.00

pcs

9.00

5,456.00

pcs
pcs
pcs
pcs
pcs
pcs
roll
pc.

2.00
3.00
3.00
2.00
4.00
2.00
6.00
1.00

5,200.00
3,450.00
5,903.00
889.50
190.00
190.00
45.00
2,400.00

gal
gal

14.00
14.00

878.00
878.00

DETAILED APPROVED AGENCY ESTIMATE


Item/Description

Unit

Blue Tinting color DB


Yellow tinting color DB
Green Tinting color DB
Black Tinting color DB
paint Roller w/ tray 7"
paint Roller 7" Foam
paint roller 6" w/ handle
paint roller 4" w/ handle
Epoxy Primer Gray
Epoxy Primer Yellow
Epoxy Strong Hold RSC
Epoxy Fortress
Reducer
QDE Paint Blue
Lettering Brush
L.T Primer White
L.T Reducer
L.T Semigloss White
L.T Cast
Paint Thinner
Lacquer Thinner
Easytite
Concrete Nuetralizer
Patching Compound
Paint tray
Paint Brush 3"
Paint Brush 2 1/2"
paint brush 2"
Sand Paper # 120
Sand Paper # 600
Sand Paper # 80
Putty Knife

Quantity

Unit Cost

Sub total

pint
4.00
160.00
pint
4.00
160.00
pint
3.00
160.00
pint
3.00
160.00
set
4.00
250.00
pcs
5.00
20.00
pcs
3.00
48.00
pcs
8.00
54.00
gal
10.00
600.00
gal
11.00
186.00
gal
4.00
2,630.00
gal
5.00
4,050.00
gal
2.00
908.00
gal
10.00
780.00
pcs
4.00
12.00
gal
16.00
720.00
gal
14.00
405.00
gal
5.00
894.00
gal
6.00
478.00
gal
7.00
216.00
gal
10.00
216.00
gal
4.00
312.00
lit
4.00
95.00
gal
30.00
24.00
pcs
5.00
30.00
pcs
3.00
42.00
pcs
3.00
48.00
pcs
17.00
75.00
pcs
54.00
13.00
pcs
11.00
14.00
ft
13.00
37.00
pairs
4.00
42.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

total

days
8.00
1,278.00
days
8.00
976.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B: Equipment Rental
1
unit 1 Bagger Concrete mixer
1
unit Concrete Vibrator

C. Labor:

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost
VII

SPL VII: Distribution Line (4,635 ln.m.)


Q=
4,635.00 ln.m.

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

Note: Slope correction and wastage factor of 20% Applied

A. Material:
150mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
100mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
75mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
63mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
50mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
13mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Fitting:
connector:
150mm CI Tee 150 x 150mm F/F w/ bolt & nuts
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts
150mm CI 90" elbow F/F w/ bolt & nuts
75mm CI 90" elbow F/F w/ bolt & nuts
50mm CI 90" elbow F/F w/ bolt & nuts
150mm CI 45" elbow F/F w/ bolt & nuts
75mm CI 45" elbow F/F w/ bolt & nuts
6

pcs

18.00

6,784.00

pcs

33.00

3,016.00

pcs

823.00

2,011.00

pcs

49.00

1,412.00

pcs

69.00

986.00

pcs

46.00

450.00

pc
pc
pc
pc
pc
pc
pc

4.00
10.00
5.00
3.00
7.00
3.00
14.00

3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00

DETAILED APPROVED AGENCY ESTIMATE


Item/Description

Unit

50mm CI 45" elbow F/F w/ bolt & nuts


Adaptor:
150mm CI Adaptor MJ/F
100mm CI Adaptor MJ/F
75mm CI Adaptor MJ/F
50mm CI Adaptor MJ/F
Reducer:
150mm x 100mm CI Reducer F/F w/ bolts
and Nuts and gasket
100mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
150mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
Gate valve:
150mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
100mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
75mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
50mm CI angle Valve F/F NRS w/ bolts
nuts and gasket
75mm CI end caps
Eslon Solvent Cement 150g

Unit Cost

6.00

3,200.00

pc
pc
pc
pc

5.00
6.00
35.00
4.00

2,400.00
2,400.00
2,400.00
2,400.00

pc

4.00

2,600.00

pc

4.00

2,600.00

pc

3.00

2,600.00

pcs

3.00

5,903.00

pcs

4.00

4,950.00

pcs

5.00

3,340.00

pcs

4.00

2,800.00

9.00
41.00

1,086.00
270.00

pcs
cans

sub total

Quantity

pc

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor: (including pipe laying & embankment)


total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost

VIII

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

SPL VIII: Tapstand


Q=
25.00 units
A. Material:
13mm Ball Faucets (Toho Brand)
13mm Water Meter (Ever Brand)
13mm x 90 Elbow
13mm x 13mm G.I. Bell Reducer
13mm G.I. Ball Valves
19mm ID x 6.0m G.I Pipe Sch 40 w/ coupling
13mm ID x 6.0m G.I. Pipe sch 40 w/ coupling
13mm G.I. Union
25mm Wide thread tape
Padlock (Egret)
150mm ID x 19mmID C.I Saddle clamp
100mm ID x 19mmID C.I Saddle clamp
75mm ID x 19mmID C.I Saddle clamp
63mm ID x 19mmID C.I Saddle clamp
50mm ID x 19mmID C.I Saddle clamp
38mm ID x 19mmID C.I Saddle clamp
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
6mm x 1.22m x 2.44 Marine Plywood
#7.5cm CWN
#3.75 cm CWN
1/8"thk x 1.22 x 2.44 Steel Plate
100 pcs 2" x 2" x 10' Gem. Lumber
Sub total

pcs
25.00
240.00
pcs
25.00
2,500.00
pcs
173.00
56.00
pcs
29.00
45.00
pcs
29.00
180.00
pcs
55.00
618.00
pcs
29.00
525.00
pcs
29.00
45.00
rolls
58.00
45.00
pcs
25.00
150.00
pcs
2.00
1,200.00
pcs
5.00
1,260.00
pcs
14.00
1,140.00
pcs
4.00
990.00
pcs
5.00
948.00
pcs
2.00
780.00
bags
334.00
280.00
m
20.00
1,000.00
m
29.00
1,000.00
pcs
115.00
204.00
kgs
6.00
100.00
pcs
58.00
520.00
kgs
21.00
100.00
kgs
9.00
100.00
sht
6.00
3,780.00
bd.ft.
518.00
30.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

C. Labor:
total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
7

DETAILED APPROVED AGENCY ESTIMATE


Item/Description

Unit

Total Estimated Direct Cost (EDC)

Quantity

Unit Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

equipment
material
labor

Amount

756.6

236,250.00
236,250.00
236,250.00
236,250.00
473.731702

9,800.00
4,000.00
5,000.00
2,595.00
784.00
6,528.00
1,620.00
1,680.00
560.00
2,600.00
600.00
1,800.00
300.00
360.00
980.00
285.00
500.00
2,400.00
2,599.80
1,200.00

740.00
360.00
50.00
178.00
450.00
500.00
870.00
180.00
200,000.00
249,519.80

112,283.91
361,803.71
361,803.71
361,803.710000
9

3783

4539.6

Amount

220,000.00
220,000.00
200,000.00
20,000.00
220,000.00
220,000.00
220,000.000000

14,560.00
4,000.00
5,000.00
2,448.00
300.00
600.00
200.00
6,000.00
7,250.00

91,260.00
6,760.00
1,340.00
950.00
150.00
240.00
150.00
4,600.00
150.00
1,300.00
1,050.00
760.00
270.00
2,400.00
149,338.00

396,000.00

67,202.10
612,540.10

10

Amount
612,540.10
3,403.000556

0% Applied

142,500.00
1,110.00
2,100.00
1,575.00
147,285.00

66,278.25
213,563.25
213,563.25
606.713778

113,680.00
25,000.00
36,000.00
60,900.00
21,420.00
177,696.00
10,500.00
13,668.00
11,800.00
3,300.00
19,000.00
7,560.00
1,530.00
4,830.00
8,820.00
43,160.00
27,600.00
60,780.00

7,500.00
1,100.00
3,250.00
1,725.00
1,960.00
25,380.00
49,104.00
10,400.00
10,350.00
17,709.00
1,779.00
760.00
380.00
270.00
2,400.00

12,292.00
12,292.00
11

Amount
640.00
640.00
480.00
480.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
892,039.00

10,223.00
7,807.00
18,030.00

401,417.55
1,311,486.55
1,311,486.55
1,311,486.550000

0% Applied

122,112.00
99,528.00
1,655,053.00
69,188.00
68,034.00
20,700.00

12,800.00
32,000.00
16,000.00
9,600.00
22,400.00
9,600.00
54,040.00
12

Amount
19,200.00
12,000.00
14,400.00
84,000.00
9,600.00
10,400.00
10,400.00
7,800.00

17,709.00
19,800.00
16,700.00
11,200.00
9,774.00
11,070.00
2,445,108.00

1,100,298.60
3,545,406.60
3,545,406.60
764.920518

6,000.00
62,500.00
9,688.00
1,305.00
5,220.00
33,990.00
15,225.00
1,305.00
2,610.00
3,750.00
2,400.00
6,300.00
15,960.00
3,960.00
4,740.00
1,560.00
93,520.00
20,000.00
29,000.00
23,460.00
600.00
30,160.00
2,100.00
900.00
22,680.00
15,540.00
414,473.00

186,512.85
13

Amount
600,985.85
600,985.85
24,039.434000

414,030.00
4,497,762.80
2,190,243.26
7,102,036.06
7,102,036.06
-

14

15

16

17

18

19

20

Back-up Estimate
Project
Location

: Construction of One (1) unit Barangay Health Station


:Brgy San Pedro, Tungawan, ZSP

Item 802 - Excavation


Column Footing F 1
Column Footing F 2
Wall Footing
Septic Tank

21.46
0.8 m x
0.7
1.5

0.8 m x
0.7
0.4
3

0.9 m x
0.9
0.6
1.54

10.0
2.0
33.0

Item 802 - Embankment


Common borrow

5.3
5.3

5.3
1.4

0.130
0.120

5.3
5.3

5.3
1.4

0.040
0.025

0.8 m x
0.7
0.2 m x
0.2
0.4
5.3
5.3
1.2
0.2
0.2

0.2 m x
0.2
3.8 m x
3.8
0.2
5.3
1.4
2.7
0.2
0.2

4.51

Selected Gravel fill


1.24

Item 900 - Reinforced Concrete


Column footing F1
Column footing F2
Column C1
Column C2
Wall Footing
Floor Slab

9.24
0.8 m x
0.7
0.2 m x
0.2

Septic Floor slab


Roof Beam

Item 404 - Reinforcing steel


55.00 pcs
256.00 pcs
25.00 kgs
4.00 pcs
Item 704 - Masonry works
Zocallo 6" x 8" x 16"
Wall 1
4" x 8" x 16"

10.0
2.0
10.0
2.0
31.0
0.1
0.1
0.15
17.0
13.8

1239.22
12 mm x 6m Def bar =
10 mm x 6m Def bar =
# 16 GI tie wire =
Hack saw blade =

0.888
0.616

131.7
0.86
5.8

31
4.9

26.66
28.42 m -

3.36

Wall 2
4" x 8" x 16"
Wall 3
4" x 8" x 16"
Wall 4
4" x 8" x 16"
Comfort room
Septic vault
38 pcs - 3" x 2' Conc Baluster

3.8
5.8
3.8
3.8

4.9
4.9
4.9
2.1

18.62 m 31.44 m 21.64 m 15.96


11.7

4.56
7.17
7.17

127.78

Item 1027 - Cement Plaster Finish


Wall 1
4" x
Wall 2
4" x
Wall 3
4" x
Wall 4
4" x
Comfort room
Septic vault

8"
8"
8"
8"

x
x
x
x

16"
16"
16"
16"

211.88
5.8
3.8
5.8
3.8
3.8

Item 1002 - Plumbing works


Kitchen Sink
Lavatory
Water Closet Ord.
4" Clean Out
4" x 2" PVC Sanitary Wye
4" x 2" PVC Sanitary Wye
4" x 2" PVC Sanitary Tee
4" x 90 PVC Sanitary Elbow
2" x 90 PVC Sanitary Elbow
4" x 3.0 m PVC Sanitary Pipe (Series 900)
2" x 3.0 m PVC Sanitary Pipe (Series 900)
4" x 45 PVC Sanitary Elbow
4" x 4" PVC Sanitary Tee
2" PVC Sanitary P - Trap
Solvent Cement
"
"
"
"
"
"
"

Stainless Faucet
Shower head
Shower Valve
x 90 PVC blue elbow
PVC Tee
PVC Coupling
x 3.0m PVC Blue pipe

4.9
4.9
4.9
4.9
2.1

56.84 m
37.24 m
59.86 m
40.26 m
31.92
11.7

3.36
4.56
7.17
7.17

" P.E. Pipe SDR 11


Tefflon Tape
Item 1003 - Carpentry and Joinery works
13 pcs - 2" x 6" x 10' - Gem. Lumber
20 pcs- 2" x 6"x 8' Gem.
4 pcs- 2" x 4"x 8' Gem.
47 pcs- 2" x 4"x 10' Gem.
15 pcs- 1"x12"x 12' Gem.
15 kgs - CWN Assorted

SPL I - Ceiling Works


Ceiling area =
76 pcs - 2" x 2" x 12' - Gem. Lumber
60 pcs- 1" x 1"x 8' Gem.
" thk. Ord. Plywood
Concrete nail
CWN Assorted

Item 1032 - Painting Works


Roofing
Walling
Ceiling
Doors & Window jamb
Total Area
Roof master
Flatwall latex paint
Gloss latex paint
Concrete neutralizer
Acri-color
Patching cement
Flatwall enamel paint
Gloss enamel paint
Easy tite w/ hardiner
Tinting color
Paint thinner
7" Paint roller w/ plate
4" paint brush
2" Paint brush
Masking tape 2"
Sand paper
Item 1010 - Wooden doors & windows
Wooden doors & Windows area =

34 pc - 2" x 6" x 8' Gemelina


19 pcs - 2" x 4 " x 8' Gemelina
" thk ord. plywood
CWN assorted
Loose pin hinges
Door knob (eagle)
Item 1009 - Glass Jalousie window
Glass jalousie window
1.2 x 0.60m Glass Jalousie window
0.6 x 0.6m Glass Jalousie window

Item 1013 - Corr. Metal roofing


Roof area =

Prepared by:

Checked by:

NMJ CONSTRUCTION & SUPPLIES


Contractor

MARVIN A. MUYARGAS
Project In-Charge

Approved by :

ROMEO C. ESTOQUIA
Chief, Construction Division

units =
units =
mtrs

5.760 m
0.88
7.92
6.93
21.492

7.4
2.9
8.8
5
9
33.1

thk

3.65
0.89
4.54 m (Compacted volume)
5.45 m ( loose volume )

thk

1.12
0.19
1.31 m (Compacted volume)
1.57 m ( loose volume )

units
units
units
units
mtrs
thk

=
=
=
=

/m
/m

1.280 m
0.2
1.520 m
0.3
2.48
2.81
0.74
0.49
0.68
0.55
11.049

3
6.2
11
5.5

3
12.4
9.8
5.9
31.1

16.5

293.04 kgs
946.18 kgs
25.00 kgs

5.33
3.7

1,264.22 kgs
333.25

26.66
25.06

2.8

6.05
3.03
4.9 16.75

14.06
24.27
14.47
15.96
11.7

2.28
0.72
1.89
3.51
1.56

1319
105.52
132.18

53.48
32.68
52.69
33.09
31.92
11.7
215.56
215.56

1.00 pc
1.00 pc
1.00 pc
4.00
3.00
1.00
2.00
5.00
8.00
3.00
2.00
1.00
1.00
2.00
1.00

pcs
pcs
pc
pcs
pcs
pcs
pcs
pcs
pc
pc
pcs
can

2.00
1.00
1.00
5.00
3.00
5.00
4.00

pcs
pc
pc
pcs
pcs
pcs
pcs

4.56
0.72
1.89
7.02
4.68
11.70

15.00 pcs
1.00 roll

130.00
160.00
21.33
235.00
180.00

bd.ft.
bd.ft.
bd.ft.
bd.ft.
bd.ft.

726.33 bd.ft.

67.5 sq.m.
304.00
40.00
23.00
0.50
9.00

bd.ft.
bd.ft.
pcs
kgs
kgs

72.54
211.88
67.50
16.22
368.14

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

5.00
8.00
8.00
1.00
4.00
15.00
3.00
3.00
1.00
4.00
2.00
1.00
4.00
4.00
1.00
15.00

gals
gals
gals
gals
pints
kgs
gals
gals
lit
pints
gals
sets
pcs
pcs
roll
pcs

28.82 sq.m.

A. MUYARGAS
ct In-Charge

C. ESTOQUIA
nstruction Division

272.00
101.33
4.00
8.00
5.00
3.00

bd.ft.
bd.ft.
pcs
kgs
pair
set

15.48 sq.m.
15.82
0.36

72sq.m.

Republic of the Philippines


PROVINCE OF ZAMBOANGA SIBUGAY
PROVINCIAL ENGINEERS OFFICE
Sanito, Ipil, Zamboanga Sibugay

Name of Project:

INDIVIDUAL PROGRAM OF WORKS


Proposed Const. Additional Ward - IDH

Location: Sanito, Ipil, Zamboanga Sibugay


Date:
May 24, 2005
Implementation Procedure: By Contract
LIMITS:
PROJECT DESCRIPTION:
Proposed const. of Additional Ward - IDH w/ Item 802 V=30.43 m
Item 404 Wt = 2,388.70kgs, Item 704 A= 160.0m,Item 1002, item 1010 A=38.77m,Item 1003 A=
Item 1018 A= 445.25m, Item 1005 A= 3.68m, Item 1100
MINIMUM LABOR & EQUIPMENT REQUIRED:
DESCRIPTION
NO.
DESCRIPTION
NO.
DESCRIPTION
Civil Engineer
Electrician
1
Welder
Material Engineer
Mason
4
Tile sitter
Const. Foreman
1
Carpenter
2
Plumber
MLT
Steelman
2
Labor
ESTIMATED COST OF PROPOSED PROJECT:
ITEM NO.

SPL I

DESCRIPTION

% of Total

802 Excavation
804 Embankment
900 Reinforced Concrete
404 Reinforcing Steel
704 Masonry Works
1002 Plumbing Works
1010 Wooden Doors & Windows
1003 Carpentry & Joinery Work
1013 Corr. Metal Roofing
1018 Tile Work
1005 Steel window Casement
1100 Electrical Works
Furn. & instal of billboards
TOTAL

BREAKDOWN OF ESTIMATED EXPENDITURES


I. ESTIMATED COST:
A. DIRECT COST:
1. Materials
1.1 Supply/Delivery
1.2 Testing Materials
2. Labor (Including Fringe Benefits)
3. Equipment Expenses
3.1 Rental
3.2 Fuel & Lubricant
Total Direct Cost
B. INDIRECT COST
1. Overhead Contingency Misc.
2. Profit

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Unit

QTY

cu.m.
cu.m.
cu.m.
kgs.
sq.m.
L. S.
sq.m.
bd.ft.
sq.m.
sq.m.
sq.m.
L. S.
l.s

1.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

3. Mobilization/Demobilization (1% of EDC)


4. Value Added Tax (10% of A2 to A3.1)
5. Furnishing & Installation of Billboards
Total Indirect Cost
TOTAL AMOUNT BUDGET FOR THE CONTRACT (ABC)
II. ESTIMATED GOVERNMENT EXPENDITURES:
1. Eng'g & Administrative Overhead (3.5% of EDC )
2. ROW/Site Acquisition
3. Materials to be furnished by the Gov't 1% of ABC
4. Preliminary and Detailed engineering
TOTAL
III. CONTINGENCIES/RESERVES:
1. Physical (Up to 5% of the Estimated Contract Cost)
2. Price escalation (Up to 12% of the estimated contract cost)
3. Technical Requirements for survey investigation of
Infrastructure Projects)
Sub total III
TOTAL ESTIMATED PROJECT COST
Prepared by:

Checked by:
ARNALDO I. BEUP Jr.
Engineering Asst.

Recommended by:
ABDURAJIK H. MAULOD,MPA
Provincial Engineer

EDGAR M. ETAC
Engineer III

ippines
GA SIBUGAY
RS OFFICE
a Sibugay
OF WORKS
Appropriation:
P 750,000.00
Source of fund:
20% LDF - 2004
Issued Obligated Authority:
Calendar Days to Complete: W.D
Desirable Starting Date: ASAP

d - IDH w/ Item 802 V=30.43 m, Item 804 V=48.50m,Item 900 V=25.99m


1010 A=38.77m,Item 1003 A= 1,521.99m, Item 1013 A = 225.70m

DESCRIPTION
Welder
Tile sitter
Plumber
Labor

NO.
1
2
1
6

Direct Cost
Total
361,803.71
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Unit Cost
###
#REF!
#REF!
#REF!
#REF!

#REF!

% OF TOTAL

#REF!
#REF!
#REF!
#REF!
#REF!

DESCRIPTION NO.
Welding Machine - 1
Grinding Machine - 1

Adjusted Unit
Direct + Indirect
Cost
cost
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
3,000.00
#REF!

AMOUNT

599.70

4,497,762.80

0.00
292.03

2,190,243.26

55.204

414,030.00

946.94

7,102,036.06

104.16
113.63

781,223.97
852,244.33

#REF!

9.469
117.42
0.40
1292.02

71,020.36
880,652.47
3,000.00
2,588,141.13
9,690,177.19

33.14

248,571.26

12.920
3.000
49.06

96,901.77
22,500.00
367,973.03

-1241.09

100

(9,308,150.22)

750,000.00

Submitted by:
ROMEL G. DURAN
Engineer IV
Chief, P P D D
Approved by:
GEORGE T. HOFER, MD
Provincial Governor

ADJUSTED PRICE
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
Mindanao Rural Developement Program-Phase II
San Jose, Imelda, Zamboanga Sibugay
PROJECT
LOCATION

:
:

Water Supply System Level II at San jose


San Jose, Imelda, ZSP
DETAILED APPROVED AGENCY ESTIMATE
Item/Description

Spl I: Trench Excavation


Q=
498.70 cu.m

Unit

Note: Slope correction and wastage factor of 20% Applied

Transmission line L = 352.0 ln.m.


Distribution Line L = 4635 ln.m.
Total
A. Labor:
15.0

V=
V=

Laborer

35.20 cu.m.
463.50 cu.m.
498.70 cu.m.

days
total

Total Estimated Direct Cost (EDC)


Direct Cost
Unit Cost
II

Quantity

45.00

>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL II: Construction of of Pump house (1 unit)


Q=
1.000 unit
A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
4" x 8" x 16" CHB
4" x 8" x 4" Fixed Louver
10mm x 6.0m Def. Bars
8mm x 6.0m Def. bars
0.90m x 2.45m Corr. G.I. Sheet Ga #26 Roofing
0.90m x 2.45m Plain G.I. Sheet ga.#26 ridge roll
6mm x 1.22m x 2.44 Marine Plywood
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire

bags
m
m
pcs
pcs
pcs
pcs
pcs
pc
pcs
kgs
kgs
kgs

35.00
4.00
5.00
173.00
28.00
32.00
18.00
6.00
2.00
5.00
6.00
18.00
3.00

#7.75cm Roofing nails ( umbrella type)


Door Knob Yale
3/16" x 4" hinges
Vulcaseal
10pcs 2" x 4" x 10' Gem. Lumber
11pcs 2" x 4" x 10' Gem. Lumber
5 pcs 1" x 8" x 10' Gem Lumber
B. Electrical
25mm ID x 3.0m PVC Pipe
25mm ID x 90 PVC bend
25mm ID male threaded adaptor
25mm ID entrance cap
25mm PVC Clip
Solvent Cement Eslon blue 150G
12mm TW stranded wire
Electrical tape
50 Kva Transformer
Sub total

kgs
set
pair
can
bd.ft.
bd.ft.
bd.ft.

3.00
1.00
3.00
2.00
80.00
86.66
40.00

pcs
4.00
pcs
10.00
pcs
2.00
pcs
2.00
pcs
18.00
can
2.00
mtr
10.00
roll
2.00
pc
1.00
>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
III

>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL III: Installation of Submersible Pump


Q=
1.00 unit

A. Material
Goulds submersible Pump Stainless Steel
casing close coupled to a 4.5 HP 1 phase 230v
60 Hz, Franklin submersible motor, with built-in
lighting protection, original brand new, made in USA
to include the foll.
- Motor lead assy
- Built-in check valve and strainer
190ft. Submersible cable wire no.14
380ft Suspension wire No.14
- Panel board metal enclosure consist of the
foll.
- magnetic starter w/ overload
B/W Water level cut-off control w/ levelelectrodes
- on/off push button switch
- lightning arrester
1 set water roof splicing tape
1.00 unit
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor:
total
Direct Cost
Unit Cost
IV

SPL IV: Drilling (180ft depth)


Q=
180.00 ft.

>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

Note: Including peremeter fence

A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire
Gravel (25mm in size) Gravel packing
burb wire

bags
m
m
pcs
kgs
kgs
kgs
cu.m.
m

52.00
4.00
5.00
12.00
3.00
6.00
2.00
6.00
290.00

Pipes:
150mm x 6.0m uPVC Pipe Class 150 (casing)
pcs
13.00
38mm x 6.0m G.I. Pipe sch 40 w/ coupling (suction)
pcs
13.00
"thk x 20mm x 38mm discharge plate
pcs
2.00
5/8" x 12" Stainless bolt w/ nut
pcs
5.00
38mm x 90 G.I. elbow
pcs
2.00
38mm G.I. Tee
pcs
3.00
38mm x 13mm G.I. bushing reducer
pcs
2.00
Pressure gauge
pcs
2.00
38mm G.I. Union
pcs
2.00
38mmx 0.20m G.I. Nipple threaded sch 40
pcs
10.00
38mm G.I. Gate Valve
pcs
3.00
38mm G.I. Swing Check Valve
pcs
2.00
25mm Wide thread tape
pcs
6.00
50mm GI Water meter
pc.
1.00
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>
B: Equipment Rental
Driling machine 180ft drill halo w/
casing installation

feet

180.00

C. Labor:
total
Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost
V

SPL V: Transmission Line (352 ln.m.)


Q=
352.00 ln.m.
A. Material:
50mm
50mm
50mm
25mm

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

Note: Slope correction and wastage factor of 20%

ID x 6.0m G.I. Pipe sch. 40 w/ coupling


x 45 G.I. Elbow
G.I. Union
Wide Thread tape
Sub total

pcs
75.00
pcs
6.00
pcs
12.00
pcs
35.00
>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor: (including pipe laying & embankment)


total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost

VI

>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL VI: Cylindrical Storage Tank (24,000.0 liters cap)


Q=
1 unit
A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
Sahara Cement
16mm x 6.0m Def. bars
12mm x 6.0m Def. Bars
12mm x 6.0m Stainless steel
10mm x 6.0m Def. Bars
#16 Tie Wire
#3.75 cm CWN
#10.02cm CWN
1/8"thk x 1.22 x 2.44 Steel Plate
Hacksaw Blade
Shovel
Welding Rod
6mm x 1.22m x 2.44 Marine Plywood
100 pcs 2" x 4" x 12' Gem. Lumber
528 pcs 2" x 2" x 10' Gem. Lumber

bags
m
m
pcs
pcs
pcs
pcs
pcs
kgs
kgs
kgs
sht
pcs
pcs
box
pcs
bd.ft.
bd.ft.

Plumbing:
150mm ID x 0.50m G.I. Nipple Threaded sch 40 pcs
150mm G.I. Elbow 45
pcs
100mm ID x 0.50 G.I. Nipple Threaded sch 40
pcs

406.00
25.00
36.00
406.00
42.00
617.00
5.00
67.00
118.00
33.00
190.00
2.00
18.00
7.00
3.00
83.00
920.00
2,026.00

10.00
5.00
5.00

75mm ID c 0.20m G.I. Nipple Threaded sch 40


50mm ID x 0.30m G.I. Nipple Threaed sch 40
150mm CI Gate Valve MJ/F NRS w/ bolts and
nuts & Gasket
150mm CI Adaptor MJ/F NRS w/ bolts and
nuts & Gasket
150mm CI Tee 150mm x 150mm F/F w/ bolts
and nuts
150mm CI 90 F/F w/ bolts and nuts
100mm G.I. Gate Valve screw end
75mm GI Elbow 90
50mm GI Elbow 90
50mm GI Union
25mm Wide Thread tape
50mm Water meter

C: Painting:
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
Blue Tinting color DB
Yellow tinting color DB
Green Tinting color DB
Black Tinting color DB
paint Roller w/ tray 7"
paint Roller 7" Foam
paint roller 6" w/ handle
paint roller 4" w/ handle
Epoxy Primer Gray
Epoxy Primer Yellow
Epoxy Strong Hold RSC
Epoxy Fortress
Reducer
QDE Paint Blue
Lettering Brush
L.T Primer White
L.T Reducer
L.T Semigloss White
L.T Cast
Paint Thinner
Lacquer Thinner
Easytite
Concrete Nuetralizer
Patching Compound
Paint tray
Paint Brush 3"
Paint Brush 2 1/2"

pcs
pcs

3.00
4.00

pcs

4.00

pcs

9.00

pcs
pcs
pcs
pcs
pcs
pcs
roll
pc.

2.00
3.00
3.00
2.00
4.00
2.00
6.00
1.00

gal
gal
pint
pint
pint
pint
set
pcs
pcs
pcs
gal
gal
gal
gal
gal
gal
pcs
gal
gal
gal
gal
gal
gal
gal
lit
gal
pcs
pcs
pcs

14.00
14.00
4.00
4.00
3.00
3.00
4.00
5.00
3.00
8.00
10.00
11.00
4.00
5.00
2.00
10.00
4.00
16.00
14.00
5.00
6.00
7.00
10.00
4.00
4.00
30.00
5.00
3.00
3.00

paint brush
Sand Paper
Sand Paper
Sand Paper
Putty Knife

2"
# 120
# 600
# 80
Sub total

B: Equipment Rental
1
unit 1 Bagger Concrete mixer
1
unit Concrete Vibrator
total

pcs
17.00
pcs
54.00
pcs
11.00
ft
13.00
pairs
4.00
>>>>>>>>>>>>>>>>>>>>>>>>

days
8.00
days
8.00
>>>>>>>>>>>>>>>>>>>>>>>>

C. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
VII

SPL VII: Distribution Line (4,635 ln.m.)


Q=
4,635.00 ln.m.
A. Material:
150mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
100mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
75mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
63mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
50mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
13mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring

>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

Note: Slope correction and wastage factor of 20%

pcs

18.00

pcs

33.00

pcs

823.00

pcs

49.00

pcs

69.00

pcs

46.00

Fitting:
connector:
150mm CI Tee 150 x 150mm F/F w/ bolt & nutspc
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts
pc
150mm CI 90" elbow F/F w/ bolt & nuts
pc
75mm CI 90" elbow F/F w/ bolt & nuts
pc
50mm CI 90" elbow F/F w/ bolt & nuts
pc
150mm CI 45" elbow F/F w/ bolt & nuts
pc
75mm CI 45" elbow F/F w/ bolt & nuts
pc
50mm CI 45" elbow F/F w/ bolt & nuts
pc
Adaptor:
150mm CI Adaptor MJ/F
pc
100mm CI Adaptor MJ/F
pc

4.00
10.00
5.00
3.00
7.00
3.00
14.00
6.00
5.00
6.00

75mm CI Adaptor MJ/F


50mm CI Adaptor MJ/F
Reducer:
150mm x 100mm CI Reducer F/F w/ bolts
and Nuts and gasket
100mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
150mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
Gate valve:
150mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
100mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
75mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
50mm CI angle Valve F/F NRS w/ bolts
nuts and gasket
75mm CI end caps
Eslon Solvent Cement 150g
sub total

pc
pc

35.00
4.00

pc

4.00

pc

4.00

pc

3.00

pcs

3.00

pcs

4.00

pcs

5.00

pcs

4.00

pcs
cans

9.00
41.00

>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor: (including pipe laying & embankment)


total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost

VIII

>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL VIII: Tapstand


Q=
25.00 units
A. Material:
13mm Ball Faucets (Toho Brand)
13mm Water Meter (Ever Brand)
13mm x 90 Elbow
13mm x 13mm G.I. Bell Reducer
13mm G.I. Ball Valves
19mm ID x 6.0m G.I Pipe Sch 40 w/ coupling
13mm ID x 6.0m G.I. Pipe sch 40 w/ coupling
13mm G.I. Union
25mm Wide thread tape
Padlock (Egret)
150mm ID x 19mmID C.I Saddle clamp
100mm ID x 19mmID C.I Saddle clamp
75mm ID x 19mmID C.I Saddle clamp

pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
rolls
pcs
pcs
pcs
pcs

25.00
25.00
173.00
29.00
29.00
55.00
29.00
29.00
58.00
25.00
2.00
5.00
14.00

63mm ID x 19mmID C.I Saddle clamp


50mm ID x 19mmID C.I Saddle clamp
38mm ID x 19mmID C.I Saddle clamp
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
6mm x 1.22m x 2.44 Marine Plywood
#7.5cm CWN
#3.75 cm CWN
1/8"thk x 1.22 x 2.44 Steel Plate
100 pcs 2" x 2" x 10' Gem. Lumber
Sub total

pcs
4.00
pcs
5.00
pcs
2.00
bags
334.00
m
20.00
m
29.00
pcs
115.00
kgs
6.00
pcs
58.00
kgs
21.00
kgs
9.00
sht
6.00
bd.ft.
518.00
>>>>>>>>>>>>>>>>>>>>>>>>

C. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost

>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

equipment
material
labor

RICE

URE
ram-Phase II
bugay

TIMATE
Unit Cost

Amount

actor of 20% Applied

250.00

168,750.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
168,750.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
168,750.00
168,750.00
338.379787

Estimated Volume)

250.00
750.00
800.00
12.00
12.00
170.00
90.00
250.00
250.00
345.00
90.00
90.00
90.00

8,750.00
3,000.00
4,000.00
2,076.00
336.00
5,440.00
1,620.00
1,500.00
500.00
1,725.00
540.00
1,620.00
270.00

120.00
850.00
95.00
250.00
24.00
24.00
24.00

360.00
850.00
285.00
500.00
1,920.00
2,079.84
960.00

185.00
740.00
15.00
150.00
18.00
36.00
25.00
50.00
8.00
144.00
120.00
240.00
87.00
870.00
90.00
180.00
200,000.00
200,000.00
>>>>>>>>>>>>>>>>>>>>>>> 240,741.84

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
108,333.83

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
349,075.67

Estimated Volume)

349,075.67
349,075.668000

220,000.00
220,000.00
>>>>>>>>>>>>>>>>>>>>>>> 220,000.00

material
labor

200,000.00
20,000.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
220,000.00
220,000.00
220,000.000000

Estimated Volume)

250.00
750.00
800.00
170.00
90.00
90.00
90.00
800.00
25.00

13,000.00
3,000.00
4,000.00
2,040.00
270.00
540.00
180.00
4,800.00
7,250.00

2,175.00
28,275.00
520.00
6,760.00
450.00
900.00
160.00
800.00
75.00
150.00
80.00
240.00
75.00
150.00
2,300.00
4,600.00
75.00
150.00
130.00
1,300.00
350.00
1,050.00
380.00
760.00
45.00
270.00
800.00
800.00
>>>>>>>>>>>>>>>>>>>>>>> 80,485.00

2,200.00

396,000.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
36,218.25

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
512,703.25

512,703.25
2,848.351389

Estimated Volume)

d wastage factor of 20% Applied

1,900.00
142,500.00
185.00
1,110.00
175.00
2,100.00
45.00
1,575.00
>>>>>>>>>>>>>>>>>>>>>>> 147,285.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
66,278.25

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
213,563.25
213,563.25
606.713778

Estimated Volume)

280.00
750.00
800.00
120.00
380.00
240.00
2,100.00
170.00
90.00
90.00
90.00
1,350.00
85.00
450.00
2,940.00
345.00
24.00
24.00

750.00
220.00
650.00

113,680.00
18,750.00
28,800.00
48,720.00
15,960.00
148,080.00
10,500.00
11,390.00
10,620.00
2,970.00
17,100.00
2,700.00
1,530.00
3,150.00
8,820.00
28,635.00
22,080.00
48,624.00

7,500.00
1,100.00
3,250.00

575.00
490.00

2,150.00
1,450.00
2,500.00
215.00
190.00
190.00
45.00
800.00

1,725.00
1,960.00
12,000.00
22,500.00
4,300.00
4,350.00
7,500.00
430.00
760.00
380.00
270.00
800.00

520.00
520.00
120.00
120.00
120.00
120.00
250.00
20.00
48.00
54.00
600.00
186.00
2,630.00
4,050.00
908.00
780.00
12.00
720.00
405.00
894.00
478.00
216.00
216.00
312.00
95.00
24.00
30.00
42.00
48.00

7,280.00
7,280.00
480.00
480.00
360.00
360.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00

3,000.00
2,500.00

75.00
1,275.00
13.00
702.00
14.00
154.00
37.00
481.00
42.00
168.00
>>>>>>>>>>>>>>>>>>>>>>> 711,078.00

1,278.00
10,223.00
976.00
7,807.00
>>>>>>>>>>>>>>>>>>>>>>>>>>
18,030.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
319,985.10

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
1,049,093.10
1,049,093.10
1,049,093.100000

Estimated Volume)

d wastage factor of 20% Applied

4,975.00

89,550.00

2,337.00

77,121.00

1,550.00

1,275,650.00

1,076.00

52,724.00

758.00

52,302.00

450.00

20,700.00

1,500.00
1,500.00
1,500.00
1,500.00
1,500.00
1,500.00
1,860.00
1,500.00

6,000.00
15,000.00
7,500.00
4,500.00
10,500.00
4,500.00
26,040.00
9,000.00

1,200.00
1,200.00

6,000.00
7,200.00

1,200.00
1,200.00

42,000.00
4,800.00

1,300.00

5,200.00

1,300.00

5,200.00

2,600.00

7,800.00

2,800.00

8,400.00

2,800.00

11,200.00

1,000.00

5,000.00

2,800.00

11,200.00

1,000.00
120.00

9,000.00
4,920.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
1,779,007.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
800,553.15

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
2,579,560.15
2,579,560.15
556.539407

Estimated Volume)

125.00
1,950.00
25.00
35.00
40.00
480.00
395.00
25.00
45.00
130.00
1,200.00
1,050.00
950.00

3,125.00
48,750.00
4,325.00
1,015.00
1,160.00
26,400.00
11,455.00
725.00
2,610.00
3,250.00
2,400.00
5,250.00
13,300.00

825.00
790.00
650.00
250.00
750.00
800.00
170.00
90.00
345.00
90.00
90.00
1,350.00
24.00
>>>>>>>>>>>>>>>>>>>>>>>

3,300.00
3,950.00
1,300.00
83,500.00
15,000.00
23,200.00
19,550.00
540.00
20,010.00
1,890.00
810.00
8,100.00
12,432.00
317,347.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
142,806.15

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
460,153.15

Estimated Volume)

460,153.15
18,406.126000

414,030.00
3,475,943.84
1,662,924.73
5,552,898.57
5,552,898.57
-

Republic of the Philippines


DEPARTMENT OF AGRICULTURE
Mindanao Rural Developement Program-Phase II
San Jose, Imelda, Zamboanga Sibugay
PROJECT
LOCATION

:
:

Water Supply System Level II at San jose


San Jose, Imelda, ZSP
DETAILED APPROVED AGENCY ESTIMATE
Item/Description

1600

Trench Excavation
Q=
587.04 cu.m

Unit

Unit Cost

Note: Slope correction and wastage factor of 20% Applied

Transmission line L = 352.0 ln.m.


Distribution Line L = 3783 ln.m.
(Slope correction and wastage factor of 20% Applied)
Total
A. Manpower:
Foreman
Laborer

V=
V=
V=

1.00
14.00

total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
II

Quantity

35.20
454.00
97.84
587.04

days
days

cu.m.
cu.m.
cu.m.
cu.m.

17.00
17.00

360.00
200.00

>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL II: Construction of of Pump house (1 unit)


Q=
1.000 unit
A. Material:
Portland Cement
Washed Sand
Washed Gravel
4" x 8" x 16" CHB
6" x 6" Fixed Louver
10 mm x 6 m. Def. bars
8 mm x 6 m. Def. bars
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Roofing
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Ridge Roll
6 mm x 1.22 x 2.44 Marine Plywood
#3.75 CW Nails
#10.02 Cw Nails
#16 Tie Wire
#7.75 cm Roofing Nails umbrella type
Pre-Fab Plastic Door
Vulcaseal
10 pcs-2"x3"x10' Lumber Gem.
5 pcs-2"x4"x10' Lumber Gem.
4 pcs-1" x 8" x 10' Lumber Gem.
50 pcs-2"x2"x10'
B. Electrical
25mm ID x 3.0m PVC Pipe
25mm ID x 90 PVC bend
25mm ID male threaded adaptor
25mm ID entrance cap
25mm PVC Clip
Solvent Cement Eslon blue 150G
12mm TW stranded wire
Electrical tape
37.5 Kva Distribution Transformer
Cut-out w/ Lightning arrester 9 KV
6 mm Aluminum Service Entrance Drop Wire
Panel board 4-Branches
100 AT Double Throw Circuit Breaker
60 AT Double Throw Circuit Breaker
30 AT Double Throw Circuit Breaker
15 AT Double Throw Circuit Breaker
#10TW Copper Wire (Stranded)
Kilo-Watt Meter
Sub total

bags
cu.m.
cu.m.
pcs
pcs
pcs
pcs
shts
shts
shts
kgs
kgs
kgs
kgs
unit
can
bdft
bdft
bdft
bdft

pcs
pcs
pcs
pcs
pcs
can
mtr
roll
unit
unit
mtrs
unit
pc
pc
pc
pc
mtrs
unit

25.00
2.00
2.50
147.00
24.00
15.00
5.00
4.00
1.00
10.00
5.00
15.00
2.00
2.00
1.00
1.00
50.00
33.33
26.67
166.67

280.00
1,000.00
1,000.00
15.00
30.00
204.00
90.00
280.00
280.00
520.00
100.00
100.00
100.00
120.00
2,500.00
250.00
30.00
30.00
30.00
30.00

4.00
10.00
2.00
2.00
18.00
2.00
10.00
2.00
1.00
1.00
300.00
1.00
1.00
1.00
1.00
1.00
30.00
1.00

185.00
36.00
25.00
89.00
25.00
250.00
87.00
90.00
125,000.00
12,000.00
40.00
700.00
2,800.00
350.00
350.00
280.00
25.00
2,700.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
III

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL III: Installation of Submersible Pump


Q=
1.00 unit
A. Material
Goulds submersible Pump Stainless Steel
casing close coupled to a 4.5 HP 1 phase 230v
60 Hz, Franklin submersible motor, with built-in
lighting protection, original brand new, made in USA
to include the foll.
- Motor lead assy
- Built-in check valve and strainer
190ft. Submersible cable wire no.14
380ft Suspension wire No.14
- Panel board metal enclosure consist of the
foll.
- magnetic starter w/ overload
B/W Water level cut-off control w/ levelelectrodes
- on/off push button switch
- lightning arrester
1 set water roof splicing tape
1.00 unit
220,000.00
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
material
labor
B. Labor:
total
Direct Cost
Unit Cost

IV

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL IV: Drilling (180ft depth) and Pumping Station


Q=
180.00 ft.
Note: Including peremeter fence
A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire
Gravel (25mm in size) Gravel packing
Barb Wire
Pipes:
150mm x 6.0m uPVC Pipe Class 150 (casing)
38mm x 6.0m G.I. Pipe sch 40 w/ coupling (suction)
"thk x 20mm x 38mm discharge plate
5/8" x 12" Stainless bolt w/ nut
50mm ID x 0.8m GI Pipe Sch.40
32mm ID x 6m GI Pipe Sch. 40 w/ coupling
50mm ID x 32mm GI Pipe bell Reducer
50mm GI Union
50mmGI Swing Check Valve
Pressure Gauge
50mm x 19 mm GI bell reducer
50mm GI Tee
50mm CI Gate Valve
50mmx0.20 m GI Nipple sch. 40
50mmx0.30 m GI Nipple Sch. 40
50mm ID x 45 GI Elbow sch.40
25mm Wide thread tape
50mm CI Water meter
Sub total
B: Equipment Rental
Driling machine 180ft drill hole w/
casing installation

bags
m
m
pcs
kgs
kgs
kgs
cu.m.
m

220.00
14.00
28.00
45.00
5.00
15.00
5.00
6.00
290.00

280.00
1,000.00
1,000.00
204.00
100.00
100.00
100.00
1,000.00
25.00

pcs
13.00
7,020.00
pcs
13.00
624.00
pcs
2.00
670.00
pcs
5.00
190.00
pcs
1.00
3,200.00
pcs
5.00
2,950.00
pcs
1.00
450.00
pcs
1.00
75.00
pcs
1.00
380.00
pcs
1.00
2,300.00
pcs
1.00
450.00
pcs
2.00
80.00
pcs
1.00
2,800.00
pcs
5.00
170.00
pcs
3.00
170.00
pcs
1.00
180.00
pcs
6.00
45.00
pc.
1.00
30,000.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

feet

180.00

2,200.00

C. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
V

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL V: Transmission Line (352 ln.m.)


Q=
352.00 ln.m.
A. Material:
50mm
50mm
50mm
25mm

ID x 6.0m G.I. Pipe sch. 40 w/ coupling


x 45 G.I. Elbow
G.I. Union
Wide Thread tape
Sub total

pcs
73.00
1,900.00
pcs
6.00
185.00
pcs
5.00
175.00
pcs
20.00
45.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor: (including pipe laying & embankment)


total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
VI

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL VI: Cylindrical Storage Tank (60,000.0 liters cap)


Q=
1 unit
A. Material:
Portland Cement
Washed Sand
Washed Gravel
Sahara Cement
25mm x 6 m Def. Bar
20mm x 6 m Def. Bar
16mm x 6 m Def. Bar
16mm x 6 m Stainless Bar
3/16" x 6' Corrugated PVC Waterstop
Plain type
10mm x 6 m Def. bars
#16 Tie Wire
#3.75 cm CWN
# 10.02 cm CWN
19mm x 1.22m x 2.44 m Marine Plywood
6mm x 1.22m x 2.44m Marine Plywood
250 pcs-2"x4"12' lumber
780 pcs-2"x3"x12' Lumber
500 pcs-2"x2"x12'lumber
1/8"x1.22mx2.44m steel Plate
50mm Egret Padlock
Hacksaw Blade
Shovel
Welding rod

bags
cu.m
cu.m.
kgs
pcs
pcs
pcs
pcs
rolls
pcs
kgs
kgs
kgs
sht
sht
bdft
bdft
bdft
sht
pcs
pcs
pcs
kgs

465.00
25.00
45.00
200.00
80.00
220.00
310.00
4.00
3.00

280.00
1,000.00
1,000.00
150.00
850.00
750.00
510.00
2,520.00
7,500.00

185.00
150.00
50.00
175.00
20.00
68.00
2,000.00
4,680.00
2,080.00
1.00
2.00
24.00
6.00
2.00

204.00
100.00
100.00
100.00
520.00
350.00
30.00
30.00
30.00
3,780.00
250.00
85.00
690.00
170.00

Plumbing:
150mm CI Gate Valve F/F w/ bolt & nut
150mm CI Adaptor MJ/F w/ bolt & nut
150mm CI Tee F/F w/ bolt & nut
150mm G.I. Elbow 90 GI Elbow sch.40
150mm ID GI Union sch. 40
150mm IDx0.80m GI Nipple Threaded sch.40
150mm ID x 3.80m GI Nipple Threaded sch. 40
50mm IDx0.50m GI Nipple Threaded sch.40
50mm ID x 0.20m GI Nipple Threaded sch. 40
50mm G.I. Elbow 90 GI Elbow sch.40
50mm ID GI Union sch. 40
25mm Wide Thread Tape

pcs
pcs
pc
pcs
pc
pc
pc
pcs
pcs
pcs
pc
roll

2.00
3.00
1.00
2.00
1.00
1.00
1.00
6.00
2.00
4.00
1.00
5.00

6,345.00
5,456.00
5,200.00
220.00
570.00
750.00
5,700.00
575.00
490.00
190.00
190.00
45.00

C: Painting:
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
Blue Tinting color DB
Yellow tinting color DB
Green Tinting color DB
Black Tinting color DB
paint Roller w/ tray 7"
paint Roller 7" Foam

gal
gal
pint
pint
pint
pint
set
pcs

14.00
14.00
4.00
4.00
3.00
3.00
4.00
5.00

878.00
878.00
160.00
160.00
160.00
160.00
250.00
20.00

paint roller 6" w/ handle

pcs

3.00

48.00

paint roller 4" w/ handle


Epoxy Primer Gray
Epoxy Primer Yellow
Epoxy Strong Hold RSC
Epoxy Fortress
Reducer
QDE Paint Blue
Lettering Brush
L.T Primer White
L.T Reducer
L.T Semigloss White
L.T Cast
Paint Thinner
Lacquer Thinner
Easytite
Concrete Nuetralizer
Patching Compound
Paint tray
Paint Brush 3"
Paint Brush 2 1/2"
paint brush 2"
Sand Paper # 120
Sand Paper # 600
Sand Paper # 80
Putty Knife

pcs
8.00
54.00
gal
10.00
600.00
gal
11.00
186.00
gal
4.00
2,630.00
gal
5.00
4,050.00
gal
2.00
908.00
gal
10.00
780.00
pcs
4.00
12.00
gal
16.00
720.00
gal
14.00
405.00
gal
5.00
894.00
gal
6.00
478.00
gal
7.00
216.00
gal
10.00
216.00
gal
4.00
312.00
lit
4.00
95.00
gal
30.00
24.00
pcs
5.00
30.00
pcs
3.00
42.00
pcs
3.00
48.00
pcs
17.00
75.00
pcs
54.00
13.00
pcs
11.00
14.00
ft
13.00
37.00
pairs
4.00
42.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Sub total
B: Equipment Rental
1
unit 1 Bagger Concrete mixer
1
unit Concrete Vibrator
total

days
8.00
1,278.00
days
8.00
976.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

C. Labor:
total

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Direct Cost
Unit Cost
VII

SPL VII: Distribution Line (3,783 ln.m.)


Q=
3,783.00 ln.m.

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)

Note: Slope correction and wastage factor of 20% Applied

A. Material:
150mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
100mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
75mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
19mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Fitting:
connector:
150mm CI Tee 150 x 150mm F/F w/ bolt & nuts
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts
150mm CI 90" elbow F/F w/ bolt & nuts
75mm CI 90" elbow F/F w/ bolt & nuts
150mm CI 45" elbow F/F w/ bolt & nuts
75mm CI 45" elbow F/F w/ bolt & nuts
Adaptor:
150mm CI Adaptor MJ/F
100mm CI Adaptor MJ/F
75mm CI Adaptor MJ/F
50mm CI Adaptor MJ/F
Reducer:
150mm x 100mm CI Reducer F/F w/ bolts
and Nuts and gasket
100mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
150mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
Gate valve:
150mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
100mm CI Gate Valve F/F NRS w/ bolts

nuts and gasket


75mm CI Gate Valve F/F NRS w/ bolts

pcs

14.00

6,784.00

pcs

25.00

3,016.00

pcs

600.00

2,011.00

pcs

46.00

450.00

pc
pc
pc
pc
pc
pc

4.00
10.00
5.00
3.00
3.00
14.00

3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00

pc
pc
pc
pc

5.00
6.00
35.00
4.00

2,400.00
2,400.00
2,400.00
2,400.00

pc

4.00

2,600.00

pc

4.00

2,600.00

pc

3.00

2,600.00

pcs

1.00

5,903.00

pcs

1.00

4,950.00

pcs

7.00

3,340.00

nuts and gasket


50mm CI angle Valve F/F NRS w/ bolts
nuts and gasket
75mm CI end caps
75mm CI TEE
75mm CI Adaptor MJ/F
75 x 50 mm Reducer
50mm CI Gate Valve
50mm CI Adaptor MJ/F
50mm uPVC Elbow
Fire Hydrant 50mm w/ accessories
Eslon Solvent Cement 150g
sub total

pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
units
cans

3.00

2,800.00

9.00
6.00
6.00
3.00
3.00
6.00
3.00
3.00
20.00

1,086.00
3,200.00
2,400.00
2,600.00
3,000.00
2,400.00
3,200.00
14,250.00
270.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B. Labor: (including pipe laying & embankment)


total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
VIII

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

SPL VIII: Tapstand


Q=
19.00 units
A. Material:
13mm Ball Faucets (Toho Brand)
13mm Water Meter (Ever Brand)
13mm x 90 Elbow
13mm x 13mm G.I. Bell Reducer
13mm G.I. Ball Valves
19mm ID x 6.0m G.I Pipe Sch 40 w/ coupling
13mm ID x 6.0m G.I. Pipe sch 40 w/ coupling
13mm G.I. Union
25mm Wide thread tape
Padlock (Egret)
150mm ID x 19mmID C.I Saddle clamp
100mm ID x 19mmID C.I Saddle clamp
75mm ID x 19mmID C.I Saddle clamp
63mm ID x 19mmID C.I Saddle clamp
50mm ID x 19mmID C.I Saddle clamp
38mm ID x 19mmID C.I Saddle clamp
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
6mm x 1.22m x 2.44 Marine Plywood
#7.5cm CWN
#3.75 cm CWN
1/8"thk x 1.22 x 2.44 Steel Plate
100 pcs 2" x 2" x 10' Gem. Lumber
Sub total
C. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost

pcs
19.00
240.00
pcs
19.00
2,500.00
pcs
160.00
56.00
pcs
29.00
45.00
pcs
29.00
180.00
pcs
55.00
618.00
pcs
29.00
525.00
pcs
29.00
45.00
rolls
58.00
45.00
pcs
25.00
150.00
pcs
2.00
1,200.00
pcs
5.00
1,260.00
pcs
14.00
1,140.00
pcs
4.00
990.00
pcs
5.00
948.00
pcs
2.00
780.00
bags
334.00
280.00
m
20.00
1,000.00
m
29.00
1,000.00
pcs
115.00
204.00
kgs
6.00
100.00
pcs
58.00
520.00
kgs
21.00
100.00
kgs
9.00
100.00
sht
6.00
3,780.00
bd.ft.
518.00
30.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

materials
Labor
equipment

handtools

equipment
material
labor

Amount

6,120.00
47,600.00

53,720.00
53,720.00
53,720.00
91.509948

7,000.00
2,000.00
2,500.00
2,205.00
720.00
3,060.00
450.00
1,120.00
280.00
5,200.00
500.00
1,500.00
200.00
240.00
2,500.00
250.00
1,500.00
999.90
800.10
5,000.10

740.00
360.00
50.00
178.00
450.00
500.00
870.00
180.00
125,000.00
12,000.00
12,000.00
700.00
2,800.00
350.00
350.00
280.00
750.00
2,700.00
166,353.10

489.20

97.84

195.68

16.31

360

66,541.24
232,894.34
232,894.34
232,894.340000

220,000.00
220,000.00
200,000.00
20,000.00
220,000.00
220,000.00
220,000.000000

61,600.00
14,000.00
28,000.00
9,180.00
500.00
1,500.00
500.00
6,000.00
7,250.00

91,260.00
8,112.00
1,340.00
950.00
3,200.00
14,750.00
450.00
75.00
380.00
2,300.00
450.00
160.00
2,800.00
850.00
510.00
180.00
270.00
30,000.00
256,567.00

396,000.00

102,626.80
755,193.80
755,193.80
4,195.521111

138,700.00
1,110.00
875.00
900.00
141,585.00

56,634.00
198,219.00
198,219.00
563.122159

130,200.00
25,000.00
45,000.00
30,000.00
68,000.00
165,000.00
158,100.00
10,080.00
22,500.00
37,740.00
15,000.00
5,000.00
17,500.00
10,400.00
23,800.00
60,000.00
140,400.00
62,400.00
3,780.00
500.00
2,040.00
4,140.00
340.00

12,690.00
16,368.00
5,200.00
440.00
570.00
750.00
5,700.00
3,450.00
980.00
760.00
190.00
225.00

12,292.00
12,292.00
640.00
640.00
480.00
480.00
1,000.00
100.00

144.00

432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
1,194,971.00

10,223.00
7,807.00
18,030.00

477,988.40
1,690,989.40
1,690,989.40
1,690,989.400000

94,976.00
75,400.00
1,206,600.00
20,700.00

12,800.00
32,000.00
16,000.00
9,600.00
9,600.00
54,040.00
12,000.00
14,400.00
84,000.00
9,600.00
10,400.00
10,400.00
7,800.00

5,903.00
4,950.00

23,380.00

8,400.00
9,774.00
19,200.00
14,400.00
7,800.00
9,000.00
14,400.00
9,600.00
42,750.00
5,400.00
1,732,723.00

693,089.20
2,425,812.20
2,425,812.20
641.240338

4,560.00
47,500.00
8,960.00
1,305.00
5,220.00
33,990.00
15,225.00
1,305.00
2,610.00
3,750.00
2,400.00
6,300.00
15,960.00
3,960.00
4,740.00
1,560.00
93,520.00
20,000.00
29,000.00
23,460.00
600.00
30,160.00
2,100.00
900.00
22,680.00
15,540.00
397,305.00
158,922.00
556,227.00
556,227.00
29,275.105263

4,089,504.10
1,629,521.64
414,030.00

6,133,055.74
37,000.00
61,330.56
735,966.69
613,305.57
7,580,658.56

1%
12%
10%

414,030.00
4,089,504.10
1,629,521.64
6,133,055.74
6,133,055.74
-

ADJUSTED PRICE
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
MINDANAO RURAL DEVELOPMENT PROGRAM-Phase II

Province of Zamboanga Sibugay


Municipality of Imelda
OFFICE OF THE MUNICIPAL ENGINEER

SUB-PROJECT PROGRAM OF WORK


Project No.
Project Title
: Water Supply System Level II
Category
:
Physical Target :
Location
Barangay
: Barangays
San joseNew Sagay, Casacon, Katipunan, Ali Alsree, Kulambugan and Magsaysay
Total Project Cost:
8,031,381.81
Equipment Needed:
Php
Implementation Mode:
Project Description:
Project Duration
Const. Of San Jose, Imelda LEVEL II
Equipment Needed:
WATER SYSTEM
Technical Personnel:
Item No.

Scope of Work

% Weight

Quantity

1
2
3
4
5

Trench Excavation
(Transmission/Distribution)
Construction of Pump house
Installation of Submersible pump
Drilling & Pumping Station
Transmission Line

2.31%
3.40%
3.38%
11.62%
3.05%

489.20
1.00
1.00
180.00
352.00

6
7
8

Cylindrical Storage tank (24,000.0 ltrs.,


cap)
Distribution line
Tapstand

26.02%
41.67%
8.56%

1.00
4,635.00
19.00

Total Direct Cost

Breakdown of Estimates
A. Direct Cost
Materials
Equipment
Labor

100.00%

Grant

SOURCES OF FUNDS
LGU Equity

3,249,748.70

Cash
3,249,748.70

2,141,238.50
207,015.00
901,495.40

2,141,238.50
207,015.00
901,495.40

B. Indirect Cost

765,942.20

765,942.20

Quality Control (1% of direct cost)


Taxes (12% of the direct cost)

18,500.00
32,497.49
389,969.84

18,500.00
32,497.49
389,969.84

Contractor's Profit (10% of the direct


cost)

324,974.87

324,974.87

C. Total Direct & Indirect Cost

4,015,690.90

4,015,690.90

E. TOTAL PROJECT COST


Percentage Sharing

4,015,690.90
50%

4,015,690.90
50%

Plumbing Tools(Threaders,Pipe Wrench, Pipe


Cutter)

Prepared by:

Recommending Approval:

EMMANUEL D. SALOMES
Municipal Engineer

Approved:

EXPEDITO B. GONZALES
Municipal Mayor

JULIO T. ALDE
Mun. Planning & Dev. Coordinator

TED PRICE

hilippines
GRICULTURE
ENT PROGRAM-Phase II

anga Sibugay

Imelda
IPAL ENGINEER

RAM OF WORK

o.

mplementation Mode:
Duration
ent Needed:

al Personnel:
Unit

By Contract
200 calendar days
Bagger Concrete Mixer, Concrete
Vibrator,Drilling Machine
Civil Engr, Foreman.Plumber,
Pipefitter, Carpenters, Laborers
Unit Price
Total

units
unit
unit
feet
ln.m.

306.62
220,819.20
220,000.00
4,195.52
563.12

150,000.00
220,819.20
220,000.00
755,193.80
198,219.00

unit
ln.m.
unit

1,690,989.40
584.26
29,275.11

1,690,989.40
2,708,049.00
556,227.00
6,499,497.40

SOURCES OF FUNDS
LGU Equity
Non-Cash
6,499,497.40

Total

4,282,477.00
414,030.00
1,802,990.80

1,531,884.41
37,000.00
64,994.98
779,939.69
649,949.74
8,031,381.81
8,031,381.81
100%

Reviewed by:

ENGR. JUANITO C. TARIPE JR.


RPCO - RIE

Approved by:

OSCAR O. PARAWAN, DVM


Regional Executive Director

Republic of the Philippines


DEPARTMENT OF AGRICULTURE
Mindanao Rural Developement Program-Phase II
Province of Zamboanga Sibugay
Municipality of Imelda
OFFICE OF THE MUNICIPAL ENGINEER

PROJECT
LOCATION

:
:

Improvement of Potable Water System Level II


San Jose, Imelda, ZSP
DETAILED APPROVED AGENCY ESTIMATE
Item/Description

Unit

Quantity

Unit Cost

1600

TRENCH EXCAVATION (Transmission line and Distribution line)


Q=
911.30 cu.m
(NOTE: Heavy soil, rock and a portion of concrete to be excav
Dimensions:
L
W
depth
Volume
Transmission Line
616.5 m
0.20m
1m
123.30 cu.m.
Distribution Line
3,940 m
0.20m
1m
788 cu.m.
Transmission line L = 616.5 ln.m.
V=
Distribution Line L = 3940 ln.m.
V=
Total Volume
Capability (Manual) = 1.5 cu.m / MD
A. Manpower:
No. of Men
Unit
Foreman
1.00
days
Laborer
15.00
days
Sub-total
Total Estimated Direct Cost (EDC)

123.30
788.00
911.30
Qty.
40.00
40.00

cu.m.
cu.m.
cu.m.
Unit Rate
360.00
200.00

>>>>>>>>>>>>>>>>>>>>>>>>>

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

300

REINFORCED CONCRETE

(NOTE: Including Furnish, Delivery and Hauling of materials on proj


Source: Bayog Quarry
Estimated Distance=15 Km
A.)Construction of of Pump house (1 unit)
Dimensions:
N
L
W
Th/H
Floor
1.00
1.50 m
1.50 m
0.10 m
0.23
Beam
4.00
0.38 m
0.25 m
1.50 m
0.57
Column
4.00
0.15 m
0.15 m
3.00 m
0.27
Foundation
4.00
0.50 m
0.50 m
0.20 m
0.20
Total Volume
1.27
a)Materials:
Portland Cement
bags
15.00
280.00
Washed Sand
cu.m.
1.00
1,000.00
Washed Gravel
cu.m.
1.50
1,200.00
4" x 8" x 16" CHB
pcs
150.00
15.00
6" x 6" Fixed Louver
pcs
24.00
30.00
10 mm x 6 m. Def. bars
pcs
15.00
204.00
8 mm x 6 m. Def. bars
pcs
5.00
90.00
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Roofing
shts
4.00
280.00
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Ridge Roll
shts
1.00
280.00
6 mm x 1.22 x 2.44 Marine Plywood
shts
10.00
520.00
#3.75 CW Nails
kgs
5.00
100.00
#10.02 Cw Nails
kgs
15.00
100.00

#16 Tie Wire


#7.75 cm Roofing Nails umbrella type
Pre-Fab Plastic Door
Vulcaseal
10 pcs-2"x3"x10' Lumber Gem.
5 pcs-2"x4"x10' Lumber Gem.
4 pcs-1" x 8" x 10' Lumber Gem.
50 pcs-2"x2"x10'

kgs
kgs
unit
can
bdft
bdft
bdft
bdft

2.00
100.00
2.00
120.00
1.00
2,500.00
1.00
250.00
50.00
30.00
33.33
30.00
26.67
30.00
166.67
30.00
Material Cost

b)Manpower
No. of Men
Foreman
1.00
Mason
1.00
Steelman
1.00
Carpenter
1.00
Laborer
2.00

Unit
days
days
days
days
days

Qty.
9.00
9.00
7.00
9.00
9.00

Unit Rate
360.00
260.00
280.00
260.00
200.00
Labor Cost

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

B) Construction of Pumping Station (1 unit)


(Included Perimeter Fence)
(NOTE: Including Furnish, Delivery and Hauling of materials on proj
Dimensions:
Source: Bayog Quarry
Estimated Distance = 15 Km
N
L
W
Th/H
Floor
1.00
12.00 m
9.00 m
0.20 m
21.60
Column
16.00
0.15 m
0.15 m
2.00 m
0.72
Foundation
16.00
0.50 m
0.50 m
0.20 m
0.80
Total Volume
23.12
a.)Materials:
Floor,Post and Foundation
Portland Cement
bags
254.00
280.00
Washed sand
m
14.00
1,000.00
Washed Gravel (50mm in size)
m
28.00
1,200.00
10mm x 6.0m Def. Bars
pcs
45.00
204.00
8 mm x 6 m. Def. bars
pcs
24.00
90.00
#3.75 cm CWN
kgs
5.00
100.00
#10.02cm CWN
kgs
15.00
100.00
#16 Tie Wire
kgs
10.00
100.00
Gravel (25mm in size) Gravel packing
cu.m.
6.00
1,200.00
Barb Wire
m
290.00
25.00
10 pcs-2"x3"x10' Lumber Gem.
bdft
50.00
30.00
5 pcs-2"x4"x10' Lumber Gem.
bdft
33.33
30.00
6 mm x 1.22 x 2.44 Marine Plywood
shts
3.00
520.00
Steel Gate
38mm x 6.0 m G.I. Pipe Sch 40
ln.m.
4.00
1,350.00
4x8 GA18 Steel Plate
sht
2.00
3,780.00
Welding Rod
kgs
2.00
170.00
Material Cost
b) Equipment Rental
1
unit Bagger Concrete mixer
1
unit Concrete Vibrator

c)Manpower:

days
days

6.00
1,278.00
6.00
976.00
Equipment Cost

Foreman
Mason
Steelman/Welder
Carpenter
Laborer

No. of Men
1
3
2
2
7

Total Estimated Direct Cost (EDC)

Unit
days
days
days
days
days

Qty.
16.00
16.00
12.00
16.00
16.00

Unit Rate
360.00
260.00
260.00
260.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

C.)Elevated Cylindrical Storage Tank (1 unit)(3 m elevation)


(NOTE: Including Furnish, Delivery and Hauling of materials on project site)
Dimensions:
Source : Bayog Quarry
Estimated Distance= 15
N
W
Th/H
L /diameter
Top&Bottom (Circle)
Slab
2.00
5.10 m
0.20
8.17
Wall(Cylinder)
1.00
5.10 m
3.50
15.83
Column
4.00
0.40 m
0.40
m
5.20
3.33
Beams
10.00
0.35 m
0.45
m
4.20
6.62
Foundation
4.00
2.50 m
2.50
m
0.40
10.00
Manhole
1.00
0.70 m
0.70
m
0.25
0.12
Total Volume
44.07
a.)Materials:
Portland Cement
bags
485.00
280.00
Washed Sand
cu.m
25.50
1,000.00
Washed Gravel
cu.m.
44.00
1,200.00
Sahara Cement
kgs
250.00
150.00
25mm x 6 m Def. Bar
pcs
100.00
850.00
20mm x 6 m Def. Bar
pcs
230.00
750.00
16mm x 6 m Def. Bar
pcs
350.00
462.00
16mm x 6 m Stainless Bar
pcs
5.00
2,520.00
10mm x 6 m Def. bars
pcs
200.00
204.00
#16 Tie Wire
kgs
150.00
100.00
1/8"x1.22mx2.44m steel Plate
sht
1.00
3,780.00
3/16"x 6' Corrugated PVC Waterstop Plain Type rolls
3.00
7,500.00
Formworks and Scaffoldings
#3.75 cm CWN
# 10.02 cm CWN
19mm x 1.22m x 2.44 m Marine Plywood
6mm x 1.22m x 2.44m Marine Plywood
250 pcs-2"x4"12' lumber
780 pcs-2"x3"x12' Lumber
500 pcs-2"x2"x12'lumber
50mm Egret Padlock
Hacksaw Blade
Shovel
Welding rod

kgs
kgs
sht
sht
bdft
bdft
bdft
pcs
pcs
pcs
kgs

b.) Equipment Rental


1
unit Bagger Concrete mixer
1
unit Concrete Vibrator
1 unit Bar cutter

days
days
days

50.00
175.00
25.00
70.00
2,000.00
4,680.00
2,000.00
2.00
24.00
6.00
5.00
Material Cost

100.00
100.00
520.00
350.00
30.00
30.00
30.00
250.00
85.00
690.00
170.00

35.00
1,278.00
35.00
976.00
30.00
700.00
Equipment Cost

c.)Manpower:
No. of Men

Unit

Qty.

Unit Rate

Foreman
Mason
Steelman
Carpenter
Laborer

1
4
3
3
15

Total Estimated Direct Cost (EDC)

days
days
days
days
days

60.00
60.00
50.00
60.00
60.00
Labor Cost

360.00
260.00
280.00
260.00
200.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

1601

BACKFILL AND FILL


Transmission line and distribution line
Transmission line L = 616.5 ln.m.
V=
Distribution Line L = 3940 ln.m.
V=
Total Volume
Capability Manual =
2 cu.m./day
Manpower:
Foreman
Laborer

No. of Men
1
15

Total Estimated Direct Cost (EDC)

Unit
days
days

123.30
788.00
911.30

Qty.
Unit Rate
31.00
360.00
31.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

1602

INSTALLATION OF PIPELINE
A.) Transmission Pipeline
Q=
616.50 ln.m.
Laying of Pipes
a.) Material:
50mm ID x 6.0m G.I. Pipe sch. 40 w/ coupling

pcs

103.00
1,900.00
Material Cost

Manpower:
No. of Men
Foreman
1
Pipe Fitter
3
Plumber
3
Laborer
6

Total Estimated Direct Cost (EDC)

Unit
days
days
days
days

Qty.
15.00
15.00
15.00
15.00

Unit Rate
360.00
280.00
280.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

b.)Connector and Fittings


50mm x 45 G.I. Elbow
50mm G.I. Union
25mm Wide Thread tape

pcs
pcs
pcs

48.00 units
10.00
185.00
8.00
175.00
30.00
45.00
Material Cost

Manpower:
Foreman

No. of Men
1

Unit
days

Qty.
3.00

Unit Rate
360.00

Pipe Fitter
Plumber

1
1

days
days

Total Estimated Direct Cost (EDC)

3.00
3.00

280.00
280.00

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

B.) Distribution Pipeline


Total Q =
3,940.00

ln.m.

Laying of Pipes
a.) Material:
Q=
205.00
ln.m. of 150mm
150mm ID x 6.0m uPVC C-150 w/
pcs
electromagnetic rubber ring
Q= 311.00
ln.m. of 100mm
100mm ID x 6.0m uPVC C-150 w/
pcs
electromagnetic rubber ring
Q=
3,424.00
ln.m. of 75mm
75mm ID x 6.0m uPVC C-150 w/
pcs
electromagnetic rubber ring

35.00

6,784.00

52.00

3,016.00

570.00

2,185.00
Material Cost

Manpower:
No. of Men
Foreman
1
Pipe Fitter
7
Plumber
7
Laborer
20

Unit
days
days
days
days

Qty.
45.00
45.00
45.00
45.00

Unit Rate
360.00
280.00
280.00
200.00
Labor Cost

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

b.) Hydrants,Connectors,Fittings and Valves:


Materials:
150mm CI Tee 150x150mm F/F w/ bolt&nuts pc
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts pc
150mm CI 90" elbow F/F w/ bolt & nuts
pc
75mm CI 90" elbow F/F w/ bolt & nuts
pc
150mm CI 45" elbow F/F w/ bolt & nuts
pc
75mm CI 45" elbow F/F w/ bolt & nuts
pc
150mm CI Adaptor MJ/F
pc
100mm CI Adaptor MJ/F
pc
75mm CI Adaptor MJ/F
pc
50mm CI Adaptor MJ/F
pc
150mm x 100mm CI Reducer F/F w/ bolts
and Nuts and gasket
pc
100mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
pc

150mm x 75mm CI Reducer F/F w/ bolts


and Nuts and gasket
150mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
100mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
75mm CI Gate Valve F/F NRS w/ bolts

263.00 units
14.00
10.00
18.00
3.00
11.00
15.00
18.00
17.00
35.00
14.00

3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00
2,400.00
2,400.00
2,400.00
2,400.00

14.00

2,600.00

11.00

2,600.00

11.00

2,600.00

pcs

1.00

5,903.00

pcs

2.00

4,950.00

pc

nuts and gasket


50mm CI angle Valve F/F NRS w/ bolts
nuts and gasket
75mm CI end caps
75mm CI TEE
75mm CI Adaptor MJ/F
75 x 50 mm Reducer
50mm CI Gate Valve
50mm CI Adaptor MJ/F
50mm uPVC Elbow
Fire Hydrant 50mm w/ accessories
Eslon Solvent Cement 150g

pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
units
cans

7.00

3,340.00

3.00
9.00
6.00
6.00
3.00
3.00
6.00
3.00
3.00
20.00

2,800.00
1,086.00
3,200.00
2,400.00
2,600.00
3,000.00
2,400.00
3,200.00
14,250.00
270.00
Material Cost

Manpower:
No. of Men
Foreman
1
Pipe Fitter
7
Plumber
7

Unit
days
days
days

Qty.
Unit Rate
30.00
360.00
30.00
280.00
30.00
280.00
Labor Cost

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

1201

WATER PUMPING SYSTEM


A.)Installation of Submersible Pump
Q=
1.00 unit

a.). Material
Goulds submersible Pump Stainless Steel
casing close coupled to a 4.5 HP 1 phase 230v
60 Hz, Franklin submersible motor, with built-in
lighting protection, original brand new, made in USA
to include the foll.
- Motor lead assy
- Built-in check valve and strainer
190ft. Submersible cable wire no.14
380ft Suspension wire No.14
- Panel board metal enclosure consist of the
foll.
_Included Installation
(Material=
- magnetic starter w/ overload
(Labor Installation=
B/W Water level cut-off control w/ level electrodes
- on/off push button switch
- lightning arrester
1 set water roof splicing tape 1.00 unit
220,000.00
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

b.)Pipes and Protection Slab


150mm x 6.0m uPVC Pipe Class 150 (casing) pcs
38mm x 6.0m G.I. Pipe sch 40 w/ coupling (suction)
pcs
"thk x 20mm x 38mm discharge plate
pcs

Dimension

13.00
7,020.00
13.00
624.00
2.00
670.00
Material Cost

Protection Slab
N
L
W
Th/H
1.00
2.30 m
2.30 m
0.20 m
1.06
(NOTE: Including Furnish, Delivery and Hauling of materials on project site)
Materials:
Source: Bayog Quarry
Estimated Distance= 15 Km.

Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
Gravel (25mm in size) Gravel packing

bags
m
m
pcs
kgs
cu.m.

10.00
280.00
0.50
1,000.00
1.00
1,200.00
10.00
204.00
1.00
100.00
2.00
1,200.00
Material Cost

Unit
days
days
days
days

Qty.
Unit Rate
2.00
360.00
2.00
260.00
2.00
260.00
2.00
200.00
Labor Cost

Manpower:
Foreman
Mason
Steelman
Laborer

No. of Men
1
1
1
1

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

c)Pipes, Fittings,gauges,Valves
Materials:
5/8" x 12" Stainless bolt w/ nut
50mm ID x 0.8m GI Pipe Sch.40
32mm ID x 6m GI Pipe Sch. 40 w/ coupling
50mm ID x 32mm GI Pipe bell Reducer
50mm GI Union
50mmGI Swing Check Valve
Pressure Gauge
50mm x 19 mm GI bell reducer
50mm GI Tee
50mm CI Gate Valve
50mmx0.20 m GI Nipple sch. 40

pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs

5.00
1.00
5.00
1.00
1.00
1.00
1.00
1.00
2.00
1.00
5.00

190.00
3,200.00
2,950.00
450.00
75.00
380.00
2,300.00
450.00
80.00
2,800.00
170.00

50mm ID x 45 GI Elbow sch.40


25mm Wide thread tape
50mm CI Water meter

pcs
pcs
pc.

1.00
6.00
1.00

180.00
45.00
30,000.00
Material Cost

Manpower:
No. of Men
Foreman
1
Pipe Fitter
3
Plumber
3
Total Estimated Direct Cost (EDC)

Unit
days
days
days

Qty.
Unit Rate
1.00
360.00
3.00
280.00
3.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

1002

PLUMBING
A)Tapstand(28 units)
(NOTE: Including Furnish, Delivery and Hauling of materials on proj
Q=
28 units
Source: Bayog Quarry
Estimated Distance= 15 K
a.)Materials:
13mm ID x 6.0m G.I. Pipe sch 40 w/ coupling pcs
52.00
525.00
Connectors,fittings,valves and hydrants
13mm Brass l Faucets
pcs
28.00
175.00
13mm Water Meter
pcs
28.00
1,700.00
13mm x 90 Elbow
pcs
235.00
56.00
13mm x 13mm G.I. Bell Reducer
pcs
44.00
45.00
13mm G.I. Ball Valves
pcs
44.00
180.00
13mm G.I. Union
pcs
44.00
45.00
25mm Wide thread tape
rolls
60.00
45.00

Padlock (Egret)
150mm ID x 19mmID C.I Saddle clamp
75mm ID x 19mmID C.I Saddle clamp
100mm ID x 19mmID C.I Saddle clamp
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
1/8"thk x 1.22 x 2.44 Steel Plate
6mm x 1.22m x 2.44 Marine Plywood
#7.5cm CWN
#3.75 cm CWN
100 pcs 2" x 2" x 10' Gem. Lumber

pcs
pcs
pcs
pcs
bags
m
m
pcs
kgs
sht
pcs
kgs
kgs
bd.ft.

31.00
150.00
1.00
1,200.00
26.00
1,140.00
1.00
990.00
197.00
280.00
21.00
1,000.00
26.00
1,200.00
120.00
204.00
7.00
100.00
7.00
3,780.00
58.00
520.00
21.00
100.00
9.00
100.00
518.00
30.00
Material Cost

No. of Men
Foreman
1
Pipe Fitter
4
Plumber
4
Mason
4
Carpenter
4
Labor
12

Unit
days
days
days
days
days
days

Qty.
Unit Rate
17.00
360.00
17.00
280.00
17.00
280.00
17.00
260.00
17.00
260.00
17.00
200.00
Labor Cost

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Manpower:

Est. Direct Cost (EDC)


( Direct Cost/Estimated Volume)
B.Elevated Cylindrical Storage Tank (1 unit)
Plumbing:
150mm CI Gate Valve F/F w/ bolt & nut
150mm CI Adaptor MJ/F w/ bolt & nut
150mm CI Tee F/F w/ bolt & nut
150mm G.I. Elbow 90 GI Elbow sch.40
150mm ID GI Union sch. 40
150mm IDx0.80m GI Nipple Threaded sch.40
150mm ID x 3.80m GI Nipple Threaded sch. 40
50mm IDx0.50m GI Nipple Threaded sch.40
50mm ID x 0.20m GI Nipple Threaded sch. 40

pcs
pcs
pc
pcs
pc
pc
pc
pcs
pcs

2.00
3.00
1.00
2.00
1.00
1.00
1.00
6.00
2.00

50mm G.I. Elbow 90 GI Elbow sch.40


50mm ID GI Union sch. 40
25mm Wide Thread Tape

pcs
pc
roll

4.00
190.00
1.00
190.00
5.00
45.00
Material Cost

6,345.00
5,456.00
5,200.00
220.00
570.00
750.00
5,700.00
575.00
490.00

Manpower:
No. of Men
Foreman
1
Pipe Fitter
2
Plumber
2

Unit
days
days
days

Qty.
Unit Rate
10.00
360.00
10.00
280.00
10.00
280.00
Labor Cost

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)

( Direct Cost/Estimated Volume)


455

PAINTING
A.Elevated Cylindrical Storage Tank (1 unit)
(NOTE: Including Furnish, Delivery and Hauling of materials on project site)
a.)Materials
Nalcrete Acrylic Latex flat (white) DB
gal
14.00
878.00
Nalcrete Acrylic Latex Gloss (White) DB
gal
14.00
878.00
Blue Tinting color DB
pint
4.00
160.00
Yellow tinting color DB
pint
4.00
160.00
Green Tinting color DB
pint
3.00
160.00
Black Tinting color DB
pint
3.00
160.00
Paint Roller w/ tray 7"
set
4.00
250.00
Paint Roller 7" Foam
pcs
5.00
20.00
Paint roller 6" w/ handle
pcs
3.00
48.00
Paint roller 4" w/ handle
pcs
8.00
54.00
Epoxy Primer Gray
gal
10.00
600.00
Epoxy Primer Yellow
gal
11.00
186.00
Epoxy Strong Hold RSC
gal
4.00
2,630.00
Epoxy Fortress
gal
5.00
4,050.00
Reducer
gal
2.00
908.00
QDE Paint Blue
gal
10.00
780.00
Lettering Brush
pcs
4.00
12.00
L.T Primer White
gal
16.00
720.00
L.T Reducer
gal
14.00
405.00
L.T Semigloss White
gal
5.00
894.00
L.T Cast
gal
6.00
478.00
Paint Thinner
gal
7.00
216.00
Lacquer Thinner
gal
10.00
216.00
Easytite
gal
4.00
312.00
Concrete Nuetralizer
lit
4.00
95.00
Patching Compound
gal
30.00
24.00
Paint tray
pcs
5.00
30.00
Paint Brush 3"
pcs
3.00
42.00
Paint Brush 2 1/2"
pcs
3.00
48.00
Paint brush 2"
pcs
17.00
75.00
Sand Paper # 120
pcs
54.00
13.00
Sand Paper # 600
pcs
11.00
14.00
Sand Paper # 80
ft
13.00
37.00
Putty Knife
pairs
4.00
42.00
Material Cost

Manpower:
Foreman
Painter
Labor

No. of Men
1
3
6

Total Estimated Direct Cost (EDC)

Unit
days
days
days

Qty.
Unit Rate
14.00
360.00
14.00
280.00
14.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

1102 POWER LOAD CENTER,SWITCHGEAR and PANELBOARDS


Construction of of Pump house (1 unit)
a.)Materials
15mm ID x 3.0m PVC Pipe
pcs
4.00
15mm ID x 90 PVC bend
pcs
10.00
15mm ID male threaded adaptor
pcs
2.00
15mm ID entrance cap
pcs
2.00

185.00
36.00
25.00
89.00

15mm PVC Clip


Solvent Cement Eslon blue 150G
12mm TW stranded wire
Electrical tape
37.5 Kva Distribution Transformer
Cut-out w/ Lightning arrester 9 KV
6 mm Aluminum Service Entrance Drop Wire
Panel board 4-Branches
100 AT Double Throw Circuit Breaker
60 AT Double Throw Circuit Breaker
30 AT Double Throw Circuit Breaker
15 AT Double Throw Circuit Breaker
#10TW Copper Wire (Stranded)
Kilo-Watt Meter

pcs
can
mtr
roll
unit
unit
mtrs
unit
pc
pc
pc
pc
mtrs
unit

18.00
25.00
2.00
250.00
10.00
87.00
2.00
90.00
1.00
125,000.00
1.00
12,000.00
300.00
40.00
1.00
700.00
1.00
2,800.00
1.00
350.00
1.00
350.00
1.00
280.00
30.00
25.00
1.00
2,700.00
Material Cost

Manpower:
No. of Men
Electrician
2.00
Laborer
2.00

Unit
days
days

Qty.

Unit Rate
5
280.00
5
200.00
Labor Cost

Total Estimated Direct Cost (EDC)

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

DEPARTMENT OF AGRICULTURE
MINDANAO RURAL DEVELOPMENT PROGRAM-Phase II

Province of Zamboanga del Sur


Municipality of Roseller T. Lim
OFFICE OF THE MUNICIPAL ENGINEER

Material

4,881,185.00

4,881,185.00

labor

1,410,720.00

1,410,720.00

equipment

Amount

113,412.00

113,412.00

6,405,317.00

6,405,317.00

6,405,317.00

6318682.9

rete to be excavated)

160
1,493.93

Amount
14,400.00
120,000.00

106.71

65
111
88
92
143

134,400.00

45
46

134,400.00

90
65

134,400.00
147.48

75
82
40
72

materials on project site)

125
64
118
90
68

cu.m.
cu.m.
cu.m.
cu.m.
cu.m.

110
79
57
147
250
130

4,200.00
1,000.00
1,800.00
2,250.00
720.00
3,060.00
450.00
1,120.00
280.00
5,200.00
500.00
1,500.00

82
117
114
65
96
184
25
57
130
82
117
114
65
96
184
3940

200.00
240.00
2,500.00
250.00
1,500.00
999.90
800.10
5,000.10
33,570.10
Amount
3,240.00
2,340.00
1,960.00
2,340.00
3,600.00
13,480.00
47,050.10
47,050.10
47,050.10

materials on project site)

cu.m
cu.m
cu.m
cu.m

71,120.00
14,000.00
33,600.00
9,180.00
2,160.00
500.00
1,500.00
1,000.00
7,200.00
7,250.00
1,500.00
999.90
1,560.00
5,400.00
7,560.00
340.00
164,869.90

7,667.00
5,855.00
13,522.00

Amount
5,760.00
12,480.00
6,240.00
8,320.00
22,400.00
55,200.00

B. Electrical

233,591.90
233,591.90
233,591.90

on project site)
d Distance= 15 Km
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
135,800.00
25,500.00
52,800.00
37,500.00
85,000.00
172,500.00
161,700.00
12,600.00
40,800.00
15,000.00
3,780.00
22,500.00

5,000.00
17,500.00
13,000.00
24,500.00
60,000.00
140,400.00
60,000.00
500.00
2,040.00
4,140.00
850.00
1,093,410.00

44,730.00
34,160.00
21,000.00
99,890.00

Amount

160

21,600.00
62,400.00
42,000.00
46,800.00
180,000.00
352,800.00
1,546,100.00
1,546,100.00
1,546,100.00

cu.m.
cu.m.
cu.m.

Amount
11,160.00
93,000.00
104,160.00
104,160.00
104,160.00
114.30

195,700.00
195,700.00
Amount
5,400.00
12,600.00
12,600.00
18,000.00
48,600.00
244,300.00
244,300.00
396.269262

1,850.00
1,400.00
1,350.00
4,600.00

Amount
1,080.00

45
205

840.00
840.00

7,360.00
7,360.00
153.333333

237,440.00

156,832.00

1,245,450.00
1,639,722.00
Amount
16,200.00
88,200.00
88,200.00
180,000.00
372,600.00
2,012,322.00
2,012,322.00
510.74

44,800.00
32,000.00
57,600.00
9,600.00
35,200.00
57,900.00
43,200.00
40,800.00
84,000.00
33,600.00
36,400.00
28,600.00

28,600.00
5,903.00
9,900.00

65
46
82
118
311

23,380.00
8,400.00
9,774.00
19,200.00
14,400.00
7,800.00
9,000.00
14,400.00
9,600.00
42,750.00
5,400.00
712,207.00
Amount
10,800.00
58,800.00
58,800.00
128,400.00
840,607.00
840,607.00
3,196.22

200,000.00
20,000.00

220,000.00
220,000.00

91,260.00
8,112.00
1,340.00
100,712.00

cu.m
on project site)

2,800.00
500.00
1,200.00
2,040.00
100.00
2,400.00
9,040.00
Amount
720.00
520.00
520.00
400.00
2,160.00
111,912.00
111,912.00
111,912.00

950.00
3,200.00
14,750.00
450.00
75.00
380.00
2,300.00
450.00
160.00
2,800.00
850.00
180.00
270.00
30,000.00
57,325.00
Amount
360.00
2,520.00
2,520.00
5,400.00
62,725.00
62,725.00
62,725.00

materials on project site)


d Distance= 15 Km.
27,300.00
4,900.00
47,600.00
13,160.00
1,980.00
7,920.00
1,980.00
2,700.00

4,650.00
1,200.00
29,640.00
990.00
55,160.00
21,000.00
31,200.00
24,480.00
700.00
26,460.00
30,160.00
2,100.00
900.00
15,540.00
351,720.00
Amount
6,120.00
19,040.00
19,040.00
17,680.00
17,680.00
40,800.00
120,360.00
472,080.00
472,080.00
16,860.00

12,690.00
16,368.00
5,200.00
440.00
570.00
750.00
5,700.00
3,450.00
980.00

760.00
190.00
225.00
47,323.00

Amount
3,600.00
2,800.00
5,600.00
12,000.00
59,323.00
59,323.00

59,323.00

on project site)
12,292.00
12,292.00
640.00
640.00
480.00
480.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
110,728.00

Amount
5,040.00
11,760.00
16,800.00
33,600.00
144,328.00
144,328.00
144,328.00

740.00
360.00
50.00
178.00

450.00
500.00
870.00
180.00
125,000.00
12,000.00
12,000.00
700.00
2,800.00
350.00
350.00
280.00
750.00
2,700.00
160,258.00
Amount
2,800.00
2,000.00
4,800.00
165,058.00
165,058.00
165,058.00

(86,634.10)

Republic of the Philippines


DEPARTMENT OF AGRICULTURE
MINDANAO RURAL DEVELOPMENT PROGRAM-Phase II
Province of Zamboanga Sibugay
Municipality of Imelda
OFFICE OF THE MUNICIPAL ENGINEER
SUB-PROJECT PROGRAM OF WORK
Project No. 01-IME-ZSP-11
Project Title
: Improvement of Potable Water System Level II
Category
: Potable Water System
Physical Target : 393 HH
Location
:Barangay San Jose
Php
Total Project Cost:
7,915,539.91
Implementation Mode:
Project Description:
Project Duration
Improvement Of San Jose, Imelda LEVEL II
Equipment Needed:
WATER SYSTEM
Technical Personnel:

Item No.

Scope of Work

1600 Trench Excavation


Transmissionnd Line and
Distribution Line
300 Reinforced Concrete
A) Construction of Pump House
B) Construction of Pumping Station
C)Elevated Cylindrical Storage
Tank(60,000 L)
1601 BackFill And Fill
Transmissionnd Line and
Distribution Line
1602 Installation of Pipeline
A.)Transmission Pipeline
a.) Laying of Pipes
b.)Connectors and Fittings
B.)Distribution Pipeline
a.)Laying of Pipes
b.)Hydrants, Connectors,
Fittings and Valves
1201 Water Pumping Sysytem
Installation of Submersible Pump
a.)Materials and Installation
b.)Pipes and Protection Slab
c)Pipes, Fittings,Gauges and
Valves
1002 Plumbing
A.) Tapstand
B.) Elevated Cylindrical
Storage Tank
411 Painting
Elevated Cylindrical Storage Tank
1102 Power Load Center, Switchgear
and Panel Board
(Electrical)

% Weight

Quantity

Unit

By Contract
200 calendar days
Bagger Concrete Mixer, Con.

Civil Engr, Foreman.Plum


Pipefitter, Carpenters, Lab
Mason, Steelman
Unit Price

2.10%

911.30

cu.m

0.73%
3.65%
24.14%

1.00
1.00
1.00

unit
unit
unit

1.63%

911.30

cu.m

114.30

3.81%
0.11%

616.50
48.00

Ln.m.
units

396.27
153.33

31.42%
13.12%

3,940.00
263.00

Ln.m.
units

510.74
3,196.22

3.43%
1.75%
0.98%

1.00
1.00
35.00

set
unit
units

###
###
1,792.14

7.37%
0.93%

28.00
1.00

units
unit

2.25%

1.00

unit

###

2.58%

1.00

unit

###

100.00%

147.48

47,050.10
###
1,546,100.00

16,860.00
59,323.00

6,405,317.00

Breakdown of Estimates

MRDP

A. Direct Cost
Materials
Equipment
Labor
B. Indirect Cost
Hand Tools
Quality Control (1% of direct cost)
Taxes (12% of the direct cost)
Contractor's Profit (10% of the direct cost)

C. Contract Cost= A + B
E. TOTAL PROJECT COST
Percentage Sharing

Prepared by:

EMMANUEL D. SALOMES
Municipal Engineer
Conformed:

HON. EXPEDITO B. GONZALES


Municipal Mayor

###

SOURCES OF FUNDS
LGU Equity
Total
Cash
Non-Cash
###
6,405,317.00

2,440,592.50
56,706.00
705,360.00
755,111.46
18,500.00
32,026.59
384,319.02
320,265.85
###

2,440,592.50
56,706.00
705,360.00
755,111.46
18,500.00
32,026.59
384,319.02
320,265.85
###

###

###

50%

50%

Recommending Approval:

JULIO T. ALDE
Mun. Planning & Dev. Coordinator

4,881,185.00
113,412.00
1,410,720.00
1,510,2
37,
64,0
768,6
640,5
7,915,5
7,915,539.91
100%

Reviewed by:

ENGR. JUANITO C. TARIP


RPCO - RIE
Approved by:

OSCAR O. PARAWAN,
DA - Regional Executive D

tract
ndar days

ncrete Mixer, Con. Vibrator

r, Foreman.Plumber,
, Carpenters, Laborers,
teelman
Total
134,400.00

47,050.10
233,591.90
1,546,100.00
104,160.00

244,300.00
7,360.00
2,012,322.00
840,607.00

220,000.00
111,912.00
62,725.00

472,080.00
59,323.00

144,328.00
165,058.00
6,405,317.00

Total

17.00
4,881,185.00
113,412.00
1,410,720.00
1,510,222.91
37,000.00
64,053.17
768,638.04
640,531.70
7,915,539.91

7,915,539.91
100%

d by:

ANITO C. TARIPE JR.


RPCO - RIE

d by:

O. PARAWAN, DVM
onal Executive Director

Republic of the Phi


DEPARTMENT OF AGR
Mindanao Rural Developemen
San Jose, Imelda, Zambo

PROJECT
LOCATION

:
:

Water Supply System Level II at San jose


San Jose, Imelda, ZSP

DETAILED APPROVED AGE


Item/Description
TRENCH EXCAVATION (Transmission line and Distribution line)
Q=
897.50 cu.m
Dimensions:
L
W
Transmission Line
616.5 m
0.20m
Distribution Line
3,871 m
0.20m
1600

Transmission line L = 616.5 ln.m.


Distribution Line L = 3871 ln.m.

(NOTE: Hea

V=
V=
Total Volume

Capability (Manual) = 1.5 cu.m / MD


A. Manpower:
No. of Men
Foreman
1.00
Laborer
15.00
Sub-total
Total Estimated Direct Cost (EDC)

300

REINFORCED CONCRETE

(NOTE: Included Furnish, Delivery and Haulin


Source: Bayog Quarry
A.)Construction of of Pump house (1 unit)
Dimensions:
N
L
W
Floor
1.00
1.50 m
1.50 m
Beam
4.00
0.38 m
0.25 m

Post
Foundation

4.00
4.00

0.15 m
0.50 m

a)Materials:
Portland Cement
Washed Sand
Washed Gravel
4" x 8" x 16" CHB
6" x 6" Fixed Louver
10 mm x 6 m. Def. bars
8 mm x 6 m. Def. bars
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Roofing
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Ridge Roll
6 mm x 1.22 x 2.44 Marine Plywood
#3.75 CW Nails
#10.02 Cw Nails

#16 Tie Wire


#7.75 cm Roofing Nails umbrella type
Pre-Fab Plastic Door
Vulcaseal
10 pcs-2"x3"x10' Lumber Gem.
5 pcs-2"x4"x10' Lumber Gem.
4 pcs-1" x 8" x 10' Lumber Gem.
50 pcs-2"x2"x10'
b)Manpower
Foreman
Mason
Steelman
Carpenter
Laborer

No. of Men
1.00
1.00
1.00
1.00
2.00

0.15 m
0.50 m

Total Estimated Direct Cost (EDC)

Dimensions:
Floor
Post
Foundation

B) Construction of Pumping Station (1 unit)


(NOTE: Included Furnish, Delivery and Haulin
Source: Bayog Quarry
N
L
W
1.00
12.00 m
9.00 m
16.00
0.15 m
0.15 m
16.00
0.50 m
0.50 m
a.)Materials:
Floor,Post and Foundation
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
8 mm x 6 m. Def. bars
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire
Gravel (25mm in size) Gravel packing
Barb Wire
10 pcs-2"x3"x10' Lumber Gem.
5 pcs-2"x4"x10' Lumber Gem.
6 mm x 1.22 x 2.44 Marine Plywood
Steel Gate
38mm x 6.0 m G.I. Pipe Sch 40
4x8 GA18 Steel Plate
Welding Rod

b) Equipment Rental
1
unit Bagger Concrete mixer
1
unit Concrete Vibrator

c)Manpower:
No. of Men
Foreman
Mason
Steelman/Welder
Carpenter
Laborer

1
3
2
2
7

Total Estimated Direct Cost (EDC)

D.)Elevated Cylindrical Storage Tank (1 unit)


(NOTE: Included Furnish, Delivery and Hauling of materials o
Dimensions:
Source : Bayog Quarry
N
W
L/diameter
Top&Bottom Slab
2.00
5.10 m
Wall(Cylinder)
1.00
5.10 m
Column
4.00
0.40 m
0.40
Beams
10.00
0.35 m
0.45
Foundation
4.00
2.50 m
2.50
Manhole
1.00
0.70 m
0.70
a.)Materials:
Portland Cement
Washed Sand
Washed Gravel
Sahara Cement
25mm x 6 m Def. Bar
20mm x 6 m Def. Bar
16mm x 6 m Def. Bar
16mm x 6 m Stainless Bar
10mm x 6 m Def. bars
#16 Tie Wire
1/8"x1.22mx2.44m steel Plate
3/16"x 6' Corrugated PVC Waterstop Plain Type
Formworks and Scaffoldings

#3.75 cm CWN
# 10.02 cm CWN
19mm x 1.22m x 2.44 m Marine Plywood
6mm x 1.22m x 2.44m Marine Plywood
250 pcs-2"x4"12' lumber
780 pcs-2"x3"x12' Lumber
500 pcs-2"x2"x12'lumber
50mm Egret Padlock
Hacksaw Blade
Shovel
Welding rod

b.) Equipment Rental


1
unit Bagger Concrete mixer
1
unit Concrete Vibrator
1 unit Bar cutter

c.)Manpower:
No. of Men
Foreman
Mason
Steelman
Carpenter
Laborer

1
4
3
3
15

Total Estimated Direct Cost (EDC)

1601

BACKFILL AND FILL


Transmission line and distribution line
Transmission line L = 616.5 ln.m.
Distribution Line L = 3871 ln.m.

Capability Manual
Manpower:
Foreman
Laborer

No. of Men
1
14

Total Estimated Direct Cost (EDC)


Direct Cost
Unit Cost
1602

INSTALLATION OF PIPELINE
A.) Transmission Pipeline
Q=
616.50 ln.m.
Laying of Pipes
a.) Material:
50mm ID x 6.0m G.I. Pipe sch. 40 w/ coupling
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber
Laborer

1
3
3
6

Total Estimated Direct Cost (EDC)

b.)Connector and Fittings


50mm x 45 G.I. Elbow
50mm G.I. Union
25mm Wide Thread tape

2 cu.m./day

Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber

1
1
1

Total Estimated Direct Cost (EDC)

B.) Distribution Pipeline


Total Q =
3,871.00

ln.m.

Laying of Pipes
a.) Material:
Q=
205.00
ln.m. of 150mm
150mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Q= 311.00
ln.m. of 100mm
100mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Q=
3,355.00
ln.m. of 75mm
75mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber
Laborer

1
7
7
20

Total Estimated Direct Cost (EDC)

b.) Hydrants,Connectors,Fittings and Valves:


Materials:
150mm CI Tee 150x150mm F/F w/ bolt&nuts
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts
150mm CI 90" elbow F/F w/ bolt & nuts
75mm CI 90" elbow F/F w/ bolt & nuts
150mm CI 45" elbow F/F w/ bolt & nuts
75mm CI 45" elbow F/F w/ bolt & nuts
150mm CI Adaptor MJ/F
100mm CI Adaptor MJ/F
75mm CI Adaptor MJ/F
50mm CI Adaptor MJ/F
150mm x 100mm CI Reducer F/F w/ bolts
and Nuts and gasket
100mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket

150mm x 75mm CI Reducer F/F w/ bolts


and Nuts and gasket
150mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
100mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
75mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
50mm CI angle Valve F/F NRS w/ bolts
nuts and gasket

75mm CI end caps


75mm CI TEE
75mm CI Adaptor MJ/F
75 x 50 mm Reducer
50mm CI Gate Valve
50mm CI Adaptor MJ/F
50mm uPVC Elbow
Fire Hydrant 50mm w/ accessories
Eslon Solvent Cement 150g
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber

1
7
7

Total Estimated Direct Cost (EDC)

1201

WATER PUMPING SYSTEM


A.) Drilling and Installation of Submersible Pump
Q=
1.00 unit
a.). Material
Goulds submersible Pump Stainless Steel
casing close coupled to a 4.5 HP 1 phase 230v
60 Hz, Franklin submersible motor, with built-in
lighting protection, original brand new, made in USA
to include the foll.
- Motor lead assy
- Built-in check valve and strainer
190ft. Submersible cable wire no.14
380ft Suspension wire No.14
- Panel board metal enclosure consist of the
foll.
_Included Installation
- magnetic starter w/ overload
B/W Water level cut-off control w/ level electrodes
- on/off push button switch
- lightning arrester
1 set water roof splicing tape
Sub total

b.)Pipes and Protection Slab


150mm x 6.0m uPVC Pipe Class 150 (casing)
38mm x 6.0m G.I. Pipe sch 40 w/ coupling (suction)
"thk x 20mm x 38mm discharge plate

Dimension

Protection Slab
N
L
W
1.00
2.30 m
2.30 m
(NOTE: Included Furnish, Delivery and Hauling of materials o
Materials:
Source: Bayog Quarry
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
Gravel (25mm in size) Gravel packing
Manpower:
No. of Men
Foreman
Mason
Steelman
Laborer

1
1
1
1

Total Estimated Direct Cost (EDC)

c)Pipes, Fittings,gauges,Valves
Materials:
5/8" x 12" Stainless bolt w/ nut

50mm ID x 0.8m GI Pipe Sch.40


32mm ID x 6m GI Pipe Sch. 40 w/ coupling
50mm ID x 32mm GI Pipe bell Reducer
50mm GI Union
50mmGI Swing Check Valve
Pressure Gauge
50mm x 19 mm GI bell reducer
50mm GI Tee
50mm CI Gate Valve
50mmx0.20 m GI Nipple sch. 40
50mmx0.30 m GI Nipple Sch. 40
50mm ID x 45 GI Elbow sch.40
25mm Wide thread tape
50mm CI Water meter
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber

1
3
3

Total Estimated Direct Cost (EDC)

1002

PLUMBING
A)Tapstand(25 units)
(NOTE: Included Furnish, Delivery and Haulin
Q=
25 units
Source: Bayog Quarry
a.)Materials:
13mm ID x 6.0m G.I. Pipe sch 40 w/ coupling
Connectors,fittings,valves and hydrants
13mm Brass l Faucets
13mm Water Meter
13mm x 90 Elbow
13mm x 13mm G.I. Bell Reducer
13mm G.I. Ball Valves
13mm G.I. Union
25mm Wide thread tape
Padlock (Egret)

150mm ID x 19mmID C.I Saddle clamp


75mm ID x 19mmID C.I Saddle clamp
63mm ID x 19mmID C.I Saddle clamp
50mm ID x 19mmID C.I Saddle clamp
38mm ID x 19mmID C.I Saddle clamp
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
1/8"thk x 1.22 x 2.44 Steel Plate
6mm x 1.22m x 2.44 Marine Plywood
#7.5cm CWN
#3.75 cm CWN
100 pcs 2" x 2" x 10' Gem. Lumber
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber
Mason
Carpenter
Labor

1
4
4
4
4
12

Total Estimated Direct Cost (EDC)

A.Elevated Cylindrical Storage Tank (1 unit)


Plumbing:
150mm CI Gate Valve F/F w/ bolt & nut
150mm CI Adaptor MJ/F w/ bolt & nut
150mm CI Tee F/F w/ bolt & nut
150mm G.I. Elbow 90 GI Elbow sch.40
150mm ID GI Union sch. 40
150mm IDx0.80m GI Nipple Threaded sch.40
150mm ID x 3.80m GI Nipple Threaded sch. 40
50mm IDx0.50m GI Nipple Threaded sch.40
50mm ID x 0.20m GI Nipple Threaded sch. 40

50mm G.I. Elbow 90 GI Elbow sch.40


50mm ID GI Union sch. 40
25mm Wide Thread Tape

Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber

1
2
2

Total Estimated Direct Cost (EDC)

455

PAINTING
A.Elevated Cylindrical Storage Tank (1 unit)
(NOTE: Included Furnish, Delivery and Hauling of materials o
a.)Materials
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
Blue Tinting color DB
Yellow tinting color DB
Green Tinting color DB
Black Tinting color DB
Paint Roller w/ tray 7"
Paint Roller 7" Foam
Paint roller 6" w/ handle
Paint roller 4" w/ handle
Epoxy Primer Gray
Epoxy Primer Yellow
Epoxy Strong Hold RSC
Epoxy Fortress
Reducer

QDE Paint Blue


Lettering Brush
L.T Primer White
L.T Reducer
L.T Semigloss White
L.T Cast
Paint Thinner
Lacquer Thinner
Easytite
Concrete Nuetralizer
Patching Compound
Paint tray
Paint Brush 3"
Paint Brush 2 1/2"
Paint brush 2"
Sand Paper # 120
Sand Paper # 600
Sand Paper # 80
Putty Knife

Manpower:
Foreman
Painter
Labor

No. of Men
1
3
6

Total Estimated Direct Cost (EDC)

1102 POWER LOAD CENTER,SWITCHGEAR and PANELBOARDS


Construction of of Pump house (1 unit)
a.)Materials
15mm ID x 3.0m PVC Pipe
15mm ID x 90 PVC bend

15mm ID male threaded adaptor


15mm ID entrance cap
15mm PVC Clip
Solvent Cement Eslon blue 150G
12mm TW stranded wire
Electrical tape
37.5 Kva Distribution Transformer
Cut-out w/ Lightning arrester 9 KV
6 mm Aluminum Service Entrance Drop Wire
Panel board 4-Branches
100 AT Double Throw Circuit Breaker
60 AT Double Throw Circuit Breaker
30 AT Double Throw Circuit Breaker
15 AT Double Throw Circuit Breaker
#10TW Copper Wire (Stranded)
Kilo-Watt Meter
Manpower:
Electrician
Laborer

No. of Men
2.00
2.00

Total Estimated Direct Cost (EDC)

Republic of the Philippines


DEPARTMENT OF AGRICULTURE
anao Rural Developement Program-Phase II
San Jose, Imelda, Zamboanga Sibugay

II at San jose

DETAILED APPROVED AGENCY ESTIMATE


Unit

Quantity

Unit Cost

ibution line)
(NOTE: Heavy soil, rock and a portion of concrete to be excavated)
depth
Volume
1m
123.30 cu.m.
1m
774.20 cu.m.
123.30
774.20
897.50
Unit
days
days

cu.m.
cu.m.
cu.m.

Qty.

Unit Rate
40.00
40.00

360.00
200.00

>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

Furnish, Delivery and Hauling of materials on project site)


Estimated Distance=15 Km

Th/H
0.10 m
1.50 m

0.23
0.57

3.00 m
0.20 m
Total Volume

0.27
0.20
1.27

bags
cu.m.
cu.m.
pcs
pcs
pcs
pcs
shts
shts
shts
kgs
kgs

15.00
1.00
1.50
150.00
24.00
15.00
5.00
4.00
1.00
10.00
5.00
15.00

280.00
1,000.00
1,200.00
15.00
30.00
204.00
90.00
280.00
280.00
520.00
100.00
100.00

kgs
kgs
unit
can
bdft
bdft
bdft
bdft

2.00
2.00
1.00
1.00
50.00
33.33
26.67
166.67
Material Cost

100.00
120.00
2,500.00
250.00
30.00
30.00
30.00
30.00

Unit
days
days
days
days
days

Qty.
9.00
9.00
7.00
9.00
9.00

Unit Rate
360.00
260.00
280.00
260.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

(Included Perimeter Fence)


Furnish, Delivery and Hauling of materials on project site)
Estimated Distance = 15 Km
Th/H
0.20 m
2.00 m
0.20 m
Total Volume

bags
m
m
pcs
pcs
kgs
kgs
kgs
cu.m.
m
bdft
bdft
shts

254.00
14.00
28.00
45.00
24.00
5.00
15.00
10.00
6.00
290.00
50.00
33.33
3.00

21.60
0.72
0.80
23.12

280.00
1,000.00
1,200.00
204.00
90.00
100.00
100.00
100.00
1,200.00
25.00
30.00
30.00
520.00

ln.m.
sht
kgs

4.00
2.00
2.00
Material Cost

1,350.00
3,780.00
170.00

days
days

6.00
6.00
Equipment Cost

1,278.00
976.00

Unit
days
days
days
days
days

Qty.

Unit Rate
16.00
16.00
12.00
16.00
16.00

360.00
260.00
260.00
260.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

(3 m elevation)
ry and Hauling of materials on project site)
ce : Bayog Quarry
Th/H

m
m
m
m
Total Volume
bags
cu.m
cu.m.
kgs
pcs
pcs
pcs
pcs
pcs
kgs
sht
rolls

Estimated Distance= 15 Km
0.20
3.50
5.20
4.20
0.40
0.25

485.00
25.50
44.00
250.00
100.00
230.00
350.00
5.00
200.00
150.00
1.00
3.00

8.17
15.83
3.33
6.62
10.00
0.12
44.07
280.00
1,000.00
1,200.00
150.00
850.00
750.00
462.00
2,520.00
204.00
100.00
3,780.00
7,500.00

m.
m.

kgs
kgs
sht
sht
bdft
bdft
bdft
pcs
pcs
pcs
kgs

50.00
175.00
25.00
70.00
2,000.00
4,680.00
2,000.00
2.00
24.00
6.00
5.00
Material Cost

days
days
days

Unit
days
days
days
days
days

100.00
100.00
520.00
350.00
30.00
30.00
30.00
250.00
85.00
690.00
170.00

35.00
35.00
30.00
Equipment Cost

Qty.

1,278.00
976.00
700.00

Unit Rate
60.00
60.00
50.00
60.00
60.00

360.00
260.00
280.00
260.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

V=
V=

123.30
774.20

Total Volume
2 cu.m./day
Unit
days
days

897.50

Qty.

Unit Rate
32.00
32.00

360.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

pcs

Unit

103.00
Material Cost
Qty.

1,900.00

Unit Rate
15.00
15.00
15.00
15.00

360.00
280.00
280.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

pcs
pcs
pcs

10.00
8.00
30.00
Material Cost

185.00
175.00
45.00

Unit
days
days
days

Qty.

Unit Rate
3.00
3.00
3.00

360.00
280.00
280.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

pcs

35.00

6,784.00

pcs

52.00

3,016.00

pcs

560.00

2,185.00
Material Cost

Unit

Qty.

Unit Rate
45.00
45.00
45.00
45.00

360.00
280.00
280.00
200.00

Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
258 units
pc
pc
pc
pc
pc
pc
pc
pc
pc
pc

14.00
10.00
18.00
3.00
11.00
13.00
18.00
17.00
33.00
14.00

3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00
2,400.00
2,400.00
2,400.00
2,400.00

pc

14.00

2,600.00

pc

11.00

2,600.00

pc

11.00

2,600.00

pcs

1.00

5,903.00

pcs

1.00

4,950.00

pcs

7.00

3,340.00

pcs

3.00

2,800.00

pcs
pcs
pcs
pcs
pcs
pcs
pcs
units
cans

Unit

9.00
6.00
6.00
3.00
3.00
6.00
3.00
3.00
20.00

1,086.00
3,200.00
2,400.00
2,600.00
3,000.00
2,400.00
3,200.00
14,250.00
270.00
Material Cost

Qty.

Unit Rate
30.00
30.00
30.00

360.00
280.00
280.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

(Material=
(Labor Installation=

w/ level electrodes

1.00 unit
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

220,000.00

pcs
pcs
pcs

13.00
13.00
2.00
Material Cost

7,020.00
624.00
670.00

Th/H
0.20 m
ry and Hauling of materials on project site)
bags
m
m
pcs
kgs
cu.m.

Unit
days
days
days
days

1.06

10.00
0.50
1.00
10.00
1.00
2.00
Material Cost
Qty.

280.00
1,000.00
1,200.00
204.00
100.00
1,200.00

Unit Rate
2.00
2.00
2.00
2.00

360.00
260.00
260.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

pcs

5.00

190.00

pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs

1.00
5.00
1.00
1.00
1.00
1.00
1.00
2.00
1.00
5.00
3.00

3,200.00
2,950.00
450.00
75.00
380.00
2,300.00
450.00
80.00
2,800.00
170.00
170.00

pcs
pcs
pc.

1.00
6.00
1.00

180.00
45.00
30,000.00
Material Cost

Unit
days
days
days

Qty.

Unit Rate
1.00
3.00
3.00

360.00
280.00
280.00

Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

Furnish, Delivery and Hauling of materials on project site)


ce: Bayog Quarry
Estimated Distance= 15 Km.
pcs
pcs
pcs
pcs
pcs
pcs
pcs
rolls
pcs

45.00

525.00

25.00
25.00
210.00
39.00
39.00
39.00
60.00
31.00

175.00
1,700.00
56.00
45.00
180.00
45.00
45.00
150.00

pcs
pcs
pcs
pcs
pcs
bags
m
m
pcs
kgs
sht
pcs
kgs
kgs
bd.ft.

Unit
days
days
days
days
days
days

2.00
16.00
5.00
7.00
3.00
160.00
21.00
26.00
120.00
7.00
7.00
58.00
21.00
9.00
518.00
Material Cost
Qty.

1,200.00
1,140.00
990.00
948.00
780.00
280.00
1,000.00
1,200.00
204.00
100.00
3,780.00
520.00
100.00
100.00
30.00

Unit Rate
17.00
17.00
17.00
17.00
17.00
17.00

360.00
280.00
280.00
260.00
260.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

pcs
pcs
pc
pcs
pc
pc
pc
pcs
pcs

2.00
3.00
1.00
2.00
1.00
1.00
1.00
6.00
2.00

6,345.00
5,456.00
5,200.00
220.00
570.00
750.00
5,700.00
575.00
490.00

pcs
pc
roll

Unit
days
days
days

4.00
1.00
5.00
Material Cost

Qty.

190.00
190.00
45.00

Unit Rate
10.00
10.00
10.00

360.00
280.00
280.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

ry and Hauling of materials on project site)


gal
gal
pint
pint
pint
pint
set
pcs
pcs
pcs
gal
gal
gal
gal
gal

14.00
14.00
4.00
4.00
3.00
3.00
4.00
5.00
3.00
8.00
10.00
11.00
4.00
5.00
2.00

878.00
878.00
160.00
160.00
160.00
160.00
250.00
20.00
48.00
54.00
600.00
186.00
2,630.00
4,050.00
908.00

gal
pcs
gal
gal
gal
gal
gal
gal
gal
lit
gal
pcs
pcs
pcs
pcs
pcs
pcs
ft
pairs

Unit
days

10.00
4.00
16.00
14.00
5.00
6.00
7.00
10.00
4.00
4.00
30.00
5.00
3.00
3.00
17.00
54.00
11.00
13.00
4.00
Material Cost

Qty.

780.00
12.00
720.00
405.00
894.00
478.00
216.00
216.00
312.00
95.00
24.00
30.00
42.00
48.00
75.00
13.00
14.00
37.00
42.00

Unit Rate
14.00
14.00
14.00

360.00
280.00
200.00

Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

pcs
pcs

4.00
10.00

185.00
36.00

pcs
pcs
pcs
can
mtr
roll
unit
unit
mtrs
unit
pc
pc
pc
pc
mtrs
unit

Unit
days
days

2.00
2.00
18.00
2.00
10.00
2.00
1.00
1.00
300.00
1.00
1.00
1.00
1.00
1.00
30.00
1.00
Material Cost
Qty.

25.00
89.00
25.00
250.00
87.00
90.00
125,000.00
12,000.00
40.00
700.00
2,800.00
350.00
350.00
280.00
25.00
2,700.00

Unit Rate
5
5

280.00
200.00
Labor Cost

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)

Amount

ted)

Amount
14,400.00
120,000.00
134,400.00
134,400.00
134,400.00
149.75

cu.m.
cu.m.

cu.m.
cu.m.
cu.m.
4,200.00
1,000.00
1,800.00
2,250.00
720.00
3,060.00
450.00
1,120.00
280.00
5,200.00
500.00
1,500.00

200.00
240.00
2,500.00
250.00
1,500.00
999.90
800.10
5,000.10
33,570.10
Amount
3,240.00
2,340.00
1,960.00
2,340.00
3,600.00
13,480.00

47,050.10
47,050.10
47,050.10

cu.m
cu.m
cu.m
cu.m

71,120.00
14,000.00
33,600.00
9,180.00
2,160.00
500.00
1,500.00
1,000.00
7,200.00
7,250.00
1,500.00
999.90
1,560.00
5,400.00
7,560.00
340.00
164,869.90

7,667.00
5,855.00
13,522.00

Amount
5,760.00
12,480.00
6,240.00
8,320.00
22,400.00
55,200.00
233,591.90
233,591.90
233,591.90

cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
135,800.00
25,500.00
52,800.00
37,500.00
85,000.00
172,500.00
161,700.00
12,600.00
40,800.00
15,000.00
3,780.00
22,500.00

5,000.00
17,500.00
13,000.00
24,500.00
60,000.00
140,400.00
60,000.00
500.00
2,040.00
4,140.00
850.00
1,093,410.00

44,730.00
34,160.00
21,000.00
99,890.00

Amount
21,600.00
62,400.00
42,000.00
46,800.00
180,000.00
352,800.00
1,546,100.00
1,546,100.00
1,546,100.00

cu.m.
cu.m.

cu.m.

Amount
11,520.00
89,600.00
101,120.00
101,120.00
101,120.00
112.668524

195,700.00
195,700.00
Amount
5,400.00
12,600.00
12,600.00
18,000.00
48,600.00
244,300.00
244,300.00
396.269262

1,850.00
1,400.00
1,350.00
4,600.00

Amount
1,080.00
840.00
840.00
2,760.00

7,360.00
7,360.00
11.938362

237,440.00

156,832.00

1,223,600.00
1,617,872.00
Amount
16,200.00
88,200.00
88,200.00
180,000.00

372,600.00
1,990,472.00
1,990,472.00
514.20

44,800.00
32,000.00
57,600.00
9,600.00
35,200.00
50,180.00
43,200.00
40,800.00
79,200.00
33,600.00
36,400.00
28,600.00

28,600.00
5,903.00
4,950.00
23,380.00
8,400.00

9,774.00
19,200.00
14,400.00
7,800.00
9,000.00
14,400.00
9,600.00
42,750.00
5,400.00
694,737.00
Amount
10,800.00
58,800.00
58,800.00
128,400.00
823,137.00
823,137.00
212.64

200,000.00
20,000.00

220,000.00
220,000.00

91,260.00
8,112.00
1,340.00
100,712.00

cu.m

2,800.00
500.00
1,200.00
2,040.00
100.00
2,400.00
9,040.00
Amount
720.00
520.00
520.00
400.00
2,160.00
111,912.00
111,912.00
111,912.00

950.00

3,200.00
14,750.00
450.00
75.00
380.00
2,300.00
450.00
160.00
2,800.00
850.00
510.00
180.00
270.00
30,000.00
57,325.00
Amount
360.00
2,520.00
2,520.00
5,400.00
62,725.00
62,725.00
62,725.00

23,625.00
4,375.00
42,500.00
11,760.00
1,755.00
7,020.00
1,755.00
2,700.00
4,650.00

2,400.00
18,240.00
4,950.00
6,636.00
2,340.00
44,800.00
21,000.00
31,200.00
24,480.00
700.00
26,460.00
30,160.00
2,100.00
900.00
15,540.00
332,046.00
Amount
6,120.00
19,040.00
19,040.00
17,680.00
17,680.00
40,800.00
120,360.00
452,406.00
452,406.00
18,096.24

12,690.00
16,368.00
5,200.00
440.00
570.00
750.00
5,700.00
3,450.00
980.00

760.00
190.00
225.00
47,323.00

Amount
3,600.00
2,800.00
5,600.00
12,000.00
59,323.00
59,323.00
59,323.00

12,292.00
12,292.00
640.00
640.00
480.00
480.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00

7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
110,728.00

Amount
5,040.00
11,760.00
16,800.00
33,600.00
144,328.00
144,328.00
144,328.00

740.00
360.00

50.00
178.00
450.00
500.00
870.00
180.00
125,000.00
12,000.00
12,000.00
700.00
2,800.00
350.00
350.00
280.00
750.00
2,700.00
160,258.00
Amount
2,800.00
2,000.00
4,800.00
165,058.00
165,058.00
165,058.00

Potrebbero piacerti anche