Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Item No.
1
2
3
4
5
6
7
8
Scope of Work
Trench Excavation
( Transmission/Distribution)
Construction of Pump house
Installation of Submersible pump
Drilling
Transmission Line
Cylindrical Storage tank (24,000.0 ltrs.,
cap)
Distribution line
Tapstand
Total Direct Cost
Breakdown of Estimates
A. Direct Cost
% Weight
Quantity
Unit
3.33%
5.09%
3.10%
8.62%
3.01%
498.70
1.00
1.00
180.00
352.00
units
unit
unit
feet
ln.m.
473.73
361,803.71
220,000.00
3,403.00
606.71
18.47%
49.92%
8.46%
1.00
4,635.00
25.00
unit
ln.m.
unit
1,311,486.55
764.92
24,039.43
Unit Price
100.00%
Grant
3,551,018.03
Materials
Equipment
Labor
By Contract
200 calendar days
DT, BackhoeLoader, Staketruck
Civil Engr, Foreman.Plumber,
Pipefitter, Carpenters, Laborers
SOURCES OF FUNDS
LGU Equity
Cash
Non-Cash
3,551,018.03
7,102,036.06
Total
2,248,881.40
207,015.00
1,095,121.63
2,248,881.40
207,015.00
1,095,121.63
817,642.48
817,642.48
1,63
32,867.50
3,551.02
426,122.16
32,867.50
3,551.02
426,122.16
85
355,101.80
355,101.80
71
4,368,660.51
4,368,660.51
8,737,321.03
4,368,660.51
50%
4,368,660.51
50%
8,737,321.03
100%
B. Indirect Cost
Plumbing Tools(Threaders,Pipe Wrench, Pipe
Cutter)
Prepared by:
Recommended Approval:
Municipal Engineer
Approved:
4,497,762.80
414,030.00
2,190,243.26
Reviewed by:
RPCO - RIE
Approved by:
Municipal Mayor
days
Loader, Staketruck
Foreman.Plumber,
Carpenters, Laborers
Total
236,250.00
361,803.71
220,000.00
612,540.10
213,563.25
1,311,486.55
3,545,406.60
600,985.85
7,102,036.06
Total
41,063.77
6
4,497,762.80
414,030.00
2,190,243.26
1,635,284.97
50304.44
###
65,735.00
7,102.04###
852,244.33###
710,203.61###
8,737,321.03
8,737,321.03
100%
PARAWAN, DVM
al Executive Director
79.32
ADJUSTED PRICE
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
Mindanao Rural Developement Program-Phase II
San Jose, Imelda, Zamboanga Sibugay
PROJECT
LOCATION
:
:
Unit
Unit Cost
V=
V=
A. Labor:
15.0 Laborer
35.20 cu.m.
463.50 cu.m.
498.70 cu.m.
days
total
45.00
350.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
II
Quantity
bags
m
m
pcs
pcs
pcs
pcs
pcs
pc
pcs
kgs
kgs
kgs
kgs
set
pair
can
bd.ft.
bd.ft.
bd.ft.
35.00
4.00
5.00
173.00
28.00
32.00
18.00
6.00
2.00
5.00
6.00
18.00
3.00
3.00
1.00
3.00
2.00
80.00
86.66
40.00
280.00
1,000.00
1,000.00
15.00
28.00
204.00
90.00
280.00
280.00
520.00
100.00
100.00
100.00
120.00
980.00
95.00
250.00
30.00
30.00
30.00
pcs
4.00
185.00
pcs
10.00
36.00
pcs
2.00
25.00
pcs
2.00
89.00
pcs
18.00
25.00
can
2.00
250.00
mtr
10.00
87.00
roll
2.00
90.00
pc
1.00
200,000.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
B. Labor:
total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
3
Unit
Quantity
Unit Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
IV
A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire
Gravel (25mm in size) Gravel packing
burb wire
bags
m
m
pcs
kgs
kgs
kgs
cu.m.
m
Pipes:
150mm x 6.0m uPVC Pipe Class 150 (casing)
38mm x 6.0m G.I. Pipe sch 40 w/ coupling (suction)
"thk x 20mm x 38mm discharge plate
5/8" x 12" Stainless bolt w/ nut
38mm x 90 G.I. elbow
38mm G.I. Tee
38mm x 13mm G.I. bushing reducer
Pressure gauge
38mm G.I. Union
38mmx 0.20m G.I. Nipple threaded sch 40
38mm G.I. Gate Valve
38mm G.I. Swing Check Valve
25mm Wide thread tape
50mm GI Water meter
Sub total
B: Equipment Rental
Driling machine 180ft drill halo w/
casing installation
52.00
4.00
5.00
12.00
3.00
6.00
2.00
6.00
290.00
280.00
1,000.00
1,000.00
204.00
100.00
100.00
100.00
1,000.00
25.00
pcs
13.00
7,020.00
pcs
13.00
520.00
pcs
2.00
670.00
pcs
5.00
190.00
pcs
2.00
75.00
pcs
3.00
80.00
pcs
2.00
75.00
pcs
2.00
2,300.00
pcs
2.00
75.00
pcs
10.00
130.00
pcs
3.00
350.00
pcs
2.00
380.00
pcs
6.00
45.00
pc.
1.00
2,400.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
feet
180.00
2,200.00
C. Labor:
total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Unit
Direct Cost
Unit Cost
V
Quantity
Unit Cost
pcs
75.00
1,900.00
pcs
6.00
185.00
pcs
12.00
175.00
pcs
35.00
45.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
VI
bags
m
m
pcs
pcs
pcs
pcs
pcs
kgs
kgs
kgs
sht
pcs
pcs
box
pcs
bd.ft.
bd.ft.
Plumbing:
150mm ID x 0.50m G.I. Nipple Threaded sch 40
150mm G.I. Elbow 45
100mm ID x 0.50 G.I. Nipple Threaded sch 40
75mm ID c 0.20m G.I. Nipple Threaded sch 40
50mm ID x 0.30m G.I. Nipple Threaed sch 40
150mm CI Gate Valve MJ/F NRS w/ bolts and
nuts & Gasket
150mm CI Adaptor MJ/F NRS w/ bolts and
nuts & Gasket
150mm CI Tee 150mm x 150mm F/F w/ bolts
and nuts
150mm CI 90 F/F w/ bolts and nuts
100mm G.I. Gate Valve screw end
75mm GI Elbow 90
50mm GI Elbow 90
50mm GI Union
25mm Wide Thread tape
50mm Water meter
C: Painting:
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
5
406.00
25.00
36.00
406.00
42.00
617.00
5.00
67.00
118.00
33.00
190.00
2.00
18.00
7.00
3.00
83.00
920.00
2,026.00
280.00
1,000.00
1,000.00
150.00
510.00
288.00
2,100.00
204.00
100.00
100.00
100.00
3,780.00
85.00
690.00
2,940.00
520.00
30.00
30.00
pcs
pcs
pcs
pcs
pcs
10.00
5.00
5.00
3.00
4.00
750.00
220.00
650.00
575.00
490.00
pcs
4.00
6,345.00
pcs
9.00
5,456.00
pcs
pcs
pcs
pcs
pcs
pcs
roll
pc.
2.00
3.00
3.00
2.00
4.00
2.00
6.00
1.00
5,200.00
3,450.00
5,903.00
889.50
190.00
190.00
45.00
2,400.00
gal
gal
14.00
14.00
878.00
878.00
Unit
Quantity
Unit Cost
Sub total
pint
4.00
160.00
pint
4.00
160.00
pint
3.00
160.00
pint
3.00
160.00
set
4.00
250.00
pcs
5.00
20.00
pcs
3.00
48.00
pcs
8.00
54.00
gal
10.00
600.00
gal
11.00
186.00
gal
4.00
2,630.00
gal
5.00
4,050.00
gal
2.00
908.00
gal
10.00
780.00
pcs
4.00
12.00
gal
16.00
720.00
gal
14.00
405.00
gal
5.00
894.00
gal
6.00
478.00
gal
7.00
216.00
gal
10.00
216.00
gal
4.00
312.00
lit
4.00
95.00
gal
30.00
24.00
pcs
5.00
30.00
pcs
3.00
42.00
pcs
3.00
48.00
pcs
17.00
75.00
pcs
54.00
13.00
pcs
11.00
14.00
ft
13.00
37.00
pairs
4.00
42.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
total
days
8.00
1,278.00
days
8.00
976.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
B: Equipment Rental
1
unit 1 Bagger Concrete mixer
1
unit Concrete Vibrator
C. Labor:
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
VII
A. Material:
150mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
100mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
75mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
63mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
50mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
13mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Fitting:
connector:
150mm CI Tee 150 x 150mm F/F w/ bolt & nuts
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts
150mm CI 90" elbow F/F w/ bolt & nuts
75mm CI 90" elbow F/F w/ bolt & nuts
50mm CI 90" elbow F/F w/ bolt & nuts
150mm CI 45" elbow F/F w/ bolt & nuts
75mm CI 45" elbow F/F w/ bolt & nuts
6
pcs
18.00
6,784.00
pcs
33.00
3,016.00
pcs
823.00
2,011.00
pcs
49.00
1,412.00
pcs
69.00
986.00
pcs
46.00
450.00
pc
pc
pc
pc
pc
pc
pc
4.00
10.00
5.00
3.00
7.00
3.00
14.00
3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00
Unit
Unit Cost
6.00
3,200.00
pc
pc
pc
pc
5.00
6.00
35.00
4.00
2,400.00
2,400.00
2,400.00
2,400.00
pc
4.00
2,600.00
pc
4.00
2,600.00
pc
3.00
2,600.00
pcs
3.00
5,903.00
pcs
4.00
4,950.00
pcs
5.00
3,340.00
pcs
4.00
2,800.00
9.00
41.00
1,086.00
270.00
pcs
cans
sub total
Quantity
pc
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
VIII
pcs
25.00
240.00
pcs
25.00
2,500.00
pcs
173.00
56.00
pcs
29.00
45.00
pcs
29.00
180.00
pcs
55.00
618.00
pcs
29.00
525.00
pcs
29.00
45.00
rolls
58.00
45.00
pcs
25.00
150.00
pcs
2.00
1,200.00
pcs
5.00
1,260.00
pcs
14.00
1,140.00
pcs
4.00
990.00
pcs
5.00
948.00
pcs
2.00
780.00
bags
334.00
280.00
m
20.00
1,000.00
m
29.00
1,000.00
pcs
115.00
204.00
kgs
6.00
100.00
pcs
58.00
520.00
kgs
21.00
100.00
kgs
9.00
100.00
sht
6.00
3,780.00
bd.ft.
518.00
30.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
C. Labor:
total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
7
Unit
Quantity
Unit Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
equipment
material
labor
Amount
756.6
236,250.00
236,250.00
236,250.00
236,250.00
473.731702
9,800.00
4,000.00
5,000.00
2,595.00
784.00
6,528.00
1,620.00
1,680.00
560.00
2,600.00
600.00
1,800.00
300.00
360.00
980.00
285.00
500.00
2,400.00
2,599.80
1,200.00
740.00
360.00
50.00
178.00
450.00
500.00
870.00
180.00
200,000.00
249,519.80
112,283.91
361,803.71
361,803.71
361,803.710000
9
3783
4539.6
Amount
220,000.00
220,000.00
200,000.00
20,000.00
220,000.00
220,000.00
220,000.000000
14,560.00
4,000.00
5,000.00
2,448.00
300.00
600.00
200.00
6,000.00
7,250.00
91,260.00
6,760.00
1,340.00
950.00
150.00
240.00
150.00
4,600.00
150.00
1,300.00
1,050.00
760.00
270.00
2,400.00
149,338.00
396,000.00
67,202.10
612,540.10
10
Amount
612,540.10
3,403.000556
0% Applied
142,500.00
1,110.00
2,100.00
1,575.00
147,285.00
66,278.25
213,563.25
213,563.25
606.713778
113,680.00
25,000.00
36,000.00
60,900.00
21,420.00
177,696.00
10,500.00
13,668.00
11,800.00
3,300.00
19,000.00
7,560.00
1,530.00
4,830.00
8,820.00
43,160.00
27,600.00
60,780.00
7,500.00
1,100.00
3,250.00
1,725.00
1,960.00
25,380.00
49,104.00
10,400.00
10,350.00
17,709.00
1,779.00
760.00
380.00
270.00
2,400.00
12,292.00
12,292.00
11
Amount
640.00
640.00
480.00
480.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
892,039.00
10,223.00
7,807.00
18,030.00
401,417.55
1,311,486.55
1,311,486.55
1,311,486.550000
0% Applied
122,112.00
99,528.00
1,655,053.00
69,188.00
68,034.00
20,700.00
12,800.00
32,000.00
16,000.00
9,600.00
22,400.00
9,600.00
54,040.00
12
Amount
19,200.00
12,000.00
14,400.00
84,000.00
9,600.00
10,400.00
10,400.00
7,800.00
17,709.00
19,800.00
16,700.00
11,200.00
9,774.00
11,070.00
2,445,108.00
1,100,298.60
3,545,406.60
3,545,406.60
764.920518
6,000.00
62,500.00
9,688.00
1,305.00
5,220.00
33,990.00
15,225.00
1,305.00
2,610.00
3,750.00
2,400.00
6,300.00
15,960.00
3,960.00
4,740.00
1,560.00
93,520.00
20,000.00
29,000.00
23,460.00
600.00
30,160.00
2,100.00
900.00
22,680.00
15,540.00
414,473.00
186,512.85
13
Amount
600,985.85
600,985.85
24,039.434000
414,030.00
4,497,762.80
2,190,243.26
7,102,036.06
7,102,036.06
-
14
15
16
17
18
19
20
Back-up Estimate
Project
Location
21.46
0.8 m x
0.7
1.5
0.8 m x
0.7
0.4
3
0.9 m x
0.9
0.6
1.54
10.0
2.0
33.0
5.3
5.3
5.3
1.4
0.130
0.120
5.3
5.3
5.3
1.4
0.040
0.025
0.8 m x
0.7
0.2 m x
0.2
0.4
5.3
5.3
1.2
0.2
0.2
0.2 m x
0.2
3.8 m x
3.8
0.2
5.3
1.4
2.7
0.2
0.2
4.51
9.24
0.8 m x
0.7
0.2 m x
0.2
10.0
2.0
10.0
2.0
31.0
0.1
0.1
0.15
17.0
13.8
1239.22
12 mm x 6m Def bar =
10 mm x 6m Def bar =
# 16 GI tie wire =
Hack saw blade =
0.888
0.616
131.7
0.86
5.8
31
4.9
26.66
28.42 m -
3.36
Wall 2
4" x 8" x 16"
Wall 3
4" x 8" x 16"
Wall 4
4" x 8" x 16"
Comfort room
Septic vault
38 pcs - 3" x 2' Conc Baluster
3.8
5.8
3.8
3.8
4.9
4.9
4.9
2.1
4.56
7.17
7.17
127.78
8"
8"
8"
8"
x
x
x
x
16"
16"
16"
16"
211.88
5.8
3.8
5.8
3.8
3.8
Stainless Faucet
Shower head
Shower Valve
x 90 PVC blue elbow
PVC Tee
PVC Coupling
x 3.0m PVC Blue pipe
4.9
4.9
4.9
4.9
2.1
56.84 m
37.24 m
59.86 m
40.26 m
31.92
11.7
3.36
4.56
7.17
7.17
Prepared by:
Checked by:
MARVIN A. MUYARGAS
Project In-Charge
Approved by :
ROMEO C. ESTOQUIA
Chief, Construction Division
units =
units =
mtrs
5.760 m
0.88
7.92
6.93
21.492
7.4
2.9
8.8
5
9
33.1
thk
3.65
0.89
4.54 m (Compacted volume)
5.45 m ( loose volume )
thk
1.12
0.19
1.31 m (Compacted volume)
1.57 m ( loose volume )
units
units
units
units
mtrs
thk
=
=
=
=
/m
/m
1.280 m
0.2
1.520 m
0.3
2.48
2.81
0.74
0.49
0.68
0.55
11.049
3
6.2
11
5.5
3
12.4
9.8
5.9
31.1
16.5
293.04 kgs
946.18 kgs
25.00 kgs
5.33
3.7
1,264.22 kgs
333.25
26.66
25.06
2.8
6.05
3.03
4.9 16.75
14.06
24.27
14.47
15.96
11.7
2.28
0.72
1.89
3.51
1.56
1319
105.52
132.18
53.48
32.68
52.69
33.09
31.92
11.7
215.56
215.56
1.00 pc
1.00 pc
1.00 pc
4.00
3.00
1.00
2.00
5.00
8.00
3.00
2.00
1.00
1.00
2.00
1.00
pcs
pcs
pc
pcs
pcs
pcs
pcs
pcs
pc
pc
pcs
can
2.00
1.00
1.00
5.00
3.00
5.00
4.00
pcs
pc
pc
pcs
pcs
pcs
pcs
4.56
0.72
1.89
7.02
4.68
11.70
15.00 pcs
1.00 roll
130.00
160.00
21.33
235.00
180.00
bd.ft.
bd.ft.
bd.ft.
bd.ft.
bd.ft.
726.33 bd.ft.
67.5 sq.m.
304.00
40.00
23.00
0.50
9.00
bd.ft.
bd.ft.
pcs
kgs
kgs
72.54
211.88
67.50
16.22
368.14
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
5.00
8.00
8.00
1.00
4.00
15.00
3.00
3.00
1.00
4.00
2.00
1.00
4.00
4.00
1.00
15.00
gals
gals
gals
gals
pints
kgs
gals
gals
lit
pints
gals
sets
pcs
pcs
roll
pcs
28.82 sq.m.
A. MUYARGAS
ct In-Charge
C. ESTOQUIA
nstruction Division
272.00
101.33
4.00
8.00
5.00
3.00
bd.ft.
bd.ft.
pcs
kgs
pair
set
15.48 sq.m.
15.82
0.36
72sq.m.
Name of Project:
SPL I
DESCRIPTION
% of Total
802 Excavation
804 Embankment
900 Reinforced Concrete
404 Reinforcing Steel
704 Masonry Works
1002 Plumbing Works
1010 Wooden Doors & Windows
1003 Carpentry & Joinery Work
1013 Corr. Metal Roofing
1018 Tile Work
1005 Steel window Casement
1100 Electrical Works
Furn. & instal of billboards
TOTAL
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Unit
QTY
cu.m.
cu.m.
cu.m.
kgs.
sq.m.
L. S.
sq.m.
bd.ft.
sq.m.
sq.m.
sq.m.
L. S.
l.s
1.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Checked by:
ARNALDO I. BEUP Jr.
Engineering Asst.
Recommended by:
ABDURAJIK H. MAULOD,MPA
Provincial Engineer
EDGAR M. ETAC
Engineer III
ippines
GA SIBUGAY
RS OFFICE
a Sibugay
OF WORKS
Appropriation:
P 750,000.00
Source of fund:
20% LDF - 2004
Issued Obligated Authority:
Calendar Days to Complete: W.D
Desirable Starting Date: ASAP
DESCRIPTION
Welder
Tile sitter
Plumber
Labor
NO.
1
2
1
6
Direct Cost
Total
361,803.71
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Unit Cost
###
#REF!
#REF!
#REF!
#REF!
#REF!
% OF TOTAL
#REF!
#REF!
#REF!
#REF!
#REF!
DESCRIPTION NO.
Welding Machine - 1
Grinding Machine - 1
Adjusted Unit
Direct + Indirect
Cost
cost
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
3,000.00
#REF!
AMOUNT
599.70
4,497,762.80
0.00
292.03
2,190,243.26
55.204
414,030.00
946.94
7,102,036.06
104.16
113.63
781,223.97
852,244.33
#REF!
9.469
117.42
0.40
1292.02
71,020.36
880,652.47
3,000.00
2,588,141.13
9,690,177.19
33.14
248,571.26
12.920
3.000
49.06
96,901.77
22,500.00
367,973.03
-1241.09
100
(9,308,150.22)
750,000.00
Submitted by:
ROMEL G. DURAN
Engineer IV
Chief, P P D D
Approved by:
GEORGE T. HOFER, MD
Provincial Governor
ADJUSTED PRICE
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
Mindanao Rural Developement Program-Phase II
San Jose, Imelda, Zamboanga Sibugay
PROJECT
LOCATION
:
:
Unit
V=
V=
Laborer
35.20 cu.m.
463.50 cu.m.
498.70 cu.m.
days
total
Quantity
45.00
>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
bags
m
m
pcs
pcs
pcs
pcs
pcs
pc
pcs
kgs
kgs
kgs
35.00
4.00
5.00
173.00
28.00
32.00
18.00
6.00
2.00
5.00
6.00
18.00
3.00
kgs
set
pair
can
bd.ft.
bd.ft.
bd.ft.
3.00
1.00
3.00
2.00
80.00
86.66
40.00
pcs
4.00
pcs
10.00
pcs
2.00
pcs
2.00
pcs
18.00
can
2.00
mtr
10.00
roll
2.00
pc
1.00
>>>>>>>>>>>>>>>>>>>>>>>>
B. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
III
>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
A. Material
Goulds submersible Pump Stainless Steel
casing close coupled to a 4.5 HP 1 phase 230v
60 Hz, Franklin submersible motor, with built-in
lighting protection, original brand new, made in USA
to include the foll.
- Motor lead assy
- Built-in check valve and strainer
190ft. Submersible cable wire no.14
380ft Suspension wire No.14
- Panel board metal enclosure consist of the
foll.
- magnetic starter w/ overload
B/W Water level cut-off control w/ levelelectrodes
- on/off push button switch
- lightning arrester
1 set water roof splicing tape
1.00 unit
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>
B. Labor:
total
Direct Cost
Unit Cost
IV
>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
A. Material:
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#3.75 cm CWN
#10.02cm CWN
#16 Tie Wire
Gravel (25mm in size) Gravel packing
burb wire
bags
m
m
pcs
kgs
kgs
kgs
cu.m.
m
52.00
4.00
5.00
12.00
3.00
6.00
2.00
6.00
290.00
Pipes:
150mm x 6.0m uPVC Pipe Class 150 (casing)
pcs
13.00
38mm x 6.0m G.I. Pipe sch 40 w/ coupling (suction)
pcs
13.00
"thk x 20mm x 38mm discharge plate
pcs
2.00
5/8" x 12" Stainless bolt w/ nut
pcs
5.00
38mm x 90 G.I. elbow
pcs
2.00
38mm G.I. Tee
pcs
3.00
38mm x 13mm G.I. bushing reducer
pcs
2.00
Pressure gauge
pcs
2.00
38mm G.I. Union
pcs
2.00
38mmx 0.20m G.I. Nipple threaded sch 40
pcs
10.00
38mm G.I. Gate Valve
pcs
3.00
38mm G.I. Swing Check Valve
pcs
2.00
25mm Wide thread tape
pcs
6.00
50mm GI Water meter
pc.
1.00
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>
B: Equipment Rental
Driling machine 180ft drill halo w/
casing installation
feet
180.00
C. Labor:
total
Total Estimated Direct Cost (EDC)
>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
V
pcs
75.00
pcs
6.00
pcs
12.00
pcs
35.00
>>>>>>>>>>>>>>>>>>>>>>>>
VI
>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
bags
m
m
pcs
pcs
pcs
pcs
pcs
kgs
kgs
kgs
sht
pcs
pcs
box
pcs
bd.ft.
bd.ft.
Plumbing:
150mm ID x 0.50m G.I. Nipple Threaded sch 40 pcs
150mm G.I. Elbow 45
pcs
100mm ID x 0.50 G.I. Nipple Threaded sch 40
pcs
406.00
25.00
36.00
406.00
42.00
617.00
5.00
67.00
118.00
33.00
190.00
2.00
18.00
7.00
3.00
83.00
920.00
2,026.00
10.00
5.00
5.00
C: Painting:
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
Blue Tinting color DB
Yellow tinting color DB
Green Tinting color DB
Black Tinting color DB
paint Roller w/ tray 7"
paint Roller 7" Foam
paint roller 6" w/ handle
paint roller 4" w/ handle
Epoxy Primer Gray
Epoxy Primer Yellow
Epoxy Strong Hold RSC
Epoxy Fortress
Reducer
QDE Paint Blue
Lettering Brush
L.T Primer White
L.T Reducer
L.T Semigloss White
L.T Cast
Paint Thinner
Lacquer Thinner
Easytite
Concrete Nuetralizer
Patching Compound
Paint tray
Paint Brush 3"
Paint Brush 2 1/2"
pcs
pcs
3.00
4.00
pcs
4.00
pcs
9.00
pcs
pcs
pcs
pcs
pcs
pcs
roll
pc.
2.00
3.00
3.00
2.00
4.00
2.00
6.00
1.00
gal
gal
pint
pint
pint
pint
set
pcs
pcs
pcs
gal
gal
gal
gal
gal
gal
pcs
gal
gal
gal
gal
gal
gal
gal
lit
gal
pcs
pcs
pcs
14.00
14.00
4.00
4.00
3.00
3.00
4.00
5.00
3.00
8.00
10.00
11.00
4.00
5.00
2.00
10.00
4.00
16.00
14.00
5.00
6.00
7.00
10.00
4.00
4.00
30.00
5.00
3.00
3.00
paint brush
Sand Paper
Sand Paper
Sand Paper
Putty Knife
2"
# 120
# 600
# 80
Sub total
B: Equipment Rental
1
unit 1 Bagger Concrete mixer
1
unit Concrete Vibrator
total
pcs
17.00
pcs
54.00
pcs
11.00
ft
13.00
pairs
4.00
>>>>>>>>>>>>>>>>>>>>>>>>
days
8.00
days
8.00
>>>>>>>>>>>>>>>>>>>>>>>>
C. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
VII
>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
18.00
pcs
33.00
pcs
823.00
pcs
49.00
pcs
69.00
pcs
46.00
Fitting:
connector:
150mm CI Tee 150 x 150mm F/F w/ bolt & nutspc
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts
pc
150mm CI 90" elbow F/F w/ bolt & nuts
pc
75mm CI 90" elbow F/F w/ bolt & nuts
pc
50mm CI 90" elbow F/F w/ bolt & nuts
pc
150mm CI 45" elbow F/F w/ bolt & nuts
pc
75mm CI 45" elbow F/F w/ bolt & nuts
pc
50mm CI 45" elbow F/F w/ bolt & nuts
pc
Adaptor:
150mm CI Adaptor MJ/F
pc
100mm CI Adaptor MJ/F
pc
4.00
10.00
5.00
3.00
7.00
3.00
14.00
6.00
5.00
6.00
pc
pc
35.00
4.00
pc
4.00
pc
4.00
pc
3.00
pcs
3.00
pcs
4.00
pcs
5.00
pcs
4.00
pcs
cans
9.00
41.00
>>>>>>>>>>>>>>>>>>>>>>>>
VIII
>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
rolls
pcs
pcs
pcs
pcs
25.00
25.00
173.00
29.00
29.00
55.00
29.00
29.00
58.00
25.00
2.00
5.00
14.00
pcs
4.00
pcs
5.00
pcs
2.00
bags
334.00
m
20.00
m
29.00
pcs
115.00
kgs
6.00
pcs
58.00
kgs
21.00
kgs
9.00
sht
6.00
bd.ft.
518.00
>>>>>>>>>>>>>>>>>>>>>>>>
C. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
equipment
material
labor
RICE
URE
ram-Phase II
bugay
TIMATE
Unit Cost
Amount
250.00
168,750.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
168,750.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
168,750.00
168,750.00
338.379787
Estimated Volume)
250.00
750.00
800.00
12.00
12.00
170.00
90.00
250.00
250.00
345.00
90.00
90.00
90.00
8,750.00
3,000.00
4,000.00
2,076.00
336.00
5,440.00
1,620.00
1,500.00
500.00
1,725.00
540.00
1,620.00
270.00
120.00
850.00
95.00
250.00
24.00
24.00
24.00
360.00
850.00
285.00
500.00
1,920.00
2,079.84
960.00
185.00
740.00
15.00
150.00
18.00
36.00
25.00
50.00
8.00
144.00
120.00
240.00
87.00
870.00
90.00
180.00
200,000.00
200,000.00
>>>>>>>>>>>>>>>>>>>>>>> 240,741.84
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
108,333.83
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
349,075.67
Estimated Volume)
349,075.67
349,075.668000
220,000.00
220,000.00
>>>>>>>>>>>>>>>>>>>>>>> 220,000.00
material
labor
200,000.00
20,000.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
220,000.00
220,000.00
220,000.000000
Estimated Volume)
250.00
750.00
800.00
170.00
90.00
90.00
90.00
800.00
25.00
13,000.00
3,000.00
4,000.00
2,040.00
270.00
540.00
180.00
4,800.00
7,250.00
2,175.00
28,275.00
520.00
6,760.00
450.00
900.00
160.00
800.00
75.00
150.00
80.00
240.00
75.00
150.00
2,300.00
4,600.00
75.00
150.00
130.00
1,300.00
350.00
1,050.00
380.00
760.00
45.00
270.00
800.00
800.00
>>>>>>>>>>>>>>>>>>>>>>> 80,485.00
2,200.00
396,000.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
36,218.25
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
512,703.25
512,703.25
2,848.351389
Estimated Volume)
1,900.00
142,500.00
185.00
1,110.00
175.00
2,100.00
45.00
1,575.00
>>>>>>>>>>>>>>>>>>>>>>> 147,285.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
66,278.25
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
213,563.25
213,563.25
606.713778
Estimated Volume)
280.00
750.00
800.00
120.00
380.00
240.00
2,100.00
170.00
90.00
90.00
90.00
1,350.00
85.00
450.00
2,940.00
345.00
24.00
24.00
750.00
220.00
650.00
113,680.00
18,750.00
28,800.00
48,720.00
15,960.00
148,080.00
10,500.00
11,390.00
10,620.00
2,970.00
17,100.00
2,700.00
1,530.00
3,150.00
8,820.00
28,635.00
22,080.00
48,624.00
7,500.00
1,100.00
3,250.00
575.00
490.00
2,150.00
1,450.00
2,500.00
215.00
190.00
190.00
45.00
800.00
1,725.00
1,960.00
12,000.00
22,500.00
4,300.00
4,350.00
7,500.00
430.00
760.00
380.00
270.00
800.00
520.00
520.00
120.00
120.00
120.00
120.00
250.00
20.00
48.00
54.00
600.00
186.00
2,630.00
4,050.00
908.00
780.00
12.00
720.00
405.00
894.00
478.00
216.00
216.00
312.00
95.00
24.00
30.00
42.00
48.00
7,280.00
7,280.00
480.00
480.00
360.00
360.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
3,000.00
2,500.00
75.00
1,275.00
13.00
702.00
14.00
154.00
37.00
481.00
42.00
168.00
>>>>>>>>>>>>>>>>>>>>>>> 711,078.00
1,278.00
10,223.00
976.00
7,807.00
>>>>>>>>>>>>>>>>>>>>>>>>>>
18,030.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
319,985.10
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
1,049,093.10
1,049,093.10
1,049,093.100000
Estimated Volume)
4,975.00
89,550.00
2,337.00
77,121.00
1,550.00
1,275,650.00
1,076.00
52,724.00
758.00
52,302.00
450.00
20,700.00
1,500.00
1,500.00
1,500.00
1,500.00
1,500.00
1,500.00
1,860.00
1,500.00
6,000.00
15,000.00
7,500.00
4,500.00
10,500.00
4,500.00
26,040.00
9,000.00
1,200.00
1,200.00
6,000.00
7,200.00
1,200.00
1,200.00
42,000.00
4,800.00
1,300.00
5,200.00
1,300.00
5,200.00
2,600.00
7,800.00
2,800.00
8,400.00
2,800.00
11,200.00
1,000.00
5,000.00
2,800.00
11,200.00
1,000.00
120.00
9,000.00
4,920.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
1,779,007.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
800,553.15
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
2,579,560.15
2,579,560.15
556.539407
Estimated Volume)
125.00
1,950.00
25.00
35.00
40.00
480.00
395.00
25.00
45.00
130.00
1,200.00
1,050.00
950.00
3,125.00
48,750.00
4,325.00
1,015.00
1,160.00
26,400.00
11,455.00
725.00
2,610.00
3,250.00
2,400.00
5,250.00
13,300.00
825.00
790.00
650.00
250.00
750.00
800.00
170.00
90.00
345.00
90.00
90.00
1,350.00
24.00
>>>>>>>>>>>>>>>>>>>>>>>
3,300.00
3,950.00
1,300.00
83,500.00
15,000.00
23,200.00
19,550.00
540.00
20,010.00
1,890.00
810.00
8,100.00
12,432.00
317,347.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
142,806.15
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
460,153.15
Estimated Volume)
460,153.15
18,406.126000
414,030.00
3,475,943.84
1,662,924.73
5,552,898.57
5,552,898.57
-
:
:
1600
Trench Excavation
Q=
587.04 cu.m
Unit
Unit Cost
V=
V=
V=
1.00
14.00
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
II
Quantity
35.20
454.00
97.84
587.04
days
days
cu.m.
cu.m.
cu.m.
cu.m.
17.00
17.00
360.00
200.00
>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
bags
cu.m.
cu.m.
pcs
pcs
pcs
pcs
shts
shts
shts
kgs
kgs
kgs
kgs
unit
can
bdft
bdft
bdft
bdft
pcs
pcs
pcs
pcs
pcs
can
mtr
roll
unit
unit
mtrs
unit
pc
pc
pc
pc
mtrs
unit
25.00
2.00
2.50
147.00
24.00
15.00
5.00
4.00
1.00
10.00
5.00
15.00
2.00
2.00
1.00
1.00
50.00
33.33
26.67
166.67
280.00
1,000.00
1,000.00
15.00
30.00
204.00
90.00
280.00
280.00
520.00
100.00
100.00
100.00
120.00
2,500.00
250.00
30.00
30.00
30.00
30.00
4.00
10.00
2.00
2.00
18.00
2.00
10.00
2.00
1.00
1.00
300.00
1.00
1.00
1.00
1.00
1.00
30.00
1.00
185.00
36.00
25.00
89.00
25.00
250.00
87.00
90.00
125,000.00
12,000.00
40.00
700.00
2,800.00
350.00
350.00
280.00
25.00
2,700.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
B. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
III
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
IV
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
bags
m
m
pcs
kgs
kgs
kgs
cu.m.
m
220.00
14.00
28.00
45.00
5.00
15.00
5.00
6.00
290.00
280.00
1,000.00
1,000.00
204.00
100.00
100.00
100.00
1,000.00
25.00
pcs
13.00
7,020.00
pcs
13.00
624.00
pcs
2.00
670.00
pcs
5.00
190.00
pcs
1.00
3,200.00
pcs
5.00
2,950.00
pcs
1.00
450.00
pcs
1.00
75.00
pcs
1.00
380.00
pcs
1.00
2,300.00
pcs
1.00
450.00
pcs
2.00
80.00
pcs
1.00
2,800.00
pcs
5.00
170.00
pcs
3.00
170.00
pcs
1.00
180.00
pcs
6.00
45.00
pc.
1.00
30,000.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
feet
180.00
2,200.00
C. Labor:
total
Total Estimated Direct Cost (EDC)
Direct Cost
Unit Cost
V
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
73.00
1,900.00
pcs
6.00
185.00
pcs
5.00
175.00
pcs
20.00
45.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
bags
cu.m
cu.m.
kgs
pcs
pcs
pcs
pcs
rolls
pcs
kgs
kgs
kgs
sht
sht
bdft
bdft
bdft
sht
pcs
pcs
pcs
kgs
465.00
25.00
45.00
200.00
80.00
220.00
310.00
4.00
3.00
280.00
1,000.00
1,000.00
150.00
850.00
750.00
510.00
2,520.00
7,500.00
185.00
150.00
50.00
175.00
20.00
68.00
2,000.00
4,680.00
2,080.00
1.00
2.00
24.00
6.00
2.00
204.00
100.00
100.00
100.00
520.00
350.00
30.00
30.00
30.00
3,780.00
250.00
85.00
690.00
170.00
Plumbing:
150mm CI Gate Valve F/F w/ bolt & nut
150mm CI Adaptor MJ/F w/ bolt & nut
150mm CI Tee F/F w/ bolt & nut
150mm G.I. Elbow 90 GI Elbow sch.40
150mm ID GI Union sch. 40
150mm IDx0.80m GI Nipple Threaded sch.40
150mm ID x 3.80m GI Nipple Threaded sch. 40
50mm IDx0.50m GI Nipple Threaded sch.40
50mm ID x 0.20m GI Nipple Threaded sch. 40
50mm G.I. Elbow 90 GI Elbow sch.40
50mm ID GI Union sch. 40
25mm Wide Thread Tape
pcs
pcs
pc
pcs
pc
pc
pc
pcs
pcs
pcs
pc
roll
2.00
3.00
1.00
2.00
1.00
1.00
1.00
6.00
2.00
4.00
1.00
5.00
6,345.00
5,456.00
5,200.00
220.00
570.00
750.00
5,700.00
575.00
490.00
190.00
190.00
45.00
C: Painting:
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
Blue Tinting color DB
Yellow tinting color DB
Green Tinting color DB
Black Tinting color DB
paint Roller w/ tray 7"
paint Roller 7" Foam
gal
gal
pint
pint
pint
pint
set
pcs
14.00
14.00
4.00
4.00
3.00
3.00
4.00
5.00
878.00
878.00
160.00
160.00
160.00
160.00
250.00
20.00
pcs
3.00
48.00
pcs
8.00
54.00
gal
10.00
600.00
gal
11.00
186.00
gal
4.00
2,630.00
gal
5.00
4,050.00
gal
2.00
908.00
gal
10.00
780.00
pcs
4.00
12.00
gal
16.00
720.00
gal
14.00
405.00
gal
5.00
894.00
gal
6.00
478.00
gal
7.00
216.00
gal
10.00
216.00
gal
4.00
312.00
lit
4.00
95.00
gal
30.00
24.00
pcs
5.00
30.00
pcs
3.00
42.00
pcs
3.00
48.00
pcs
17.00
75.00
pcs
54.00
13.00
pcs
11.00
14.00
ft
13.00
37.00
pairs
4.00
42.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Sub total
B: Equipment Rental
1
unit 1 Bagger Concrete mixer
1
unit Concrete Vibrator
total
days
8.00
1,278.00
days
8.00
976.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
C. Labor:
total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Direct Cost
Unit Cost
VII
A. Material:
150mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
100mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
75mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
19mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Fitting:
connector:
150mm CI Tee 150 x 150mm F/F w/ bolt & nuts
75mm CI Tee 75 x 75mm F/F w/ bolt & nuts
150mm CI 90" elbow F/F w/ bolt & nuts
75mm CI 90" elbow F/F w/ bolt & nuts
150mm CI 45" elbow F/F w/ bolt & nuts
75mm CI 45" elbow F/F w/ bolt & nuts
Adaptor:
150mm CI Adaptor MJ/F
100mm CI Adaptor MJ/F
75mm CI Adaptor MJ/F
50mm CI Adaptor MJ/F
Reducer:
150mm x 100mm CI Reducer F/F w/ bolts
and Nuts and gasket
100mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
150mm x 75mm CI Reducer F/F w/ bolts
and Nuts and gasket
Gate valve:
150mm CI Gate Valve F/F NRS w/ bolts
nuts and gasket
100mm CI Gate Valve F/F NRS w/ bolts
pcs
14.00
6,784.00
pcs
25.00
3,016.00
pcs
600.00
2,011.00
pcs
46.00
450.00
pc
pc
pc
pc
pc
pc
4.00
10.00
5.00
3.00
3.00
14.00
3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00
pc
pc
pc
pc
5.00
6.00
35.00
4.00
2,400.00
2,400.00
2,400.00
2,400.00
pc
4.00
2,600.00
pc
4.00
2,600.00
pc
3.00
2,600.00
pcs
1.00
5,903.00
pcs
1.00
4,950.00
pcs
7.00
3,340.00
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
units
cans
3.00
2,800.00
9.00
6.00
6.00
3.00
3.00
6.00
3.00
3.00
20.00
1,086.00
3,200.00
2,400.00
2,600.00
3,000.00
2,400.00
3,200.00
14,250.00
270.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
19.00
240.00
pcs
19.00
2,500.00
pcs
160.00
56.00
pcs
29.00
45.00
pcs
29.00
180.00
pcs
55.00
618.00
pcs
29.00
525.00
pcs
29.00
45.00
rolls
58.00
45.00
pcs
25.00
150.00
pcs
2.00
1,200.00
pcs
5.00
1,260.00
pcs
14.00
1,140.00
pcs
4.00
990.00
pcs
5.00
948.00
pcs
2.00
780.00
bags
334.00
280.00
m
20.00
1,000.00
m
29.00
1,000.00
pcs
115.00
204.00
kgs
6.00
100.00
pcs
58.00
520.00
kgs
21.00
100.00
kgs
9.00
100.00
sht
6.00
3,780.00
bd.ft.
518.00
30.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
materials
Labor
equipment
handtools
equipment
material
labor
Amount
6,120.00
47,600.00
53,720.00
53,720.00
53,720.00
91.509948
7,000.00
2,000.00
2,500.00
2,205.00
720.00
3,060.00
450.00
1,120.00
280.00
5,200.00
500.00
1,500.00
200.00
240.00
2,500.00
250.00
1,500.00
999.90
800.10
5,000.10
740.00
360.00
50.00
178.00
450.00
500.00
870.00
180.00
125,000.00
12,000.00
12,000.00
700.00
2,800.00
350.00
350.00
280.00
750.00
2,700.00
166,353.10
489.20
97.84
195.68
16.31
360
66,541.24
232,894.34
232,894.34
232,894.340000
220,000.00
220,000.00
200,000.00
20,000.00
220,000.00
220,000.00
220,000.000000
61,600.00
14,000.00
28,000.00
9,180.00
500.00
1,500.00
500.00
6,000.00
7,250.00
91,260.00
8,112.00
1,340.00
950.00
3,200.00
14,750.00
450.00
75.00
380.00
2,300.00
450.00
160.00
2,800.00
850.00
510.00
180.00
270.00
30,000.00
256,567.00
396,000.00
102,626.80
755,193.80
755,193.80
4,195.521111
138,700.00
1,110.00
875.00
900.00
141,585.00
56,634.00
198,219.00
198,219.00
563.122159
130,200.00
25,000.00
45,000.00
30,000.00
68,000.00
165,000.00
158,100.00
10,080.00
22,500.00
37,740.00
15,000.00
5,000.00
17,500.00
10,400.00
23,800.00
60,000.00
140,400.00
62,400.00
3,780.00
500.00
2,040.00
4,140.00
340.00
12,690.00
16,368.00
5,200.00
440.00
570.00
750.00
5,700.00
3,450.00
980.00
760.00
190.00
225.00
12,292.00
12,292.00
640.00
640.00
480.00
480.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
1,194,971.00
10,223.00
7,807.00
18,030.00
477,988.40
1,690,989.40
1,690,989.40
1,690,989.400000
94,976.00
75,400.00
1,206,600.00
20,700.00
12,800.00
32,000.00
16,000.00
9,600.00
9,600.00
54,040.00
12,000.00
14,400.00
84,000.00
9,600.00
10,400.00
10,400.00
7,800.00
5,903.00
4,950.00
23,380.00
8,400.00
9,774.00
19,200.00
14,400.00
7,800.00
9,000.00
14,400.00
9,600.00
42,750.00
5,400.00
1,732,723.00
693,089.20
2,425,812.20
2,425,812.20
641.240338
4,560.00
47,500.00
8,960.00
1,305.00
5,220.00
33,990.00
15,225.00
1,305.00
2,610.00
3,750.00
2,400.00
6,300.00
15,960.00
3,960.00
4,740.00
1,560.00
93,520.00
20,000.00
29,000.00
23,460.00
600.00
30,160.00
2,100.00
900.00
22,680.00
15,540.00
397,305.00
158,922.00
556,227.00
556,227.00
29,275.105263
4,089,504.10
1,629,521.64
414,030.00
6,133,055.74
37,000.00
61,330.56
735,966.69
613,305.57
7,580,658.56
1%
12%
10%
414,030.00
4,089,504.10
1,629,521.64
6,133,055.74
6,133,055.74
-
ADJUSTED PRICE
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
MINDANAO RURAL DEVELOPMENT PROGRAM-Phase II
Scope of Work
% Weight
Quantity
1
2
3
4
5
Trench Excavation
(Transmission/Distribution)
Construction of Pump house
Installation of Submersible pump
Drilling & Pumping Station
Transmission Line
2.31%
3.40%
3.38%
11.62%
3.05%
489.20
1.00
1.00
180.00
352.00
6
7
8
26.02%
41.67%
8.56%
1.00
4,635.00
19.00
Breakdown of Estimates
A. Direct Cost
Materials
Equipment
Labor
100.00%
Grant
SOURCES OF FUNDS
LGU Equity
3,249,748.70
Cash
3,249,748.70
2,141,238.50
207,015.00
901,495.40
2,141,238.50
207,015.00
901,495.40
B. Indirect Cost
765,942.20
765,942.20
18,500.00
32,497.49
389,969.84
18,500.00
32,497.49
389,969.84
324,974.87
324,974.87
4,015,690.90
4,015,690.90
4,015,690.90
50%
4,015,690.90
50%
Prepared by:
Recommending Approval:
EMMANUEL D. SALOMES
Municipal Engineer
Approved:
EXPEDITO B. GONZALES
Municipal Mayor
JULIO T. ALDE
Mun. Planning & Dev. Coordinator
TED PRICE
hilippines
GRICULTURE
ENT PROGRAM-Phase II
anga Sibugay
Imelda
IPAL ENGINEER
RAM OF WORK
o.
mplementation Mode:
Duration
ent Needed:
al Personnel:
Unit
By Contract
200 calendar days
Bagger Concrete Mixer, Concrete
Vibrator,Drilling Machine
Civil Engr, Foreman.Plumber,
Pipefitter, Carpenters, Laborers
Unit Price
Total
units
unit
unit
feet
ln.m.
306.62
220,819.20
220,000.00
4,195.52
563.12
150,000.00
220,819.20
220,000.00
755,193.80
198,219.00
unit
ln.m.
unit
1,690,989.40
584.26
29,275.11
1,690,989.40
2,708,049.00
556,227.00
6,499,497.40
SOURCES OF FUNDS
LGU Equity
Non-Cash
6,499,497.40
Total
4,282,477.00
414,030.00
1,802,990.80
1,531,884.41
37,000.00
64,994.98
779,939.69
649,949.74
8,031,381.81
8,031,381.81
100%
Reviewed by:
Approved by:
PROJECT
LOCATION
:
:
Unit
Quantity
Unit Cost
1600
123.30
788.00
911.30
Qty.
40.00
40.00
cu.m.
cu.m.
cu.m.
Unit Rate
360.00
200.00
>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
300
REINFORCED CONCRETE
kgs
kgs
unit
can
bdft
bdft
bdft
bdft
2.00
100.00
2.00
120.00
1.00
2,500.00
1.00
250.00
50.00
30.00
33.33
30.00
26.67
30.00
166.67
30.00
Material Cost
b)Manpower
No. of Men
Foreman
1.00
Mason
1.00
Steelman
1.00
Carpenter
1.00
Laborer
2.00
Unit
days
days
days
days
days
Qty.
9.00
9.00
7.00
9.00
9.00
Unit Rate
360.00
260.00
280.00
260.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
c)Manpower:
days
days
6.00
1,278.00
6.00
976.00
Equipment Cost
Foreman
Mason
Steelman/Welder
Carpenter
Laborer
No. of Men
1
3
2
2
7
Unit
days
days
days
days
days
Qty.
16.00
16.00
12.00
16.00
16.00
Unit Rate
360.00
260.00
260.00
260.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
kgs
kgs
sht
sht
bdft
bdft
bdft
pcs
pcs
pcs
kgs
days
days
days
50.00
175.00
25.00
70.00
2,000.00
4,680.00
2,000.00
2.00
24.00
6.00
5.00
Material Cost
100.00
100.00
520.00
350.00
30.00
30.00
30.00
250.00
85.00
690.00
170.00
35.00
1,278.00
35.00
976.00
30.00
700.00
Equipment Cost
c.)Manpower:
No. of Men
Unit
Qty.
Unit Rate
Foreman
Mason
Steelman
Carpenter
Laborer
1
4
3
3
15
days
days
days
days
days
60.00
60.00
50.00
60.00
60.00
Labor Cost
360.00
260.00
280.00
260.00
200.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
1601
No. of Men
1
15
Unit
days
days
123.30
788.00
911.30
Qty.
Unit Rate
31.00
360.00
31.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
1602
INSTALLATION OF PIPELINE
A.) Transmission Pipeline
Q=
616.50 ln.m.
Laying of Pipes
a.) Material:
50mm ID x 6.0m G.I. Pipe sch. 40 w/ coupling
pcs
103.00
1,900.00
Material Cost
Manpower:
No. of Men
Foreman
1
Pipe Fitter
3
Plumber
3
Laborer
6
Unit
days
days
days
days
Qty.
15.00
15.00
15.00
15.00
Unit Rate
360.00
280.00
280.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
pcs
pcs
48.00 units
10.00
185.00
8.00
175.00
30.00
45.00
Material Cost
Manpower:
Foreman
No. of Men
1
Unit
days
Qty.
3.00
Unit Rate
360.00
Pipe Fitter
Plumber
1
1
days
days
3.00
3.00
280.00
280.00
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
ln.m.
Laying of Pipes
a.) Material:
Q=
205.00
ln.m. of 150mm
150mm ID x 6.0m uPVC C-150 w/
pcs
electromagnetic rubber ring
Q= 311.00
ln.m. of 100mm
100mm ID x 6.0m uPVC C-150 w/
pcs
electromagnetic rubber ring
Q=
3,424.00
ln.m. of 75mm
75mm ID x 6.0m uPVC C-150 w/
pcs
electromagnetic rubber ring
35.00
6,784.00
52.00
3,016.00
570.00
2,185.00
Material Cost
Manpower:
No. of Men
Foreman
1
Pipe Fitter
7
Plumber
7
Laborer
20
Unit
days
days
days
days
Qty.
45.00
45.00
45.00
45.00
Unit Rate
360.00
280.00
280.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
263.00 units
14.00
10.00
18.00
3.00
11.00
15.00
18.00
17.00
35.00
14.00
3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00
2,400.00
2,400.00
2,400.00
2,400.00
14.00
2,600.00
11.00
2,600.00
11.00
2,600.00
pcs
1.00
5,903.00
pcs
2.00
4,950.00
pc
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
units
cans
7.00
3,340.00
3.00
9.00
6.00
6.00
3.00
3.00
6.00
3.00
3.00
20.00
2,800.00
1,086.00
3,200.00
2,400.00
2,600.00
3,000.00
2,400.00
3,200.00
14,250.00
270.00
Material Cost
Manpower:
No. of Men
Foreman
1
Pipe Fitter
7
Plumber
7
Unit
days
days
days
Qty.
Unit Rate
30.00
360.00
30.00
280.00
30.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
1201
a.). Material
Goulds submersible Pump Stainless Steel
casing close coupled to a 4.5 HP 1 phase 230v
60 Hz, Franklin submersible motor, with built-in
lighting protection, original brand new, made in USA
to include the foll.
- Motor lead assy
- Built-in check valve and strainer
190ft. Submersible cable wire no.14
380ft Suspension wire No.14
- Panel board metal enclosure consist of the
foll.
_Included Installation
(Material=
- magnetic starter w/ overload
(Labor Installation=
B/W Water level cut-off control w/ level electrodes
- on/off push button switch
- lightning arrester
1 set water roof splicing tape 1.00 unit
220,000.00
Sub total
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Dimension
13.00
7,020.00
13.00
624.00
2.00
670.00
Material Cost
Protection Slab
N
L
W
Th/H
1.00
2.30 m
2.30 m
0.20 m
1.06
(NOTE: Including Furnish, Delivery and Hauling of materials on project site)
Materials:
Source: Bayog Quarry
Estimated Distance= 15 Km.
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
Gravel (25mm in size) Gravel packing
bags
m
m
pcs
kgs
cu.m.
10.00
280.00
0.50
1,000.00
1.00
1,200.00
10.00
204.00
1.00
100.00
2.00
1,200.00
Material Cost
Unit
days
days
days
days
Qty.
Unit Rate
2.00
360.00
2.00
260.00
2.00
260.00
2.00
200.00
Labor Cost
Manpower:
Foreman
Mason
Steelman
Laborer
No. of Men
1
1
1
1
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
c)Pipes, Fittings,gauges,Valves
Materials:
5/8" x 12" Stainless bolt w/ nut
50mm ID x 0.8m GI Pipe Sch.40
32mm ID x 6m GI Pipe Sch. 40 w/ coupling
50mm ID x 32mm GI Pipe bell Reducer
50mm GI Union
50mmGI Swing Check Valve
Pressure Gauge
50mm x 19 mm GI bell reducer
50mm GI Tee
50mm CI Gate Valve
50mmx0.20 m GI Nipple sch. 40
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
5.00
1.00
5.00
1.00
1.00
1.00
1.00
1.00
2.00
1.00
5.00
190.00
3,200.00
2,950.00
450.00
75.00
380.00
2,300.00
450.00
80.00
2,800.00
170.00
pcs
pcs
pc.
1.00
6.00
1.00
180.00
45.00
30,000.00
Material Cost
Manpower:
No. of Men
Foreman
1
Pipe Fitter
3
Plumber
3
Total Estimated Direct Cost (EDC)
Unit
days
days
days
Qty.
Unit Rate
1.00
360.00
3.00
280.00
3.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
1002
PLUMBING
A)Tapstand(28 units)
(NOTE: Including Furnish, Delivery and Hauling of materials on proj
Q=
28 units
Source: Bayog Quarry
Estimated Distance= 15 K
a.)Materials:
13mm ID x 6.0m G.I. Pipe sch 40 w/ coupling pcs
52.00
525.00
Connectors,fittings,valves and hydrants
13mm Brass l Faucets
pcs
28.00
175.00
13mm Water Meter
pcs
28.00
1,700.00
13mm x 90 Elbow
pcs
235.00
56.00
13mm x 13mm G.I. Bell Reducer
pcs
44.00
45.00
13mm G.I. Ball Valves
pcs
44.00
180.00
13mm G.I. Union
pcs
44.00
45.00
25mm Wide thread tape
rolls
60.00
45.00
Padlock (Egret)
150mm ID x 19mmID C.I Saddle clamp
75mm ID x 19mmID C.I Saddle clamp
100mm ID x 19mmID C.I Saddle clamp
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
1/8"thk x 1.22 x 2.44 Steel Plate
6mm x 1.22m x 2.44 Marine Plywood
#7.5cm CWN
#3.75 cm CWN
100 pcs 2" x 2" x 10' Gem. Lumber
pcs
pcs
pcs
pcs
bags
m
m
pcs
kgs
sht
pcs
kgs
kgs
bd.ft.
31.00
150.00
1.00
1,200.00
26.00
1,140.00
1.00
990.00
197.00
280.00
21.00
1,000.00
26.00
1,200.00
120.00
204.00
7.00
100.00
7.00
3,780.00
58.00
520.00
21.00
100.00
9.00
100.00
518.00
30.00
Material Cost
No. of Men
Foreman
1
Pipe Fitter
4
Plumber
4
Mason
4
Carpenter
4
Labor
12
Unit
days
days
days
days
days
days
Qty.
Unit Rate
17.00
360.00
17.00
280.00
17.00
280.00
17.00
260.00
17.00
260.00
17.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Manpower:
pcs
pcs
pc
pcs
pc
pc
pc
pcs
pcs
2.00
3.00
1.00
2.00
1.00
1.00
1.00
6.00
2.00
pcs
pc
roll
4.00
190.00
1.00
190.00
5.00
45.00
Material Cost
6,345.00
5,456.00
5,200.00
220.00
570.00
750.00
5,700.00
575.00
490.00
Manpower:
No. of Men
Foreman
1
Pipe Fitter
2
Plumber
2
Unit
days
days
days
Qty.
Unit Rate
10.00
360.00
10.00
280.00
10.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
PAINTING
A.Elevated Cylindrical Storage Tank (1 unit)
(NOTE: Including Furnish, Delivery and Hauling of materials on project site)
a.)Materials
Nalcrete Acrylic Latex flat (white) DB
gal
14.00
878.00
Nalcrete Acrylic Latex Gloss (White) DB
gal
14.00
878.00
Blue Tinting color DB
pint
4.00
160.00
Yellow tinting color DB
pint
4.00
160.00
Green Tinting color DB
pint
3.00
160.00
Black Tinting color DB
pint
3.00
160.00
Paint Roller w/ tray 7"
set
4.00
250.00
Paint Roller 7" Foam
pcs
5.00
20.00
Paint roller 6" w/ handle
pcs
3.00
48.00
Paint roller 4" w/ handle
pcs
8.00
54.00
Epoxy Primer Gray
gal
10.00
600.00
Epoxy Primer Yellow
gal
11.00
186.00
Epoxy Strong Hold RSC
gal
4.00
2,630.00
Epoxy Fortress
gal
5.00
4,050.00
Reducer
gal
2.00
908.00
QDE Paint Blue
gal
10.00
780.00
Lettering Brush
pcs
4.00
12.00
L.T Primer White
gal
16.00
720.00
L.T Reducer
gal
14.00
405.00
L.T Semigloss White
gal
5.00
894.00
L.T Cast
gal
6.00
478.00
Paint Thinner
gal
7.00
216.00
Lacquer Thinner
gal
10.00
216.00
Easytite
gal
4.00
312.00
Concrete Nuetralizer
lit
4.00
95.00
Patching Compound
gal
30.00
24.00
Paint tray
pcs
5.00
30.00
Paint Brush 3"
pcs
3.00
42.00
Paint Brush 2 1/2"
pcs
3.00
48.00
Paint brush 2"
pcs
17.00
75.00
Sand Paper # 120
pcs
54.00
13.00
Sand Paper # 600
pcs
11.00
14.00
Sand Paper # 80
ft
13.00
37.00
Putty Knife
pairs
4.00
42.00
Material Cost
Manpower:
Foreman
Painter
Labor
No. of Men
1
3
6
Unit
days
days
days
Qty.
Unit Rate
14.00
360.00
14.00
280.00
14.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
185.00
36.00
25.00
89.00
pcs
can
mtr
roll
unit
unit
mtrs
unit
pc
pc
pc
pc
mtrs
unit
18.00
25.00
2.00
250.00
10.00
87.00
2.00
90.00
1.00
125,000.00
1.00
12,000.00
300.00
40.00
1.00
700.00
1.00
2,800.00
1.00
350.00
1.00
350.00
1.00
280.00
30.00
25.00
1.00
2,700.00
Material Cost
Manpower:
No. of Men
Electrician
2.00
Laborer
2.00
Unit
days
days
Qty.
Unit Rate
5
280.00
5
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
DEPARTMENT OF AGRICULTURE
MINDANAO RURAL DEVELOPMENT PROGRAM-Phase II
Material
4,881,185.00
4,881,185.00
labor
1,410,720.00
1,410,720.00
equipment
Amount
113,412.00
113,412.00
6,405,317.00
6,405,317.00
6,405,317.00
6318682.9
rete to be excavated)
160
1,493.93
Amount
14,400.00
120,000.00
106.71
65
111
88
92
143
134,400.00
45
46
134,400.00
90
65
134,400.00
147.48
75
82
40
72
125
64
118
90
68
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
110
79
57
147
250
130
4,200.00
1,000.00
1,800.00
2,250.00
720.00
3,060.00
450.00
1,120.00
280.00
5,200.00
500.00
1,500.00
82
117
114
65
96
184
25
57
130
82
117
114
65
96
184
3940
200.00
240.00
2,500.00
250.00
1,500.00
999.90
800.10
5,000.10
33,570.10
Amount
3,240.00
2,340.00
1,960.00
2,340.00
3,600.00
13,480.00
47,050.10
47,050.10
47,050.10
cu.m
cu.m
cu.m
cu.m
71,120.00
14,000.00
33,600.00
9,180.00
2,160.00
500.00
1,500.00
1,000.00
7,200.00
7,250.00
1,500.00
999.90
1,560.00
5,400.00
7,560.00
340.00
164,869.90
7,667.00
5,855.00
13,522.00
Amount
5,760.00
12,480.00
6,240.00
8,320.00
22,400.00
55,200.00
B. Electrical
233,591.90
233,591.90
233,591.90
on project site)
d Distance= 15 Km
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
135,800.00
25,500.00
52,800.00
37,500.00
85,000.00
172,500.00
161,700.00
12,600.00
40,800.00
15,000.00
3,780.00
22,500.00
5,000.00
17,500.00
13,000.00
24,500.00
60,000.00
140,400.00
60,000.00
500.00
2,040.00
4,140.00
850.00
1,093,410.00
44,730.00
34,160.00
21,000.00
99,890.00
Amount
160
21,600.00
62,400.00
42,000.00
46,800.00
180,000.00
352,800.00
1,546,100.00
1,546,100.00
1,546,100.00
cu.m.
cu.m.
cu.m.
Amount
11,160.00
93,000.00
104,160.00
104,160.00
104,160.00
114.30
195,700.00
195,700.00
Amount
5,400.00
12,600.00
12,600.00
18,000.00
48,600.00
244,300.00
244,300.00
396.269262
1,850.00
1,400.00
1,350.00
4,600.00
Amount
1,080.00
45
205
840.00
840.00
7,360.00
7,360.00
153.333333
237,440.00
156,832.00
1,245,450.00
1,639,722.00
Amount
16,200.00
88,200.00
88,200.00
180,000.00
372,600.00
2,012,322.00
2,012,322.00
510.74
44,800.00
32,000.00
57,600.00
9,600.00
35,200.00
57,900.00
43,200.00
40,800.00
84,000.00
33,600.00
36,400.00
28,600.00
28,600.00
5,903.00
9,900.00
65
46
82
118
311
23,380.00
8,400.00
9,774.00
19,200.00
14,400.00
7,800.00
9,000.00
14,400.00
9,600.00
42,750.00
5,400.00
712,207.00
Amount
10,800.00
58,800.00
58,800.00
128,400.00
840,607.00
840,607.00
3,196.22
200,000.00
20,000.00
220,000.00
220,000.00
91,260.00
8,112.00
1,340.00
100,712.00
cu.m
on project site)
2,800.00
500.00
1,200.00
2,040.00
100.00
2,400.00
9,040.00
Amount
720.00
520.00
520.00
400.00
2,160.00
111,912.00
111,912.00
111,912.00
950.00
3,200.00
14,750.00
450.00
75.00
380.00
2,300.00
450.00
160.00
2,800.00
850.00
180.00
270.00
30,000.00
57,325.00
Amount
360.00
2,520.00
2,520.00
5,400.00
62,725.00
62,725.00
62,725.00
4,650.00
1,200.00
29,640.00
990.00
55,160.00
21,000.00
31,200.00
24,480.00
700.00
26,460.00
30,160.00
2,100.00
900.00
15,540.00
351,720.00
Amount
6,120.00
19,040.00
19,040.00
17,680.00
17,680.00
40,800.00
120,360.00
472,080.00
472,080.00
16,860.00
12,690.00
16,368.00
5,200.00
440.00
570.00
750.00
5,700.00
3,450.00
980.00
760.00
190.00
225.00
47,323.00
Amount
3,600.00
2,800.00
5,600.00
12,000.00
59,323.00
59,323.00
59,323.00
on project site)
12,292.00
12,292.00
640.00
640.00
480.00
480.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
110,728.00
Amount
5,040.00
11,760.00
16,800.00
33,600.00
144,328.00
144,328.00
144,328.00
740.00
360.00
50.00
178.00
450.00
500.00
870.00
180.00
125,000.00
12,000.00
12,000.00
700.00
2,800.00
350.00
350.00
280.00
750.00
2,700.00
160,258.00
Amount
2,800.00
2,000.00
4,800.00
165,058.00
165,058.00
165,058.00
(86,634.10)
Item No.
Scope of Work
% Weight
Quantity
Unit
By Contract
200 calendar days
Bagger Concrete Mixer, Con.
2.10%
911.30
cu.m
0.73%
3.65%
24.14%
1.00
1.00
1.00
unit
unit
unit
1.63%
911.30
cu.m
114.30
3.81%
0.11%
616.50
48.00
Ln.m.
units
396.27
153.33
31.42%
13.12%
3,940.00
263.00
Ln.m.
units
510.74
3,196.22
3.43%
1.75%
0.98%
1.00
1.00
35.00
set
unit
units
###
###
1,792.14
7.37%
0.93%
28.00
1.00
units
unit
2.25%
1.00
unit
###
2.58%
1.00
unit
###
100.00%
147.48
47,050.10
###
1,546,100.00
16,860.00
59,323.00
6,405,317.00
Breakdown of Estimates
MRDP
A. Direct Cost
Materials
Equipment
Labor
B. Indirect Cost
Hand Tools
Quality Control (1% of direct cost)
Taxes (12% of the direct cost)
Contractor's Profit (10% of the direct cost)
C. Contract Cost= A + B
E. TOTAL PROJECT COST
Percentage Sharing
Prepared by:
EMMANUEL D. SALOMES
Municipal Engineer
Conformed:
###
SOURCES OF FUNDS
LGU Equity
Total
Cash
Non-Cash
###
6,405,317.00
2,440,592.50
56,706.00
705,360.00
755,111.46
18,500.00
32,026.59
384,319.02
320,265.85
###
2,440,592.50
56,706.00
705,360.00
755,111.46
18,500.00
32,026.59
384,319.02
320,265.85
###
###
###
50%
50%
Recommending Approval:
JULIO T. ALDE
Mun. Planning & Dev. Coordinator
4,881,185.00
113,412.00
1,410,720.00
1,510,2
37,
64,0
768,6
640,5
7,915,5
7,915,539.91
100%
Reviewed by:
OSCAR O. PARAWAN,
DA - Regional Executive D
tract
ndar days
r, Foreman.Plumber,
, Carpenters, Laborers,
teelman
Total
134,400.00
47,050.10
233,591.90
1,546,100.00
104,160.00
244,300.00
7,360.00
2,012,322.00
840,607.00
220,000.00
111,912.00
62,725.00
472,080.00
59,323.00
144,328.00
165,058.00
6,405,317.00
Total
17.00
4,881,185.00
113,412.00
1,410,720.00
1,510,222.91
37,000.00
64,053.17
768,638.04
640,531.70
7,915,539.91
7,915,539.91
100%
d by:
d by:
O. PARAWAN, DVM
onal Executive Director
PROJECT
LOCATION
:
:
(NOTE: Hea
V=
V=
Total Volume
300
REINFORCED CONCRETE
Post
Foundation
4.00
4.00
0.15 m
0.50 m
a)Materials:
Portland Cement
Washed Sand
Washed Gravel
4" x 8" x 16" CHB
6" x 6" Fixed Louver
10 mm x 6 m. Def. bars
8 mm x 6 m. Def. bars
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Roofing
0.90 mx 2.45 Corr.G.I. Sht. GA.26 Ridge Roll
6 mm x 1.22 x 2.44 Marine Plywood
#3.75 CW Nails
#10.02 Cw Nails
No. of Men
1.00
1.00
1.00
1.00
2.00
0.15 m
0.50 m
Dimensions:
Floor
Post
Foundation
b) Equipment Rental
1
unit Bagger Concrete mixer
1
unit Concrete Vibrator
c)Manpower:
No. of Men
Foreman
Mason
Steelman/Welder
Carpenter
Laborer
1
3
2
2
7
#3.75 cm CWN
# 10.02 cm CWN
19mm x 1.22m x 2.44 m Marine Plywood
6mm x 1.22m x 2.44m Marine Plywood
250 pcs-2"x4"12' lumber
780 pcs-2"x3"x12' Lumber
500 pcs-2"x2"x12'lumber
50mm Egret Padlock
Hacksaw Blade
Shovel
Welding rod
c.)Manpower:
No. of Men
Foreman
Mason
Steelman
Carpenter
Laborer
1
4
3
3
15
1601
Capability Manual
Manpower:
Foreman
Laborer
No. of Men
1
14
INSTALLATION OF PIPELINE
A.) Transmission Pipeline
Q=
616.50 ln.m.
Laying of Pipes
a.) Material:
50mm ID x 6.0m G.I. Pipe sch. 40 w/ coupling
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber
Laborer
1
3
3
6
2 cu.m./day
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber
1
1
1
ln.m.
Laying of Pipes
a.) Material:
Q=
205.00
ln.m. of 150mm
150mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Q= 311.00
ln.m. of 100mm
100mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Q=
3,355.00
ln.m. of 75mm
75mm ID x 6.0m uPVC C-150 w/
electromagnetic rubber ring
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber
Laborer
1
7
7
20
1
7
7
1201
Dimension
Protection Slab
N
L
W
1.00
2.30 m
2.30 m
(NOTE: Included Furnish, Delivery and Hauling of materials o
Materials:
Source: Bayog Quarry
Portland Cement
Washed sand
Washed Gravel (50mm in size)
10mm x 6.0m Def. Bars
#16 Tie Wire
Gravel (25mm in size) Gravel packing
Manpower:
No. of Men
Foreman
Mason
Steelman
Laborer
1
1
1
1
c)Pipes, Fittings,gauges,Valves
Materials:
5/8" x 12" Stainless bolt w/ nut
1
3
3
1002
PLUMBING
A)Tapstand(25 units)
(NOTE: Included Furnish, Delivery and Haulin
Q=
25 units
Source: Bayog Quarry
a.)Materials:
13mm ID x 6.0m G.I. Pipe sch 40 w/ coupling
Connectors,fittings,valves and hydrants
13mm Brass l Faucets
13mm Water Meter
13mm x 90 Elbow
13mm x 13mm G.I. Bell Reducer
13mm G.I. Ball Valves
13mm G.I. Union
25mm Wide thread tape
Padlock (Egret)
1
4
4
4
4
12
Manpower:
No. of Men
Foreman
Pipe Fitter
Plumber
1
2
2
455
PAINTING
A.Elevated Cylindrical Storage Tank (1 unit)
(NOTE: Included Furnish, Delivery and Hauling of materials o
a.)Materials
Nalcrete Acrylic Latex flat (white) DB
Nalcrete Acrylic Latex Gloss (White) DB
Blue Tinting color DB
Yellow tinting color DB
Green Tinting color DB
Black Tinting color DB
Paint Roller w/ tray 7"
Paint Roller 7" Foam
Paint roller 6" w/ handle
Paint roller 4" w/ handle
Epoxy Primer Gray
Epoxy Primer Yellow
Epoxy Strong Hold RSC
Epoxy Fortress
Reducer
Manpower:
Foreman
Painter
Labor
No. of Men
1
3
6
No. of Men
2.00
2.00
II at San jose
Quantity
Unit Cost
ibution line)
(NOTE: Heavy soil, rock and a portion of concrete to be excavated)
depth
Volume
1m
123.30 cu.m.
1m
774.20 cu.m.
123.30
774.20
897.50
Unit
days
days
cu.m.
cu.m.
cu.m.
Qty.
Unit Rate
40.00
40.00
360.00
200.00
>>>>>>>>>>>>>>>>>>>>>>>>>
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
Th/H
0.10 m
1.50 m
0.23
0.57
3.00 m
0.20 m
Total Volume
0.27
0.20
1.27
bags
cu.m.
cu.m.
pcs
pcs
pcs
pcs
shts
shts
shts
kgs
kgs
15.00
1.00
1.50
150.00
24.00
15.00
5.00
4.00
1.00
10.00
5.00
15.00
280.00
1,000.00
1,200.00
15.00
30.00
204.00
90.00
280.00
280.00
520.00
100.00
100.00
kgs
kgs
unit
can
bdft
bdft
bdft
bdft
2.00
2.00
1.00
1.00
50.00
33.33
26.67
166.67
Material Cost
100.00
120.00
2,500.00
250.00
30.00
30.00
30.00
30.00
Unit
days
days
days
days
days
Qty.
9.00
9.00
7.00
9.00
9.00
Unit Rate
360.00
260.00
280.00
260.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
bags
m
m
pcs
pcs
kgs
kgs
kgs
cu.m.
m
bdft
bdft
shts
254.00
14.00
28.00
45.00
24.00
5.00
15.00
10.00
6.00
290.00
50.00
33.33
3.00
21.60
0.72
0.80
23.12
280.00
1,000.00
1,200.00
204.00
90.00
100.00
100.00
100.00
1,200.00
25.00
30.00
30.00
520.00
ln.m.
sht
kgs
4.00
2.00
2.00
Material Cost
1,350.00
3,780.00
170.00
days
days
6.00
6.00
Equipment Cost
1,278.00
976.00
Unit
days
days
days
days
days
Qty.
Unit Rate
16.00
16.00
12.00
16.00
16.00
360.00
260.00
260.00
260.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
(3 m elevation)
ry and Hauling of materials on project site)
ce : Bayog Quarry
Th/H
m
m
m
m
Total Volume
bags
cu.m
cu.m.
kgs
pcs
pcs
pcs
pcs
pcs
kgs
sht
rolls
Estimated Distance= 15 Km
0.20
3.50
5.20
4.20
0.40
0.25
485.00
25.50
44.00
250.00
100.00
230.00
350.00
5.00
200.00
150.00
1.00
3.00
8.17
15.83
3.33
6.62
10.00
0.12
44.07
280.00
1,000.00
1,200.00
150.00
850.00
750.00
462.00
2,520.00
204.00
100.00
3,780.00
7,500.00
m.
m.
kgs
kgs
sht
sht
bdft
bdft
bdft
pcs
pcs
pcs
kgs
50.00
175.00
25.00
70.00
2,000.00
4,680.00
2,000.00
2.00
24.00
6.00
5.00
Material Cost
days
days
days
Unit
days
days
days
days
days
100.00
100.00
520.00
350.00
30.00
30.00
30.00
250.00
85.00
690.00
170.00
35.00
35.00
30.00
Equipment Cost
Qty.
1,278.00
976.00
700.00
Unit Rate
60.00
60.00
50.00
60.00
60.00
360.00
260.00
280.00
260.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
V=
V=
123.30
774.20
Total Volume
2 cu.m./day
Unit
days
days
897.50
Qty.
Unit Rate
32.00
32.00
360.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
Unit
103.00
Material Cost
Qty.
1,900.00
Unit Rate
15.00
15.00
15.00
15.00
360.00
280.00
280.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
pcs
pcs
10.00
8.00
30.00
Material Cost
185.00
175.00
45.00
Unit
days
days
days
Qty.
Unit Rate
3.00
3.00
3.00
360.00
280.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
35.00
6,784.00
pcs
52.00
3,016.00
pcs
560.00
2,185.00
Material Cost
Unit
Qty.
Unit Rate
45.00
45.00
45.00
45.00
360.00
280.00
280.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
258 units
pc
pc
pc
pc
pc
pc
pc
pc
pc
pc
14.00
10.00
18.00
3.00
11.00
13.00
18.00
17.00
33.00
14.00
3,200.00
3,200.00
3,200.00
3,200.00
3,200.00
3,860.00
2,400.00
2,400.00
2,400.00
2,400.00
pc
14.00
2,600.00
pc
11.00
2,600.00
pc
11.00
2,600.00
pcs
1.00
5,903.00
pcs
1.00
4,950.00
pcs
7.00
3,340.00
pcs
3.00
2,800.00
pcs
pcs
pcs
pcs
pcs
pcs
pcs
units
cans
Unit
9.00
6.00
6.00
3.00
3.00
6.00
3.00
3.00
20.00
1,086.00
3,200.00
2,400.00
2,600.00
3,000.00
2,400.00
3,200.00
14,250.00
270.00
Material Cost
Qty.
Unit Rate
30.00
30.00
30.00
360.00
280.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
(Material=
(Labor Installation=
w/ level electrodes
1.00 unit
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
220,000.00
pcs
pcs
pcs
13.00
13.00
2.00
Material Cost
7,020.00
624.00
670.00
Th/H
0.20 m
ry and Hauling of materials on project site)
bags
m
m
pcs
kgs
cu.m.
Unit
days
days
days
days
1.06
10.00
0.50
1.00
10.00
1.00
2.00
Material Cost
Qty.
280.00
1,000.00
1,200.00
204.00
100.00
1,200.00
Unit Rate
2.00
2.00
2.00
2.00
360.00
260.00
260.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
5.00
190.00
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
1.00
5.00
1.00
1.00
1.00
1.00
1.00
2.00
1.00
5.00
3.00
3,200.00
2,950.00
450.00
75.00
380.00
2,300.00
450.00
80.00
2,800.00
170.00
170.00
pcs
pcs
pc.
1.00
6.00
1.00
180.00
45.00
30,000.00
Material Cost
Unit
days
days
days
Qty.
Unit Rate
1.00
3.00
3.00
360.00
280.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
45.00
525.00
25.00
25.00
210.00
39.00
39.00
39.00
60.00
31.00
175.00
1,700.00
56.00
45.00
180.00
45.00
45.00
150.00
pcs
pcs
pcs
pcs
pcs
bags
m
m
pcs
kgs
sht
pcs
kgs
kgs
bd.ft.
Unit
days
days
days
days
days
days
2.00
16.00
5.00
7.00
3.00
160.00
21.00
26.00
120.00
7.00
7.00
58.00
21.00
9.00
518.00
Material Cost
Qty.
1,200.00
1,140.00
990.00
948.00
780.00
280.00
1,000.00
1,200.00
204.00
100.00
3,780.00
520.00
100.00
100.00
30.00
Unit Rate
17.00
17.00
17.00
17.00
17.00
17.00
360.00
280.00
280.00
260.00
260.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
pcs
pc
pcs
pc
pc
pc
pcs
pcs
2.00
3.00
1.00
2.00
1.00
1.00
1.00
6.00
2.00
6,345.00
5,456.00
5,200.00
220.00
570.00
750.00
5,700.00
575.00
490.00
pcs
pc
roll
Unit
days
days
days
4.00
1.00
5.00
Material Cost
Qty.
190.00
190.00
45.00
Unit Rate
10.00
10.00
10.00
360.00
280.00
280.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
14.00
14.00
4.00
4.00
3.00
3.00
4.00
5.00
3.00
8.00
10.00
11.00
4.00
5.00
2.00
878.00
878.00
160.00
160.00
160.00
160.00
250.00
20.00
48.00
54.00
600.00
186.00
2,630.00
4,050.00
908.00
gal
pcs
gal
gal
gal
gal
gal
gal
gal
lit
gal
pcs
pcs
pcs
pcs
pcs
pcs
ft
pairs
Unit
days
10.00
4.00
16.00
14.00
5.00
6.00
7.00
10.00
4.00
4.00
30.00
5.00
3.00
3.00
17.00
54.00
11.00
13.00
4.00
Material Cost
Qty.
780.00
12.00
720.00
405.00
894.00
478.00
216.00
216.00
312.00
95.00
24.00
30.00
42.00
48.00
75.00
13.00
14.00
37.00
42.00
Unit Rate
14.00
14.00
14.00
360.00
280.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
pcs
pcs
4.00
10.00
185.00
36.00
pcs
pcs
pcs
can
mtr
roll
unit
unit
mtrs
unit
pc
pc
pc
pc
mtrs
unit
Unit
days
days
2.00
2.00
18.00
2.00
10.00
2.00
1.00
1.00
300.00
1.00
1.00
1.00
1.00
1.00
30.00
1.00
Material Cost
Qty.
25.00
89.00
25.00
250.00
87.00
90.00
125,000.00
12,000.00
40.00
700.00
2,800.00
350.00
350.00
280.00
25.00
2,700.00
Unit Rate
5
5
280.00
200.00
Labor Cost
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
Est. Direct Cost (EDC)
( Direct Cost/Estimated Volume)
Amount
ted)
Amount
14,400.00
120,000.00
134,400.00
134,400.00
134,400.00
149.75
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
4,200.00
1,000.00
1,800.00
2,250.00
720.00
3,060.00
450.00
1,120.00
280.00
5,200.00
500.00
1,500.00
200.00
240.00
2,500.00
250.00
1,500.00
999.90
800.10
5,000.10
33,570.10
Amount
3,240.00
2,340.00
1,960.00
2,340.00
3,600.00
13,480.00
47,050.10
47,050.10
47,050.10
cu.m
cu.m
cu.m
cu.m
71,120.00
14,000.00
33,600.00
9,180.00
2,160.00
500.00
1,500.00
1,000.00
7,200.00
7,250.00
1,500.00
999.90
1,560.00
5,400.00
7,560.00
340.00
164,869.90
7,667.00
5,855.00
13,522.00
Amount
5,760.00
12,480.00
6,240.00
8,320.00
22,400.00
55,200.00
233,591.90
233,591.90
233,591.90
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
135,800.00
25,500.00
52,800.00
37,500.00
85,000.00
172,500.00
161,700.00
12,600.00
40,800.00
15,000.00
3,780.00
22,500.00
5,000.00
17,500.00
13,000.00
24,500.00
60,000.00
140,400.00
60,000.00
500.00
2,040.00
4,140.00
850.00
1,093,410.00
44,730.00
34,160.00
21,000.00
99,890.00
Amount
21,600.00
62,400.00
42,000.00
46,800.00
180,000.00
352,800.00
1,546,100.00
1,546,100.00
1,546,100.00
cu.m.
cu.m.
cu.m.
Amount
11,520.00
89,600.00
101,120.00
101,120.00
101,120.00
112.668524
195,700.00
195,700.00
Amount
5,400.00
12,600.00
12,600.00
18,000.00
48,600.00
244,300.00
244,300.00
396.269262
1,850.00
1,400.00
1,350.00
4,600.00
Amount
1,080.00
840.00
840.00
2,760.00
7,360.00
7,360.00
11.938362
237,440.00
156,832.00
1,223,600.00
1,617,872.00
Amount
16,200.00
88,200.00
88,200.00
180,000.00
372,600.00
1,990,472.00
1,990,472.00
514.20
44,800.00
32,000.00
57,600.00
9,600.00
35,200.00
50,180.00
43,200.00
40,800.00
79,200.00
33,600.00
36,400.00
28,600.00
28,600.00
5,903.00
4,950.00
23,380.00
8,400.00
9,774.00
19,200.00
14,400.00
7,800.00
9,000.00
14,400.00
9,600.00
42,750.00
5,400.00
694,737.00
Amount
10,800.00
58,800.00
58,800.00
128,400.00
823,137.00
823,137.00
212.64
200,000.00
20,000.00
220,000.00
220,000.00
91,260.00
8,112.00
1,340.00
100,712.00
cu.m
2,800.00
500.00
1,200.00
2,040.00
100.00
2,400.00
9,040.00
Amount
720.00
520.00
520.00
400.00
2,160.00
111,912.00
111,912.00
111,912.00
950.00
3,200.00
14,750.00
450.00
75.00
380.00
2,300.00
450.00
160.00
2,800.00
850.00
510.00
180.00
270.00
30,000.00
57,325.00
Amount
360.00
2,520.00
2,520.00
5,400.00
62,725.00
62,725.00
62,725.00
23,625.00
4,375.00
42,500.00
11,760.00
1,755.00
7,020.00
1,755.00
2,700.00
4,650.00
2,400.00
18,240.00
4,950.00
6,636.00
2,340.00
44,800.00
21,000.00
31,200.00
24,480.00
700.00
26,460.00
30,160.00
2,100.00
900.00
15,540.00
332,046.00
Amount
6,120.00
19,040.00
19,040.00
17,680.00
17,680.00
40,800.00
120,360.00
452,406.00
452,406.00
18,096.24
12,690.00
16,368.00
5,200.00
440.00
570.00
750.00
5,700.00
3,450.00
980.00
760.00
190.00
225.00
47,323.00
Amount
3,600.00
2,800.00
5,600.00
12,000.00
59,323.00
59,323.00
59,323.00
12,292.00
12,292.00
640.00
640.00
480.00
480.00
1,000.00
100.00
144.00
432.00
6,000.00
2,046.00
10,520.00
20,250.00
1,816.00
7,800.00
48.00
11,520.00
5,670.00
4,470.00
2,868.00
1,512.00
2,160.00
1,248.00
380.00
720.00
150.00
126.00
144.00
1,275.00
702.00
154.00
481.00
168.00
110,728.00
Amount
5,040.00
11,760.00
16,800.00
33,600.00
144,328.00
144,328.00
144,328.00
740.00
360.00
50.00
178.00
450.00
500.00
870.00
180.00
125,000.00
12,000.00
12,000.00
700.00
2,800.00
350.00
350.00
280.00
750.00
2,700.00
160,258.00
Amount
2,800.00
2,000.00
4,800.00
165,058.00
165,058.00
165,058.00