PEC (M) Sdn Bhd

Shell Malaysia Trading PDLOBP PD120 Expansion Project Daily Site Surveillance Date Location No. 1 2 3 4 5 6 : 14 July 2011 : Base Oil Area Items / Findings Noise signage at welding machine area Posters to hang up along rd55 Silt trap was not provided at every sump pit base oil area Drain at base oil area with full of mud LSR board was not attached to bundwall Road along to base oil area with full of debris / dust Action Taken Contractor to provide noise signages PEC and contractor will provide posters and banners for that area To provide silt trap at every sump pit To clear up all the muds at base oil area drain system Reattach the LSR Board at any suitable location Contractor to clear up the debris and dust using sweep or water Remarks

Person In Charge KSL PEC/TG/KSL/TBK TBK TBK TBK TBK / TG

* All findings must be close up on Saturday, 16th July 2011. Completed by: PEC(M)